Cast-in-place layer structure for vertical shaft construction

By using an annular supporting formwork operation platform and an automated concrete casting system in the construction of the vertical shaft, the problem of high labor intensity and low efficiency of pipe sheet assembly in the existing technology is solved, and efficient and automated vertical shaft construction is achieved to adapt to uneven surrounding rocks and Reduced construction costs.

CN222010210UActive Publication Date: 2024-11-15CHINA RAILWAY ELEVENTH BUREAU GROUP FIFTH ENGINEERING CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420800552.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-17
Publication Date
2024-11-15
Estimated Expiration
2034-04-17

AI Technical Summary

Technical Problem

The existing vertical shaft construction pipe sheet assembly method has high labor intensity and low efficiency, and has poor rock formation adaptability, high safety risks and high construction costs.

Method used

The cast-in-place layer structure of the vertical shaft construction includes an annular support mold operation platform, annular bottom formwork, a side formwork and a feeding hoist is adopted. The supporting mold operation platform is fixed on the surrounding rock of the vertical shaft through the power layer, and the side formwork and the annular bottom formwork are assembled into an annular shape. Integrated, automatic concrete casting and demolding is achieved using edge-sealed airbags and mold release cylinders, equipped with plug-in vibrators and electric screw mechanisms for reinforcement and support.

Benefits of technology

It improves construction efficiency, reduces the labor intensity of workers, adapts to uneven surrounding rocks, has a high degree of automation, and effectively reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222010210U_ABST
    Figure CN222010210U_ABST
Patent Text Reader

Abstract

The utility model discloses a vertical shaft construction cast-in-place layer structure which comprises an annular bottom formwork, a plurality of side formworks and a formwork erecting operation platform fixed to vertical shaft surrounding rock, the annular bottom formwork is coaxially arranged on the formwork erecting operation platform, and the position between the periphery of the annular bottom formwork and the vertical shaft surrounding rock is blocked through an edge sealing air bag. The side formworks are vertically supported on the formwork erecting operation platform, the bottoms of the side formworks are hinged to the inner side end of the annular bottom formwork, all the side formworks are spliced into an annular whole on the formwork erecting operation platform, and a demolding oil cylinder is arranged between the back face of each side formwork and the formwork erecting operation platform. The two ends of the demolding oil cylinder are hinged to the upper end of the side formwork and the inner end of the formwork erecting operation platform respectively, a pouring window is further formed in the top of the side wall of the side formwork, the vertical shaft construction cast-in-place layer structure further comprises a feeding winch, the feeding winch is fixed to the upper portion of the vertical shaft, and a concrete conveying hopper is arranged on the feeding winch in a hung mode. The device is high in automation degree and high in construction efficiency, and the labor intensity of operators is effectively reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of shaft excavation, in particular to a cast-in-place layer structure for shaft construction. Background Art

[0002] Existing shaft excavation technology and equipment have various shortcomings, such as poor adaptability to rock formations, high safety risks, high construction costs, and complex construction techniques. At present, the surrounding rock support layer of the shaft is generally assembled in the form of pipe segments. There are two existing ways to assemble pipe segments: one is to complete the shaft first and then assemble the pipe segments, which will greatly delay the construction progress; the other is to assemble the pipe segments while excavating the shaft. This method mostly uses the method of making the shaft wall or sinking the shaft wall with a gantry crane for support. The pipe segments are assembled through a large amount of support, which has high labor intensity and low efficiency for construction workers. Utility Model Content

[0003] In view of the problems existing in the above-mentioned prior art, the utility model aims to provide a cast-in-place layer structure for shaft construction, so as to solve the problems of high labor intensity and low efficiency of the existing segment assembly method.

[0004] In order to achieve the above-mentioned purpose, the utility model proposes a cast-in-place layer structure for shaft construction, comprising a plurality of side formworks, an annular bottom formwork and a formwork working platform fixed on the shaft surrounding rock, the formwork working platform being an annular platform, the outer diameter of the annular bottom formwork being smaller than the diameter of the shaft opening, the annular bottom formwork being coaxially arranged on the formwork working platform, and the outer circle thereof and the shaft surrounding rock being sealed by an edge sealing air bag, the side formwork being vertically supported on the formwork working platform, and the bottom thereof being hinged to the inner end of the annular bottom formwork, all the side formworks are assembled into an annular whole on the formwork working platform, a demoulding cylinder is provided between the back side of each side formwork and the formwork working platform, the two ends of the demoulding cylinder are respectively hinged to the upper end of the side formwork and the inner end of the formwork working platform, and a casting window is also provided on the top of the side wall of the side formwork, the cast-in-place layer structure for shaft construction also comprises a feeding winch, the feeding winch is fixed above the shaft, and a concrete conveying hopper is suspended on the feeding winch.

[0005] In the above scheme: the formwork work platform is fixed on the surrounding rock of the shaft through a power layer, the power layer includes a number of main trusses arranged circumferentially, the main trusses are horizontally erected, one end of each main truss converges at the center of the shaft and is fixed together, and the other end is fixed to the surrounding rock of the shaft through hydraulic support shoes. The formwork work platform is erected on each main truss, with a simple structure and easy layout.

[0006] In the above scheme: each side formwork is also equipped with two inserted vibrators and two retractable electric screw mechanisms. The side formwork is provided with through holes for the inserted vibrators to pass through. The electric screw mechanism is supported between the back of the side formwork and the formwork work platform. The inserted vibrator is used to vibrate the concrete, and the electric screw mechanism plays a supporting and reinforcing role. The two ends of the electric screw mechanism are also hinged with the corresponding side formwork and the formwork work platform.

[0007] In the above scheme: each side formwork is provided with a demoulding bevel, and the supporting surface of the annular bottom formwork is set with a certain slope from the inside to the outside, which is convenient for demoulding on the one hand, and for cleaning the floating slurry generated by vibration when pouring the next mold on the other hand.

[0008] In the above scheme: the outer diameter of the annular bottom template is 5-10 cm smaller than the diameter of the shaft opening to adapt to the uneven initial spraying surface of the shaft surrounding rock.

[0009] The beneficial effects of the utility model are as follows: 1. Concrete slurry can be first transported into the shaft hole through the feeding winch, and concrete can be poured into the space surrounded by the annular bottom template, the side template and the shaft surrounding rock through the pouring window to form a concrete support layer. When the concrete support layer is formed, the side template is driven to flip and demould by the demoulding cylinder; 2. The outer diameter of the annular bottom template is set to be smaller than the diameter of the shaft hole to adapt to the uneven initial spraying surface of the shaft surrounding rock, and the sealing of the edge sealing airbag is conducive to leak prevention; 3. When the deep underground space shaft excavation equipment steps to the next ring position, the side template can be reset under the drive of the demoulding cylinder. In short, the utility model has a high degree of automation and high construction efficiency, and effectively reduces the labor intensity of operators. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 It is a structural schematic diagram of the utility model.

[0011] Figure 2 It is a top view of the utility model.

[0012] Figure 3 It is a schematic diagram of the layout of the feeding winch. DETAILED DESCRIPTION

[0013] like Figure 1 As shown in FIG. 3 , a cast-in-place layer structure for shaft construction is mainly composed of a feeding winch 7, an annular bottom formwork 2, a plurality of side formworks 1 and a formwork operation platform 3 fixed on the surrounding rock of the shaft.

[0014] The formwork platform 3 is an annular platform. The outer diameter of the annular bottom formwork 2 is smaller than the diameter of the shaft opening. The annular bottom formwork 2 is coaxially arranged on the formwork platform 3, and its outer circle is sealed with the surrounding rock of the shaft by an edge sealing airbag 4.

[0015] The side formwork 1 is vertically supported on the formwork work platform 3, and its bottom is hinged to the inner side end of the annular bottom formwork 2; all side formworks 1 are assembled into a ring-shaped whole on the formwork work platform 3. A demoulding cylinder 5 is provided between the back of each side formwork 1 and the formwork work platform 3, and the two ends of the demoulding cylinder 5 are respectively hinged to the upper end of the side formwork 1 and the inner end of the formwork work platform 3, and a pouring window 6 is also provided on the top of the side wall of the side formwork 1.

[0016] The feeding winch 7 is fixed above the shaft, and a concrete conveying hopper is suspended on the feeding winch 7.

[0017] Preferably, the formwork work platform 3 is fixed to the surrounding rock of the shaft through a power layer, and the power layer includes a plurality of main trusses 8 arranged circumferentially, the main trusses 8 are horizontally erected, one end of each main truss 8 converges at the center of the shaft and is fixed together, and the other end is fixed to the surrounding rock of the shaft through a hydraulic support shoe 9. The formwork work platform 3 is erected on each main truss 8, with a simple structure and easy layout.

[0018] Preferably, each side formwork 1 is also equipped with two inserted vibrators 10 and two retractable electric screw mechanisms 11. The side formwork 1 is provided with through holes for the inserted vibrators 10 to pass through. The electric screw mechanism 11 is supported between the back of the side formwork 1 and the formwork work platform 3. The inserted vibrators 10 are used to vibrate concrete, and the electric screw mechanism 11 plays a supporting and reinforcing role. The two ends of the electric screw mechanism 11 are also hinged with the corresponding side formwork 1 and the formwork work platform 3.

[0019] Preferably, each side formwork 1 is provided with a demoulding bevel, and the supporting surface of the annular bottom formwork 2 is provided with a certain slope from inside to outside, which is convenient for demoulding on the one hand, and for cleaning the floating slurry generated by vibration when pouring the next mold on the other hand.

[0020] Preferably, the outer diameter of the annular bottom template 2 is 5-10 cm smaller than the diameter of the shaft opening to adapt to the uneven initial blasting surface of the shaft surrounding rock.

[0021] Preferably, a gantry is set above the shaft, and the feeding winch 7 is fixed on the gantry.

Claims

1. A cast-in-place structure for shaft construction, characterized in that: The invention comprises an annular bottom template (2), a plurality of side templates (1) and a formwork operation platform (3) fixed on the surrounding rock of the shaft, wherein the formwork operation platform (3) is an annular platform, the outer diameter of the annular bottom template (2) is smaller than the diameter of the shaft opening, the annular bottom template (2) is coaxially arranged on the formwork operation platform (3), and the outer circle of the annular bottom template and the surrounding rock of the shaft are sealed by edge sealing air bags (4), the side templates (1) are vertically supported on the formwork operation platform (3), and the bottom of the side templates is hinged to the inner side end of the annular bottom template (2), and all the side templates ( 1) are assembled into a ring-shaped whole on a formwork operation platform (3), a demoulding cylinder (5) is provided between the back of each side formwork (1) and the formwork operation platform (3), the two ends of the demoulding cylinder (5) are respectively hinged to the upper end of the side formwork (1) and the inner end of the formwork operation platform (3), and a pouring window (6) is also provided on the top of the side wall of the side formwork (1), and the cast-in-place layer structure of the shaft construction also includes a feeding winch (7), the feeding winch (7) is fixed above the shaft, and a concrete conveying hopper is suspended on the feeding winch (7).

2. The cast-in-place layer structure for shaft construction according to claim 1 is characterized in that: The formwork operation platform (3) is fixed to the surrounding rock of the shaft through a power layer, and the power layer includes a plurality of main trusses (8) arranged circumferentially. The main trusses (8) are horizontally erected, and one end of each main truss (8) converges at the center of the shaft and is fixed together, and the other end is fixed to the surrounding rock of the shaft through a hydraulic support shoe (9). The formwork operation platform (3) is erected on each main truss (8).

3. The cast-in-place layer structure for shaft construction according to claim 1 is characterized in that: Each side formwork (1) is also equipped with two inserted vibrators (10) and two retractable electric screw mechanisms (11); the side formwork (1) is provided with through holes for the inserted vibrators (10) to pass through; the electric screw mechanisms (11) are supported between the back of the side formwork (1) and the formwork work platform (3).

4. The cast-in-place layer structure for shaft construction according to claim 1 is characterized in that: Each side template (1) is provided with a demoulding bevel, and the supporting surface of the annular bottom template (2) is provided with a certain slope from the inside to the outside.

5. The cast-in-place layer structure for shaft construction according to claim 1 is characterized in that: The outer diameter of the annular bottom template (2) is 5-10 cm smaller than the diameter of the shaft opening.

Citation Information

Cited By

  • Deep underground space vertical shaft excavation and tunneling equipment and cast-in-place construction method thereof

    CN118292886A

  • Deep underground space shaft excavation equipment and cast-in-place construction method thereof

    CN118292886B