Waste incineration power plant deslagging workshop with demisting function
By setting up air supply and exhaust components in the slag discharge workshop of the waste incineration power plant, the hot air at the lower part of the grate is used to accelerate the air circulation, the serious problem of fog is solved, the defog efficiency and operating environment safety are improved, and the maintenance difficulty and cost are reduced .
Patent Information
- Application Number
- CN202420094343.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-15
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-01-15
AI Technical Summary
The fog in the waste incineration power plant slag discharge workshop is severe, resulting in low visibility and high dust content, which affects operation safety and equipment life. At the same time, the existing technology sewage cooling system is complex and difficult to maintain, and there is a risk of cavitation.
The air supply and exhaust components are installed in the slag discharge workshop. The air circulation is accelerated through the air duct and fan, the temperature and air pressure are controlled, the temperature and air pressure are reduced, the temperature in the lower part of the grate is reduced, and the generation of fog vapor is used to provide a stable heat source. Improve the defogging effect.
It has achieved a slag discharge workshop environment with high defog efficiency, reliable operation and low cost, improved the operating environment and energy utilization rate, and reduced safety hazards and maintenance difficulties.
Smart Images

Figure CN222026962U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of garbage incineration, and in particular relates to a slag discharge workshop of a garbage incineration power plant with a demisting function. Background Art
[0002] In the grate-type incinerator used in the waste incineration power plant, after the waste materials are burned violently on the grate, the formed slag finally falls into the slag discharger. After being submerged and cooled, it is discharged from the slag outlet, grabbed by a grab bucket and transported to a transport vehicle, and finally transported to a designated place.
[0003] The hot slag falls from the grate into the slag discharger with water level, which is used to cool the slag and to break up the large pieces of slag so that the slag can be discharged from the slag outlet. This makes the slag carry a lot of hot steam when it is discharged, causing the slag to roll down continuously and the steam to overflow continuously. With the continuous slag discharge every day, the temperature, humidity and dust content in the slag pit workshop are significantly higher than those outdoors. When the low-temperature outdoor air is blown in, it encounters high-temperature, high-humidity and high-dust gas, which easily forms fog and haze, resulting in low visibility and high dust content in the slag pit workshop, which makes the slag crane operator's vision obstructed and inconvenient to operate. There are great safety hazards to personnel and equipment, and it also makes the vehicles entering the workshop have blurred vision and personnel have difficulty breathing. In addition, the gas overflow from the slag pit is also easy to pollute the environment.
[0004] In a waste incineration power plant, the boiler combustion area is located above the grate, where the temperature can reach up to 1000°C. Although the grate is cooled by primary air, the temperature of the grate itself is also around 400°C. By installing a slag leaking pipe and thermal insulation cotton under the grate, the temperature in the grate maintenance passage can also reach up to 60°C. On the one hand, long-term high temperature conditions bring great safety challenges to the equipment and lines in the grate maintenance passage area, and also greatly affect the service life of the equipment and lines; on the other hand, when personnel enter for maintenance, they can only enter for a short time each time because the area is dense, the temperature is high, the air is not circulated, and there is a lot of dust accumulation, which greatly affects the maintenance efficiency and also poses a hidden danger to the safety of the maintenance personnel.
[0005] In Chinese patent CN217829444U, the waste heat from the sewage cooling well is used to heat the slag pit, which involves heat exchangers, heat exchange pipes and other equipment. The heat exchange pipes pass through the heat exchangers, and the resistance along the way increases, resulting in insufficient output of the water pump, which is originally prone to cavitation, and even no water. In addition, the system is also relatively complex, which increases the workload of later maintenance and increases potential risks. Utility Model Content
[0006] The technical problem to be solved by the utility model is to solve the problem of serious fog in the slag pit and provide a slag discharge workshop of a garbage incineration power plant with a demisting function, which has a compact structure, reliable operation, high demisting efficiency and low cost.
[0007] In order to solve the above technical problems, the utility model adopts the following technical solutions:
[0008] A slag discharge workshop of a waste incineration power plant with a defog function comprises a slag pit, a slag lifting operation room, a grab bucket, an air supply assembly and an exhaust assembly; the slag pit is connected to the slag outlet of a slag discharger, the grab bucket is arranged at the top of the slag pit, and an operator controls the operation of the grab bucket in the slag lifting operation room to grab the slag in the slag pit to a transport vehicle; the air supply assembly and the exhaust assembly are used to accelerate the air circulation in the slag discharge workshop, the air outlet of the air supply assembly is arranged at the upper part of the side wall of the slag discharge workshop, and the air inlet of the air supply assembly is located at the bottom of the grate to realize the transportation of hot air from the bottom of the grate to the slag discharge workshop; the air inlet of the exhaust assembly is located at the top of the slag discharge workshop, and the air outlet of the exhaust assembly is connected to the furnace of the incinerator to realize the transportation of air in the slag discharge workshop to the furnace for incineration.
[0009] As a further improvement of the utility model, the air supply component includes: an air duct and an air blower, the input end of the air blower is connected to the gap at the bottom of the grate through the air duct, and the output end of the air blower is connected to the air inlet on the upper part of the side wall of the slag discharge workshop through the air duct, so as to realize the input of dry hot air at 30°C to 60°C at the bottom of the grate into the slag discharge workshop.
[0010] As a further improvement of the utility model, the exhaust assembly includes: an air duct and an exhaust fan, the input end of the exhaust fan is connected to the exhaust port on the top of the slag discharge workshop through the air duct, and the output end of the exhaust fan is connected to the furnace of the incinerator through the air duct to realize the transportation of air in the slag discharge workshop to the furnace for incineration.
[0011] As a further improvement of the utility model, both the air supply fan and the exhaust fan are variable frequency fans.
[0012] As a further improvement of the utility model, a control valve is provided between the output end of the blower and the air inlet; a control valve is provided between the output end of the exhaust fan and the furnace; the control valve is used to control the air inlet and outlet rates in the slag discharge workshop.
[0013] As a further improvement of the present utility model, the control valve adopts a solenoid valve.
[0014] As a further improvement of the utility model, the slag discharge workshop is also provided with a small door and a large door; the small door is used for personnel to enter and exit, and the small door is provided with a door closer; the large door is used for transport vehicles to enter and exit, and the large door is provided with an automatic induction door; when the large door is closed, the interior of the slag discharge workshop is maintained in a slightly negative pressure state of -12Pa to -8Pa through the air supply assembly and the exhaust assembly; when the large door is opened, the interior of the slag discharge workshop is maintained in a slightly positive pressure state of 5Pa to 10Pa through the air supply assembly and the exhaust assembly.
[0015] Compared with the prior art, the advantages of the utility model are:
[0016] The utility model discloses a slag discharge workshop of a garbage incineration power plant with a defogger function, wherein an air supply component and an exhaust component are arranged in the slag discharge workshop, the air outlet of the air supply component is arranged on the upper part of the side wall of the slag discharge workshop, the air inlet of the air supply component is arranged under the grate, the air supply component extracts the heat under the grate and sends it into the slag discharge workshop; the air inlet of the exhaust component is arranged on the top of the slag discharge workshop, the air outlet of the exhaust component is connected to the furnace of the incinerator, the air supply component and the exhaust component are utilized to accelerate the air circulation in the slag discharge workshop, and the influx of outdoor gas can be controlled, so as to achieve the purpose of lowering the temperature of the channel under the grate and reducing the generation of fog and steam in the slag discharge workshop, and at the same time realize the dual effects of improving the working environment under the grate and defoggering the slag pit, thereby improving the energy utilization rate. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the spatial arrangement principle of the slag pit demisting system in a specific embodiment of the utility model.
[0018] Figure 2 It is a schematic diagram of the plane layout principle of the slag pit demisting system in a specific embodiment of the utility model.
[0019] Legend: 1. Slag pit; 2. Air duct; 3. Blower; 4. Control valve; 5. Small door; 6. Main door; 7. Exhaust vent; 8. Exhaust fan; 9. Air inlet; 10. Slag lifting operation room; 11. Grab bucket; 100. Grate; 101. Drying section grate; 102. Combustion section grate; 103. Burning section grate; 200. Slag discharger. DETAILED DESCRIPTION
[0020] The present invention is further described below in conjunction with the accompanying drawings and specific preferred embodiments, but the protection scope of the present invention is not limited thereby.
[0021] Example
[0022] like Figure 1 and Figure 2As shown, the slag discharge workshop of a waste incineration power plant with a demisting function of the utility model comprises a slag pit 1, a slag hanging operation room 10, a grab 11, an air supply assembly and an exhaust assembly. The slag pit 1 is connected to the slag outlet of the slag discharge machine 200, and the grab 11 is arranged at the top of the slag pit 1. The operator controls the operation of the grab 11 in the slag hanging operation room 10 to realize the grabbing of the slag in the slag pit 1 to the transport vehicle. The air supply assembly and the exhaust assembly are used to accelerate the air circulation in the slag discharge workshop. The air outlet of the air supply assembly is arranged on the upper part of the side wall of the slag discharge workshop, and the air inlet of the air supply assembly is located at the bottom of the grate 100 to realize the hot air under the grate 100 to be transported to the slag discharge workshop. The air inlet of the exhaust assembly is located at the top of the slag discharge workshop, and the air outlet of the exhaust assembly is connected to the furnace of the incinerator to realize the air in the slag discharge workshop to be transported to the furnace for incineration.
[0023] In this embodiment, an air supply component and an exhaust component are arranged in the slag discharge workshop, the air outlet of the air supply component is arranged on the upper part of the side wall of the slag discharge workshop, and the air inlet of the air supply component is located at the lower part of the grate. The air supply component extracts the heat from under the grate and sends it into the slag discharge workshop; the air inlet of the exhaust component is located at the top of the slag discharge workshop, and the air outlet of the exhaust component is connected to the furnace of the incinerator. The air supply component and the exhaust component are used to accelerate the air circulation in the slag discharge workshop, and the influx of outdoor gas can be controlled, thereby achieving the purpose of lowering the temperature of the lower channel of the grate and reducing the generation of fog and steam in the slag discharge workshop, realizing the dual effects of improving the working environment under the grate and demisting the slag pit, and improving energy utilization.
[0024] In this embodiment, the air supply component includes: an air duct 2 and an air blower 3. The input end of the air blower 3 is connected to the gap at the bottom of the grate through the air duct 2, and the output end of the air blower 3 is connected to the air inlet 9 on the upper part of the side wall of the slag discharge workshop through the air duct 2, so as to realize the input of dry hot air at 30°C to 60°C at the bottom of the grate into the slag discharge workshop.
[0025] Specifically, air ducts 2 are arranged in the gaps below the drying grate 101, the combustion grate 102 and the burnout grate 103 to fully extract the dry hot air in the gaps below the grate 100 to improve the utilization rate of thermal energy. The high-temperature hot air below the grate 100 is transported through the air duct 2 without heat exchange and directly sent to the slag discharge workshop through the wall over a short distance, thereby reducing the transportation resistance. In the present embodiment, an exhaust duct 2 is provided at the middle part under the grate 100, and the hot air in the gap under the grate 100 is extracted by the blower 3 and sent to the slag pit, so that the cold air around the grate 100 flows into the gap under the grate 100. On the one hand, it can effectively and continuously reduce the temperature under the grate 100, and because of the air flow, the maintenance personnel will not feel too stuffy, thereby improving the maintenance environment; on the other hand, because the heat dissipation of the grate 100 is stable and continuous, it can also stably and continuously provide a large amount of dry hot air with a temperature of 30°C to 60°C for the slag discharge workshop, thereby ensuring the defog effect of the slag discharge workshop.
[0026] In this embodiment, the exhaust assembly includes: an air duct 2 and an exhaust fan 8. The input end of the exhaust fan 8 is connected to the exhaust port 7 on the top of the slag discharge workshop through the air duct 2, and the output end of the exhaust fan 8 is connected to the furnace of the incinerator through the air duct 2, so as to realize the air in the slag discharge workshop being transported to the furnace for incineration. Furthermore, both the air supply fan 3 and the exhaust fan 8 are variable frequency fans.
[0027] like Figure 1 As shown, in this embodiment, a control valve 4 is provided between the output end of the blower 3 and the air inlet 9; a control valve 4 is provided between the output end of the exhaust fan 8 and the furnace. The control valve 4 is used to control the air inlet and outlet rates in the slag discharge workshop. Further, the control valve 4 is a solenoid valve.
[0028] like Figure 2 As shown, in this embodiment, the slag discharge workshop is further provided with a small door 5 and a large door 6. The small door 5 is used for personnel to enter and exit, and the small door 5 is provided with a door closer. The large door 6 is used for transport vehicles to enter and exit, and the large door 6 is provided with an automatic induction door; when the large door 6 is closed, the interior of the slag discharge workshop is maintained at a slight negative pressure state of -12Pa to -8Pa through the air supply component and the exhaust component; when the large door 6 is opened, the interior of the slag discharge workshop is maintained at a slight positive pressure state of 5Pa to 10Pa through the air supply component and the exhaust component.
[0029] Specifically, there are two factors that cause fogging in the slag pit: the temperature and humidity in the slag pit. High humidity is caused by the slag being cooled by the slag discharger and carrying water vapor with it. This is related to the cooling method and is not studied in this utility model. When the temperature is lower than the dew point temperature of the humid air in the slag discharge workshop, fog will continue to form in the slag pit, which is also the main reason for fogging in the slag pit. Therefore, increasing the temperature in the slag discharge workshop or reducing the intrusion of cold air can solve the problem of fogging. The dew point temperature can be calculated according to the Magnus-Tetens approximation method, and the calculation formula is as follows:
[0030]
[0031]
[0032] in:
[0033] T d : is the dew point temperature, unit: ℃;
[0034] T: temperature, unit: °C
[0035] RH: relative humidity, unit: %
[0036] a: constant, 17.27
[0037] b: constant, 237.7℃
[0038] Select two states of the slag discharge workshop for calculation: state 1: temperature 20℃, humidity 50%; state 2: temperature 20℃, humidity 80%. According to the formula calculation, in state 1, T d1 =9.3℃; in state 2, T d2 =16.4℃.
[0039] By comparison, it can be seen that under the condition of 20℃, the higher the humidity, the higher the dew point temperature, that is, the easier it is to condense. It also shows that when the temperature is 20℃ and above and the humidity is between 50% and 80%, there will be no condensation as long as the temperature in the slag pit is controlled not lower than 16.4℃.
[0040] In order to maintain the temperature in the slag discharge workshop above 20℃ and prevent the intrusion of cold air below 16.4℃, two aspects are mainly taken into consideration: one is to reduce the intrusion of cold air, and the other is to control the temperature in the slag discharge workshop at 20-30℃.
[0041] The intrusion of cold air mainly comes from the small door 5 and the big door 6 of the slag discharge workshop. In order to avoid the big door 6 being open for a long time and considering the entry and exit of vehicles, the big door 6 is set as an automatic sensing door. When the vehicle approaches the big door, it will open automatically, and when the vehicle leaves, it will close in time. At the same time, a door closer is set for the small door 5. When people enter and exit, they can push it open with a little force, and it will close automatically after leaving.
[0042] On the basis of the modification of gate 6, if other heat sources are not considered, the temperature and humidity of the slag after cooling will still condense when encountering external cold air, especially in winter. Therefore, the temperature of the slag discharge workshop itself cannot achieve the effect of complete demisting, and it is necessary to introduce external heat sources to increase the temperature in the slag discharge workshop. Considering the high ambient temperature under the grate, an air duct can be led from under the grate to the slag discharge workshop, and the hot air under the grate can be pumped into the slag discharge workshop to provide a stable and continuous heat source for the slag discharge workshop. In order to avoid gas overflow in the slag discharge workshop, an opening is opened from the top of the slag discharge workshop to lead the air duct to the gas pipeline for boiler combustion.
[0043] After adding external heat source and modifying gate 6, fogging in the slag discharge workshop is greatly reduced. In order to avoid the influence of extreme weather on fogging in the slag discharge workshop, it is necessary to control the air pressure in the slag discharge workshop. When the automatic gate 6 is closed, the slag discharge workshop maintains a slight negative pressure (-10Pa). When the automatic gate 6 is opened, the air pressure is gradually increased to maintain a slight positive pressure (+5Pa). This can not only ensure the gas overflow in the slag discharge workshop, but also minimize the intrusion of cold air. The air pressure control can be automatically adjusted by adjusting the opening of the outlet door of the blower 3 and the exhaust fan 8.
[0044] Although the utility model is disclosed as above with preferred embodiments, it is not intended to limit the utility model. Any technician familiar with the art can use the above disclosed methods and technical contents to make many possible changes and modifications to the technical solution of the utility model without departing from the spirit and technical solution of the utility model, or modify it into an equivalent embodiment with equivalent changes. Therefore, any simple modification, equivalent replacement, equivalent change and modification made to the above embodiments according to the technical essence of the utility model without departing from the content of the technical solution of the utility model still falls within the scope of protection of the technical solution of the utility model.
Claims
1. A slag discharge workshop of a waste incineration power plant with a demisting function, characterized in that: The invention comprises a slag pit (1), a slag lifting operation room (10), a grab bucket (11), an air supply component and an exhaust component; the slag pit (1) is connected to the slag outlet of the slag discharger (200); the grab bucket (11) is arranged at the top of the slag pit (1); an operator controls the operation of the grab bucket (11) in the slag lifting operation room (10) to grab the slag in the slag pit (1) and put it into a transport vehicle; the air supply component and the exhaust component are used to accelerate the air circulation in the slag discharge workshop; the air outlet of the air supply component is arranged at the upper part of the side wall of the slag discharge workshop; the air inlet of the air supply component is located at the lower part of the grate (100) to realize the hot air under the grate (100) to be transported to the slag discharge workshop; the air inlet of the exhaust component is located at the top of the slag discharge workshop; the air outlet of the exhaust component is connected to the furnace of the incinerator to realize the air in the slag discharge workshop to be transported to the furnace for incineration.
2. The slag discharge workshop of a waste incineration power plant with a demisting function according to claim 1 is characterized in that: The air supply assembly comprises: an air duct (2) and an air blower (3); the input end of the air blower (3) is connected to the gap below the grate (100) through the air duct (2); the output end of the air blower (3) is connected to the air inlet (9) at the upper part of the side wall of the slag discharge workshop through the air duct (2), so that dry hot air at a temperature of 30°C to 60°C below the grate is input into the slag discharge workshop.
3. The slag discharge workshop of a waste incineration power plant with a demisting function according to claim 2 is characterized in that: The exhaust assembly comprises: an air duct (2) and an exhaust fan (8); the input end of the exhaust fan (8) is connected to an exhaust port (7) at the top of a slag discharge workshop through the air duct (2); the output end of the exhaust fan (8) is connected to the furnace of an incinerator through the air duct (2), so as to transport air in the slag discharge workshop to the furnace for incineration.
4. The slag discharge workshop of a waste incineration power plant with a demisting function according to claim 3 is characterized in that: The air supply fan (3) and the exhaust fan (8) are both variable frequency fans.
5. The slag discharge workshop of a waste incineration power plant with a demisting function according to claim 3, characterized in that: A control valve (4) is provided between the output end of the blower (3) and the air inlet (9); a control valve (4) is provided between the output end of the exhaust fan (8) and the furnace; the control valve (4) is used to control the air inlet and outlet rates in the slag discharge workshop.
6. The slag discharge workshop of a waste incineration power plant with a demisting function according to claim 5, characterized in that: The control valve (4) is a solenoid valve.
7. The slag discharge workshop of a waste incineration power plant with a demisting function according to claim 3, characterized in that: The slag discharge workshop is also provided with a small door (5) and a large door (6); the small door (5) is used for personnel to enter and exit, and the small door (5) is provided with a door closer; the large door (6) is used for transport vehicles to enter and exit, and the large door (6) is provided with an automatic sensing door; when the large door (6) is closed, the interior of the slag discharge workshop is maintained at a slightly negative pressure state of -12Pa to -8Pa through the air supply component and the exhaust component; when the large door (6) is opened, the interior of the slag discharge workshop is maintained at a slightly positive pressure state of 5Pa to 10Pa through the air supply component and the exhaust component.