Pile stabilizing platform for holding steel pipe pile

By using a dual-axis motor to drive the screw rotation and hydraulic cylinder drive the connecting rod movement on the offshore wind pile stabilization platform, the problem of difficult to adjust the pipe pile distance in the existing technology is solved, and flexible adjustment and stability of the pipe pile distance is achieved Fixed, improving engineering efficiency.

CN222008910UActive Publication Date: 2024-11-15JIANGSU SUNLIKE ENVIRONMENTAL ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323504068.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-21
Publication Date
2024-11-15
Estimated Expiration
2033-12-21

AI Technical Summary

Technical Problem

After the installation of the existing foundation steel pipe pile in shallow water area of ​​offshore wind power, the pipe pile distance is difficult to adjust, resulting in a large project volume, and the pile stabilization platform needs to be reconstructed.

Method used

Design a pile stabilization platform that holds steel pipe piles tightly, adopts platform base, dual-axis motor, screw rod, hydraulic cylinder and clamping plate and other components. The screw rod is driven to rotate through the dual-axis motor, and the hydraulic cylinder drives the connecting rod to move. The pipe pile distance adjustment and limit fixation are achieved using sliders and limit grooves, and the clamping plate prevents displacement.

Benefits of technology

It realizes flexible adjustment and stable fixation of pipe pile distances, avoids the need for re-construction, and improves the practicality and efficiency of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008910U_ABST
    Figure CN222008910U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of piling, in particular to a pile stabilizing platform for holding a steel pipe pile, which comprises a platform base, the left side of the platform base is connected with a first pipe holding part, the right side of the platform base is connected with a second pipe holding part, and two guide grooves are formed in the first pipe holding part and the second pipe holding part respectively. Limiting rods fixedly connected with the platform base are slidably inserted into the two guide grooves, a double-shaft motor is fixed into the platform base through bolts, and a power output shaft of the double-shaft motor is connected with a lead screw. The double-shaft motor in the platform base drives the two lead screws to rotate synchronously, the first pipe holding part and the second pipe holding part can be driven synchronously to move relatively when the two lead screws rotate under the cooperation of the threaded grooves, the distance between two pipe piles can be adjusted, the platform does not need to be disassembled for pile stabilization again, and the working efficiency is improved. The practicability is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of piling, in particular to a pile stabilizing platform for holding a steel pipe pile. Background Art

[0002] Domestic offshore wind power generation technology has developed rapidly, the capacity of single units is gradually expanding, and wind turbine foundation forms such as high-pile sinking platform foundation, jacket foundation, and single pile foundation have also had relatively mature application experience. Wind energy is used in the field of power generation as a clean and renewable energy. Due to the large amount of available space in the sea and the strong wind force, more and more wind farms are built at sea. Usually, a stable pile platform is built at sea, and then engineering piles are driven into the water one by one through the stable pile platform to complete the construction of the jacket.

[0003] The patent specification with the announcement number CN213143112U discloses a bottom platform for offshore wind power shallow water foundation steel pipe piles, which includes a bottom platform body and a tilted pile guide frame. The bottom platform body includes an anti-sinking plate, a middle platform and an upper platform arranged in sequence from bottom to top; the main structure and size of the upper platform and the middle platform are the same; four pairs of ear plates are arranged at intervals on the two upper transverse inner box beams and the two upper longitudinal inner box beams of the upper platform, and six pin holes are provided on each ear plate; the tilted pile guide frame is arranged on the two transverse inner box beams or the two longitudinal inner box beams, and the two main box beams of the base are clamped by three pairs of ear plates on each upper transverse inner box beam or three pairs of ear plates on each upper longitudinal inner box beam, and then fixed on the upper platform by inserting a pin rod into at least three pin holes on each pair of ear plates and the main box beam of the base. It can realize the tilted pile driving in shallow water areas, and the tilted pile slope and plane position have a large adjustable space and accurate control.

[0004] However, in the implementation of relevant technologies, it was found that the above-designed offshore wind power shallow water foundation steel pipe pile inclined pile sinking stabilizing pile base platform has the following problems: in the above-mentioned technical scheme, the locking position of the pin rod is adjusted and the distance from the inclined pile guide frame to the center of the base platform body is adjusted to achieve the purpose of controlling the distribution radius of the inclined piles. This can meet the construction requirements of the planar position of the inclined piles facing the seabed at different water depths. However, after the platform is installed, the distance between the pipe piles is not easy to adjust. If the distance between the pipe piles is to be adjusted, the pile stabilizing platform needs to be re-constructed and erected, resulting in a large amount of engineering work. In view of this, a pile stabilizing platform that holds the steel pipe piles tightly is provided to overcome the above-mentioned defects. Utility Model Content

[0005] The utility model aims to solve the shortcomings in the prior art and provides a pile stabilizing platform for holding a steel pipe pile.

[0006] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a pile stabilizing platform for holding steel pipe piles, comprising a platform base, a first pipe holding member is connected to the left side of the platform base, a second pipe holding member is connected to the right side of the platform base, two guide grooves are provided inside the first pipe holding member and the second pipe holding member, limit rods fixedly connected to the platform base are slidably inserted inside the two guide grooves, a dual-axis motor is fixed inside the platform base by bolts, a power output shaft of the dual-axis motor is connected to a screw rod, and the side walls of the first pipe holding member and the second pipe holding member are provided with threaded grooves threadedly connected to the screw rod.

[0007] As a further description of the above technical solution: the first pipe holding member and the second pipe holding member are both fixed with hydraulic cylinders by bolts, and the telescopic ends of the hydraulic cylinders are connected to connecting rods. When the hydraulic cylinders are started, the connecting rods are driven to move, thereby driving the pile holding mechanism to move and limit the position of the pipe piles.

[0008] As a further description of the above technical solution: a slider is fixed to the end of the connecting rod, and the outer wall of the slider is slidably connected to a limiting groove opened on the inner wall of the first pipe holding member, which plays a role of limiting guide under the cooperation of the slider and the limiting groove.

[0009] As a further description of the above technical solution: a clamping plate is fixed on one side of the slider, and a number of anti-slip protrusions are evenly distributed inside the clamping plate. The anti-slip protrusions arranged on the clamping plate can play an anti-slip role and reduce the displacement of the pipe pile.

[0010] As a further description of the above technical solution: four fixing columns are fixed on the lower surface of the platform base in the vertical direction, and support plates are fixed on the lower surfaces of the four fixing columns. Through the fixing columns on the platform base and with the cooperation of the support plates, the stability of the platform can be guaranteed.

[0011] As a further description of the above technical solution: fixing bolts are installed inside the support plate, and the support plate is fixed by using the fixing bolts to prevent the platform from shifting.

[0012] As a further description of the above technical solution: the screw rod and the dual-axis motor form a rotating structure, the first pipe holding member forms a telescopic structure with the platform base through the guide groove and the limit rod, the set guide groove and limit rod can play a guiding role, and the limit rod can prevent the first pipe holding member and the second pipe holding member from falling off due to excessive movement.

[0013] The utility model has the following beneficial effects:

[0014] The utility model designs a pile stabilizing platform for holding steel pipe piles. A double-axis motor in the platform base drives two screw rods to rotate synchronously respectively. With the cooperation of the threaded groove, when the two screw rods rotate, the first pipe holding member and the second pipe holding member can be synchronously driven to move relative to each other, so the distance between the two pipe piles can be adjusted. There is no need to disassemble the platform for re-stabilizing the piles, thereby improving practicality.

[0015] The utility model designs a pile stabilizing platform for holding a steel pipe pile. The arranged hydraulic cylinder is started to drive the movement of the connecting rod, thereby driving the pile holding mechanism to move, and the pipe pile is limited and fixed. With the cooperation of the sliding block and the limiting groove, it plays a role of limiting guide. The anti-skid protrusions arranged on the clamping plate can play an anti-skid role and reduce the displacement of the pipe pile. The fixed columns on the platform base can ensure the stability of the platform with the cooperation of the supporting plate, and the supporting plate is fixed with fixing bolts to avoid the deviation of the platform. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a three-dimensional structural schematic diagram of the utility model;

[0017] Figure 2 This is a schematic diagram of the cross-sectional structure of the first pipe holding member of the utility model;

[0018] Figure 3 This is a schematic diagram of the three-dimensional structure of the second pipe holding member of the utility model;

[0019] Figure 4 For this utility model Figure 2 Enlarged view of point A in the middle.

[0020] Legend:

[0021] 1. Platform base; 2. First pipe holding piece; 3. Second pipe holding piece; 4. Guide groove; 5. Limit rod; 6. Dual-axis motor; 7. Screw rod; 8. Threaded groove; 9. Hydraulic cylinder; 10. Connecting rod; 11. Slider; 12. Limit groove; 13. Clamping plate; 14. Anti-slip bump; 15. Fixed column; 16. Support plate; 17. Fixing bolt. DETAILED DESCRIPTION

[0022] Reference Figure 1-Figure 4The utility model provides a pile stabilizing platform for holding steel pipe piles: it comprises a platform base 1, a first pipe holding member 2 is connected to the left side of the platform base 1, and a second pipe holding member 3 is connected to the right side of the platform base 1. Two guide grooves 4 are provided inside the first pipe holding member 2 and the second pipe holding member 3, and limit rods 5 fixedly connected to the platform base 1 are slidably inserted inside the two guide grooves 4. A double-axis motor 6 is fixed to the inside of the platform base 1 by bolts, and a screw rod 7 is connected to the power output shaft of the double-axis motor 6. The side walls of the first pipe holding member 2 and the second pipe holding member 3 are provided with thread grooves 8 threadedly connected to the screw rod 7. The double-axis motor 6 in the platform base 1 drives the two screw rods 7 to rotate synchronously respectively. With the cooperation of the thread grooves 8, when the two screw rods 7 rotate, the first pipe holding member 2 and the second pipe holding member 3 can be synchronously driven to move relative to each other, so that the distance between the two pipe piles can be adjusted, and there is no need to disassemble the platform for pile stabilization again, thereby improving practicality.

[0023] As a further implementation scheme of the above technical scheme: hydraulic cylinders 9 are fixed inside the first pipe holding member 2 and the second pipe holding member 3 by bolts, and the telescopic ends of the hydraulic cylinders 9 are connected to connecting rods 10. When the hydraulic cylinders 9 are started, the connecting rods 10 are driven to move, thereby driving the pile holding mechanism to move and limit the position of the pipe piles.

[0024] As a further implementation scheme of the above technical scheme: a slider 11 is fixed to the end of the connecting rod 10, and the outer wall of the slider 11 is slidably connected to a limiting groove 12 opened on the inner wall of the first pipe holding member 2, and the cooperation of the slider 11 and the limiting groove 12 plays a role of limiting guide.

[0025] As a further implementation scheme of the above technical scheme: a clamping plate 13 is fixed on one side of the slider 11, and a number of anti-skid protrusions 14 are evenly distributed inside the clamping plate 13. The anti-skid protrusions 14 arranged on the clamping plate 13 can play an anti-skid role and reduce the displacement of the pipe pile.

[0026] In specific implementation, when in use, the two pipe piles are respectively passed through the limiting cavities on the first pipe holding member 2 and the second pipe holding member 3, and the hydraulic cylinder 9 is started to drive the connecting rod 10 to move. Under the cooperation of the slider 11 and the limiting groove 12, it plays a role of limiting guide, so that the slider 11 drives the clamping plate 13 to approach the pipe pile, and the pipe pile is clamped tightly. The anti-skid protrusions 14 provided on the clamping plate 13 can play an anti-skid role, reduce the displacement of the pipe pile, and thus stabilize the pipe pile. When the distance between the two pipe piles is When there is an error, the two screw rods 7 can be driven to rotate synchronously by the dual-axis motor 6 in the platform base 1. The provided guide groove 4 and limit rod 5 can play a guiding role, and the limit rod 5 can prevent the first pipe holding member 2 and the second pipe holding member 3 from falling off due to excessive movement. With the cooperation of the threaded groove 8, when the two screw rods 7 rotate, the first pipe holding member 2 and the second pipe holding member 3 can be driven synchronously to move relative to each other, and the distance between the two pipe piles can be adjusted without disassembling the platform to stabilize the piles again, thereby improving practicality.

[0027] As a further implementation scheme of the above technical scheme: four fixing columns 15 are fixed in the vertical direction on the lower surface of the platform base 1, and support plates 16 are fixed on the lower surfaces of the four fixing columns 15. Through the fixing columns 15 on the platform base 1 and with the cooperation of the support plates 16, the stability of the platform can be ensured.

[0028] As a further implementation scheme of the above technical scheme: fixing bolts 17 are installed inside the support plate 16, and the support plate 16 is fixed by using the fixing bolts 17 to avoid the platform from deflecting.

[0029] As a further implementation scheme of the above technical scheme: a rotating structure is formed between the screw rod 7 and the dual-axis motor 6, and a telescopic structure is formed between the first pipe holding member 2 and the platform base 1 through the guide groove 4 and the limit rod 5. The provided guide groove 4 and the limit rod 5 can play a guiding role, and the limit rod 5 can prevent the first pipe holding member 2 and the second pipe holding member 3 from falling off due to excessive movement.

[0030] During specific implementation, the platform base 1 is placed in a suitable position. The stability of the platform can be ensured by the fixing columns 15 on the platform base 1 with the cooperation of the support plate 16. The support plate 16 is fixed with fixing bolts 17 to avoid the platform from deflecting.

[0031] Finally, it should be noted that the above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A pile stabilizing platform for holding a steel pipe pile, comprising a platform base (1), a first pipe holding member (2) being connected to the left side of the platform base (1), and a second pipe holding member (3) being connected to the right side of the platform base (1). Features: The first pipe holding member (2) and the second pipe holding member (3) are each provided with two guide grooves (4), and the two guide grooves (4) are each slidably inserted with a limit rod (5) fixedly connected to the platform base (1). A dual-axis motor (6) is fixed to the platform base (1) by bolts, and the power output shaft of the dual-axis motor (6) is connected to a screw rod (7). The side walls of the first pipe holding member (2) and the second pipe holding member (3) are each provided with a threaded groove (8) threadedly connected to the screw rod (7).

2. A pile stabilizing platform for holding a steel pipe pile according to claim 1, Features: A hydraulic cylinder (9) is fixed inside the first pipe holding member (2) and the second pipe holding member (3) via bolts, and a connecting rod (10) is connected to the telescopic end of the hydraulic cylinder (9).

3. A pile stabilizing platform for holding a steel pipe pile according to claim 2, Features: A slider (11) is fixed to the end of the connecting rod (10), and the outer wall of the slider (11) is slidably connected to a limiting groove (12) provided on the inner wall of the first pipe holding member (2).

4. A pile stabilizing platform for holding a steel pipe pile according to claim 3, Features: A clamping plate (13) is fixed to one side of the sliding block (11), and a plurality of anti-slip convex points (14) are evenly distributed inside the clamping plate (13).

5. A pile stabilizing platform for holding a steel pipe pile according to claim 1, Features: Four fixing columns (15) are fixed in a vertical direction on the lower surface of the platform base (1), and a support plate (16) is fixed on the lower surface of each of the four fixing columns (15).

6. A pile stabilizing platform for holding a steel pipe pile according to claim 5, Features: A fixing bolt (17) is installed inside the support plate (16).

7. A pile stabilizing platform for holding a steel pipe pile according to claim 1, Features: The screw rod (7) and the dual-axis motor (6) form a rotating structure, and the first pipe holding member (2) forms a telescopic structure with the platform base (1) through the guide groove (4) and the limit rod (5).