Anti-slide pile retaining wall punching pre-embedded steel bar step-by-step pouring baffle structure
By using anti-sliding pile wall-proofing pre-embedded planting ribs to pour the baffle structure step by step, the problem of insufficient baffle thickness and compressive resistance in the existing technology is solved, and the load-bearing capacity and construction of the baffle are improved. Safety, achieving better soil retaining effect and material saving.
Patent Information
- Application Number
- CN202420054391.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-10
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-01-10
AI Technical Summary
The existing soil slope slope-top anti-sliding pile step-type pile baffle structure reduces the excavation area while reducing the thickness and compressive resistance between the upper and lower stages of the baffle, increasing the risk of soil extrusion between piles, but failing to Effectively exert the soil retaining function of anti-sliding pile structures.
The anti-sliding pile wall-proofing pre-embedded planting ribs are used to pour the baffle structure step by step. By pre-embedding the planting ribs and baffles between the anti-sliding piles, the baffle structure is superimposed in the vertical direction, and the planting ribs and anti-sliding are used to pour. The piles and baffles are poured as a whole, horizontal and vertical support steel bars and wooden formwork are set up, and the number of steel bars on the baffles is calculated and determined to withstand soil pressure and reduce excavation risks.
The load-bearing capacity of the baffle in weak soil is improved, the risk of soil extrusion during excavation is reduced, construction safety is enhanced, and materials are saved, achieving better anti-slip pile structure soil retaining function.
Smart Images

Figure CN221956749U_ABST
Abstract
Description
Technical Field
[0001] The utility model patent belongs to the technical field of slope retaining structure, and specifically relates to an anti-sliding pile wall punching pre-embedded reinforcement step-by-step casting baffle structure. Background Art
[0002] Most of the major small and medium-sized cities in Yunnan Province are located in the piedmont areas of mountainous areas. The soil in these areas is mostly special soft soil such as expansive soil and red clay. In engineering construction, high slopes often have problems such as instability of soft soil slopes and landslides. In the existing technology, such as the anti-sliding pile stepped pile baffle structure at the top of the soil slope announced by the Chinese patent (CN212052807U), although this design reduces the excavation area, it also reduces the thickness and compressive strength of the upper and lower connecting parts of the stepped pile baffle, increases the risk of soil extrusion between piles, and does not play a good role in the retaining function of the anti-sliding pile structure.
[0003] To this end, this paper proposes an anti-sliding pile wall protection with pre-embedded reinforcement and step-by-step casting of the baffle structure. Utility Model Content
[0004] In order to achieve the above-mentioned technical effect, the utility model is realized through the following technical scheme: an anti-slip pile protective wall with pre-embedded rebar and step-by-step casting of a baffle structure, including a protective wall before the anti-slip piles are cast, a baffle structure arranged between the anti-slip piles and a filter layer behind the plate; a pre-embedded pipe is pre-embedded in the protective wall before the anti-slip piles are cast, and the two ends of the pre-embedded pipe extend to the inside and outside of the protective wall respectively, and rebar is placed in the pre-embedded pipe, the rebar on the inside of the protective wall is cast as a whole with the anti-slip piles, and the rebar on the outside of the protective wall is cast as a whole with the baffle, and the baffle structure is stacked in the vertical direction; the baffle structure includes a number of baffles, which are reversely cast step by step from the top of the anti-slip piles downward in sequence; a bottom formwork is arranged under the baffle; horizontal supporting steel bars and vertical supporting wood are arranged on the inside of the mountain and perpendicular to the rebar under the bottom formwork.
[0005] Preferably, the embedded pipe is a 35mm PVC pipe.
[0006] Preferably, the embedded reinforcement adopts φ25mm steel bars, and the horizontal embedded reinforcement is set at 30~50cm away from the anti-sliding pile on the inner slope side; the distance between the embedded reinforcements in the vertical direction can be determined according to the soil pressure calculation, and the soil pressure calculation can adopt the Rankine, Coulomb and other methods, and the baffle embedded reinforcement is designed as follows: Assuming that a circular steel bar with a diameter of d (mm) is used, the total number of steel bars required on both sides of the baffle is N (roots), and the soil pressure e at the top of the i-th baffle below the pile top is calculated. i (kpa), bottom soil pressure e i+1(kpa), baffle design height h (m), baffle retaining net distance b (m), baffle borne total pressure P (KN), steel material design shear strength t (Mpa), safety factor K (can be 1.5~2 based on slope experience).
[0007] P = (e i + e i+1 )×(h / 2)×b
[0008] P is the total earth pressure on the baffle
[0009] N = P × (0.25 × Π × d 2 ×t / 1000) -1 × (4 / 3) × K
[0010] N is an integer with the remainder increasing by 1, and the number of steel bars required for single-sided wall protection is N / 2.
[0011] Preferably, the horizontal supporting steel bars are 1.5 m long and driven into the mountain laterally to a depth greater than 0.7 m. The steel bars are arranged at intervals of 0.5 m per bar, and a total of 7 bars are driven into the bottom of each baffle.
[0012] Preferably, the vertical support wood has a diameter greater than 5 cm, a support wood spacing of 1.5 m, and a total of 3 support woods are provided.
[0013] The beneficial effects of the utility model are:
[0014] 1. The baffle reinforcement can be determined by calculation and can be applied to high earth pressure during deep excavation in soft soil;
[0015] 2. The embedded reinforcement that bears the soil pressure in this structure is integrally cast into the pile body, which does not damage the anti-sliding pile structure and can better play the function of retaining soil;
[0016] 3. After the anti-slide pile construction is completed, the slope excavation in front of the pile can be constructed step by step from top to bottom, making the construction excavation more convenient and safer;
[0017] 4. The risk of soil extrusion between piles during excavation is greatly reduced, which greatly increases construction safety;
[0018] 5. The baffle is only set between the piles, which saves more materials than the traditional pile back plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solution of the embodiment of the utility model, the drawings required for describing the embodiment are briefly introduced below. Those skilled in the art can also obtain other drawings based on these drawings without paying any creative work.
[0020] Figure 1This is a schematic diagram of the pre-embedded reinforcement punching and pipe embedding on the side of the protective wall of the utility model;
[0021] Figure 2 This is a front view of the utility model of pre-embedded reinforcement punching and burying pipes on the side of the wall protection;
[0022] Figure 3 For the utility model Figure 2 A is a cross-sectional schematic diagram;
[0023] Figure 4 This is a schematic diagram of calculation of embedded reinforcement for baffles of the utility model;
[0024] Figure 5 This is a schematic diagram of the construction formwork of the utility model;
[0025] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0026] Anti-slip piles 1, baffles 2, filter layer 3, embedded pipes 4, PVC pipes 5, embedded reinforcement 6, bottom formwork 7, horizontal supporting steel bars 8, vertical supporting wood 9, and wall protection 10. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the utility model.
[0028] like Figures 1 to 5 As shown, the prior art in this embodiment has the following problems: the inventors found that the prior art, such as the anti-sliding pile stepped pile baffle structure at the top of the soil slope published in the Chinese patent (CN212052807U), although such a design reduces the excavation area, simultaneously reduces the thickness and compressive strength of the upper and lower connecting parts of the stepped pile baffle, increases the risk of soil extrusion between the piles, and does not play a good role in the soil retaining function of the anti-sliding pile structure;
[0029] Therefore, the inventor provides a structure in which an anti-slip pile 1 is punched in a protective wall and pre-embedded with rebars 6 and a baffle 2 is cast step by step, including a protective wall 10 before the anti-slip pile 1 is cast, a baffle 2 structure arranged between the anti-slip piles 1, and a filter layer 3 behind the plate; a pre-embedded pipe 4 is pre-embedded in the protective wall 10 before the anti-slip pile 1 is cast, and both ends of the pre-embedded pipe 4 extend to the inside and outside of the protective wall 10 respectively, and rebars 6 are placed in the pre-embedded pipe 4, and the rebars 6 on the inside of the protective wall 10 are cast as one body with the anti-slip pile 1, and the rebars 6 on the outside of the protective wall 10 are cast as one body with the baffle 2, and the baffle 2 structure is stacked in the vertical direction; the baffle 2 structure includes a plurality of baffles 2, which are reversely cast step by step from the top of the anti-slip pile 1 downward in sequence; a bottom formwork 7 is arranged below the baffle 2; a horizontal support steel bar 8 and a vertical support wood 9 are arranged on the inside of the horizontal mountain and perpendicular to the rebars 6 below the bottom formwork 7;
[0030] The principle and effect are as follows: when the anti-sliding pile 1 is excavated, a small hole is drilled in the retaining wall 10 to enter the soil between the piles and bury the pipe, which is cast into the retaining wall 10. When the steel bars of the anti-sliding pile 1 are tied, the pre-buried rebar 6 is put in. The rebar 6 and the steel bars of the anti-sliding pile 1 are cast as one piece, and the extended section enters the pre-buried pipe 4 in the soil between the piles. The exposed section of the pre-buried rebar resists the soil pressure in the form of shear resistance, and the size of the pre-buried rebar is determined comprehensively according to the soil pressure calculation result and the required safety factor.
[0031] When the anti-slide pile 1 is completed, the excavation of the slope in front of the pile can be realized by reverse construction from top to bottom, which makes the construction and excavation more convenient; the anti-slide pile 1 already bears the soil pressure or thrust behind the pile during the excavation process, so the safety of the excavation process in front of the pile is greatly improved, and the risk of soil extrusion between piles during the excavation process is reduced, which greatly increases the construction safety. At the same time, relying on the shear resistance of the pre-buried reinforcement 6 to withstand the soil pressure, it is possible to accurately calculate and design a reasonable retaining plate. This method does not destroy the structure of the anti-slide pile 1 and can better play the retaining function.
[0032] The embedded pipe 4 is a PVC pipe 5 with a diameter of φ35 mm.
[0033] Among them, the embedded reinforcement 6 uses φ25mm steel bars, and the embedded reinforcement 6 in the horizontal direction is set at 30~50cm away from the anti-sliding pile 1 on the inner slope side; the distance between the embedded reinforcement 6 in the vertical direction can be determined according to the soil pressure calculation, and the soil pressure calculation can adopt the Rankine, Coulomb and other methods, and the embedded reinforcement of the baffle 2 is designed as follows: Assuming that circular steel bars with a diameter of d (mm) are used, the total number of steel bars required on both sides of the baffle 2 is N (roots), and the soil pressure ei (kpa) at the top of the i-th baffle 2 below the pile top, the bottom soil pressure ei+1 (kpa), the design height h (m) of the baffle 2, the net retaining distance b (m) of the baffle 2, the total pressure P (KN) borne by the baffle 2, the design shear strength t (Mpa) of the steel material, and the safety factor K (which can be taken as 1.5~2 according to the slope experience) are calculated.
[0034] P=(ei+ ei+1)×(h / 2)×b
[0035] P is the total earth pressure on baffle 2
[0036] N=P×(0.25×Π×d2×t / 1000)-1×(4 / 3)×K
[0037] N is an integer with the remainder increasing by 1, and the number of steel bars required for single-sided wall protection is N / 2.
[0038] Among them, the horizontal support steel bar 8 is 1.5m long and is driven into the mountain horizontally to a depth greater than 0.7m. The steel bars are arranged at intervals of 0.5m / bar, and a total of 7 bars are driven into the bottom of each baffle 2.
[0039] Among them, the vertical support wood 9 has a diameter greater than 5 cm, the support wood spacing is 1.5 m, and a total of 3 are set.
[0040] like Figures 1 to 5 As shown, based on the above embodiments, this embodiment provides a vertical construction process for planting reinforcement 6 baffle 2:
[0041] S1. When setting the first board from top to bottom, manually clear the pouring space inside the mountain. The clearing thickness exceeds the thickness of the baffle 2 by 20cm. Set the bottom wooden template. The bottom template 7 is preferably made of wooden plywood with a thickness of less than 1cm. The width of the bottom template 7 is the same as the horizontal clearing depth of the mountain. Then set the template according to the designed board thickness and tie the steel bars. After the steel bars are poured, set the back filter layer 3 of the thick board. After pouring, remove the templates on both sides and keep the bottom wooden template.
[0042] S2. Starting from the second baffle 2, the construction is still from top to bottom, excavating 1.1 meters vertically downward along the outer side of the first baffle 2 that has been constructed. After the excavation is completed, 25mm steel bars are driven into the bottom of the upper formwork as (temporary) horizontal support. The length of the steel bar is 1.5m, and the driving depth is not less than 0.7m. The steel bars are set at an interval of 0.5m / bar, and a total of 7 bars are driven into the bottom of each baffle 2.
[0043] S3. After the construction of the transverse supporting steel bars is completed, they are cleaned in sections along the excavated section toward the mountain side. The cleaning width is 1.2m each time, and the cleaning thickness is still the thickness of the baffle 2 + 0.2m. After a section is cleaned, a vertical supporting wood 9 is set up with a diameter of not less than 5cm and a spacing of 1.5m between the supporting woods. A total of 3 supporting woods are set up.
[0044] S5. After cleaning and setting the vertical support wood 9, knock off the corresponding thickness of the retaining wall on both sides according to the designed thickness, tie the steel bars, support the formwork (the filter layer 3 is set at the same time as the formwork), and pour;
[0045] To facilitate construction and ensure quality, pouring begins when the external formwork is set at a height of 0.5m, and one layer is poured every 20cm above 0.5m. The top 10cm is poured using an artificial reserved hole.
[0046] The template on the side close to the mountain and the bottom template 7 are not disposable consumables, and old templates should be used as much as possible. The bottom template must bear the gravity of the upper filter layer 3, so new templates should be used as much as possible.
[0047] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
[0048] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A structure of anti-sliding pile wall punching, pre-embedded reinforcement and step-by-step casting of baffles, comprising a wall before the anti-sliding piles are cast, a baffle structure arranged between the anti-sliding piles and a filter layer behind the plate; characterized in that: Before the anti-slip piles are cast, embedded pipes are embedded in the retaining wall, and both ends of the embedded pipes extend to the inside and outside of the retaining wall respectively. Embedded steel bars are placed in the embedded pipes, and the embedded steel bars on the inside of the retaining wall are cast as one body with the anti-slip piles, and the embedded steel bars on the outside of the retaining wall are cast as one body with the baffles. The baffle structure is stacked in the vertical direction; the baffle structure includes a number of baffles that are reversely cast step by step from the top of the anti-slip piles downward; a bottom formwork is arranged under the baffle; and horizontal supporting steel bars and vertical supporting wood that are transverse to the inside of the mountain and perpendicular to the embedded steel bars are arranged under the bottom formwork.
2. According to claim 1, the anti-sliding pile wall protection punching pre-embedded reinforcement step-by-step casting baffle structure is characterized by: The embedded pipe is a 35mm PVC pipe.
3. According to claim 1, the anti-sliding pile wall protection punching pre-embedded reinforcement step-by-step casting baffle structure is characterized by: The embedded reinforcement adopts φ25mm steel bars, and the embedded reinforcement in the horizontal direction is arranged at 30-50cm away from the anti-sliding piles on the inner slope side.
4. According to claim 1, the anti-sliding pile wall protection punching pre-embedded reinforcement step-by-step casting baffle structure is characterized by: The horizontal support steel bars are 1.5m long and driven into the mountain body transversely to a depth greater than 0.7m. The steel bars are arranged at intervals of 0.5m / bar, and a total of 7 bars are driven into the bottom of each baffle.
5. According to claim 1, the anti-sliding pile wall protection punching pre-embedded reinforcement step-by-step casting baffle structure is characterized by: The vertical support wood has a diameter greater than 5 cm, the support wood spacing is 1.5 m, and a total of 3 support woods are provided.