Combination template device for building base layer

By designing a rapidly splicing-based building base formwork device, the problems of difficulty in dismantling existing formwork and low construction efficiency are solved, and the effect of rapid installation and cost reduction is achieved.

CN221973006UActive Publication Date: 2024-11-08SHANGHAI HENGSHUO DECORATION DESIGN ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322897814.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-27
Publication Date
2024-11-08
Estimated Expiration
2033-10-27

AI Technical Summary

Technical Problem

The existing building base-level combined formwork is difficult to dismantle during construction and requires a lot of labor and time, resulting in inefficient construction and increased costs.

Method used

A template device including base assembly, planar splicing assembly and spacer splicing assembly was designed. Through the structural design of the clamps and connection holes, the components can be prepared in advance in the factory and spliced ​​quickly on site, simplifying the installation process and reducing the Disassembly required.

Benefits of technology

It greatly shortens the construction cycle and labor costs, reduces the construction difficulty, avoids later demolition work, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221973006U_ABST
    Figure CN221973006U_ABST
Patent Text Reader

Abstract

The utility model discloses a combined formwork device for a building base layer. The combined formwork device comprises a base assembly, a plane splicing assembly and an interval splicing assembly, wherein the plane splicing assembly and the interval splicing assembly are matched with the base assembly. The interval splicing assembly comprises an interval splicing body, the two ends of the interval splicing body are fixedly connected with a first clamping clamp and a second clamping clamp respectively, and the first clamping clamp and the second clamping clamp are the same in structure. The first clamping clip comprises a first clamping strip and a second clamping strip which are arranged in parallel at an interval, the first clamping strip and the second clamping strip are the same in structure, the first clamping strip comprises a straight rod section and a clamping section integrally connected with the straight rod section, and the outer surface of the clamping section is of an arc-shaped structure; and the outer surface of the clamping section protrudes out of the plane of the straight rod section. According to the utility model, the installation is convenient, the possibility of various types of splicing in site construction is realized, the construction period is greatly shortened, the labor cost is greatly reduced, the splicing does not need related technical requirements of workers, and the construction difficulty is greatly reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of templates, in particular to a combined template device for building bases. Background Art

[0002] Due to the rapid development of the domestic economy, large-scale high-rise buildings have increased dramatically, and most of them are reinforced concrete structures. Therefore, speeding up the efficiency of cast-in-place construction of reinforced concrete structures of large-scale high-rise buildings has become an urgent issue to be solved in construction. At present, combined formwork is usually used in construction to improve the efficiency of cast-in-place construction of reinforced concrete structures. However, the existing formworks are all made of wood and need to be disassembled after pouring. Some formworks cannot be disassembled quickly, and many formworks need to be made now and then spliced, which cannot shorten the construction period and requires more manpower, increasing costs. Utility Model Content

[0003] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a composite formwork device for building base. In order to achieve the above-mentioned purpose and other advantages according to the present invention, a composite formwork device for building base is provided, comprising:

[0004] A base assembly and a plane splicing assembly and a spacing splicing assembly that match the base assembly;

[0005] The interval splicing assembly includes an interval splicing body, and two ends of the interval splicing body are respectively fixed with a first clamping clip and a second clamping clip, and the first clamping clip and the second clamping clip have the same structure;

[0006] The first clamping clip includes a first clamping strip and a second clamping strip spaced apart and arranged parallel to the first clamping strip. The first clamping strip and the second clamping strip have the same structure, and the first clamping strip includes a straight rod section and a clamping section integrally connected to the straight rod section. The outer surface of the clamping section is an arc-shaped structure, and the outer surface of the clamping section protrudes from the plane of the straight rod section.

[0007] Preferably, the base assembly comprises a base body, at least one structural through hole is opened in the middle portion of the base body, and at least one connecting hole is respectively arranged on both sides of the structural through hole;

[0008] A first connecting through hole is provided on one side of the structural through hole, a second connecting through hole is provided on the other side, and a third connecting hole is provided on one side of the second connecting through hole;

[0009] The first connecting through hole, the second connecting through hole and the third connecting hole all extend along the length direction of the base body.

[0010] Preferably, the plane splicing assembly comprises a plane splicing body, at least one first structural through hole is opened in the middle of the plane splicing body, and at least one clamping through hole is respectively arranged on both sides of the first structural through hole;

[0011] A first clamping through hole and a second clamping through hole are disposed on one side of the first structural through hole, and a first clamping through hole and a clamping clip are disposed on the other side of the first structural through hole;

[0012] The clamping clip, the first structural through hole, the first clamping through hole and the second clamping through hole all extend along the length direction of the plane splicing body, and the structure of the clamping clip is the same as that of the first clamping clip.

[0013] Preferably, the first snap-fit ​​clip or the second snap-fit ​​clip can match the first connecting through hole, the second connecting through hole or the third connecting hole.

[0014] Preferably, the first snap-in clip or the second snap-in clip can match the first snap-in through hole or the second snap-in through hole.

[0015] Preferably, the base assembly, the plane splicing assembly and the interval splicing assembly can be selected to have appropriate lengths according to actual use.

[0016] Compared with the prior art, the utility model has the following beneficial effects: through the arrangement of the first snap-in clip, the second snap-in clip and the snap-in clip, the plane splicing components, the interval splicing components and the base components can be mutually selected for installation and matching, which greatly facilitates installation convenience and the possibility of multiple splicing possibilities in on-site construction. The interval splicing components can be spliced ​​on-site with the plane splicing components or the interval splicing components respectively. The plane splicing components, the interval splicing components and the base components are prepared in advance in the factory according to the on-site construction requirements, and only workers are required to splice them on-site, which greatly shortens the construction period and labor costs. The splicing does not require workers to have relevant technical requirements, which greatly reduces the difficulty of construction. There is no need to dismantle the plane splicing components, the interval splicing components and the base components at a later stage. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a structural schematic diagram of the interval splicing assembly used for the building base composite formwork device according to the utility model;

[0018] Figure 2 It is a structural schematic diagram of two structural through holes of a base assembly used for a building base composite formwork device according to the utility model;

[0019] Figure 3 It is a structural schematic diagram of a structural through hole of a base assembly used for a building base composite formwork device according to the utility model;

[0020] Figure 4It is a structural schematic diagram of a plurality of structural through holes and a second connecting through hole of a base assembly for a building base composite formwork device according to the utility model;

[0021] Figure 5 It is a structural schematic diagram of a plane splicing assembly for a building base composite formwork device according to the utility model;

[0022] Figure 6 It is a structural schematic diagram of a plurality of first structural through holes of a plane splicing component used for a building base composite formwork device according to the utility model. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] Reference Figure 1-6 A composite formwork device for building base layers comprises: a base assembly and a plane splicing assembly and an interval splicing assembly matched with the base assembly; the interval splicing assembly comprises an interval splicing body 30, and the two ends of the interval splicing body 30 are respectively fixed with a first clamping clip 31 and a second clamping clip 32, and the first clamping clip 31 and the second clamping clip 32 have the same structure; the first clamping clip 31 comprises a first clamping strip and a second clamping strip spaced and arranged in parallel with the first clamping strip, the first clamping strip and the second clamping strip have the same structure, and the first clamping strip comprises a straight rod section and a clamping section integrally connected to the straight rod section, the outer surface of the clamping section is an arc-shaped structure, and the outer surface of the clamping section protrudes from the plane of the straight rod section. By setting the first clamp 31 and the second clamp 32, the interval splicing components can be spliced ​​on-site with the plane splicing components or the interval splicing components respectively. The plane splicing components, the interval splicing components and the base components are prepared in the factory in advance according to the on-site construction requirements, and only workers are needed to splice them on-site, which greatly shortens the construction period and labor costs. The splicing does not require workers to have relevant technical requirements, which greatly reduces the difficulty of construction, and there is no need to dismantle the plane splicing components, the interval splicing components and the base components in the later stage, unlike the wooden formwork that needs to be dismantled in the later stage.

[0025] Furthermore, the base assembly includes a base body 10, wherein at least one structural through hole 11 is provided at the middle portion of the base body 10, and at least one connecting hole is provided on both sides of the structural through hole 11;

[0026] A first connecting through hole 12 is provided on one side of the structural through hole 11, and a second connecting through hole 14 is provided on the other side. A third connecting hole 13 is provided on one side of the second connecting through hole 14.

[0027] The first connecting through hole 12, the second connecting through hole 14 and the third connecting hole 13 all extend along the length direction of the base body 10. By providing a plurality of connecting holes, the base structure can be connected to the plane splicing structure and the spaced splicing assembly through the connecting holes, and the base structure can be divided into multiple sections. According to the needs of current construction, corresponding connecting holes can be opened on the base body 10.

[0028] The first connection hole 12 is located at one end of the base body 10, and the third connection hole 13 is located at the other end of the base body 10, and the base body 10 has a first connection hole 12 at one end and a third connection hole 13 at the other end. By providing the third connection hole 13, the base structure can be spliced ​​with the plane splicing structure and the interval splicing assembly through the third connection hole 13, and the length of the base structure is lengthened. Moreover, according to the needs of the site, the length of the base structure can be determined in advance, and the on-site splicing can be performed. An opening is provided on the third connection hole 13 and the first connection hole 12, and the opening of the third connection hole 13 is located on the side of the end, and the opening of the first connection hole 12 is located on the side adjacent to the opening of the third connection hole 13. The opening of the second connection hole 14 is located on a side surface opposite to the opening of the first connection hole 12, or the opening of the second connection hole 14 is located on the same side surface as the opening of the first connection hole 12, and at least one second connection hole 14 is provided on one side surface of the base body 10. By opening connection holes on both sides of the base body 10, the two surfaces of the base body 10 can be divided to meet more on-site needs. Moreover, the structure only needs to be spliced ​​and installed on-site, and no technical requirements are required for workers, which greatly improves the construction effect of workers. Moreover, the base structure does not need to be disassembled later, which further saves labor costs and reduces the construction cycle.

[0029] Furthermore, the second connection through hole 14 is disposed adjacent to the third connection through hole 13 and the first connection through hole 12 , and the structures of the first connection through hole 12 , the second connection through hole 14 and the third connection through hole 13 are all different.

[0030] Furthermore, the plane splicing assembly includes a plane splicing body 20, at least one first structure through hole 21 is opened in the middle of the plane splicing body 20, and at least one clamping through hole is respectively provided on both sides of the first structure through hole 21;

[0031] A first clamping through hole 24 and a second clamping through hole 22 are disposed on one side of the first structural through hole 21, and a first clamping through hole 24 and a clamping clip 23 are disposed on the other side of the first structural through hole 21;

[0032] The clamping clip 23, the first structural through hole 21, the first clamping through hole 24 and the second clamping through hole 22 all extend along the length direction of the plane splicing body 20, and the clamping clip 23 has the same structure as the first clamping clip 31. By setting a plurality of clamping through holes, the plane splicing structure can be conveniently spliced ​​with other structures, which greatly reduces the technical requirements of the construction personnel and shortens the construction period.

[0033] The clamping clip 23 is located at one end of the planar splicing body 20 , and the second clamping through hole 22 is located at the other end of the planar splicing body 20 .

[0034] Furthermore, both the first card-connection hole 24 and the second card-connection hole 22 have an opening, the opening of the second card-connection hole 22 is located on the side of the end, and the opening of the first card-connection hole 24 is located on the side adjacent to the opening of the second card-connection hole 22. The first card-connection hole 24 includes a first make way interval 241 and a second make way interval 242 connected to the first make way interval 241; the second card-connection hole 22 includes a third make way interval 241 and a fourth make way interval 242 connected to the third make way interval 241. The card-connection clip 23 can be inserted into the first card-connection hole 24 and the second card-connection hole 22, and the card-connection clip 23 is limited in its degree of freedom in a direction perpendicular to the length direction of the plane splicing body 20 by the first make way interval 241 and the third make way interval 241. The planar splicing structure can be matched with the second snap-in through hole 22 of another planar splicing structure through the snap-in clip 23, so that the planar splicing structures can be spliced ​​on site to achieve the required length, and the planar splicing structure can also be spliced ​​and assembled on site with other structures through the snap-in through hole, so that there is no requirement for workers to have installation technology, and there is no need to disassemble the planar splicing structure after the construction is completed, which greatly shortens the construction period and further reduces the cost of workers.

[0035] Further, the first snap-on clip 31 or the second snap-on clip 32 can match the first connection through hole 12, the second connection through hole 14 or the third connection hole 13. The first snap-on clip 31 or the second snap-on clip 32 can match the first connection through hole 24 or the second connection through hole 22. Through the arrangement of the first snap-on clip 31, the second snap-on clip 32 and the snap-on clip 23, the plane splicing components, the interval splicing components and the base components can be mutually selected for installation and matching, which greatly facilitates the installation convenience and the possibility of multiple splicing in on-site construction.

[0036] Furthermore, the base assembly, the plane splicing assembly and the interval splicing assembly can be selected to have appropriate lengths according to actual use.

[0037] The number of devices and processing scale described here are used to simplify the description of the utility model. The application, modification and variation of the utility model are obvious to those skilled in the art.

[0038] Although the implementation scheme of the utility model has been disclosed as above, it is not limited to the applications listed in the specification and implementation scheme. It can be fully applied to various fields suitable for the utility model. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the utility model is not limited to the specific details and the illustrations shown and described here.

Claims

1. A composite formwork device for building base, It is characterized in that include: A base assembly and a plane splicing assembly and a spacing splicing assembly that match the base assembly; The interval splicing assembly comprises an interval splicing body (30), and the two ends of the interval splicing body (30) are respectively fixedly connected with a first clamping clip (31) and a second clamping clip (32), and the first clamping clip (31) and the second clamping clip (32) have the same structure; The first clamping clip (31) comprises a first clamping strip and a second clamping strip which are spaced apart from and arranged in parallel with the first clamping strip, the first clamping strip and the second clamping strip having the same structure, and the first clamping strip comprises a straight rod section and a clamping section connected to the straight rod section in an integral manner, the outer surface of the clamping section presents an arc-shaped structure, and the outer surface of the clamping section protrudes from the plane of the straight rod section.

2. A composite formwork device for building base as claimed in claim 1, It is characterized in that The base assembly comprises a base body (10), wherein at least one structural through hole (11) is provided at a middle portion of the base body (10), and at least one connecting hole is respectively provided on both sides of the structural through hole (11); A first connecting through hole (12) is provided on one side of the structural through hole (11), a second connecting through hole (14) is provided on the other side, and a third connecting hole (13) is provided on one side of the second connecting through hole (14); The first connecting through hole (12), the second connecting through hole (14) and the third connecting hole (13) all extend along the length direction of the base body (10).

3. A composite formwork device for building base as claimed in claim 2, It is characterized in that The plane splicing assembly comprises a plane splicing body (20), wherein at least one first structural through hole (21) is provided at the middle portion of the plane splicing body (20), and at least one clamping through hole is provided on both sides of the first structural through hole (21); A first clamping through hole (24) and a second clamping through hole (22) are provided on one side of the first structural through hole (21), and a first clamping through hole (24) and a clamping clip (23) are provided on the other side of the first structural through hole (21); The snap-fit ​​clip (23), the first structural through hole (21), the first snap-fit ​​through hole (24) and the second snap-fit ​​through hole (22) all extend along the length direction of the planar splicing body (20), and the snap-fit ​​clip (23) has the same structure as the first snap-fit ​​clip (31).

4. A composite formwork device for building base as claimed in claim 3, It is characterized in that The first snap-fit ​​clip (31) or the second snap-fit ​​clip (32) can match the first connecting through hole (12), the second connecting through hole (14) or the third connecting hole (13).

5. A composite formwork device for building base as claimed in claim 4, It is characterized in that The first snap-on clip (31) or the second snap-on clip (32) can match the first snap-on through hole (24) or the second snap-on through hole (22).

6. A composite formwork device for building base as claimed in claim 1, It is characterized in that The base component, the plane splicing component and the interval splicing component can be selected to have appropriate lengths according to actual use.