Large screw assembling and hoisting equipment

By using lifting rings, positioning rings and adjustment mechanisms to fix the screw spindle in screw assembly and hoisting equipment, synchronous transfer is achieved by combining pallets and hanging frames, and providing auxiliary positioning through positioning mechanisms, the problem of tilt fall off during screw assembly is solved, and the problem of tilt fall off during screw assembly is improved Safety and operational efficiency.

CN221971037UActive Publication Date: 2024-11-08HUANGSHAN HAINA INTELLIGENT MFG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420743984.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-11
Publication Date
2024-11-08
Estimated Expiration
2034-04-11

AI Technical Summary

Technical Problem

During the screw assembly process of screw pumps, the existing lifting method can easily cause the screw to tilt and fall off, causing safety hazards and equipment damage.

Method used

Large screw assembly hoisting equipment is adopted to fix the screw spindle through the lifting ring, positioning ring and adjustment mechanism, and synchronous transfer is achieved by combining the pallet and the hanging frame, and auxiliary positioning is provided through the positioning mechanism to improve the fixing effect of the screw.

Benefits of technology

It effectively avoids the tilt and fall off during the lifting process, improves safety, and simplifies the synchronous transfer process of multiple screws.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221971037U_ABST
    Figure CN221971037U_ABST
Patent Text Reader

Abstract

The utility model provides large screw assembling and hoisting equipment which comprises a hoisting assembly, the hoisting assembly comprises symmetrically-arranged hoisting ropes, hoisting hooks are fixed to the bottoms of the hoisting ropes and used for being connected with hoisting rings or a supporting plate in a hanging mode, the number of the hoisting rings is two, hoisting frames are fixed to the two ends of the supporting plate, and the longitudinal section of each hoisting frame is in an inverted V shape. The top of the hanging bracket extends to the position above the supporting plate. By arranging the hanging ring, the positioning rings and the adjusting mechanism, when the screw rod body is hoisted and transferred, the two positioning rings are respectively sleeved outside the main shafts at the two ends of the screw rod body, so that the propping pieces and the positioning rings are propped against the main shafts, and the two positioning rings can be respectively fixed with the main shafts at the two ends of the screw rod body; the positioning mode that a lifting rope is tied on a main shaft of the screw body is replaced, the fixing effect on the screw body is greatly improved, the situation that the screw body falls on the ground when inclining in the lifting process of the screw body is effectively avoided, and the lifting safety is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of hoisting equipment, in particular to large-scale screw rod assembly hoisting equipment. Background Art

[0002] The screw pump is a positive displacement rotor pump that relies on the volume change of the sealed chamber formed by the screw and the bushing to suck in and discharge the liquid. According to the number of screws, the screw pump is divided into single screw pump, double screw pump, triple screw pump and five screw pump. The characteristics of the screw pump are stable flow, small pressure pulsation, self-priming ability, low noise, high efficiency, long life and reliable operation; and its outstanding advantage is that it does not form eddy currents when conveying the medium, is not sensitive to the viscosity of the medium, and can convey high-viscosity media;

[0003] After the screw in the screw pump is processed, when it is assembled with the shell, it is necessary to use a crane to lift and transfer the screw to the assembly site for the screw pump to be assembled. At present, when lifting and transferring the screw, most of them are fixed by bolting the lifting rope to the main shaft at both ends of the screw, and then hanging the cloth belt by the hook of the crane, and then transferring. Although this method can lift and transfer the screw, it still has the following defects in actual use:

[0004] By tying the lifting rope to the main shaft of the screw, if the screw tilts during the screw lifting process, the main shaft at one end of the screw is easy to slip between the cloth belt, causing the screw to fall off and fall to the ground during the lifting process, causing damage to the screw, which is less safe;

[0005] Therefore, the present application proposes a large screw rod assembly hoisting device. Utility Model Content

[0006] In view of the deficiencies in the prior art, the utility model provides large-scale screw assembly and hoisting equipment, which solves the problems mentioned in the background technology.

[0007] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:

[0008] Large screw assembly hoisting equipment, including a hoisting assembly, the hoisting assembly includes symmetrically arranged hoisting ropes, a hook is fixed at the bottom of the hoisting rope, the hook is used to hang with a hoisting ring or a pallet, the number of the hoisting ring is two, and both ends of the pallet are fixed with a hanger, the longitudinal section of the hanger is an inverted V shape, and the top of the hanger extends above the pallet;

[0009] The upper surface of the support plate is provided with a plurality of limit grooves in a linear array, a screw body is placed in the limit groove, both ends of the screw body are fixed with a main shaft, an adjustment mechanism is installed on the lifting ring, a positioning ring is installed on the adjustment mechanism, and the positioning ring is used to be sleeved on the outside of the main shaft;

[0010] The adjusting mechanism is provided with a conflicting piece which can be connected with the main shaft, and the adjusting mechanism is used to make the conflicting piece and the positioning ring come into conflict with the main shaft.

[0011] Furthermore: the adjusting mechanism comprises an adjusting rod fixedly mounted on the lifting ring, the adjusting rod thread passes through the positioning ring, and the abutment is mounted on one end of the adjusting rod away from the lifting ring.

[0012] Furthermore: the resistance member includes a resistance block rotatably mounted on the end of the adjusting rod away from the lifting ring, and a rubber pad is fixed to the end of the resistance block away from the adjusting rod.

[0013] Furthermore: a rubber ring is fixedly installed on the inner side wall of the positioning ring, and the adjustment rod movably passes through the rubber ring.

[0014] Furthermore: a positioning mechanism acting on the main shaft is installed on the positioning ring, and the positioning mechanism is used to assist in positioning the main shaft.

[0015] Further: the positioning mechanism includes two positioning rods which are respectively threaded through the two sides of the positioning ring, one end of the positioning rod passes through the positioning ring and movably passes through the rubber ring, one end of the positioning rod passes through the positioning ring and is rotatably installed with a positioning plate, and a rubber pad 2 is fixedly installed on the positioning plate.

[0016] Further: positioning blocks are fixed on the support plate and on the outer sides of both ends of the plurality of limit grooves, a groove is provided on the top of the positioning block, a positioning ring can be placed in the groove, a through groove connected to the groove is provided at the bottom of the positioning block, and an adjusting rod can movably pass through the through groove.

[0017] Further: Plug holes are symmetrically provided on the support plate and below the plurality of limit grooves.

[0018] The utility model provides a large screw assembly hoisting device. Compared with the prior art, it has the following beneficial effects:

[0019] 1. By setting the lifting ring, the positioning ring and the adjusting mechanism, when the screw body is lifted and transferred, the two positioning rings are respectively sleeved on the outside of the main shaft at both ends of the screw body, so that the abutment and the positioning ring are in abutment with the main shaft, and the two positioning rings can be respectively fixed to the main shaft at both ends of the screw body, replacing the positioning method of bolting the lifting rope on the main shaft of the screw body, which greatly improves the fixing effect of the screw body, effectively avoids the situation that the screw body falls off and falls on the ground when it tilts during the lifting process of the screw body, and improves the lifting safety;

[0020] 2. By setting a pallet and a hanger, when in use, two hooks are used to hang the two hangers respectively, and the pallet can be hoisted and transferred by an external crane, so as to realize the simultaneous transfer of multiple screw bodies on the pallet, which is convenient for the synchronous transfer of multiple screw bodies;

[0021] 3. By setting a positioning mechanism, an auxiliary positioning effect of the main shaft is achieved, thereby achieving a further positioning effect on the positioning ring and the main shaft, and further improving the fixing effect of the screw body. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0023] Figure 1 A three-dimensional structural schematic diagram of the utility model is shown;

[0024] Figure 2 The utility model is shown Figure 1 The enlarged view of point A in the middle;

[0025] Figure 3 A schematic diagram of the connection structure between the positioning ring and the positioning block of the utility model is shown;

[0026] Figure 4 A schematic diagram of the installation structure of the positioning mechanism of the utility model is shown;

[0027] As shown in the figure: 1. lifting assembly; 11. lifting rope; 12. lifting hook; 2. lifting ring; 3. supporting plate; 31. hanging bracket; 32. limiting groove; 33. socket; 4. screw body; 41. main shaft; 5. adjusting mechanism; 51. adjusting rod; 6. positioning ring; 61. rubber ring; 7. resistance; 71. resistance block; 72. rubber pad 1; 8. positioning mechanism; 81. positioning rod; 82. positioning plate; 83. rubber pad 2; 9. positioning block; 91. groove; 92. through groove. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solution and advantages of the embodiments of the utility model clearer, the technical solution in the embodiments of the utility model is described clearly and completely. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0029] Embodiment 1

[0030] In order to solve the technical problems in the background technology, the following large screw assembly hoisting equipment is provided:

[0031] Combination Figure 1-Figure 4 As shown, the large screw assembly hoisting equipment provided by the utility model includes a hoisting assembly 1, and the hoisting assembly 1 includes symmetrically arranged hoisting ropes 11, and a hook 12 is fixed to the bottom of the hoisting rope 11. It is worth noting that the top of the hoisting rope 11 is connected to the external driving, and the hook 12 is used to hang with the hoisting ring 2 or the support plate 3. The number of the hoisting ring 2 is two, and both ends of the support plate 3 are fixed with a hanger 31. The longitudinal section of the hanger 31 is an inverted V shape, and the top of the hanger 31 extends to the support plate 3. The upper surface of the support plate 3 is provided with a plurality of limit grooves 32 in a linear array, a screw body 4 is placed in the limit grooves 32, both ends of the screw body 4 are fixed with a main shaft 41, an adjusting mechanism 5 is installed on the lifting ring 2, a positioning ring 6 is installed on the adjusting mechanism 5, and the positioning ring 6 is used to be sleeved on the outside of the main shaft 41; a resistance member 7 connectable to the main shaft 41 is installed on the adjusting mechanism 5, and the adjusting mechanism 5 is used to make the resistance member 7 and the positioning ring 6 form a resistance with the main shaft 41.

[0032] By setting the lifting ring 2, the positioning ring 6 and the adjusting mechanism 5, when the screw body 4 is lifted and transferred, the two positioning rings 6 are respectively sleeved on the outside of the main shaft 41 at both ends of the screw body 4, and the main shaft 41 is located on the side of the abutment 7 away from the adjusting mechanism 5, and then the abutment 7 and the positioning ring 6 are both abutted against the main shaft 41 through the adjusting mechanism 5, so that the two positioning rings 6 can be fixed to the main shaft 41 at both ends of the screw body 4, and at this time, the two hooks 12 are respectively hung on the two lifting rings 2, and the screw body 4 can be lifted and transferred. The positioning method of bolting the screw body 4 on the main shaft 41 by a lifting rope greatly improves the fixing effect of the screw body 4, effectively avoids the situation that the screw body 4 falls off and falls to the ground when it tilts during the lifting of the screw body 4, and improves the lifting safety; by setting the support plate 3 and the hanger 31, when in use, two hooks 12 are used to hang with the two hangers 31 respectively, and the support plate 3 can be lifted and transferred by an external crane, thereby realizing the simultaneous transfer of multiple screw bodies 4 on the support plate 3, which is convenient for the synchronous transfer of multiple screw bodies 4.

[0033] Embodiment 2

[0034] like Figure 1-Figure 4 As shown, based on the above embodiment, this embodiment further provides the following contents:

[0035] In this embodiment, the adjusting mechanism 5 includes an adjusting rod 51 fixedly installed on the lifting ring 2, and the adjusting rod 51 is threaded through the positioning ring 6. The resistance member 7 is installed at the end of the adjusting rod 51 away from the lifting ring 2. When the resistance member 7 and the positioning ring 6 both form a resistance with the main shaft 41, a force is applied to the lifting ring 2 to make it rotate around the adjusting rod 51, so that the adjusting rod 51 can be spirally moved on the positioning ring 6, driving the resistance member 7 to move along the adjusting rod 51 toward the main shaft 41, so that the resistance member 7 forms a resistance with the main shaft 41, and the positioning ring 6 and the main shaft 41 can be fixed, which is simple to operate.

[0036] In this embodiment, the abutment 7 comprises an abutment block 71 rotatably mounted on the end of the adjusting rod 51 away from the lifting ring 2, and a rubber pad 72 is fixed to the end of the abutment block 71 away from the adjusting rod 51. By applying a force to the lifting ring 2, the adjusting rod 51 is spirally moved on the positioning ring 6, and the abutment block 71 can be driven to move toward the main shaft 41, so that the rubber pad 72 is in conflict with the main shaft 41, so that the rubber pad 72 and the positioning ring 6 are in conflict with the main shaft 41, and the positioning ring 6 and the main shaft 41 are in conflict. The rubber pad 72 is provided so that the rubber pad 72 is in contact with the main shaft 41, and when the adjusting rod 51 rotates on the positioning ring 6, the friction between the rubber pad 72 and the main shaft 41 on the surface of the main shaft 41 is effectively avoided. By providing the rubber pad 72, the rubber pad 72 is in contact with the main shaft 41, and the wear on the surface of the main shaft 41 caused by the hard contact between the friction block 71 and the main shaft 41 is effectively avoided.

[0037] In this embodiment, a rubber ring 61 is fixedly installed on the inner wall of the positioning ring 6, and the adjusting rod 51 movably passes through the rubber ring 61. By setting the rubber ring 61, when the positioning ring 6 and the main shaft 41 form a conflict, the main shaft 41 and the rubber ring 61 form a conflict, which effectively avoids the hard contact between the main shaft 41 and the positioning ring 6 to prevent the surface of the main shaft 41 from being worn.

[0038] In this embodiment, a positioning mechanism 8 acting on the main shaft 41 is installed on the positioning ring 6. The positioning mechanism 8 is used to assist in positioning the main shaft 41. By setting the positioning mechanism 8, an auxiliary positioning effect of the main shaft 41 is achieved, thereby achieving a further positioning effect on the positioning ring 6 and the main shaft 41, and further improving the fixing effect of the screw body 4.

[0039] Embodiment 3

[0040] like Figure 1-Figure 4 As shown, based on the above embodiment, this embodiment further provides the following contents:

[0041] In this embodiment, the positioning mechanism 8 includes two positioning rods 81 that are respectively threaded through the two sides of the positioning ring 6. One end of the positioning rod 81 passes through the positioning ring 6 and movably passes through the rubber ring 61. One end of the positioning rod 81 passes through the positioning ring 6 and is rotatably installed with a positioning plate 82. A rubber pad 83 is fixedly installed on the positioning plate 82. When in use, the two positioning rods 81 are rotated to make the two positioning rods 81 spirally move on the positioning ring 6 respectively, so that the two positioning plates 82 are displaced toward the direction of the main shaft 41, so that the two rubber pads 83 are both in contact with the main shaft 41, thereby achieving an auxiliary positioning effect on the main shaft 41.

[0042] In this embodiment, positioning blocks 9 are fixed on the support plate 3 and on the outer sides of both ends of the plurality of limiting grooves 32, and a groove 91 is provided on the top of the positioning block 9. It is worth noting that when the screw body 4 is placed in the limiting groove 32, the spindles 41 at both ends of the screw body 4 are respectively located in the grooves 91 on the tops of the two positioning blocks 9, and the positioning ring 6 can be placed in the groove 91. A through groove 92 connected to the groove 91 is provided at the bottom of the positioning block 9, and the adjusting rod 51 can movably penetrate the through groove 92. By setting the positioning block 9 and the through groove 92. When in use, the two positioning rings 6 can be respectively sleeved on the outside of the main shaft 41 at both ends of the screw body 4, so that the adjusting rod 51 passes through the through groove 92 on the positioning block 9, and the adjusting rod 51 threadedly passes through the positioning ring 6, so that the rubber pad 72 is in conflict with the main shaft 41, so that the rubber pad 72 and the positioning ring 6 are in conflict with the main shaft 41, thereby achieving the positioning effect between the positioning block 9 and the screw body 4, and effectively avoiding the situation that the screw body 4 slips out of the limiting groove 32 and falls when the pallet 3 is suspended and transferred.

[0043] In this embodiment, insertion holes 33 are symmetrically provided on the pallet 3 and below the plurality of limit grooves 32. By symmetrically providing the insertion holes 33 on the pallet 3, when transferring the plurality of screw bodies 4 on the pallet 3, two fork plates of a forklift can be respectively inserted into the two insertion holes 33, so that the pallet 3 can be transferred by a forklift, which facilitates the transfer of the plurality of screw bodies 4.

[0044] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0045] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. Large screw assembly hoisting equipment, characterized by: The lifting assembly (1) comprises a lifting rope (11) arranged symmetrically, a lifting hook (12) being fixed at the bottom of the lifting rope (11), the lifting hook (12) being used for hanging with a lifting ring (2) or a supporting plate (3), the number of the lifting rings (2) being two, and a hanging bracket (31) being fixed at both ends of the supporting plate (3), the longitudinal section of the hanging bracket (31) being in an inverted V shape, and the top of the hanging bracket (31) extending above the supporting plate (3); The upper surface of the support plate (3) is provided with a plurality of limit grooves (32) in a linear array, a screw body (4) is placed in the limit groove (32), both ends of the screw body (4) are fixed with a main shaft (41), an adjustment mechanism (5) is installed on the lifting ring (2), a positioning ring (6) is installed on the adjustment mechanism (5), and the positioning ring (6) is used to be sleeved on the outside of the main shaft (41); The adjusting mechanism (5) is provided with a resisting member (7) which can be connected to the main shaft (41). The adjusting mechanism (5) is used to make the resisting member (7) and the positioning ring (6) both contact the main shaft (41).

2. The large screw rod assembly and hoisting equipment according to claim 1 is characterized in that: The adjusting mechanism (5) comprises an adjusting rod (51) fixedly mounted on the lifting ring (2), wherein the adjusting rod (51) is threadedly passed through the positioning ring (6), and the abutment member (7) is mounted on an end of the adjusting rod (51) away from the lifting ring (2).

3. The large screw rod assembly and hoisting equipment according to claim 2 is characterized in that: The resisting member (7) comprises a resisting block (71) rotatably mounted on the end of the adjusting rod (51) away from the lifting ring (2); a rubber pad (72) is fixed to the end of the resisting block (71) away from the adjusting rod (51).

4. The large screw rod assembly and hoisting equipment according to claim 3 is characterized in that: A rubber ring (61) is fixedly mounted on the inner side wall of the positioning ring (6), and the adjusting rod (51) movably passes through the rubber ring (61).

5. The large screw rod assembly and hoisting equipment according to claim 1 is characterized in that: The positioning ring (6) is provided with a positioning mechanism (8) acting on the main shaft (41), and the positioning mechanism (8) is used for assisting the positioning of the main shaft (41).

6. The large screw rod assembly and hoisting equipment according to claim 5 is characterized in that: The positioning mechanism (8) comprises two positioning rods (81) respectively threadedly penetrating two sides of the positioning ring (6); one end of the positioning rod (81) penetrating the positioning ring (6) movably penetrates the rubber ring (61); one end of the positioning rod (81) penetrating the positioning ring (6) is rotatably mounted with a positioning plate (82); and a second rubber pad (83) is fixedly mounted on the positioning plate (82).

7. The large screw rod assembly and hoisting equipment according to claim 2 is characterized in that: Positioning blocks (9) are fixed on the support plate (3) and located at the outer sides of both ends of the plurality of limiting grooves (32); a groove (91) is provided on the top of the positioning block (9); the positioning ring (6) can be placed in the groove (91); a through groove (92) connected to the groove (91) is provided on the bottom of the positioning block (9); and the adjusting rod (51) can movably pass through the through groove (92).

8. The large screw rod assembly and hoisting equipment according to claim 7 is characterized in that: Insertion holes (33) are symmetrically provided on the support plate (3) and below the plurality of limit slots (32).