Concrete structure construction anti-deformation support
By designing the deformation-resistant bracket for concrete structure construction, and adjusting the spacing and slide position of the support plates using the support plates and ring body components, the problem of deformation of the guard plates during concrete construction is solved, and better support performance and flexibility are achieved.
Patent Information
- Application Number
- CN202420586642.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-25
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-25
AI Technical Summary
In concrete construction, the large side pressure during concrete pouring leads to inclination or bending deformation of the guard plate, affecting the construction quality.
A concrete structure construction anti-deformation bracket is designed, using supporting plates, ring bodies, double-headed screws, nuts, slide rails and sliders. By adjusting the spacing and slide position of the supporting plate, the vertical state of the supporting plate and Flexible assembly to enhance resistance to deformation.
It effectively avoids the inclination or deformation of the support plate, improves the support performance, is suitable for different on-site conditions, and facilitates the assembly of multiple support plates to extend the support length.
Smart Images

Figure CN222009611U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to an anti-deformation bracket for concrete structure construction. Background Art
[0002] Concrete refers to a general term for engineering composite materials in which aggregates are bonded into a whole by cementitious materials. Concrete pouring is an indispensable operation in the construction of concrete structures. However, during the current concrete pouring, there is a situation in which the guard plate is tilted or bent due to the large lateral pressure during the concrete pouring, thereby affecting the construction quality. In view of the above problems, the inventor proposes an anti-deformation bracket for concrete structure construction to solve the above problems. Utility Model Content
[0003] In order to solve the problem that the guard plate is tilted or bent due to the large lateral pressure during concrete pouring, the utility model aims to provide an anti-deformation bracket for concrete structure construction.
[0004] In order to solve the above technical problems, the utility model adopts the following technical solutions: a deformation-resistant bracket for concrete structure construction, comprising a support plate, a ring body is arranged above the support plate, the ring body comprises a ring mouth, a double-headed screw is inserted in the ring mouth, a first nut is arranged on one side of the ring body, a second nut is arranged on the other side of the ring body, the first nut and the second nut are both matched with the double-headed screw, the side wall of the support plate is fixedly connected with a slide rail, the side wall of the slide rail is sleeved with a slider, the side of the slider facing away from the slide rail is hingedly provided with a cylinder, the cylinder mouth of the cylinder is inserted and slidably connected with a movable rod, the end of the movable rod away from the cylinder is hinged with a bottom plate, and the top surface of the bottom plate is inserted with a ground nail.
[0005] Preferably, the side wall of the ring body is fixedly connected with a fixing seat, the bottom surface of the fixing seat is fixedly connected to the top surface of the support plate, the ring body is installed through the fixing seat, and there are two ring bodies on each support plate, and the two ring bodies are symmetrically distributed. The poured concrete can be blocked by the two support plates to prevent the concrete from flowing sideways. The first nut is put on the double-headed screw, and the double-headed screw is inserted into the ring mouth of the ring body. Then, the second nut is screwed on so that the first nut is located on one side of the ring body and the second nut is located on the other side of the ring body. By screwing the first nut and the second nut, the distance between the two support plates can be adjusted, and the support plate can be placed in a vertical state, so that the support plate can better support the lateral pressure during concrete pouring and prevent the support plate from tilting or deformation.
[0006] Preferably, a first convex plate is fixedly connected to one side of the support plate, and a second convex plate is fixedly connected to the other side of the support plate. The first convex plate corresponds to and cooperates with the second convex plate. When multiple support plates need to be assembled, the first convex plate of one support plate can be made to correspond to the second convex plate of another support plate, and the first convex plate can be made to contact the second convex plate, so as to complete the assembly of the two support plates and extend the support length.
[0007] Preferably, a slide groove is provided on one side of the slider facing the support plate, and the slide groove is slidably connected to the slide rail. A threaded hole is penetrated on one side of the slider facing away from the support plate, and one end of the threaded hole extends into the slide groove. A first fastening knob is provided on one side of the slider, and the first fastening knob corresponds to and cooperates with the threaded hole. Through the mutual cooperation between the slider and the slide rail, the position of the slider can be adjusted so as to support different positions of the support plate according to the actual conditions on site. After adjusting the position of the slider, the first fastening knob is turned. Knob, the rod of the first tightening knob is a threaded rod, and the rod end of the first tightening knob is tightly fitted with the slide rail through the mutual cooperation between the rod of the first tightening knob and the threaded hole, so that the slider can be limited and fixed, and the side wall of the cylinder is provided with a second tightening knob with a thread inserted near the cylinder mouth, and the rod end of the second tightening knob extends to the cylinder mouth of the cylinder, and the rod of the second tightening knob is also a threaded rod, and the extension length of the movable rod can be adjusted by turning the second tightening knob to cooperate with the slider to adjust the installation position of the ground nail.
[0008] Compared with the prior art, the beneficial effects of the utility model are:
[0009] 1. The utility model has good supporting performance and avoids deformation. A double-headed screw is provided. By screwing the first nut and the second nut on the double-headed screw, the distance between the two support plates can be adjusted, and the support plate can be placed in a vertical state, so that the support plate can better support the lateral pressure during concrete pouring, and avoid the support plate from tilting or deforming. The provided cylinder and ground nails can play an auxiliary supporting role, thereby increasing the anti-deformation performance;
[0010] 2. The utility model facilitates the assembly of multiple support plates to extend the support length, and the position of the slider can be adjusted through the cooperation between the slider and the slide rail, so that the force points of the slider and the support plate can be adjusted according to the actual situation on site to improve the support performance. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0012] Figure 1 It is a schematic diagram of the overall structure of the utility model.
[0013] Figure 2 This is another schematic diagram of the overall structure of the utility model.
[0014] Figure 3 It is an enlarged view of point A of the present utility model.
[0015] In the figure: 1, support plate; 2, first convex plate; 3, second convex plate; 4, fixed seat; 5, ring body; 6, ring mouth; 7, first nut; 8, second nut; 9, double-headed screw; 10, slide rail; 11, slider; 12, threaded hole; 13, first tightening knob; 14, cylinder; 15, movable rod; 16, second tightening knob; 17, bottom plate; 18, ground nail. DETAILED DESCRIPTION
[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0017] Example: Figure 1-3 As shown, the utility model provides an anti-deformation support for concrete structure construction, including a support plate 1, a ring body 5 is arranged above the support plate 1, the ring body 5 includes a ring mouth 6, a double-headed screw 9 is inserted in the ring mouth 6, a first nut 7 is arranged on one side of the ring body 5, and a second nut 8 is arranged on the other side of the ring body 5. The first nut 7 and the second nut 8 are both matched with the double-headed screw 9, and a slide rail 10 is fixedly connected to the side wall of the support plate 1, and a slider 11 is sleeved on the side wall of the slide rail 10. A cylinder body 14 is hingedly provided on the side of the slider 11 facing away from the slide rail 10, and a movable rod 15 is inserted and slidably connected to the cylinder mouth of the cylinder body 14. The end of the movable rod 15 away from the cylinder body 14 is hinged to a bottom plate 17, and a ground nail 18 is inserted on the top surface of the bottom plate 17.
[0018] The side wall of the ring body 5 is fixedly connected with a fixing seat 4 , and the bottom surface of the fixing seat 4 is fixedly connected with the top surface of the support plate 1 .
[0019] By adopting the above technical solution, the ring body 5 is installed through the fixing seat 4, and there are two ring bodies 5 on each support plate 1, and the two ring bodies 5 are symmetrically distributed. The two support plates 1 can block the poured concrete to prevent the concrete from flowing sideways. The first nut 7 is mounted on the double-headed screw 9, and the double-headed screw 9 is inserted into the ring mouth 6 of the ring body 5. Then, the second nut 8 is screwed on so that the first nut 7 is located on one side of the ring body 5 and the second nut 8 is located on the other side of the ring body 5. By screwing the first nut 7 and the second nut 8, the distance between the two support plates 1 can be adjusted, and the support plate 1 can be placed in a vertical state, so that the support plate 1 can better support the lateral pressure during concrete pouring and prevent the support plate 1 from tilting or deforming.
[0020] A first convex plate 2 is fixedly connected to one side of the support plate 1 , and a second convex plate 3 is fixedly connected to the other side of the support plate 1 . The first convex plate 2 corresponds to and matches the second convex plate 3 .
[0021] By adopting the above technical solution, when multiple support plates 1 need to be assembled, the first protruding plate 2 of one support plate 1 can be made to correspond to the second protruding plate 3 of another support plate 1, and the first protruding plate 2 can be made to contact the second protruding plate 3, so that the assembly of the two support plates 1 can be completed to extend the support length.
[0022] A slide groove is provided on the side of the slider 11 facing the support plate 1, and the slide groove is slidably connected to the slide rail 10. A threaded hole 12 is penetrated by the side of the slider 11 facing away from the support plate 1, and one end of the threaded hole 12 extends into the slide groove. A first tightening knob 13 is provided on one side of the slider 11, and the first tightening knob 13 corresponds to and cooperates with the threaded hole 12.
[0023] By adopting the above technical solution, the position of the slider 11 can be adjusted through the mutual cooperation between the slider 11 and the slide rail 10, so as to support different positions of the support plate 1 according to the actual situation on site. After adjusting the position of the slider 11, the first tightening knob 13 is turned. The rod of the first tightening knob 13 is a threaded rod. Through the mutual cooperation between the rod of the first tightening knob 13 and the threaded hole 12, the rod end of the first tightening knob 13 is tightly fitted with the slide rail 10, so that the slider 11 can be limited and fixed.
[0024] A second tightening knob 16 is threadedly provided on the side wall of the cylinder 14 near the cylinder opening, and the rod end of the second tightening knob 16 extends to the cylinder opening of the cylinder 14 .
[0025] By adopting the above technical solution, the rod portion of the second tightening knob 16 is also a threaded rod. By turning the second tightening knob 16 , the extension length of the movable rod 15 can be adjusted to cooperate with the slider 11 to adjust the installation position of the ground nail 18 .
[0026] Working principle: When the utility model is in use, the two support plates 1 are used to block the poured concrete to prevent the concrete from flowing sideways. The first nut 7 is mounted on the double-headed screw 9, and the double-headed screw 9 is inserted into the ring opening 6 of the ring body 5. Then, the second nut 8 is screwed on, so that the first nut 7 is located on one side of the ring body 5, and the second nut 8 is located on the other side of the ring body 5. By screwing the first nut 7 and the second nut 8, the distance between the two support plates 1 can be adjusted, and the support plate 1 can be placed in a vertical state, so that the support plate 1 can better support the lateral pressure during concrete pouring, and avoid the support plate 1 from tilting or deforming.
[0027] Next, the position of the slider 11 can be adjusted by the mutual cooperation between the slider 11 and the slide rail 10, so as to support different positions of the support plate 1 according to the actual situation on site. After adjusting the position of the slider 11, the first tightening knob 13 is turned. The rod of the first tightening knob 13 is a threaded rod. Through the mutual cooperation between the rod of the first tightening knob 13 and the threaded hole 12, the rod end of the first tightening knob 13 is tightly fitted with the slide rail 10, so that the slider 11 can be limited and fixed. By turning the second tightening knob 16, the extension length of the movable rod 15 can be adjusted to cooperate with the slider 11 to adjust the installation position of the ground nail 18;
[0028] When multiple support plates 1 need to be assembled, the first convex plate 2 of one support plate 1 can be made to correspond to the second convex plate 3 of another support plate 1, and the first convex plate 2 can be made to contact the second convex plate 3, so that the two support plates 1 can be assembled to extend the support length.
[0029] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A concrete structure construction anti-deformation support, comprising a support plate (1), characterized in that: A ring body (5) is arranged above the support plate (1), and the ring body (5) includes a ring mouth (6). A double-headed screw (9) is inserted in the ring mouth (6). A first nut (7) is arranged on one side of the ring body (5), and a second nut (8) is arranged on the other side of the ring body (5). The first nut (7) and the second nut (8) are both matched with the double-headed screw (9). The side wall of the support plate (1) is fixedly connected with a slide rail (10), and the side wall of the slide rail (10) is sleeved with a slider (11). The slider (11) is hingedly provided with a cylinder (14) on the side facing away from the slide rail (10), and a movable rod (15) is inserted and slidably connected to the cylinder mouth of the cylinder (14). The movable rod (15) is hingedly connected to a bottom plate (17) at one end away from the cylinder (14), and a ground nail (18) is inserted on the top surface of the bottom plate (17).
2. The anti-deformation bracket for concrete structure construction as claimed in claim 1, characterized in that: The side wall of the ring body (5) is fixedly connected to a fixing seat (4), and the bottom surface of the fixing seat (4) is fixedly connected to the top surface of the support plate (1).
3. The anti-deformation bracket for concrete structure construction as claimed in claim 1, characterized in that: A first convex plate (2) is fixedly connected to one side of the support plate (1), and a second convex plate (3) is fixedly connected to the other side of the support plate (1); the first convex plate (2) corresponds to and matches the second convex plate (3).
4. The anti-deformation support for concrete structure construction as claimed in claim 1, characterized in that: A sliding groove is provided on a side of the sliding block (11) facing the support plate (1), and the sliding groove is slidably connected to the sliding rail (10).
5. The anti-deformation support for concrete structure construction as claimed in claim 4, characterized in that: A threaded hole (12) is provided through a surface of the sliding block (11) that faces away from the support plate (1), and one end of the threaded hole (12) extends into the sliding groove.
6. The anti-deformation support for concrete structure construction as claimed in claim 5, characterized in that: A first tightening knob (13) is provided on one side of the sliding block (11), and the first tightening knob (13) corresponds to and matches the threaded hole (12).
7. The anti-deformation support for concrete structure construction as claimed in claim 1, characterized in that: A second tightening knob (16) is threadedly provided on the side wall of the cylinder (14) near the cylinder mouth, and the rod end of the second tightening knob (16) extends to the cylinder mouth of the cylinder (14).
8. The anti-deformation support for concrete structure construction as claimed in claim 1, characterized in that: There are two ring bodies (5) on each support plate (1), and the two ring bodies (5) are symmetrically distributed.