Highway engineering bridge and culvert abutment back sand filling construction framework
By using the combination technology of river sand filling and water discharge pipeline structure in the backfilling construction of the bridge and culvert platform, the problem of large demand for soil sources in the traditional construction structure is solved, and efficient backfilling of the bridge and culvert platform is achieved, ensuring the construction progress and quality , and use discarded sand for filling, meeting green and environmental protection requirements.
Patent Information
- Application Number
- CN202420398303.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-01
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-03-01
AI Technical Summary
Traditional construction structures have a large demand for cement soil sources in the backfill of bridge and culverts on highway engineering, resulting in extended construction progress and low efficiency, affecting the economics of the project, especially in plain areas where soil resources are scarce.
Adopt abutment structure, step base, river sand backfill layer, drainage pipeline structure and non-woven geotextile layer, and replace traditional lime soil backfill through river sand filling and lime soil edge layer, and combine the drainage pipeline structure to achieve river sand Filling backfilling construction reduces soil source demand and improves construction efficiency.
Effectively alleviate the lack of pressure on soil sources, ensure construction progress and quality, use abandoned sand for filling, meet the requirements of green and environmental protection, and improve the functional practicality and economicality of the construction structure.
Smart Images

Figure CN222025071U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway engineering bridge and culvert abutment backfill construction, in particular to a highway engineering bridge and culvert abutment backfill sand construction framework. Background Art
[0002] In recent years, under the "Belt and Road" initiative, the scale of transportation infrastructure construction has gradually expanded, and highway construction has developed rapidly. For plain areas, earthwork resources are quite scarce, especially when the soil source has not been solved in the early stage, it is very easy to cause serious impact on the roadbed filling construction.
[0003] As the construction of the bridge substructure and beams and slabs progresses relatively quickly, in order to ensure the safety of the bridge structure, during the beam erection construction, especially for the rib-type abutments, the backfill of the abutments should be completed before the beam erection construction.
[0004] From this point of view, the use of traditional construction structure requires a large amount of cement and soil sources, making it difficult to ensure the overall progress of the beam erection construction. The backfill construction period is extended, the construction efficiency is reduced, and it is not conducive to the economic efficiency of the project. Utility Model Content
[0005] To this end, the utility model provides a highway engineering bridge and culvert abutment sand filling construction structure to solve the technical problems in the prior art that the traditional construction structure has a large demand for soil sources during the backfill construction of the roadbed abutment, making it difficult to ensure the overall beam erection construction progress, reducing construction efficiency, and being unfavorable to the economic efficiency of the project.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] A highway engineering bridge and culvert abutment backfill sand construction structure, comprising:
[0008] abutment structure;
[0009] Step base;
[0010] A river sand backfill layer is arranged between the abutment structure and the step base;
[0011] The drainage pipe structure is arranged and laid at the bottom of the river sand backfill layer.
[0012] On the basis of the above technical solution, the utility model is further described as follows:
[0013] As a further solution of the utility model, the abutment structure is fixed to the ground through its bottom embedded component, the step base is fixed on the ground, and the step base is excavated and provided with layered steps corresponding to one side of the abutment structure;
[0014] The river sand backfill layer is arranged between the abutment structure and the layered steps of the step base.
[0015] As a further solution of the utility model, a roadbed layer is paved correspondingly on the top of the river sand backfill layer and the top of the step base.
[0016] As a further solution of the utility model, it also includes:
[0017] The lime soil edging layer is simultaneously paved and arranged on the lateral outer portion of the river sand backfill layer and the lateral outer portion of the roadbed layer.
[0018] As a further solution of the utility model, the lime soil edging layer is set to 6% lime soil edging layer with an overall spacing width of 3m.
[0019] As a further solution of the utility model, a plurality of drainage pipe structures are provided, and the plurality of drainage pipe structures are all laid between the bottom of the river sand backfill layer and the bottom of the lime soil edging layer, and the extension arrangement direction of the plurality of drainage pipe structures is from the bottom of the river sand backfill layer to the bottom of the lime soil edging layer.
[0020] As a further solution of the utility model, each of the drainage pipe structures comprises a drainage pipe body and a flow guide pipe body connected and integrated;
[0021] The drainage pipe body is arranged correspondingly at the bottom of the river sand backfill layer;
[0022] The guide pipe body is arranged correspondingly at the bottom of the lime soil edging layer.
[0023] As a further solution of the utility model, a plurality of drainage holes are evenly provided on the top and side of the drainage pipe body.
[0024] As a further solution of the utility model, the outer side of the drain pipe body and the outer side of the guide pipe body are both covered with a non-woven geotextile layer.
[0025] As a further solution of the utility model, a pavement structure layer is paved correspondingly on the top of the roadbed layer and the top of the lime soil edging layer.
[0026] The utility model has the following beneficial effects:
[0027] This construction structure can effectively complete the river sand backfill construction between the abutment structure and the step base through the river sand backfill layer, and can cooperate with the lime soil edging layer, drainage pipe structure and non-woven geotextile layer to effectively replace the lime soil backfill construction, effectively alleviate the pressure of extreme soil shortage for a certain period of time, complete the initial part of the bridge abutment backfill construction tasks, and ensure the smooth and normal construction of subsequent bridges, culverts and roadbeds, thereby ensuring the construction progress and the overall construction quality is excellent. At the same time, the abandoned sand from river channel repair and foundation pit excavation can be directly used for filling, turning waste into treasure, meeting green environmental protection requirements, and improving the practicality of the structure function. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the implementation methods of the utility model or the technical solutions in the prior art, the drawings required for the implementation methods or the description of the prior art will be briefly introduced below. The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical contents disclosed in the utility model without affecting the effects and purposes that can be achieved by the utility model.
[0029] Figure 1 The present invention is a schematic diagram of the overall plan structure of the sand filling construction framework for the back of a highway engineering bridge and culvert platform provided by an embodiment of the present invention.
[0030] Figure 2 The highway engineering bridge and culvert abutment backfill sand construction framework provided by the embodiment of the utility model corresponds to Figure 1 Schematic diagram of the cross-sectional structure of the middle river sand backfill layer.
[0031] Figure 3 This is one of the cross-sectional structural schematic diagrams of the drainage pipe structure in the sand filling construction framework of the bridge and culvert abutment of a highway project provided by an embodiment of the utility model.
[0032] Figure 4 The present invention is a second schematic cross-sectional view of a drainage pipe structure in a sand-filled construction framework for a bridge or culvert abutment in a highway project provided by an embodiment of the present invention.
[0033] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0034] Abutment structure 1; step base 2; river sand backfill layer 3; roadbed layer 4; lime soil edging layer 5;
[0035] Drain pipe structure 6: drain pipe body 61, drain opening 611, guide pipe body 62;
[0036] Non-woven geotextile layer 7; pavement structure layer 8. DETAILED DESCRIPTION
[0037] The following is a specific embodiment of the present invention. People familiar with the technology can easily understand the other advantages and functions of the present invention from the contents disclosed in this specification. Obviously, the described embodiment is a part of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0038] The terms such as "upper", "lower", "left", "right", and "middle" used in this specification are only for the convenience of description and are not intended to limit the scope of the present invention. Changes or adjustments to their relative relationships shall be deemed to be within the scope of the present invention without substantially changing the technical content.
[0039] like Figures 1 to 4 As shown, the embodiment of the utility model provides a highway engineering bridge culvert abutment backfill sand construction framework, including abutment structure 1, step base 2, river sand backfill layer 3, roadbed layer 4, lime soil edging layer 5, drainage pipe structure 6, non-woven geotextile layer 7 and pavement structure layer 8, which is used to effectively correspond to the abutment structure 1 and the step base 2 through the river sand backfill layer 3 to complete the river sand backfill construction, and can cooperate with the lime soil edging layer 5, drainage pipe structure 6 and non-woven geotextile layer 7 to effectively replace the lime soil backfill construction, effectively alleviate the pressure of extreme lack of soil sources for a certain period of time, complete the initial part of the bridge abutment backfill construction tasks, and ensure the smooth and normal construction of subsequent bridges, culverts and roadbeds, thereby ensuring the construction progress, and the overall construction quality is excellent, and at the same time, the abandoned sand from river channel repair and foundation pit excavation can be directly used for filling, turning waste into treasure, meeting green environmental protection requirements, and improving the practicality of the framework function. The specific settings are as follows:
[0040] Please refer to Figure 1 and Figure 2 The abutment structure 1 is fixed to the ground through its bottom embedded components, the step base 2 is fixed on the ground, and the step base 2 is excavated with layered steps corresponding to one side of the abutment structure 1, and the river sand backfill layer 3 is filled between the layered steps of the step base 2 and the abutment structure 1, so as to effectively form a river sand filling type abutment backfill construction structure.
[0041] Please continue to refer to Figure 1 and Figure 2The top of the river sand backfill layer 3 and the top of the step base 2 are paved with the roadbed layer 4 correspondingly, and the lateral outer portion of the river sand backfill layer 3 and the lateral outer portion of the roadbed layer 4 are synchronously paved with the lime soil edging layer 5, and the lime soil edging layer 5 is set to 6% lime edging soil with an overall spacing width of 3m, so as to improve the bearing stability of the soil layer based on the outer side of the river sand backfill construction structure, and effectively reduce the water content of the soil layer.
[0042] Please refer to Figures 1 to 4 A plurality of drainage pipe structures 6 are laid between the bottom of the river sand backfill layer 3 and the bottom of the lime soil edging layer 5, and the extension arrangement direction of the plurality of drainage pipe structures 6 is from the bottom of the river sand backfill layer 3 to the bottom of the lime soil edging layer 5.
[0043] Specifically, each of the drainage pipe structures 6 includes a drainage pipe body 61 and a guide pipe body 62 that are connected to each other in an integral manner; wherein the drainage pipe body 61 is correspondingly arranged at the bottom of the river sand backfill layer 3, and a plurality of drainage openings 611 are evenly opened at the top and side positions of the drainage pipe body 61, so as to collect the infiltrated water from the river sand backfill layer 3 through the plurality of drainage openings 611 and the drainage pipe body 61; the guide pipe body 62 is correspondingly arranged at the bottom of the lime soil edging layer 5, so as to further transport the infiltrated water collected by the drainage pipe body 61 to the outside through the guide pipe body 62.
[0044] As a preferred solution of the present embodiment, the outer side portions of the drainage pipe body 61 and the outer side portions of the guide pipe body 62 are both covered with the non-woven geotextile layer 7, so as to utilize the water absorption and permeability of the non-woven geotextile layer 7 to further improve the collection efficiency of the infiltrated water and enhance the functional practicality on the basis of the function of the non-woven geotextile layer 7 to effectively prevent the drainage opening 611 from being blocked by river sand.
[0045] Please continue to refer to Figure 1 to Figure 2 A pavement structure layer 8 is paved correspondingly on the top of the roadbed layer 4 and the top of the lime soil edging layer 5, so as to effectively complete the established paving construction framework through the pavement structure layer 8, thereby solving the disadvantage of the traditional construction framework having a large demand for soil sources, ensuring the subsequent overall beam erection construction progress and construction efficiency, and thus improving the overall engineering economy.
[0046] Although the utility model has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements can be made to the utility model. Therefore, these modifications or improvements made without departing from the spirit of the utility model are within the scope of protection claimed by the utility model.
Claims
1. A highway engineering bridge and culvert abutment backfill sand construction structure, It is characterized in that include: abutment structure; Step base; A river sand backfill layer is arranged between the abutment structure and the step base; The drainage pipe structure is arranged and laid at the bottom of the river sand backfill layer.
2. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 1, It is characterized in that The abutment structure is fixed to the ground through its bottom embedded component, the step base is fixed on the ground, and the step base is excavated and provided with layered steps corresponding to one side of the abutment structure; The river sand backfill layer is arranged between the abutment structure and the layered steps of the step base.
3. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 1 or 2, It is characterized in that A roadbed layer is paved correspondingly on the top of the river sand backfill layer and the top of the step base.
4. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 3, It is characterized in that Also includes: The lime soil edging layer is simultaneously paved and arranged on the lateral outer portion of the river sand backfill layer and the lateral outer portion of the roadbed layer.
5. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 4, It is characterized in that The lime soil edging layer is set to be 6% lime soil edging with an overall spacing width of 3m.
6. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 4, It is characterized in that There are several drainage pipe structures, and the several drainage pipe structures are all laid between the bottom of the river sand backfill layer and the bottom of the lime soil edging layer, and the extension arrangement direction of the several drainage pipe structures is from the bottom of the river sand backfill layer to the bottom of the lime soil edging layer.
7. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 6, It is characterized in that Each of the drainage pipe structures comprises a drainage pipe body and a flow guide pipe body which are connected and integrated into one piece; The drainage pipe body is arranged correspondingly at the bottom of the river sand backfill layer; The guide pipe body is arranged correspondingly at the bottom of the lime soil edging layer.
8. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 7, It is characterized in that A plurality of drainage openings are evenly arranged on the top and side of the drainage pipe body.
9. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 7, It is characterized in that The outer side of the drain pipe body and the outer side of the guide pipe body are both covered with a non-woven geotextile layer.
10. The highway engineering bridge and culvert abutment backfill sand construction structure according to claim 4, It is characterized in that A pavement structure layer is paved correspondingly on the top of the roadbed layer and the top of the lime soil edging layer.