Feeding and deslagging system of biomass chain boiler
By designing the feeding and slag discharge system of biomass chain boiler, using the cooperation of external hoppers, furnace hoppers and sensors, automatic feeding is achieved, reducing the working strength of the furnace driver and improving the slag discharge efficiency, and solving the problem of the existing technology. The problem of high labor intensity and time-consuming and labor-intensive production of slag during the material process.
Patent Information
- Application Number
- CN202420522570.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-03-18
AI Technical Summary
During the loading process of existing biomass chain boilers, the furnace body hopper is small, resulting in high working density, high labor intensity, easy fatigue and safety hazards; the existing slag production system is divided into multiple parts and requires manual cleaning. , time-consuming and labor-intensive.
A feeding and slag discharge system for biomass chain boilers is designed, including external hoppers, furnace body hoppers, feeding and conveying mechanisms, feeding mechanisms, furnace body chain conveying mechanisms, ceramic multi-tube dust collectors and air box pulse bag dust removal Through the cooperation of sensors and electrical control boxes, the automatic loading and centralized slag production processing are realized.
It reduces the working intensity of the furnace driver, avoids the occurrence of fatigue and safety accidents at night operations, and improves the working efficiency of slag output, realizing automated and centralized feeding and slag output treatment.
Smart Images

Figure CN221975300U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of heating equipment, and in particular relates to a feeding and slag discharging system of a biomass chain boiler. Background Art
[0002] A boiler is an energy conversion device. The energy input to the boiler includes chemical energy and electrical energy in the fuel. The boiler outputs steam, high-temperature water or organic heat carrier with a certain amount of thermal energy. The boiler is divided into two parts: a "pot" and a "furnace". The "pot" is a pressurized component that holds water and steam, and heats, vaporizes and separates the water. The "furnace" is a place where fuel combustion or other heat release is carried out. It has combustion equipment, a combustion chamber, a furnace, and a heat-releasing flue. The pot and the furnace are both undergoing a heat conversion process. The interface between heat release and heat absorption is called the heating surface. In addition to the pot and the furnace, there are also auxiliary equipment such as frames, platforms, escalators, combustion, slag discharge, smoke and air ducts, pipelines, and furnace walls.
[0003] In the prior art, during the charging process of the biomass chain boiler, since the furnace hopper of the chain grate is small, it is necessary to frequently add fuel to the furnace hopper. The boiler operator has a high work density and labor intensity, and is easily fatigued when working at night, which can easily cause safety accidents. In addition, the existing slag discharge system is divided into chain furnace slag discharge, ceramic multi-tube dust collector slag discharge, and air box pulse bag dust collector slag discharge. The three slags are discharged on site and then manually cleaned to the ash pile, which is time-consuming and labor-intensive. Utility Model Content
[0004] The purpose of the utility model is to provide a feeding and slag discharging system for a biomass chain boiler to solve the technical problems raised in the above background technology.
[0005] In order to achieve the above technical purpose, the technical solution of the utility model is:
[0006] A feeding and slag discharging system for a biomass chain boiler, comprising a boiler body and an electric control box, a feeding mechanism is provided on one side of the boiler body, and a slag discharging mechanism, a ceramic multi-tube dust collector and an air box pulse bag dust collector are provided on the other side, the feeding mechanism comprises an external hopper and a furnace body hopper, a feeding conveying mechanism is provided below the external hopper, an end of the feeding conveying mechanism away from the external hopper extends to the top of the furnace body hopper, a second sensor is provided on the top side of the furnace body hopper, a first sensor is provided on the bottom side of the furnace body hopper, and a material-discharging mechanism is provided on the rotation of the lower part of the furnace body hopper;
[0007] The slag discharge mechanism comprises a furnace chain conveying mechanism, a furnace ash collecting hopper is provided at a position of the boiler close to the end of the chain conveying mechanism, and a auger conveyor is provided below the furnace ash collecting hopper;
[0008] A slag conveying mechanism is provided below the ceramic multi-tube dust collector and the air box pulse bag dust collector, and the end of the auger conveyor away from the furnace ash hopper is connected to the slag conveying mechanism, and an ash storage yard is provided at the end of the slag conveying mechanism away from the auger conveyor.
[0009] As an improvement, a fixed baffle is fixedly provided on the upper part of the furnace hopper, a sliding baffle is slidably provided on the lower part of one side of the fixed baffle, and an adjustment handle is connected to the top of the sliding baffle;
[0010] The material-discharging mechanism comprises a material-discharging roller rotatably arranged below the sliding baffle, a support rod is arranged below the material-discharging roller, an arc-shaped groove is fixedly connected to the top surface of the support rod, and the bottom of the arc-shaped groove is fixedly connected to the side wall of the furnace body hopper.
[0011] As a further improvement, a channel steel is provided at the lower part of the external hopper, and the channel steel is located above the blanking opening of the external hopper. A third sensor is provided at the bottom of the external hopper, and the third sensor is located between the channel steel and the blanking opening of the external hopper.
[0012] The electric control box is linked with the first sensor, the second sensor, the third sensor and the feeding and conveying mechanism by electrical signals.
[0013] As a further improvement, an auger ash inlet is provided on the top surface of one end of the auger conveyor, and the auger ash inlet is connected to the furnace body ash hopper. An auger ash outlet is provided on the bottom surface of the other end of the auger conveyor, and the auger ash outlet is located above the slag conveying mechanism.
[0014] As a further improvement, the slag conveying mechanism is arranged to be inclined upward at one end close to the ash dump.
[0015] As a further improvement, a first material distributor is provided at the bottom of the ceramic multi-tube dust collector, and a second material distributor is provided at the bottom of the air box pulse bag dust collector.
[0016] As a further improvement, the electric control box is connected to the auger conveyor, the first material feeder, the second material feeder and the slag conveying mechanism via electrical signals.
[0017] Due to the adoption of the above technical solution, the beneficial effects of the utility model are:
[0018] The feeding and slag discharging system of the biomass chain boiler provided by the utility model and the setting of the feeding mechanism reduce the work intensity of the boiler operator, so that the boiler operator does not need to add fuel to the equipment all the time, avoids the situation that the boiler operator is prone to fatigue during nighttime operation, and thus avoids the occurrence of safety accidents; the setting of the slag discharging mechanism combines the slag discharging of the boiler furnace body, the slag discharging of the ceramic multi-tube dust collector and the slag discharging of the air box pulse bag dust collector together, without the need to discharge the slag separately, thereby improving the slag discharging work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of the utility model;
[0020] Figure 2 It is a structural diagram of the feeding mechanism;
[0021] Figure 3 It is a schematic diagram of the internal structure of the external hopper;
[0022] Figure 4 It is a schematic diagram of the internal structure of the furnace hopper;
[0023] Figure 5 It is a structural schematic diagram of the slag discharge mechanism;
[0024] Figure 6 It is a structural diagram of the auger conveyor;
[0025] Figure 7 It is a structural schematic diagram of a ceramic multi-tube dust collector;
[0026] Figure 8 It is a schematic diagram of the structure of the air box pulse bag dust collector;
[0027] Fig. 9 It is a schematic diagram of the structure of the ash dump;
[0028] Among them: 1- boiler furnace body; 11- furnace body hopper; 12- material discharging mechanism; 121- material discharging roller; 122- support rod; 123- arc groove; 13- first sensor; 14- second sensor; 15- fixed baffle; 16- sliding baffle; 17- adjustment handle; 18- furnace body chain conveying mechanism; 19- furnace body ash collecting hopper; 2- external hopper; 21- channel steel; 22- third sensor; 3- feeding conveying mechanism; 4- auger conveyor; 5- ceramic multi-tube dust collector; 51- first material discharging device; 6- air box pulse bag dust collector; 61- second material discharging device; 7- slag conveying mechanism; 8- ash dump. DETAILED DESCRIPTION
[0029] The present invention is further described below in conjunction with the specific implementation methods and the accompanying drawings. The accompanying drawings are only for illustrative purposes and are only schematic diagrams, not actual drawings, and should not be construed as limiting the present application. In order to better illustrate the embodiments of the present invention, some parts of the accompanying drawings may be omitted, enlarged, or reduced, and do not represent the size of the actual product. It is understandable to those skilled in the art that some well-known structures and their descriptions in the accompanying drawings may be omitted.
[0030] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on the present application. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0031] like Figure 1-9 As shown, a feeding and slag discharging system of a biomass chain boiler includes a boiler body 1 and an electric control box. A feeding mechanism is provided on one side of the boiler body 1, and a slag discharging mechanism, a ceramic multi-tube dust collector 5 and an air box pulse bag dust collector 6 are provided on the other side. The feeding mechanism includes an external hopper 2 and a furnace body hopper 11. A feeding conveying mechanism 3 is provided below the external hopper 2. One end of the feeding conveying mechanism 3 away from the external hopper 2 extends to the top of the furnace body hopper 11. A second sensor 14 is provided on the top side of the furnace body hopper 11 for detecting the feeding situation in the furnace body hopper 11. A first sensor 13 is provided on the bottom side of the furnace body hopper 11 for detecting whether there is a lack of material in the furnace body hopper 11. Specifically, the first sensor 13 and the second sensor 14 are both photoelectric switches. A material diverting mechanism 12 is provided at the bottom of the furnace body hopper 11.
[0032] Furthermore, the material discharging mechanism 12 includes a material discharging roller 121 rotatably arranged below the sliding baffle, a support rod 122 is provided below the material discharging roller 121, the top surface of the support rod 122 is fixedly connected with an arc groove 123, and the bottom of the arc groove 123 is fixedly connected to the side wall of the furnace body hopper 11.
[0033] In this embodiment, a fixed baffle 15 is fixedly provided on the upper part of the furnace body hopper 11, and a sliding baffle 16 is slidably provided on the lower part of one side of the fixed baffle 15. An adjusting handle 17 is connected to the top of the sliding baffle 16 for adjusting the distance between the sliding baffle 16 and the material discharging mechanism 12, thereby controlling the material dropping speed.
[0034] A channel steel 21 is provided at the lower part of the external hopper 2, and the channel steel 21 is located above the blanking opening of the external hopper 2. The channel steel 21 is used to reduce the pressure on the lower feeding conveying mechanism 3 and the blanking opening of the external hopper 2, and reduce the bridging phenomenon of the fuel at the bottom of the external hopper 2.
[0035] A third sensor 22 is provided at the bottom of the external hopper 2 above the blanking port of the external hopper 2. Specifically, the third sensor 22 is a photoelectric switch. The third sensor 22 is located between the channel steel 21 and the blanking port of the external hopper 2. The electric control box is electrically connected to the first sensor, the second sensor, the third sensor 22 and the feeding and conveying mechanism 3.
[0036] The setting of the feeding mechanism reduces the workload of the boiler operator, so that the boiler operator does not need to add fuel to the equipment all the time, avoiding fatigue caused by night operations and thus avoiding the occurrence of safety accidents.
[0037] In this embodiment, the slag discharge mechanism includes a furnace body chain conveying mechanism 18, a furnace body ash hopper 19 is provided at a position of the boiler near the end of the chain conveying mechanism, an auger conveyor 4 is provided below the furnace body ash hopper 19, a slag discharge conveying mechanism 7 is provided below the ceramic multi-tube dust collector 5 and the air box pulse bag dust collector 6, the end of the auger conveyor 4 away from the furnace body ash hopper 19 is connected to the slag discharge conveying mechanism 7, and an ash dump 8 is provided at the end of the slag discharge conveying mechanism 7 away from the auger conveyor 4.
[0038] The arrangement of the slag discharging mechanism combines the slag discharging of the boiler body 1, the slag discharging of the ceramic multi-tube dust collector 5 and the slag discharging of the air box pulse bag dust collector 6 together, eliminating the need for separate slag discharging, thereby improving the slag discharging work efficiency.
[0039] An auger ash inlet is provided on the top surface of one end of the auger conveyor 4, and the auger ash inlet is connected to the furnace body ash collecting hopper 19. An auger ash outlet is provided on the bottom surface of the other end of the auger conveyor 4, and the auger ash outlet is located above the slag conveying mechanism 7. Due to the different operating conditions of the boiler body 1, the amount of slag generated is different. The electric control box controls the auger conveyor 4 to operate in different time periods according to the different operating conditions of the boiler body 1, and always keeps a part of slag at the bottom of the furnace body ash collecting hopper 19 to prevent air from entering the furnace along the auger conveyor from the furnace body ash collecting hopper 19.
[0040] The end of the slag conveying mechanism 7 close to the ash dump 8 is tilted upward so that more slag on the slag conveying mechanism 7 can be conveyed to the ash dump 8, avoiding the situation where the slag on the slag conveying mechanism 7 is piled up at the end of the slag conveying mechanism 7.
[0041] A first material distributor 51 is provided at the bottom of the ceramic multi-tube dust collector 5 for discharging slag from the ceramic multi-tube dust collector 5 , and a second material distributor 61 is provided at the bottom of the air box pulse bag dust collector 6 for discharging slag from the air box pulse bag dust collector 6 .
[0042] The electric control box is connected with the auger conveyor 4 , the first material distributor 51 , the second material distributor 61 and the slag conveying mechanism 7 via electrical signals.
[0043] When the feeding mechanism provided in this embodiment is in use, it is only necessary to put the biomass fuel to be consumed by the biomass chain boiler into the external hopper 2. When the first sensor 13 detects that there is a lack of biomass fuel in the furnace body hopper 11, the first sensor 13 triggers a signal to the electric control box, and the electric control box controls the feeding and conveying mechanism 3 to operate, and transports the biomass fuel in the external hopper 2 to the furnace body hopper 11. When the fuel in the furnace body hopper 11 is added to the position of the second sensor 14, the second sensor 14 triggers a signal to the electric control box, and the electric control box controls the feeding and conveying mechanism 3 to stop operating, thereby completing the feeding operation of the furnace body hopper 11.
[0044] When the slag discharge mechanism provided in this embodiment is in use, the slag produced by the combustion of the biomass chain boiler is conveyed to the furnace body ash hopper 19 by the furnace body chain conveying mechanism 18, and then falls into the auger conveyor 4, and the auger conveyor 4 transports the slag to the slag discharge conveying mechanism 7, the first feeder 51 feeds the ash in the ceramic multi-tube dust collector 5 to the slag discharge conveying mechanism 7, and the second feeder 61 feeds the ash in the air box pulse bag dust collector 6 to the slag discharge conveying mechanism 7. When discharging slag, the slag discharge conveying mechanism 7 needs to be started first, and the slag discharge conveying mechanism 7 needs to be closed last.
[0045] The feeding and slag discharging system of the biomass chain boiler provided by the utility model comprises a boiler body 1, an electric control box, a feeding mechanism, a slag discharging mechanism, a ceramic multi-tube dust collector 5 and an air box pulse bag dust collector 6. The feeding mechanism comprises a feeding conveying mechanism 3, an external hopper 2 and a furnace body hopper 11. The setting of the feeding mechanism reduces the work intensity of the boiler operator, so that the boiler operator does not need to add fuel to the equipment all the time, avoids the situation that the boiler operator is prone to fatigue during nighttime operations, and thus avoids the occurrence of safety accidents; the slag discharging mechanism comprises a furnace body chain conveying mechanism 18, a furnace body ash collecting hopper 19, an auger conveyor 4, and a slag discharging conveying mechanism 7. The setting of the slag discharging mechanism combines the slag discharging of the boiler body 1, the slag discharging of the ceramic multi-tube dust collector 5 and the slag discharging of the air box pulse bag dust collector 6 together, without the need to discharge the slag separately, thereby improving the slag discharging work efficiency.
[0046] The specific implementation methods of the utility model described above do not constitute a limitation on the protection scope of the utility model. Any other corresponding changes and modifications made according to the technical concept of the utility model should be included in the protection scope of the claims of the utility model.
Claims
1. A feeding and slag discharging system for a biomass chain boiler, comprising a boiler body and an electric control box, wherein a feeding mechanism is provided on one side of the boiler body, and a slag discharging mechanism, a ceramic multi-tube dust collector and an air box pulse bag dust collector are provided on the other side, characterized in that: The feeding mechanism comprises an external hopper and a furnace body hopper, a feeding conveying mechanism is provided below the external hopper, one end of the feeding conveying mechanism away from the external hopper extends to the top of the furnace body hopper, and a material shifting mechanism is provided at the bottom of the furnace body hopper for rotation; The slag discharge mechanism comprises a furnace chain conveying mechanism, a furnace ash collecting hopper is provided at a position of the boiler close to the end of the chain conveying mechanism, and a auger conveyor is provided below the furnace ash collecting hopper; A slag conveying mechanism is provided below the ceramic multi-tube dust collector and the air box pulse bag dust collector, and the end of the auger conveyor away from the furnace ash hopper is connected to the slag conveying mechanism, and an ash storage yard is provided at the end of the slag conveying mechanism away from the auger conveyor.
2. The feeding and slag discharging system of a biomass chain boiler according to claim 1, characterized in that: A second sensor is provided on the top side of the furnace body hopper, a first sensor is provided on the bottom side of the furnace body hopper, a fixed baffle is fixedly provided on the upper part of the furnace body hopper, a sliding baffle is slidably provided on the lower part of one side of the fixed baffle, and an adjustment handle is connected to the top of the sliding baffle; The material-discharging mechanism comprises a material-discharging roller rotatably arranged below the sliding baffle, a support rod is arranged below the material-discharging roller, an arc-shaped groove is fixedly connected to the top surface of the support rod, and the bottom of the arc-shaped groove is fixedly connected to the side wall of the furnace body hopper.
3. The feeding and slag discharging system of a biomass chain boiler according to claim 2, characterized in that: A channel steel is provided at the lower part of the external hopper, and the channel steel is located above the blanking opening of the external hopper. A third sensor is provided at the bottom of the external hopper, and the third sensor is located between the channel steel and the blanking opening of the external hopper. The electric control box is linked with the first sensor, the second sensor, the third sensor and the feeding and conveying mechanism by electrical signals.
4. The feeding and slag discharging system of a biomass chain boiler according to claim 1, characterized in that: An auger ash inlet is provided on the top surface of one end of the auger conveyor, and the auger ash inlet is connected to the furnace body ash collecting hopper. An auger ash outlet is provided on the bottom surface of the other end of the auger conveyor, and the auger ash outlet is located above the slag conveying mechanism.
5. The feeding and slag discharging system of a biomass chain boiler according to claim 4, characterized in that: The slag conveying mechanism is arranged to be inclined upward at one end close to the ash dump.
6. A feeding and slag discharging system for a biomass chain boiler according to claim 5, characterized in that: A first material distributor is provided at the bottom of the ceramic multi-tube dust collector, and a second material distributor is provided at the bottom of the air box pulse bag dust collector.
7. The feeding and slag discharging system of a biomass chain boiler according to claim 6, characterized in that: The electric control box is connected with the auger conveyor, the first material distributor, the second material distributor and the slag conveying mechanism by electrical signals.