Existing railway line overhead system

By setting up hole piles on both sides of the railway line and using the combination of special steel cross beams and longitudinal beams, the problems of personal and driving safety risks and low construction efficiency in railway frame culvert hoisting construction are solved, and a safe and stable overhead system is achieved, shortening and shortening Construction period and reduce costs.

CN222008684UActive Publication Date: 2024-11-15GUANGXI NINGTIE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420622432.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-28
Publication Date
2024-11-15
Estimated Expiration
2034-03-28

AI Technical Summary

Technical Problem

In the construction of railway frame culverts, the existing technology is limited by steel beams, and hole piles can only be excavated on both sides of the railway line, which poses problems such as personal driving safety risks, affecting the stability of railway subgrade, low construction efficiency and long construction period.

Method used

Design an existing railway line overhead system, with hole piles arranged on both sides of the railway line, each group of hole piles is 4.8m away from the railway center, and a 9.6m-long and 0.45m-high steel cross beam is combined with steel longitudinal beams to form a stable overhead System to avoid manually digging holes on the side of the railway line and reduce the impact on the railway subgrade.

Benefits of technology

By moving the excavation position of the hole piles outside the fence, we ensure construction safety, improve construction efficiency, shorten construction period, reduce costs, and form a stable overhead system, the level of construction and transportation safety control is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008684U_ABST
    Figure CN222008684U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of railway existing line frame culvert jacking construction, and particularly discloses a railway existing line overhead system. The overhead system comprises hole piles, steel cross beams and steel longitudinal beams. The hole piles are divided into four groups, the four groups of hole piles are arranged in the length direction of the railway line, each group of hole piles are symmetrically arranged on the two sides of the railway line, and the distance between each hole pile and the center of the railway line is 4.8 m. The steel cross beams penetrate through the lower portion of a steel rail of the railway line and stretch across the railway line, the length of each steel cross beam is 9.6 m, and the height of each steel cross beam is 0.45 m. The steel longitudinal beams are divided into a group, the group of steel longitudinal beams are symmetrically arranged on the two sides of the railway line and erected on the hole piles, and the two ends of each steel cross beam are connected with the steel longitudinal beams on the corresponding sides through connecting parts. The overhead system can be constructed outside the railway line fence, personal safety and driving safety are ensured, the construction period is shortened, cost is reduced, and the whole overhead system is stable in stress.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The utility model relates to the technical field of jacking construction of frame culverts on existing railway operating lines, in particular to an overhead system for existing railway lines. [Background technology]

[0002] In the construction of the frame culvert under the railway, it is necessary to suspend the existing railway with a D-shaped steel temporary beam system, and then use the gap between trains to push the frame culvert to the designed position, and finally remove the temporary beam to restore the line. The construction process is frame prefabrication - pile excavation - line reinforcement - frame jacking - removal of temporary beams - line restoration.

[0003] During the construction of the current overhead system, due to the limitation of steel beams, bored piles can only be excavated on both sides of the railway line, and the distance between the center of the bored pile and the center of the line is only 1.98m. Due to the limitation of the existing railway, bored piles can only be excavated manually within the fence, which has the following problems:

[0004] 1. There is a high risk of personal and vehicle safety. When excavating bored piles on the side of the line, attention must be paid to the safety of vehicles on the line at all times. When vehicles come on the line, personnel and machinery must get off the road in time to avoid them, and there is a risk of construction machinery and materials invading the limit.

[0005] 2. Impact on the stability of the railway subgrade. Excavating piles on the side of the line will have a great impact on the surrounding railway subgrade. It is easy to cause the subsidence of the subgrade in high slope areas. When there is abundant groundwater and serious quicksand, it will cause the subgrade to collapse, affecting personal and driving safety.

[0006] 3. Slow construction is required, resulting in transportation losses. The construction of bored piles along the line requires the submission of a Class III slow construction plan, and the speed limit for passing trains is 45km / h, which will affect the dispatch of passenger and freight trains.

[0007] 4. Low construction efficiency and long construction period. Manual bored piles are affected by railway traffic and need to be excavated by skipping piles. The daily excavation depth is limited, the construction efficiency is low, the construction period is too long, and the construction needs to be stopped when a train is coming to the line to avoid the train. [Utility Model Content]

[0008] In order to overcome the shortcomings of the prior art, the purpose of the utility model is to provide an overhead system for existing railway lines, which can be constructed outside the railway line fence, ensuring personal safety and driving safety, shortening the construction period, reducing costs, and the entire overhead system is stable in force.

[0009] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is:

[0010] An overhead system for an existing railway line comprises bored piles, steel cross beams and steel longitudinal beams, wherein the bored piles are in four groups, and the four groups of bored piles are arranged along the length direction of the railway line, and each group of the bored piles are symmetrically arranged on both sides of the railway line, and each of the bored piles is 4.8m away from the center of the railway line; a number of the steel cross beams pass under the steel rails of the railway line and span across the railway line, and the length of the steel cross beams is 9.6m and the height is 0.45m; the steel longitudinal beams are in one group, and one group of the steel longitudinal beams is symmetrically arranged on both sides of the railway line and erected on the bored piles, and both ends of each of the steel cross beams are connected to the steel longitudinal beams on the corresponding side through connecting parts.

[0011] Furthermore, there is a sleeper between two adjacent steel beams.

[0012] Furthermore, the material of the steel crossbeam is Q345qD.

[0013] Furthermore, the design conditions of the steel beam are:

[0014] (1) Train live load: ZKH live load;

[0015] (2) Speed ​​limit: 45 km / h;

[0016] (3) Impact coefficient: 1.34;

[0017] (4) Fatigue times: 300,000 times.

[0018] Furthermore, the four groups of bored piles are, from left to right, the first group of bored piles, the second group of bored piles, the third group of bored piles and the fourth group of bored piles, and the second group of bored piles and the third group of bored piles are respectively located on both sides of the frame culvert top construction site, and the spacing between the first group of bored piles and the second group of bored piles is equal to the spacing between the third group of bored piles and the fourth group of bored piles.

[0019] Furthermore, the spacing between the first group of bored piles and the second group of bored piles is 0.7-0.8 m.

[0020] Due to the use of the technical solution of the utility model, the utility model has the following beneficial effects:

[0021] By moving the location of the bored pile excavation from the line side to outside the fence, 4.8m away from the center of the line, the bored pile excavation is ensured to be far away from the line and not restricted by the railway site. At the same time, the skylight points are used to erect temporary beams, which not only better ensures construction safety, but also allows construction at any time to improve construction efficiency. At the same time, according to the location of the bored piles, through mechanical calculations, a special steel beam with a length of 9.6m and a height of 0.45m is specially made. Through the arrangement and combination of special steel beams, bored piles and steel longitudinal beams, the overall force is stable, and a safe and stable line overhead system can be formed. The plan is feasible. In addition, there is no need to submit a slow-moving construction plan during the bored pile excavation, and there is no impact on the railway subgrade, which effectively improves the level of safety control and ensures transportation safety and construction safety.

Brief Description of the Drawings

[0022] Figure 1 It is a plan view of the overhead system of the utility model.

[0023] Figure 2 It is the front view of the overhead system of the utility model.

[0024] The main component symbols in the figure are explained as follows:

[0025] In the figure, 1- bored piles, 11- the first group of bored piles, 12- the second group of bored piles, 13- the third group of bored piles, 14- the fourth group of bored piles, 2- steel cross beams, 3- steel longitudinal beams, 4- railway lines, 41- steel rails, 42- sleepers, 5- connecting parts, 6- frame culverts.

[0026] The following specific implementation manner will further illustrate the present utility model in conjunction with the above-mentioned drawings. [Specific implementation method]

[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0028] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0029] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed", "located on", etc. should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, or a communication; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0030] In addition, in the present application, unless otherwise clearly specified and limited, the first feature is "on" or "under" the second feature, and the first and second features may be in direct contact, or the first and second features may be in indirect contact through an intermediate medium. In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in an appropriate manner in any one or more embodiments or examples.

[0031] like Figure 1-2 As shown, in one embodiment of the utility model, an overhead system of an existing railway line includes bored piles 1, steel cross beams 2 and steel longitudinal beams 3, the bored piles 1 are four groups, and the four groups of bored piles 1 are arranged along the length direction of the railway line 4, each group of the bored piles 1 are symmetrically arranged on both sides of the railway line 4, and each of the bored piles 1 is 4.8m away from the center of the railway line 4; a number of the steel cross beams 2 pass under the steel rails 41 of the railway line 4 and span the railway line 4, and the length of the steel cross beam 2 is 9.6m and the height is 0.45m; the steel longitudinal beams 3 are one group, one group of the steel longitudinal beams 3 are symmetrically arranged on both sides of the railway line 4 and erected on the bored piles 1, and both ends of each of the steel cross beams 2 are connected to the steel longitudinal beams 3 on the corresponding side through connecting parts 5.

[0032] The overhead system has achieved good results in ensuring the safety and stability of the line and roadbed, saving construction time and costs. First, in terms of safety benefits. The original overhead system is an on-road operation on the operating line. Materials and equipment are constructed within the limit, which is prone to traffic safety incidents. The solution of the utility model is to construct the bored piles 1 outside the fence, and personnel and equipment do not need to go on the road to work, avoiding safety incidents and effectively improving the level of safety management and control. Second, in terms of construction period benefits. The manual bored piles next to the sleepers of the original overhead system are affected by railway traffic, and the excavation progress is slow. The construction period of 8 bored piles is about 64 days. In this embodiment, the construction period of excavating bored piles 1 outside the fence is only 32 days, saving about 32 days of construction time. Third, in terms of economic benefits, it reduces construction costs and transportation losses, and achieves remarkable results in saving costs and reducing consumption.

[0033] In this embodiment, specifically, there is a sleeper 42 between two adjacent steel beams 2, so that the railway line runs stably.

[0034] In this embodiment, specifically, the material of the steel beam 2 is Q345qD, and its elastic modulus is 2.1×10 5 MPa, Poisson's ratio 0.3.

[0035] In this embodiment, the length of the steel beam 2 is 9.6 m and the height is 0.45 m, which satisfies the following design conditions:

[0036] (1) Train live load: ZKH live load;

[0037] (2) Speed ​​limit: 45 km / h;

[0038] (3) Impact coefficient: 1.34;

[0039] (4) Fatigue times: 300,000 times.

[0040] At the same time, the force on the steel beam 2 is calculated, and the results are shown in Table 1 below:

[0041] Table 1 Calculation results of steel beam stress

[0042] Load on a single steel beam 65kN Bending stress 138MPa Static deflection 16.2mm support reaction force 88.5kN Fatigue stress Meet the 300,000 times allowable fatigue requirement

[0043] It can be seen from the above table that, through force calculation, it is proved that by using the steel crossbeam 2, the overhead system of the utility model can be stabilized in force, and the solution is confirmed to be feasible.

[0044] In this embodiment, specifically, the four groups of bored piles 1 are the first group of bored piles 11, the second group of bored piles 12, the third group of bored piles 13 and the fourth group of bored piles 14 from left to right, and the second group of bored piles 12 and the third group of bored piles 13 are respectively located on both sides of the top construction site of the frame culvert 6, and the spacing between the first group of bored piles 11 and the second group of bored piles 12 is equal to the spacing between the third group of bored piles 13 and the fourth group of bored piles 14, and the spacing is 0.7-0.8m. Through the arrangement of the bored piles 1, the force stability of the overhead system can be guaranteed, and the safety of the top construction of the frame culvert 6 can be improved.

[0045] The construction process of using this overhead system is: pile position marking → manual excavation of bored piles → installation of steel cage → pouring of concrete → line reinforcement → frame jacking.

[0046] At present, the overhead system has been applied to three underpass projects undertaken by China Railway Construction Corporation, saving a total of more than 5 million yuan in costs. Among them, the use of the overhead system in the Nanning-Kunming Line K423+436 crossing level-to-level conversion project alone can save 1.48 million yuan in costs. The specific cost comparison is shown in Table 2 below:

[0047] Table 2 Cost comparison analysis of overhead system before and after

[0048]

[0049] In summary, the overhead system of the utility model can be constructed outside the railway fence, ensuring personal safety and driving safety, shortening the construction period, reducing costs, and the entire overhead system is stable in force.

Claims

1. An existing railway overhead system, characterized in that: It includes bored piles, steel cross beams and steel longitudinal beams. The bored piles are divided into four groups, which are arranged along the length direction of the railway line. Each group of the bored piles is symmetrically arranged on both sides of the railway line, and each bored pile is 4.8m away from the center of the railway line; a number of the steel cross beams pass under the steel rails of the railway line and span across the railway line, and the length of the steel cross beam is 9.6m and the height is 0.45m; the steel longitudinal beams are divided into one group, which is symmetrically arranged on both sides of the railway line and erected on the bored piles, and both ends of each steel cross beam are connected to the steel longitudinal beam on the corresponding side through connecting parts.

2. The existing railway overhead system according to claim 1, characterized in that: There is a sleeper between two adjacent steel beams.

3. The existing railway overhead system according to claim 1, characterized in that: The material of the steel cross beam is Q345qD.

4. The existing railway overhead system according to claim 1, characterized in that: The design conditions of the steel beam are: (1) Train live load: ZKH live load; (2) Speed ​​limit: 45 km / h; (3) Impact coefficient: 1.34; (4) Fatigue times: 300,000 times.

5. The existing railway overhead system according to claim 1, characterized in that: The four groups of bored piles are, from left to right, the first group of bored piles, the second group of bored piles, the third group of bored piles and the fourth group of bored piles, and the second group of bored piles and the third group of bored piles are respectively located on both sides of the frame culvert top construction site, and the spacing between the first group of bored piles and the second group of bored piles is equal to the spacing between the third group of bored piles and the fourth group of bored piles.

6. The existing railway overhead system according to claim 5, characterized in that: The spacing between the first group of bored piles and the second group of bored piles is 0.7-0.8 m.