Novel geotextile tube bag for offshore cofferdam

By using high-strength, spun fabrics, transverse tensioning and looping ties in geopipe bags, the problems of low UV resistance and poor durability in traditional geopipe bags are solved, and higher tensile strength and stability are achieved, simplifying Construction has been carried out to meet high environmental protection requirements.

CN221956757UActive Publication Date: 2024-11-05CCCC FIRST HARBOR ENGINEERING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323641030.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-05
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

Traditional geopipe bags have low UV resistance, poor durability, low tensile strength, easy to age and corrosion, and weak connections, resulting in short service life and filling material loss.

Method used

The main body of the geopipe bag with high-strength splicing is adopted, with horizontal tension and ring tie inside and outside, which increases the filling and filling ports, which facilitates filling and fixing, improves the thickness and stability of the pipe bag, and is woven through high-strength geotextile and polyester. Belts enhance tensile strength and durability.

Benefits of technology

It improves the durability and tensile strength of geopipe bags, ensures that the shape does not collapse easily after filling, enhances the splicing quality and cofferdam stability, simplifies the construction process, reduces environmental pollution, and meets high environmental protection requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221956757U_ABST
    Figure CN221956757U_ABST
Patent Text Reader

Abstract

The utility model relates to a novel geotextile tube bag for an offshore cofferdam, which is characterized in that the novel geotextile tube bag comprises a geotextile tube bag main body, cerclage belts and transverse tie bars, the geotextile tube bag main body is spliced and sewn into a tube shape by woven cloth, two ends of the geotextile tube bag main body are sewn into closed ends, the cerclage belts are arranged outside the geotextile tube bag main body at intervals, and the transverse tie bars are arranged on the geotextile tube bag main body. Transverse tie bars are arranged in the geotextile tube bag body at intervals and are made of strip-shaped geotextile materials, and the two ends of each transverse tie bar are fixed to the opposite inner surfaces of the geotextile tube bag body. Filling openings are sewn in the geotextile tube bag body at intervals. According to the novel geotextile tube bag for the offshore cofferdam, after being folded, the geotextile tube bag is small in size and weight, convenient to transport, convenient and rapid to construct, short in construction period, easy to operate and low in needed supporting facilities and power consumption; the controllability of the appearance of the geotextile pipe bag is improved, and the problems that the overall shape of a common pipe bag collapses and is not easy to control after filling is completed are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of offshore cofferdam geotextile tube bags, in particular to a novel geotextile tube bag used for offshore cofferdams. Background Art

[0002] Geotextile tube bags are made by sewing geotextile tube bag cloth into large-volume tube bags. According to the design section and the length of the tube bag, multiple filled tubular cuffs are left. In the offshore cofferdam, a pump is used to flush the water-carrying fine particles into the geotextile tube bag through the pipeline. The water is filtered out from the holes of the tube bag cloth. The fine sand material gradually consolidates and compacts under its own weight and seepage pressure. Multiple geotextile tube bags are arranged at the cofferdam to play a fence role. Traditional geotextile tube bags are usually sewn with low-weight geotechnical materials. Without special treatment, they have low UV resistance. If exposed to the outside, they are prone to aging under direct UV radiation; they have poor durability against long-term wave erosion, low tensile strength, poor corrosion resistance and anti-microbial erosion, and a short service life. Due to processing technology, geotextile tube bags are prone to weak points at the joints, which may cause the geotextile tube bag to rupture during construction, resulting in the loss of filling, thus affecting the use effect of the geotextile tube bag. Utility Model Content

[0003] The utility model aims to overcome the deficiencies of the prior art and provide a new type of geotextile tube bag for offshore cofferdams, which has good durability and is not easy to collapse after filling, thereby ensuring the splicing quality of the geotextile tube bag and the quality of the cofferdam.

[0004] The utility model solves the technical problem through the following technical solutions:

[0005] A new type of geotextile tube bag for offshore cofferdams, characterized in that it includes a geotextile tube bag body, a cincture belt and transverse reinforcement bars, the geotextile tube bag body is made of woven fabric spliced ​​and sewn into a tube shape, the two ends of the geotextile tube bag body are sewn into closed ends, cincture belts are arranged at intervals outside the geotextile tube bag body, and transverse reinforcement bars are arranged at intervals inside the geotextile tube bag body, the transverse reinforcement bars are made of strip-shaped geotextile material, and the two ends thereof are fixed on the opposite inner surfaces of the geotextile tube bag body; the geotextile tube bag body is sewn with filling ports at intervals.

[0006] Moreover, the length of the geotube bag body is 20 to 22 m, the height is 1.1 to 1.3 m, and the width is 2 to 2.2 m.

[0007] Moreover, three to five tie bars are arranged at intervals of 7 meters inside the tube bag, and the length of the tie bars is 2 to 2.2 meters, which controls the width of the geotube bag after the main body of the geotube bag is filled, thereby ensuring the thickness of the geotube bag.

[0008] Moreover, the ring tie belt is a polyester woven belt or a high-strength geotextile woven belt, which is sewn on the outer surface of the geotextile tube bag body at intervals of 1.8 to 2.2 meters.

[0009] Moreover, the main body of the geotextile tube bag is made of high-strength geotextile, and its unit area mass is 1200-1500g / m2.

[0010] Moreover, the transverse tensioning bars and the circumferential straps are staggered in the reverse length positions of the geotube bag body.

[0011] Moreover, the filling port has a diameter of 30 cm, and the distance between the filling ports is 4 to 5 m.

[0012] Moreover, a fastening positioning belt is provided along the longitudinal direction of the outer surface of the geotextile tube bag body, which is used to fix and connect the upper and lower geotextile tube bag bodies.

[0013] The advantages and beneficial effects of the utility model are:

[0014] 1. The new geotextile tube bag used for offshore cofferdams of the utility model uses high-strength woven fabrics, which improves the durability of the geotextile tube bag and effectively solves the problem of short service life of the geotextile tube bag.

[0015] 2. The new geotextile tube bag used for offshore cofferdams of the utility model improves the controllability of the shape of the geotextile tube bag by arranging tie bars inside the tube bag and arranging ring straps in the transverse direction, thereby solving the problem that the overall shape of the ordinary tube bag collapses and is difficult to control after filling.

[0016] 3. The new geotextile tube bag used for offshore cofferdam of the utility model is convenient for multiple devices to carry out geotextile tube bag filling operation at the same time by arranging multiple filling ports on the geotextile tube bag, and the filling efficiency is greatly improved.

[0017] 4. The new geotextile tube bag used for offshore cofferdams of the utility model has a small volume and weight after folding, is easy to transport, has convenient and quick construction, a short construction period, simple operation, and requires very few supporting facilities and electricity consumption; the water filtered out of the geotextile tube bag reduces the harmful element index in the sludge mixture by 92% to 96%, meeting high environmental protection requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 This is a schematic diagram of the structure of the new geotube bag used for offshore cofferdams;

[0019] Figure 2 yes Figure 1 A cross-sectional view of a

[0020] Figure 3 This is a schematic diagram of the construction structure of a new type of geotube bag used for offshore cofferdams.

[0021] Description of reference numerals:

[0022] 1- ring tie, 2- filling port, 3- geotube body, 4- transverse reinforcement, 5- fastening positioning belt, 6- bamboo raft, 7- geotube, 8- sand storage pit, 9- sand pump, 10- high-pressure water pump, 11- backfill sand. DETAILED DESCRIPTION

[0023] The present invention will be further described in detail below through specific embodiments. The following embodiments are merely descriptive and not restrictive, and the protection scope of the present invention cannot be limited by them.

[0024] A new type of geotextile tube bag for offshore cofferdams, comprising a geotextile tube bag body 3, a circumferential tie 1 and a transverse tie 4. The geotextile tube bag body is made of high-strength woven fabric stitched and sewn into a tube shape. The technical indicators of the geotextile are shown in Table 1. The two ends of the geotextile tube bag body are sewn into closed ends. The geotextile tube bag body is made of high-strength geotextile, and its unit area mass is not less than 1200-1500g / m 2 In this embodiment, the unit area mass is 1200g / m 2 .

[0025] The length of the geotube bag body is 20-22m, the height is 1.1-1.3m, the width is 2-2.2m, and the optimal length is 21m, the height is 1.1m, and the width is 2.1m. The geotube bag body is first processed into a rectangle. The processing of the geotextile takes into account the segmented length and width of the geotube bag cofferdam and the "upper and lower layers of the bag body should be staggered to avoid relative sliding of the bag body and the phenomenon of through gaps". The fabric of the geotube bag body should be a whole in the horizontal direction, and its width is based on the design geobag size, while considering adding 3% surplus to prepare for shrinkage during filling; the longitudinal direction (length direction) should be larger than the transverse direction (diameter direction).

[0026] Ring tie belts are arranged at intervals outside the main body of the geotextile tube bag. The ring tie belts are polyester woven belts or high-strength geotextile woven belts and are sewn to the outer surface of the main body of the geotextile tube bag at intervals of 2m.

[0027] Transverse reinforcements are arranged at intervals inside the main body of the geotextile tube bag. The transverse reinforcements are made of strip geotextile material, and the two ends are fixed on the opposite inner surfaces of the main body of the geotextile tube bag. Three to five reinforcements are arranged at intervals of 7 meters inside the tube bag, and the length of the reinforcement is 2 to 2.2 meters. In this embodiment, four reinforcements are used, and the length of the reinforcement is 2.1 meters. The width of the geotextile tube bag after the main body of the geotextile tube bag is filled is controlled, thereby ensuring the thickness of the geotextile tube bag. The transverse reinforcements and the geotextile tube bag main body where the circumferential belt is located are staggered along the length direction.

[0028] The geotube bag body is sewn with filling ports 2 at intervals, with a diameter of 30 cm and a spacing of 4 m between the filling ports. The cuffs of the filling ports should be exposed to the water surface. A tightening positioning belt 5 is provided along the longitudinal direction of the bag to fix and connect the upper and lower bags.

[0029] Table 1. Technical indicators of new geotextile tube bag 1200g / m2 woven geotextile

[0030] project Test standards index Longitudinal tensile strength ASTMD4595-17 ≥55KN / m Transverse tensile strength ASTMD4595-17 ≥70KN / m Longitudinal elongation ASTMD4595-17 ≤110% Transverse elongation ASTMD4595-17 ≤120% Puncture strength ASTMD6241-14 ≥2000N 2KPa pressure thickness ASTM D5199-12 (2019) ≥9mm weight ASTM D5261-10 (2018) ≥1200g / m2 Dielectric constant ASTMD4491-21 ≥0.94s-1 Effective aperture ENISO12956 ≤0.06mm

[0031] The main body of the geotextile tube bag is stitched and sewn. To facilitate bag processing, the bag cloth should be wider. Nylon thread is used for stitching and sewing. The splicing is folded into three layers, with a width of about 5 to 10 cm. 35 three-strand nylon thread industrial sewing machines are used to sew three times (sew one first, fold and then sew two more times), and the stitching is required to be firm. The size of the geotextile bag after processing should meet the design requirements. Each bag should not have too many splicing seams, and the spacing between adjacent splicing seams should be greater than 2m.

[0032] The construction steps of the new geotube bag used for offshore cofferdam of the utility model are as follows:

[0033] Filling test: To ensure the quality of construction, a typical trial filling test is carried out on the beach before the official start of construction to obtain relevant parameters, such as filling sand concentration, filling pressure, slurry screen time, consolidation effect, etc., to guide the formal construction.

[0034] Leveling: Before the construction of geotube bag filling with sand, in order to ensure the flatness of the 7 layers of geotube bag, the original lower layer of geotextile should be leveled.

[0035] Ensure the accurate position of each layer of filling tube bags: Calculate the stacking edge of each layer of geobags according to the cross-sectional dimensions and bottom elevation of the filling tube bags. Use a total station or GPS to measure the edge position of the geobags and the center axis position of both ends of the bag when spreading the geobags. When laying the bottom layer and filling the tube bags underwater, insert or drive a φ63-φ75mm long steel pipe (the length of the steel pipe depends on the water depth) into the mud about 1 meter outside the perimeter of the bag body every 4-6 meters to fix the geobags when laying. During the bag laying construction, check the center axis of the cofferdam, the inner and outer edges, and the starting point of the geobags. If the tolerance exceeds the allowable deviation range, adjust it in time. After the filling tube bags are out of water, the center axis and edge of the upper filling bag can be directly marked on the lower filling bag with red paint to ensure the accurate position of each layer of filling tube bags.

[0036] Bag laying: The geotube bag should be unfolded during low tide. After unfolding, the four sides of the geotube bag are tied with ropes or 8# iron wires. The other end is made into a ring and buckled on the positioning steel pipe to prevent the empty geobag on the bamboo raft 6 from drifting and displacing due to waves or wind. After the filling tube bag is fixed, the position of the filling tube bag is re-measured and the filling geotube bag is checked to see if it is firmly fixed. In order to make the sand filling uniform and easy to fill, water can be added to the bag before filling the sand to put the empty geotube bag in place.

[0037] Geotube bag laying: The geotube bag body is required to be laid in the same position as the edge line. The upper and lower layers of the bag body should be staggered, and the staggered position should be more than 2m to avoid relative sliding of the bag body and the phenomenon of through gaps. The joints of adjacent geotube bags in the same layer should be reserved for shrinkage of 1 to 2m. When filling, fill the two ends first, and then fill in the overall direction of the filling to ensure that the two bags are squeezed tightly against each other after filling.

[0038] Build sand storage pits: arrange the sand storage pits 8 in the middle of the first layer of backfill sand on the seawall, with one sand pit every 250m. The sand pits are temporarily built with backfill sand, with a size of 10m×15m. Excavators are used to feed sand during the construction process. Construction water is pumped directly from the sea into the sand pits using a high-pressure water pump 10 through the laying of a water diversion pipe, and is pumped into the geotube bag through a sand delivery pipe using a sand pump for construction.

[0039] Filling geotextile tube bag: insert the plastic tube mouth of conveying sand into the cuff of geotextile tube bag and fill in sand. When filling, pay attention to timely adjust the direction of the conveying tube mouth, start from the four corners, and flush and irrigate evenly, check the position and shape in real time, if the position meets the requirements and the shape is not distorted, the tube bag can be filled normally. Use a sand pump 9 to fill from both ends to the middle, and check the filling flatness and fullness for each bag mouth. If it meets the requirements, fill the next bag mouth until it is completed. The tube bag arranges the drainage outlet reasonably at the longitudinal tube bag position according to the runoff of the backfill sand 11. The filling fullness and thickness should be controlled well, and the filling height of the geotextile tube bag should be controlled at an appropriate level. If the ideal height cannot be reached once during the filling process, wait for the geotextile tube bag to be slightly consolidated, and then fill it twice or more until the ideal filling height. The unevenness of the bag body affects the stability between bags, and the fullness is generally controlled at 85%. After filling, tie the cuffs tightly.

[0040] The filling pressure should be controlled within the range of 0.2-0.3 MPa. If the pressure is too low, the filling material is easy to settle, affecting the filling effect. If the pressure is too high, it is easy to cause the filling bag to burst.

[0041] Each geotube bag is filled according to the capacity of the filling bag, and the number of sand pumps and high-pressure water guns are pre-arranged to meet the construction progress requirements. When filling, fill in layers from bottom to top. Before the lower bag body is 70% filtered and solidified, another bag body should not be filled on it. The construction of the same cofferdam prism should be carried out in a step-by-step manner according to the progress direction.

Claims

1. A new type of geotextile tube bag for offshore cofferdam, characterized by: The invention comprises a geotextile tube bag body (3), a truss belt (1) and transverse reinforcement (4); the geotextile tube bag body (3) is formed into a tube by splicing and sewing woven fabric; the two ends of the geotextile tube bag body (3) are sewn into closed ends; truss belts (1) are arranged at intervals outside the geotextile tube bag body (3); transverse reinforcement (4) is arranged at intervals inside the geotextile tube bag body (3); the transverse reinforcement (4) is made of strip-shaped geotextile material, and the two ends are fixed to the opposite inner surfaces of the geotextile tube bag body (3); and the geotextile tube bag body (3) is sewn with filling ports (2) at intervals.

2. The novel geotube bag for offshore cofferdam according to claim 1 is characterized in that: The geotube bag body (3) has a length of 20 to 22 m, a height of 1.1 to 1.3 m, and a width of 2 to 2.2 m.

3. The novel geotube bag for offshore cofferdam according to claim 1 is characterized in that: Three to five tie bars are arranged at intervals of 7 m in the tube bag, and the length of the tie bars is 2 to 2.2 m, so as to control the width of the geotextile tube bag after the geotextile tube bag body (3) is filled, thereby ensuring the thickness of the geotextile tube bag.

4. The novel geotube bag for offshore cofferdam according to claim 1 is characterized in that: The ring tie belt (1) is a polyester woven belt or a high-strength geotextile woven belt, and is sewn on the outer surface of the geotube bag body (3) at intervals of 1.8 to 2.2 m.

5. The novel geotube bag for offshore cofferdam according to claim 1 is characterized by: The geotextile bag body (3) is made of high-strength geotextile with a unit area mass of 1200-1500 g / m 2 .

6. The novel geotube bag for offshore cofferdam according to claim 1 is characterized by: The transverse tensioning bars (4) and the circumferential tie bands (1) are staggered in the reverse positions along the length of the geotube bag body (3).

7. The novel geotube bag for offshore cofferdam according to claim 1 is characterized by: The filling port (2) has a diameter of 30 cm, and the distance between the filling ports (2) is 4 to 5 m.

8. The novel geotube bag for offshore cofferdam according to claim 1 is characterized by: A tightening positioning belt (5) is provided along the longitudinal direction of the outer surface of the geotextile tube bag body (3) to fix and connect the upper and lower geotextile tube bag bodies (3).