Supporting structure for subway station deep foundation pit construction
By adopting a combination design of underground continuous wall and internal support structure in the construction of deep foundation pits of subway stations, and using arc plates and support components to form a triangular compressive structure, the problem of poor stability of support structure in deep foundation pit construction is solved, and the problem of poor support structure in deep foundation pit construction is achieved. High durability and stability, suitable for deep foundation pit construction in complex soil conditions.
Patent Information
- Application Number
- CN202420358750.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-27
- Publication Date
- 2024-11-05
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing deep foundation pit construction support structure lacks effective support and reinforcement measures in the construction of subway stations with complex soil conditions, poor slope stability, complex underground facilities, urgent construction period, limited construction site and high environmental protection requirements.
A support structure including underground continuous wall and inner support structure was designed. A triangular compressive structure was formed through components such as concrete support frames, curved plates, support components and elastic parts to enhance the support effect on underground continuous walls, and through The construction methods of concrete pouring and steel cages improve the stability and durability of support.
It realizes effective support and reinforcement of deep foundation pits, improves the durability and stability of the support structure, enhances the compression resistance, and is suitable for deep foundation pit construction, and is convenient to construct and has low cost.
Smart Images

Figure CN221956742U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of subway stations, in particular to a supporting structure for deep foundation pit construction of subway stations. Background Art
[0002] The subway station is a rapid urban transportation system located underground. It is a mode of transportation that uses underground roads and operates in a track system, aiming to provide efficient, fast and convenient urban transportation services. The construction sequence of the open-cut method is to build the cushion layer, side wall and top plate in order after excavating to the predetermined depth. This is the standard construction method of the open-cut method.
[0003] Deep foundation pit projects have the characteristics of complex soil conditions, poor slope stability, complex underground facilities, tight construction period, limited construction site, high engineering risk and high environmental protection requirements. The existing deep foundation pit support structure usually adopts underground continuous wall, pile row and other methods, lacking the reinforcement of the internal support structure of the deep foundation pit.
[0004] Therefore, the utility model designs a support structure for deep foundation pit construction of a subway station to solve the above problems. Utility Model Content
[0005] In order to solve the above technical problems, the utility model provides a support structure for deep foundation pit construction of a subway station.
[0006] The technical solution of the utility model is: a support structure for deep foundation pit construction of a subway station, comprising a foundation pit, an underground continuous wall arranged around the foundation pit, and an internal support structure arranged in the foundation pit, a spacing is left between the underground continuous wall and the bottom of the foundation pit, a cushion layer formed by pouring concrete is arranged in the foundation pit located within the spacing, and the internal support structure comprises four concrete support frames arranged in sequence from top to bottom, and the four concrete support frames are all perpendicular to the underground continuous wall;
[0007] The concrete support frame is provided with a reinforcement structure, which includes a first sleeve and a second sleeve fixedly mounted on the concrete support frame, a first arc plate used to fix the first sleeve to the underground continuous wall, and a third arc plate used to fix the second sleeve to the underground continuous wall.
[0008] Furthermore, the underground continuous wall includes a locking pipe and a steel cage, and joints are provided on both side walls of the steel cage. The locking pipes are arranged on both sides of the steel cage and welded to the joints, and the interior of the steel cage is filled with concrete.
[0009] Description: The underground continuous wall is constructed by the construction method of locking pipes and steel cages. The construction is convenient and the technology is mature. It is easy to brush the wall and clean the mud on the side walls of the wall section, which is beneficial to ensure the quality of the joint concrete. It is convenient to lower the steel cage in the later construction trench section; the cost is low.
[0010] Further, one end of the first curved plate is fixedly connected to the upper part of the first sleeve, one end of the third curved plate is fixedly connected to the upper part of the second sleeve, and a support assembly is provided between two adjacent concrete support frames, and the support assembly includes two cross-arranged support rods and an auxiliary rod for connecting the support rods to the first curved plate or the third curved plate.
[0011] The support rod is connected between the first sleeve and the second sleeve on another concrete support frame, one end of the auxiliary rod is slidably sleeved with the support rod, and the other end of the auxiliary rod is hinged with the first arc plate or the third arc plate.
[0012] Description: By setting up a support assembly, a part of the force of the first curved plate can be transferred to the support rod through the auxiliary rod, and then the force is further dispersed to the first sleeve and the second sleeve through the support rod, so as to continue to disperse to the previous first curved plate and the third curved plate on the same side to support the underground continuous wall, and the auxiliary rod is subjected to force and slides on the support rod, so that part of the force is offset by the displacement, thereby improving the support effect.
[0013] Furthermore, the first arc plate and the third arc plate are both composed of a movable plate and a fixed plate, the movable plate is provided with a protrusion, the fixed plate is provided with a notch for staggered rotation with the protrusion, and both sides of the protrusion are penetrated through the fixed plate by bolts and fastened by nuts.
[0014] Description: By setting the arc plate into a movable plate and a fixed plate, the connection angle between the movable plate and the fixed plate can be adjusted, thereby adjusting the force distribution of the arc plate in various directions, and the bending degree of the arc plate can be adjusted according to the depth of the foundation pit and the spacing between the first sleeve and the second sleeve, thereby increasing the scope of application.
[0015] Furthermore, two second arc-shaped plates are provided between the first sleeve and the second sleeve.
[0016] Description: By setting two second arc-shaped plates, the first sleeve and the second sleeve can transmit part of the force to the second arc-shaped plate, and the force is buffered and dispersed through the arc, thereby enhancing the pressure resistance effect.
[0017] Furthermore, the second arc-shaped plates located between the four concrete support frames are correspondingly connected through elastic members.
[0018] Description: The upper and lower second arc plates are connected by an elastic member. When the second arc plate is subjected to pressure from the first sleeve and the second sleeve, part of the force can be transferred to the next second arc plate through the elastic member. When both arc plates are subjected to force, an antagonistic force can be formed to counteract the pressure from the first sleeve and the second sleeve.
[0019] Furthermore, waterproof panels are provided on the inner walls on both sides of the underground continuous wall, and the elastic member is a first airbag rod, and both sides of the first airbag rod are fixedly connected to the corresponding waterproof panels through a second airbag rod connected thereto.
[0020] Description: By setting up a waterproof board, the anti-seepage property of the underground continuous wall can be improved, and through the pneumatic effect of the first airbag rod and the second airbag rod, the second arc plate can disperse the force to the waterproof board when it is compressed, thereby exerting anti-pressure on the underground continuous wall and improving the supporting effect.
[0021] The beneficial effects of the utility model are:
[0022] (1) The supporting structure of the utility model supports and reinforces the deep foundation pit by setting up an underground continuous wall and an internal support structural system, and by setting up concrete supports at the crown beam, it has high durability and stability. The remaining supporting parts continue to use concrete supports, which is suitable for deep foundation pits and is relatively strong and not easy to deform or damage.
[0023] (2) The support structure of the utility model forms a triangle with the underground continuous wall and the concrete support frame to resist compression by setting the first arc plate and the third arc plate, and strengthens the resistance force by the first sleeve and the second sleeve, thereby further improving the supporting effect on the underground continuous wall. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is the overall structural diagram of the supporting structure embodiment 1 of the utility model;
[0025] Figure 2 It is a structural diagram of the underground continuous wall of the supporting structure of the utility model;
[0026] Figure 3 This is a structural diagram of the first support assembly of the support structure embodiment 2 of the utility model;
[0027] Figure 4 It is a structural diagram of the elastic member of the support structure of the utility model;
[0028] Figure 5 This is a structural diagram of the first curved plate of the support structure of the utility model;
[0029] Among them, 1-foundation pit, 2-underground continuous wall, 21-rebar cage, 22-locking pipe, 3-cushion, 4-concrete support frame, 41-first casing, 42-second casing, 43-first arc plate, 431-movable plate, 432-fixed plate, 433-bolt, 44-second arc plate, 45-third arc plate, 46-support rod, 47-auxiliary rod, 5-elastic member, 51-waterproof board, 52-second airbag rod. DETAILED DESCRIPTION
[0030] The present invention will be further described in detail below in conjunction with specific implementation methods to better reflect the advantages of the present invention.
[0031] Example 1
[0032] A support structure for deep foundation pit construction of a subway station, such as Figure 1 As shown, it includes a foundation pit 1, an underground continuous wall 2 arranged around the foundation pit 1, and an internal support structure arranged in the foundation pit 1, a spacing is left between the underground continuous wall 2 and the bottom of the foundation pit 1, and a cushion layer 3 formed by pouring concrete is arranged in the foundation pit 1 located within the spacing, and the internal support structure includes four concrete support frames 4 arranged in sequence from top to bottom; it can be understood that one of the concrete support frames 4 can be composed of a plurality of concrete support bodies arranged side by side at equal intervals in the horizontal direction and having a rectangular cross section, but it is not limited to this structure;
[0033] like Figure 2 As shown, the underground continuous wall 2 includes a locking pipe 22 and a steel cage 21. Joints are provided on both side walls of the steel cage 21. The locking pipe 22 is arranged on both sides of the steel cage 21 and welded to the joints. The interior of the steel cage 21 is filled with concrete.
[0034] like Figure 1 As shown, the concrete support frame 4 is provided with a reinforcement structure, which includes a first sleeve 41 and a second sleeve 42 fixedly mounted on the concrete support frame 4, a first curved plate 43 for fixedly connecting the first sleeve 41 with the underground continuous wall 2, and a third curved plate 45 for fixedly connecting the second sleeve 42 with the underground continuous wall 2, and two second curved plates 44 are arranged between the first sleeve 41 and the second sleeve 42.
[0035] The construction method of the support structure for the deep foundation pit construction of the lower track is as follows: excavate the foundation pit 1, then set up the underground continuous wall 2 according to the slot section, and pour C30 early strength concrete into the gap between the bottom of the underground continuous wall 2 and the support of the foundation pit 1 to form a cushion layer 3;
[0036] First, the first sleeve 41 and the second sleeve 42 are sleeved on the concrete support frame 4, and the first curved plate 43 and the third curved plate 45 are arranged on the first sleeve 41 and the second sleeve 42, and then the second curved plate 44 is arranged between the first sleeve 41 and the second sleeve 42, and then 4 supports are placed vertically along the foundation pit 1, the first one is a 800×1000 concrete support frame 4, and the second to fourth ones are 1000×1100 concrete support frames 4,
[0037] When the first curved plate 43 receives the pressure from the foundation pit 1, the first curved plate 43 transfers part of the force to the first sleeve 41, and the first sleeve 41 transfers part of the force to the second sleeve 42 through the second curved plate 44. The second sleeve 42 forms a counteraction with the first sleeve 41 under the combined action of the pressure of the third curved plate 45 and the underground continuous wall 2 and the pressure of the second curved plate 44, thereby improving stability; finally, C30 concrete is poured on top of the concrete support frame 4 for the crown beam to complete the construction.
[0038] Example 2
[0039] This embodiment is different from Embodiment 1 in that Figure 3 As shown, the right end of the first curved plate 43 is fixedly connected to the upper part of the first sleeve 41, and the left end of the third curved plate 45 is fixedly connected to the upper part of the second sleeve 42. A support assembly is provided between two adjacent concrete support frames 4, and the support assembly includes two cross-arranged support rods 46 and an auxiliary rod 47 for the support rod 46 and the first curved plate 43 or the third curved plate 45. The support rod 46 is connected between the first sleeve 41 and the second sleeve 42 on another concrete support frame 4, one end of the auxiliary rod 47 is slidably sleeved with the support rod 46, and the other end of the auxiliary rod 47 is hinged to the first curved plate 43 or the third curved plate 45.
[0040] The construction method of this embodiment is different from that of the first embodiment in that after the four concrete support frames 4 are constructed in the foundation pit 1, an auxiliary rod 47 is hingedly provided on the first sleeve 41 and the second sleeve 42 on the second to fourth concrete support frames 4, and then the support rod 46 and the auxiliary rod 47 are sleeved, so that the two ends of the support rod 46 are respectively connected to the corresponding first sleeve 41 and the second sleeve 42;
[0041] The force on the first curved plate 43 can be partially transferred to the support rod 46 through the auxiliary rod 47, and then further dispersed to the first sleeve 41 and the second sleeve 42 through the support rod 46, so as to continue to be dispersed to the previous first curved plate 43 and the third curved plate 45 on the same side to support the underground continuous wall 2, and the auxiliary rod 47 is subjected to force and slides on the support rod 46, so that part of the force is offset by the displacement, thereby improving the supporting effect.
[0042] Example 3
[0043] This embodiment is different from Embodiment 1 in that Figure 4 As shown, the second arc-shaped plates 44 located between the four concrete support frames 4 are correspondingly connected through elastic members 5; waterproof plates 51 are provided on the inner walls on both sides of the underground continuous wall 2, and the elastic member 5 is a first airbag rod, and the two sides of the first airbag rod are respectively fixedly connected to the corresponding waterproof plates 51 through a second airbag rod 52 connected thereto;
[0044] like Figure 5 As shown, the first arc plate 43 and the third arc plate 45 are both composed of a movable plate 431 and a fixed plate 432, the movable plate 431 is provided with a protrusion, the fixed plate 432 is provided with a notch for staggered rotation with the protrusion, and both sides of the protrusion are penetrated by bolts 433 through the fixed plate 432 and fastened by nuts.
[0045] The construction method of this embodiment is different from that of the first embodiment in that the second curved plate 44 is connected by the first airbag rod, and waterproof plates 51 are arranged on both side walls of the underground continuous wall 2. After the waterproof plates 51 are constructed, the second airbag rod 52 is used to connect the first airbag rod with the corresponding waterproof plates 51 on both sides, and the bending degrees of the first curved plate 43 and the third curved plate 45 are adjusted according to the width and pressure of the foundation pit 1.
[0046] When the second arc-shaped plate 44 is subjected to force, the force is transmitted to the first airbag rod, and the first airbag rod distributes the force to the second airbag rods 52 on both sides to resist the pressure on the waterproof plate 51 and the foundation pit 1.
Claims
1. A support structure for deep foundation pit construction of a subway station, characterized in that: The invention comprises a foundation pit (1), an underground continuous wall (2) arranged around the foundation pit (1), and an internal support structure arranged in the foundation pit (1); a spacing is left between the underground continuous wall (2) and the bottom of the foundation pit (1); a cushion layer (3) formed by pouring concrete is arranged in the foundation pit (1) within the spacing; the internal support structure comprises four concrete support frames (4) arranged in sequence from top to bottom; the four concrete support frames (4) are all perpendicular to the underground continuous wall (2); The concrete support frame (4) is provided with a reinforcement structure, which comprises a first sleeve (41) and a second sleeve (42) fixedly sleeved on the concrete support frame (4), a first curved plate (43) used for fixedly connecting the first sleeve (41) and the underground continuous wall (2), and a third curved plate (45) used for fixedly connecting the second sleeve (42) and the underground continuous wall (2).
2. A support structure for deep foundation pit construction of a subway station according to claim 1, characterized in that: The underground continuous wall (2) comprises a locking pipe (22) and a steel cage (21), the side walls of the steel cage (21) are provided with joints, the locking pipe (22) is arranged on both sides of the steel cage (21) and welded to the joints, and the interior of the steel cage (21) is filled with concrete.
3. The supporting structure for deep foundation pit construction of a subway station according to claim 1, characterized in that: One end of the first curved plate (43) is fixedly connected to the upper part of the first sleeve (41), one end of the third curved plate (45) is fixedly connected to the upper part of the second sleeve (42), and a support assembly is provided between two adjacent concrete support frames (4), the support assembly comprising two cross-arranged support rods (46) and an auxiliary rod (47) for connecting the support rod (46) to the first curved plate (43) or the third curved plate (45), The support rod (46) is connected between the first sleeve (41) and the second sleeve (42) on another concrete support frame (4); one end of the auxiliary rod (47) is slidably sleeved with the support rod (46); and the other end of the auxiliary rod (47) is hinged with the first arc plate (43) or the third arc plate (45).
4. The supporting structure for deep foundation pit construction of a subway station according to claim 1, characterized in that: The first arc-shaped plate (43) and the third arc-shaped plate (45) are both composed of a movable plate (431) and a fixed plate (432); the movable plate (431) is provided with a protrusion; the fixed plate (432) is provided with a notch for staggered rotation with the protrusion; both sides of the protrusion are penetrated through the fixed plate (432) by bolts (433) and fastened by nuts.
5. The supporting structure for deep foundation pit construction of a subway station according to claim 1, characterized in that: Two second arc-shaped plates (44) are provided between the first sleeve (41) and the second sleeve (42).
6. A support structure for deep foundation pit construction of a subway station according to claim 5, characterized in that: The second arc-shaped plates (44) located between the four concrete support frames (4) are correspondingly connected via elastic members (5).
7. A support structure for deep foundation pit construction of a subway station according to claim 6, characterized in that: Waterproof plates (51) are provided on the inner walls of both sides of the underground continuous wall (2); the elastic member (5) is a first airbag rod; both sides of the first airbag rod are fixedly connected to the corresponding waterproof plates (51) via a second airbag rod (52) connected thereto.