High-pressure water pipeline and low-pressure water pipeline series connection structure for ironmaking

By designing a series structure between high-pressure water pipes and low-pressure water pipes in ironmaking equipment, the problem of high-pressure water supply interruption in power outages or failures is solved, rapid water replenishment is achieved, and damage and losses of blast furnace equipment are reduced.

CN222011666UActive Publication Date: 2024-11-15LINYI IRON & STEEL INVESTMENT GRP SPECIAL STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420373359.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-28
Publication Date
2024-11-15
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

Existing high-pressure pumps cannot supply water in a timely manner in case of a sudden power outage or equipment failure, resulting in the stop of the blast furnace cooling water, which may cause damage to the blast furnace small sleeve.

Method used

Design a series structure of high-pressure water pipes for iron smelting and low-pressure water pipes. Through the check valve, first and second connecting pipes, first and second gate valves and other components, the low-pressure water pipe main body can quickly adjust the power outage or failure. Cooling water is sent to the main body of the high-pressure water pipe to replenish water in the high-pressure pipe.

Benefits of technology

It effectively reduces damage to blast furnace equipment, reduces the degree of equipment loss, ensures that blast furnace can still obtain cooling water supply in the event of power outage or failure, and reduces unnecessary losses.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222011666U_ABST
    Figure CN222011666U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of ironmaking equipment, and discloses an ironmaking high-pressure water pipeline and low-pressure water pipeline series connection structure which comprises a check valve, a high-pressure water pipe body and a low-pressure water pipe body. A first connection pipeline is detachably arranged at the output end of the check valve, and a second connection pipeline is detachably arranged at the input end of the check valve; the high-pressure water pipe main body is arranged on one side of the first connecting pipeline, and a first gate valve is detachably arranged between the high-pressure water pipe main body and the first connecting pipeline; the low-pressure water pipe body is arranged on one side of the second connection pipeline, and a second gate valve is detachably arranged between the low-pressure water pipe body and the second connection pipeline. In the application, when the high-pressure water cannot be supplied due to sudden power failure or equipment failure, the low-pressure water pipe main body can convey the cooling water into the high-pressure water pipe main body through the second connection pipeline and the first connection pipeline at the first time, so that the high-pressure pipeline is supplemented with water, the cooling water is conveyed to the blast furnace, and unnecessary loss of the blast furnace is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of ironmaking equipment, for example, to a series structure of a high-pressure water pipeline and a low-pressure water pipeline for ironmaking. Background Art

[0002] Since the iron-making operation was put into operation, the high-pressure pump in the central pump room has been required to supply water for cooling the blast furnace sleeve, so the role of high-pressure water is crucial. When the existing high-pressure pump is in use, when it encounters an abnormal situation and cannot supply water in time, there is no auxiliary cooling water for water supply, thus failing to ensure the normal production of the blast furnace, and the blast furnace sleeve may be burned out due to the outage of cooling water.

[0003] Therefore, how to effectively replenish the high-pressure pipeline to deliver cooling water to the blast furnace and reduce losses when a sudden power outage or equipment failure makes it impossible to supply high-pressure water has become a technical problem that needs to be urgently solved by technical personnel in this field. Utility Model Content

[0004] In order to provide a basic understanding of some aspects of the disclosed embodiments, a brief summary is given below. The summary is not an extensive review, nor is it intended to identify key / critical components or delineate the scope of protection of these embodiments, but rather serves as a prelude to the detailed description that follows.

[0005] The disclosed embodiment provides a series structure of a high-pressure water pipeline and a low-pressure water pipeline for ironmaking to solve the problem of how to effectively replenish water in the high-pressure pipeline when a sudden power outage or equipment failure makes it impossible to supply high-pressure water, so as to deliver cooling water to the blast furnace and reduce losses.

[0006] In some embodiments, the high-pressure water pipe and the low-pressure water pipe for iron smelting are connected in series, including: a check valve, a high-pressure water pipe body and a low-pressure water pipe body; the output end of the check valve is detachably provided with a first communication pipe, and the input end of the check valve is detachably provided with a second communication pipe; the high-pressure water pipe body is arranged on one side of the first communication pipe, and a first gate valve is detachably provided between the high-pressure water pipe body and the first communication pipe; the low-pressure water pipe body is arranged on one side of the second communication pipe, and a second gate valve is detachably provided between the low-pressure water pipe body and the second communication pipe.

[0007] The series connection structure of the high-pressure water pipeline and the low-pressure water pipeline for ironmaking provided in the embodiment of the present disclosure can achieve the following technical effects:

[0008] It can reduce damage to blast furnace equipment and lower the degree of equipment loss. When a sudden power outage or equipment failure makes it impossible to supply high-pressure water, the low-pressure water pipe body can immediately send cooling water through the second connecting pipe and the first connecting pipe to the high-pressure water pipe body to replenish the high-pressure pipe and send cooling water to the blast furnace, thereby reducing unnecessary losses for the blast furnace.

[0009] The above general description and the following description are exemplary and explanatory only and are not intended to limit the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] One or more embodiments are exemplarily described by corresponding drawings, which do not limit the embodiments. Elements with the same reference numerals in the drawings are shown as similar elements, and the drawings do not constitute a scale limitation, and wherein:

[0011] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0012] Figure 2 It is an exploded view of the utility model.

[0013] Figure numerals: 1. first communication pipeline; 2. first connection plate; 3. second connection plate; 4. second communication pipeline; 5. third connection plate; 6. fourth connection plate; 7. check valve; 8. first flange; 9. second flange; 10. high-pressure water pipe body; 11. fifth connection plate; 12. first gate valve; 13. third flange; 14. fourth flange; 15. low-pressure water pipe body; 16. sixth connection plate; 17. second gate valve; 18. fifth flange; 19. sixth flange. DETAILED DESCRIPTION

[0014] In order to be able to understand the features and technical contents of the embodiments of the present disclosure in more detail, the implementation of the embodiments of the present disclosure is described in detail below in conjunction with the accompanying drawings. The attached drawings are for reference only and are not used to limit the embodiments of the present disclosure. In the following technical description, for the convenience of explanation, a full understanding of the disclosed embodiments is provided through multiple details. However, one or more embodiments can still be implemented without these details. In other cases, to simplify the drawings, well-known structures and devices can be simplified for display.

[0015] The terms "first", "second", etc. in the specification and claims of the embodiments of the present disclosure and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the terms used in this way can be interchanged where appropriate, so that the embodiments of the embodiments of the present disclosure described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions.

[0016] In the embodiments of the present disclosure, the terms "upper", "lower", "inside", "middle", "outside", "front", "back" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. These terms are mainly intended to better describe the embodiments of the present disclosure and their embodiments, and are not intended to limit the indicated devices, elements or components to have a specific direction, or to be constructed and operated in a specific direction. Moreover, in addition to being used to indicate directions or positional relationships, some of the above terms may also be used to indicate other meanings. For example, the term "upper" may also be used to indicate a certain dependency or connection relationship in certain circumstances. For those of ordinary skill in the art, the specific meanings of these terms in the embodiments of the present disclosure can be understood according to specific circumstances.

[0017] In addition, the terms "disposed", "connected", and "fixed" should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments of the present disclosure can be understood according to specific circumstances.

[0018] Unless otherwise stated, the term "plurality" means two or more.

[0019] In the embodiment of the present disclosure, the character " / " indicates that the preceding and following objects are in an "or" relationship. For example, A / B indicates: A or B.

[0020] The term "and / or" is a description of the association relationship between objects, indicating that three relationships can exist. For example, A and / or B means: A or B, or, A and B.

[0021] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present disclosure may be combined with each other.

[0022] Combination Figure 1-2 As shown, the embodiment of the present disclosure provides a series structure of a high-pressure water pipeline and a low-pressure water pipeline for ironmaking, including: a check valve 7, a high-pressure water pipe body 10 and a low-pressure water pipe body 15; the output end of the check valve 7 is detachably provided with a first communication pipeline 1, and the input end of the check valve 7 is detachably provided with a second communication pipeline 4; the high-pressure water pipe body 10 is arranged on one side of the first communication pipeline 1, and a first gate valve 12 is detachably provided between the high-pressure water pipe body 10 and the first communication pipeline 1; the low-pressure water pipe body 15 is arranged on one side of the second communication pipeline 4, and a second gate valve 17 is detachably provided between the low-pressure water pipe body 15 and the second communication pipeline 4.

[0023] The series structure of the high-pressure water pipeline and the low-pressure water pipeline for ironmaking provided in the embodiment of the present disclosure can reduce damage to blast furnace equipment and reduce the degree of equipment loss. When a sudden power outage or equipment failure makes it impossible to supply high-pressure water, the low-pressure water pipe body 15 can immediately deliver cooling water to the high-pressure water pipe body 10 through the second connecting pipeline 4 and the first connecting pipeline 1 to replenish the high-pressure pipeline and deliver cooling water to the blast furnace, thereby reducing unnecessary losses for the blast furnace.

[0024] Optionally, the input end of the check valve 7 is fixedly connected with a second flange 9, the output end of the check valve 7 is fixedly connected with a first flange 8, and the end of the first communication pipe 1 facing the check valve 7 is fixedly connected with a second connection plate 3, and the second connection plate 3 corresponds to and matches the first flange 8. In this way, by fixing the second connection plate 3 with the first flange 8, the check valve 7 can be installed on the first communication pipe 1. When a power outage or equipment failure occurs and the high-pressure water cannot be supplied, the low-pressure water pipe body 15 can immediately send cooling water to the high-pressure water pipe body 10 through the second communication pipe 4 and the first communication pipe 1 to replenish the high-pressure pipe. The check valve 7 is used to prevent the water in the high-pressure water pipe body 10 from flowing back into the low-pressure water pipe body 15.

[0025] Optionally, the end of the second communication pipe 4 facing the check valve 7 is fixedly connected with a third connection plate 5, and the third connection plate 5 corresponds to and matches the second flange 9. In this way, by fixing the third connection plate 5 to the second flange 9, the check valve 7 can be installed on the second communication pipe 4. When a power outage or equipment failure occurs and the high-pressure water cannot be supplied, the low-pressure water pipe body 15 can immediately send cooling water to the high-pressure water pipe body 10 through the second communication pipe 4 and the first communication pipe 1 to replenish the high-pressure pipe.

[0026] Optionally, the end of the first communication pipeline 1 facing away from the second connection disk 3 is fixedly connected to the first connection disk 2, and the port of the first gate valve 12 is fixedly connected to the fourth flange 14, and the fourth flange 14 corresponds to and cooperates with the first connection disk 2. In this way, by fixing the fourth flange 14 to the first connection disk 2, the first gate valve 12 can be installed on the first communication pipeline 1, and the first gate valve 12 is used to control the unblocking of the first communication pipeline 1.

[0027] Optionally, the end of the first gate valve 12 facing away from the fourth flange 14 is fixedly connected to the third flange 13, and the mouth of the high-pressure water pipe body 10 is fixedly connected to the fifth connection plate 11, and the fifth connection plate 11 corresponds to and matches the third flange 13. In this way, the high-pressure water pipe body 10 can be connected to the first gate valve 12 by fixing the fifth connection plate 11 to the third flange 13, and when the first gate valve 12 is unblocked, the water in the first communication pipeline 1 can enter the high-pressure water pipe body 10.

[0028] Optionally, the end of the second communication pipeline 4 facing away from the third connection disk 5 is fixedly connected to the fourth connection disk 6, and the port of the second gate valve 17 is fixedly connected to the sixth flange 19, which corresponds to and matches the fourth connection disk 6. In this way, the sixth flange 19 is fixed to the fourth connection disk 6, so that the second gate valve 17 can be installed on the second communication pipeline 4, and the second gate valve 17 is used to control the unblocking of the second communication pipeline 4.

[0029] Optionally, the end of the second gate valve 17 facing away from the sixth flange 19 is fixedly connected to the fifth flange 18, and the pipe mouth of the low-pressure water pipe body 15 is fixedly connected to the sixth connection plate 16, and the sixth connection plate 16 corresponds to and matches the fifth flange 18. In this way, the sixth connection plate 16 is fixed to the fifth flange 18, so that the second gate valve 17 can be installed on the low-pressure water pipe body 15.

[0030] The above description and the accompanying drawings sufficiently illustrate the embodiments of the present disclosure to enable those skilled in the art to practice them. Other embodiments may include structural and other changes. The embodiments represent only possible variations. Unless explicitly required, individual components and functions are optional, and the order of operations may vary. Portions and features of some embodiments may be included in or replace portions and features of other embodiments. The embodiments of the present disclosure are not limited to the structures described above and shown in the accompanying drawings, and various modifications and changes may be made without departing from the scope thereof. The scope of the present disclosure is limited only by the appended claims.

Claims

1. A series connection structure of a high-pressure water pipeline and a low-pressure water pipeline for ironmaking, characterized in that: include: A check valve (7), wherein an output end of the check valve (7) is detachably provided with a first communication pipeline (1), and an input end of the check valve (7) is detachably provided with a second communication pipeline (4); A high-pressure water pipe body (10) is arranged on one side of the first communication pipe (1), and a first gate valve (12) is detachably arranged between the high-pressure water pipe body (10) and the first communication pipe (1); The low-pressure water pipe body (15) is arranged on one side of the second communication pipe (4), and a second gate valve (17) is detachably arranged between the low-pressure water pipe body (15) and the second communication pipe (4).

2. The ironmaking high-pressure water pipeline and low-pressure water pipeline series structure according to claim 1 is characterized in that: The input end of the check valve (7) is fixedly connected to a second flange (9), and the output end of the check valve (7) is fixedly connected to a first flange (8).

3. The ironmaking high-pressure water pipeline and low-pressure water pipeline series structure according to claim 2 is characterized in that: A second connection plate (3) is fixedly connected to one end of the first communication pipe (1) facing the check valve (7), and the second connection plate (3) corresponds to and matches the first flange (8).

4. The ironmaking high-pressure water pipeline and low-pressure water pipeline series structure according to claim 2 is characterized in that: One end of the second communication pipe (4) facing the check valve (7) is fixedly connected to a third connection plate (5), and the third connection plate (5) corresponds to and matches the second flange (9).

5. The ironmaking high-pressure water pipeline and low-pressure water pipeline series structure according to claim 3, characterized in that: The end of the first communication pipe (1) facing away from the second connection plate (3) is fixedly connected to the first connection plate (2), and the port of the first gate valve (12) is fixedly connected to the fourth flange (14), and the fourth flange (14) corresponds to and cooperates with the first connection plate (2).

6. The ironmaking high-pressure water pipeline and low-pressure water pipeline series structure according to claim 5, characterized in that: The end of the first gate valve (12) facing away from the fourth flange (14) is fixedly connected to the third flange (13), and the pipe mouth of the high-pressure water pipe body (10) is fixedly connected to the fifth connecting plate (11), and the fifth connecting plate (11) corresponds to and cooperates with the third flange (13).

7. The ironmaking high-pressure water pipeline and low-pressure water pipeline series connection structure according to claim 4, characterized in that: The end of the second communication pipe (4) facing away from the third connection plate (5) is fixedly connected to the fourth connection plate (6), and the port of the second gate valve (17) is fixedly connected to the sixth flange (19), and the sixth flange (19) corresponds to and cooperates with the fourth connection plate (6).

8. The ironmaking high-pressure water pipeline and low-pressure water pipeline series connection structure according to claim 7, characterized in that: The end of the second gate valve (17) facing away from the sixth flange (19) is fixedly connected to the fifth flange (18), and the pipe mouth of the low-pressure water pipe body (15) is fixedly connected to the sixth connecting plate (16), and the sixth connecting plate (16) corresponds to and cooperates with the fifth flange (18).