Bilateral box girder interconnection positioning device
Through the use of the bilateral box girder positioning device, laser pre-checking and coaxial connection of combined prism structures are used to solve the problem of bolts deviating the holes in the steel box girder installation, the installation efficiency and accuracy are improved, and construction safety is ensured. Positioning quality.
Patent Information
- Application Number
- CN202420581599.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-25
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-03-25
AI Technical Summary
During the installation of steel box girders, it is difficult to manually install bolts on the holes, resulting in the bolts being unable to penetrate normally, affecting the construction progress and reducing the structural stress, posing a safety risk.
Using a bilateral box girder positioning device, including mounting bolts, snap rings, support rods and combined prism structures, the bolts are pre-checked by laser linear perforation, and the bolts are fixed through removable coaxial connections and support rods to ensure the bolts' Accurate installation.
It improves the accuracy and efficiency of steel box girder installation, reduces the investment of construction personnel and equipment, enhances the construction safety of surveyors, and improves positioning quality and accuracy.
Smart Images

Figure CN221989123U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel box girder positioning and installation, and more specifically, to a bilateral box girder interconnection positioning device. Background Art
[0002] With the vigorous development of national infrastructure, the technology of large-span bridge engineering has become increasingly mature, and the advantages of steel box girders have become more obvious. The steel box girder is a structure in which the prefabricated bridge deck is installed after the steel box girder is assembled by bolting the steel box girder to form an overall support. It has the advantages of fast construction speed, clear force structure, and more convenient linear control; secondly, the steel box girder solves the risk of web cracks in the concrete box girder over time. Therefore, steel structure assembly will be the direction of subsequent development of bridge engineering. However, the box girder assembly accuracy is better, and the installation of each component needs to be hoisted in sections and then assembled, bolted or welded. If there is a deviation in the installation of each steel structure component or a large deviation in the production, the bolts will not be able to penetrate normally. Secondly, the bolt connection installation accuracy of the steel structure is high, and the steel structure is greatly affected by temperature, resulting in deviations in the installation at different times, which makes the bolt connection unable to be transmitted normally, which not only delays the construction progress, but also reduces the force of the structure itself, and the safety risk is relatively large. This patent uses the characteristics of laser linear perforation while positioning the double-sided steel box girder to check and verify the bolt hole situation in advance, providing support for the smooth penetration of subsequent bolts. Utility Model Content
[0003] The utility model aims to provide a bilateral box girder interconnection positioning device to solve the technical problem of difficulty in manually installing bolt holes when positioning bilateral steel box girders in the prior art.
[0004] In order to achieve these purposes and other advantages according to the utility model, a bilateral box girder interconnection positioning device is provided, comprising:
[0005] A mounting bolt is used to coaxially penetrate into a bolt hole on the opposite side of the double-sided steel box girder, and one end of the mounting bolt is coaxially connected to a laser transmitter;
[0006] A snap ring, which is clamped on the mounting bolt and can rotate freely around the mounting bolt;
[0007] The support rod is a C-shaped structure, comprising an upper crossbar, a lower crossbar and a telescopic rod vertically connected between the upper crossbar and the lower crossbar, the outer end of the lower crossbar is fixedly connected to a clamp, and the outer end of the upper crossbar is connected to a pipe clamp that penetrates vertically;
[0008] A combined prism structure includes a prism rod, which is vertically inserted into a pipe clamp and fixed by the pipe clamp. The bottom of the prism rod is used to abut against the upper surface of the top plate of the steel box girder. A first prism is arranged on the top of the prism rod, and a second prism is arranged near the bottom of the prism rod. The centers of the prism rod, the pipe clamp, the mounting bolts, the first prism and the second prism are located on the same vertical axis.
[0009] Preferably, the bottom of the prism rod is a conical structure, and the center of the conical structure is coaxially arranged with the prism rod.
[0010] Preferably, the telescopic rod is an elastic telescopic rod.
[0011] Preferably, a sleeve is sleeved and connected to the mounting bolt, and the outer diameter of the sleeve is matched with the bolt hole so that the central axis of the mounting bolt coincides with the central axis of the bolt hole.
[0012] Preferably, the clamping ring includes a pair of U-shaped clamps, the diameter of the slot of the U-shaped clamps is the same as the outer diameter of the sleeve, the pair of U-shaped clamps are laterally inserted into the sleeve, a gasket is connected between the sides of the pair of U-shaped clamps opposite to the slot, and the outer end of the lower cross bar is horizontally inserted into the gasket and fixedly connected to the gasket.
[0013] Preferably, a threaded sleeve is disposed upwardly on the top of the prism rod, the first prism is mounted on the prism frame, a threaded rod is disposed downwardly at the bottom center of the prism frame, and the threaded rod is screwed into the threaded sleeve.
[0014] The utility model at least includes the following beneficial effects: the bilateral box girder interconnection positioning device of the utility model comprises mounting bolts, clamping rings, support rods and a combined prism structure, the overall structure is simple, the installation and connection are convenient and the reliability is strong, by coaxially arranging the mounting bolts at the bolt holes of the interconnection structure of the steel box girder, the support rods and the combined prism structure are detachably coaxially installed and connected with the mounting bolts by using the clamping rings, and the laser is emitted from the coaxially connected laser transmitter toward the laser target in the bolt hole on the opposite side, so that the bolt perforation deviation can be quickly pre-checked and adjusted in time, thereby ensuring the accuracy of the installation of the steel cross beam, improving the efficiency and accuracy of the installation of the bilateral steel box girder, and saving the investment of construction personnel and equipment, at the same time, the prism rod and the mounting bolt are aligned and fixed by the arranged support rods, thereby eliminating the operation of the surveyor standing on the edge to set up the prism, thereby improving the construction safety of the surveyor, and using the first prism and the second prism to vertically coaxially continuously observe and compare the deviation values to verify the reliability of the measurement result of the calibration device, improve the measurement accuracy, and enhance the positioning quality of the steel box girder.
[0015] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through research and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is the main structural diagram of the utility model;
[0017] Figure 2 It is a side structural diagram of the utility model;
[0018] Figure 3 This is a side structural diagram of the utility model installed on a double-sided box girder for positioning.
[0019] Explanation of the reference numerals in the drawings in the specification: 1. bilateral box girder interconnection positioning device, 2. mounting bolts, 3. bolt holes, 4. laser transmitter, 5. clamping ring, 6. support rod, 7. upper cross bar, 8. lower cross bar, 9. telescopic rod, 10. pipe clamp, 11. prism rod, 12. first prism, 13. second prism, 14. sleeve, 15. laser beam, 16. steel box girder. DETAILED DESCRIPTION
[0020] The present invention will be further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0021] In the description of the present invention, terms such as "lateral", "longitudinal", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.
[0022] like Figure 1 , Figure 2 , Figure 3 As shown, the bilateral box girder interconnection positioning device 1 of the utility model comprises:
[0023] A mounting bolt 2 is used to coaxially penetrate into a bolt hole 3 on the opposite side of the double-sided steel box girder 16, and one end of the mounting bolt 2 is coaxially connected to a laser transmitter 4;
[0024] A clamping ring 5, which is clamped on the mounting bolt 2 and can rotate freely around the mounting bolt 2;
[0025] The support rod 6 is a C-shaped structure, comprising an upper crossbar 7, a lower crossbar 8 and a telescopic rod 9 vertically connected between the upper crossbar 7 and the lower crossbar 8, the outer end of the lower crossbar 8 is fixedly connected to the clamp 5, and the outer end of the upper crossbar 7 is connected to a pipe clamp 10 that penetrates vertically;
[0026] The combined prism structure includes a prism rod 11, which is vertically inserted into the tube clamp 10 and clamped and fixed by the tube clamp 10. The bottom of the prism rod 11 is used to abut against the upper surface of the top plate of the steel box girder 16. A first prism 12 is arranged on the top of the prism rod 11, and a second prism 13 is arranged near the bottom of the prism rod 11. The centers of the prism rod 11, the tube clamp 10, the mounting bolt 2, the first prism 12, and the second prism 13 are located on the same vertical axis.
[0027] The bilateral box girder interconnection positioning device of the utility model can be used in the following order:
[0028] (1) The mounting bolt 2 is made with a diameter of φ26 mm, a screw rod length of 150 mm, and a nut diameter of φ34 mm. The laser transmitter 4 is coaxially connected to the nut of the mounting bolt 2 to ensure that the screw rod fits tightly with the bolt hole 3 and the laser axis coincides with the axis of the bolt hole 3.
[0029] (2) Production of support rod 6 and clamping ring 5: A 5 mm thick washer is welded to the lower end of the U-shaped clamping ring 5 so that it can rotate freely after the bolt 2 is installed. A 300 mm long telescopic rod 9 is welded to the end of the clamping ring 5, and the telescopic range is ±50 mm. The upper cross bar 7 is welded to the upper part of the telescopic rod 9, and the lower cross bar 8 is welded to the lower part. The upper and lower cross bars 8 are of the same length, and a round pipe clamp 10 is installed at the end.
[0030] (3) Production of combined prism structure: A Leica small prism is installed as the second prism 13, and a first prism 12 circular prism is installed on the top of the prism rod 11.
[0031] (4) The process of positioning the steel box beam 16: the installation bolt 2 is inserted and fixed in the bolt hole 3, and the center of the installation bolt 2 is ensured to coincide with the center of the bolt hole 3 of the steel beam. Then the clamping ring 5 connected with the support rod 6 is installed to fix the position. The lower cross bar 8 of the support rod 6 is located below the top plate of the steel box beam 16, the telescopic rod 9 is located on the side of the top plate of the steel box beam 16, and the upper cross bar 7 is located above the top plate of the steel box beam 16 facing the inside of the steel box beam 16. The clamping prism rod 11 is inserted into the pipe clamp 10 so that The bottom of the prism rod 11 is vertically abutted against the top plate of the steel box girder 16 to keep the prism rod 11 completely vertical. The combined prism is installed on the prism rod 11. The prism rod 11 is fixed to the top surface of the steel box girder 16 by the support rod 6 and the prism level bubble is adjusted to level it. The coordinates of the Leica small prism and the circular prism are measured to verify that their positioning accuracy and height difference meet the requirements. The three-dimensional coordinates of the circular prism are measured and compared with the design coordinates to calculate the deviation of the web of the steel box girder 16, and the position of the steel box girder 16 is adjusted until the requirements are met.
[0032] (5) Laser hole inspection: After the steel box girder 16 is positioned, turn on the laser transmitter 4 to emit the laser beam 15, install the device and the laser target sticker in the holes with the same number on the left and right side boxes, and inspect at least two groups of bolt holes 3 with the same number. Combined with the three-dimensional coordinates of the steel beam positioning and the offset of the laser target, the steel beam is comprehensively positioned to ensure that the offset of the steel beam and the bolts meet the deviation range.
[0033] The bilateral box girder interconnection positioning device of the utility model comprises a mounting bolt 2, a clamping ring 5, a support rod 6, and a combined prism structure. The overall structure is simple, the installation and connection are convenient, and the reliability is strong. By coaxially arranging the mounting bolt 2 at the interconnection structure bolt hole 3 of the steel box girder 16, the clamping ring 5 is used to detachably connect the support rod 6 and the combined prism structure to the mounting bolt 2 for coaxial installation. By emitting a laser from the coaxially connected laser transmitter 4 toward the laser target in the bolt hole 3 on the opposite side, the bolt perforation deviation can be quickly pre-checked and adjusted in time, thereby ensuring the accuracy of the steel beam installation, improving the efficiency and accuracy of the installation of the bilateral steel box girder 16, and saving the investment of construction personnel and equipment. At the same time, the prism rod 11 is fixed to the mounting bolt 2 by the support rod 6, thereby eliminating the operation of the surveyor standing on the edge to set up the prism, thereby improving the construction safety of the surveyor. The first prism 12 and the second prism 13 are used to vertically coaxially continuously observe and compare the deviation values to verify the reliability of the measurement result of the calibration device, thereby improving the measurement accuracy and the positioning quality of the steel box girder 16.
[0034] In another technical solution, Figure 1-3 As shown, the bottom of the prism rod 11 is a conical structure, and the center of the conical structure is coaxially arranged with the prism rod 11 .
[0035] The bottom of the prism rod 11 is set as a conical structure, which is in point contact with the top plate of the steel box beam 16, which is conducive to adjusting the vertical angle of the prism rod 11, eliminating the influence of the force, and ensuring the coaxiality and safe adjustment of the structural position.
[0036] In another technical solution, Figure 1-2 As shown, the telescopic rod 9 is an elastic telescopic rod 9. By setting it as an elastic telescopic rod 9, the support rod 6 can adapt to the height change within a certain range, and it is beneficial to temporarily fix the prism rod 11 on the top plate of the steel box beam 16 in a relatively stable position.
[0037] In another technical solution, Figure 2 As shown, a sleeve 14 is sleeved and connected to the mounting bolt 2 , and the outer diameter of the sleeve 14 is matched with the bolt hole 3 so that the central axis of the mounting bolt 2 coincides with the central axis of the bolt hole 3 .
[0038] φ28mm, 30mm, and 32mm sleeves 14 are added, which are suitable for mounting bolts 2 of various diameters. After the mounting bolts 2 with laser transmitters 4 are inserted into the bolt holes 3, suitable sleeves 14 are installed, which improves the positioning of the box girder axis and the installation accuracy of the mounting bolts 2 in the construction of bilaterally interconnected box girder bolt connections. The deviation of the perforation is pre-checked and accurately adjusted by bidirectional positioning, which not only ensures the accuracy of the steel box girder 16 axis and elevation installation, but also ensures the accuracy of the subsequent crossbeam installation.
[0039] In another technical solution, Figure 1-2 As shown, the clamping ring 5 includes a pair of U-shaped clamps, the diameter of the notch of the U-shaped clamps is the same as the outer diameter of the sleeve 14, the pair of U-shaped clamps are laterally inserted into the sleeve 14, and a gasket is connected between the sides of the pair of U-shaped clamps opposite to the notch, and the outer end of the lower cross bar 8 is horizontally inserted into the gasket and fixedly connected to the gasket.
[0040] A clamping ring 5 structure is provided to quickly coaxially connect the support rod 6 and the mounting bolt 2. The U-shaped clamp is matched with the sleeve 14, and the clamp is arranged on the outside of the sleeve 14. Preferably, a transverse guide groove is provided on the sleeve 14 to improve the installation efficiency and ensure that the installation direction of the lower cross bar 8 is horizontal, thereby ensuring that the installation direction of the upper cross bar 7 is horizontal and the installation direction of the prism rod 11 is vertical.
[0041] In another technical solution, Figure 1-2 As shown, a threaded sleeve is provided upward at the top of the prism rod 11, and the first prism 12 is installed on the prism frame. A threaded rod is provided downward at the bottom center of the prism frame, and the threaded rod is screwed into the threaded sleeve to quickly install the first prism 12 and adjust the position and height of the first prism 12.
[0042] Although the implementation scheme of the utility model has been disclosed as above, it is not limited to the applications listed in the specification and implementation scheme. It can be fully applied to various fields suitable for the utility model. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the utility model is not limited to the specific details and the drawings shown and described herein.
Claims
1. A bilateral box girder interconnection positioning device, characterized in that: include: A mounting bolt is used to coaxially penetrate into a bolt hole on the opposite side of the double-sided steel box girder, and one end of the mounting bolt is coaxially connected to a laser transmitter; A snap ring, which is clamped on the mounting bolt and can rotate freely around the mounting bolt; The support rod is a C-shaped structure, comprising an upper crossbar, a lower crossbar and a telescopic rod vertically connected between the upper crossbar and the lower crossbar, the outer end of the lower crossbar is fixedly connected to a clamp, and the outer end of the upper crossbar is connected to a pipe clamp that penetrates vertically; A combined prism structure includes a prism rod, which is vertically inserted into a pipe clamp and fixed by the pipe clamp. The bottom of the prism rod is used to abut against the upper surface of the top plate of the steel box girder. A first prism is arranged on the top of the prism rod, and a second prism is arranged near the bottom of the prism rod. The centers of the prism rod, the pipe clamp, the mounting bolts, the first prism and the second prism are located on the same vertical axis.
2. The bilateral box girder interconnection positioning device according to claim 1, characterized in that: The bottom of the prism rod is a cone-shaped structure, and the center of the cone-shaped structure is coaxially arranged with the prism rod.
3. The bilateral box girder interconnection positioning device according to claim 1, characterized in that: The telescopic rod is an elastic telescopic rod.
4. The bilateral box girder interconnection positioning device according to claim 1, characterized in that: A sleeve is sleeved and connected on the mounting bolt, and the outer diameter of the sleeve is matched with the bolt hole so that the central axis of the mounting bolt and the bolt hole coincide with each other.
5. The bilateral box girder interconnection positioning device according to claim 4, characterized in that: The clamping ring includes a pair of U-shaped clamps, the diameter of the notch of the U-shaped clamps is the same as the outer diameter of the sleeve, the pair of U-shaped clamps are horizontally inserted into the sleeve, a gasket is connected between the sides of the pair of U-shaped clamps opposite to the notch, and the outer end of the lower cross bar is horizontally inserted into the gasket and fixedly connected to the gasket.
6. The bilateral box girder interconnection positioning device according to claim 1, characterized in that: A threaded sleeve is arranged upwardly on the top of the prism rod, the first prism is installed on the prism frame, and a threaded rod is arranged downwardly at the bottom center of the prism frame, and the threaded rod is screwed into the threaded sleeve.