Steel pipe hot piercing plug

By adopting triangular reinforcement rod structure and cooling pipe in the heat perforated head of steel pipes and combining the design of lubricating chutes, the problems of shaking and compressive resistance reduction caused by uneven pressure in the production of seamless steel pipes are solved, and the perforation process is improved The stability and durability extend the service life of the head.

CN222036326UActive Publication Date: 2024-11-22CHANGZHOU YUYUAN METAL MATERIAL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420744062.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-11
Publication Date
2024-11-22
Estimated Expiration
2034-04-11

AI Technical Summary

Technical Problem

During the production process of seamless steel pipes, the head is susceptible to uneven pressure, resulting in shaking, offset and compressive resistance, which in turn affects the perforation accuracy and quality, and insufficient internal support may lead to deformation or damage.

Method used

A steel pipe heat perforated head is designed, and a limiting block and a triangular reinforcement rod structure are arranged in the head body, combining cooling pipes and lubrication chutes to ensure uniform support and reduce friction, and improve stability and durability.

Benefits of technology

Effectively disperse pressure, reduce stress concentration, improve head durability and thermal stability, extend service life, and reduce deformation and damage risks through uniform support and cooling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222036326U_ABST
    Figure CN222036326U_ABST
Patent Text Reader

Abstract

The utility model relates to a steel pipe hot piercing plug, which belongs to the technical field of plugs and comprises a plug end, a plug body is mounted at the right end of the plug end, a limit block is mounted on the inner wall of the plug body, and a support block is mounted on the left side wall of the limit block. The top head has the advantages that the top head end is arranged to be of the taper structure so that friction and resistance in the perforating process can be reduced, then the first reinforcing rod and the second reinforcing rod form the triangular structure, the inner wall of the top head body is evenly supported through the supporting blocks, it is guaranteed that the inner wall of the top head body is evenly supported in all directions, and the perforating effect is improved. According to the technical scheme, deformation or damage caused by uneven stress in the working process of the ejector head can be reduced, pressure from a pipe blank can be effectively dispersed, stress concentration of the ejector head in the perforating process is reduced, and therefore the durability of the ejector head is improved; forces from all directions can be effectively resisted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of plugs, in particular to a hot perforation plug for a steel pipe. Background Art

[0002] Among the seamless steel pipe production equipment of metallurgical enterprises, the piercing machine is the main equipment for seamless steel pipe production. In the process of rolling seamless steel pipes or high-temperature alloy pipes, the round steel billet heated to the specified temperature is first pierced and rolled into a seamless steel pipe using a header on the piercing machine.

[0003] The plug may be easily affected by the uneven pressure from the tube during operation, causing the plug to shake or deviate, which will not only affect the accuracy and quality of the perforation, but also increase the risk of plug damage. Insufficient internal support will cause the overall compressive resistance of the plug to decrease. During the perforation process, the plug needs to withstand the high pressure from the tube. If the support structure is not strong enough, the plug may be deformed or damaged due to uneven force. In response to the above situation, we have launched a steel pipe hot perforation plug. Utility Model Content

[0004] The utility model aims to provide a hot perforation plug for a steel pipe, so as to solve the problem of poor internal support effect in the above-mentioned background technology.

[0005] The technical solution of the utility model is:

[0006] A plug end, the right end of which is equipped with a plug body, a limit block is installed on the inner wall of the plug body, a support block is installed on the left wall of the limit block, a first reinforcing rod is installed on the upper end surface of the support block, a second reinforcing rod is installed on the inner wall of the first reinforcing rod, a first cooling pipe passes through the interior of the plug body, and a second cooling pipe flows through the left end of the first cooling pipe.

[0007] Furthermore, a locking plate is installed on the right side wall of the top head body, a mounting hole is opened inside the locking plate, a connecting shaft is installed on the outer wall of the mounting plate, a locking bracket is installed on the outer surface of the connecting shaft, and a locking bolt is installed inside the locking bracket.

[0008] After the plug body is connected to the punching machine connecting rod, the locking bracket is rotated along the connecting axis, the locking bracket is aligned with the locking plate, and then the locking bolt is rotated to connect with the mounting hole, and the installed plug body is further locked to ensure that it is not easy to loosen or fall off during the punching process, thereby improving the stability of the entire punching process.

[0009] Furthermore, lubrication grooves are evenly arranged on the outer wall of the plug body.

[0010] Lubrication grooves are opened on the outer surface or a lubrication coating is applied so that the lubricant can be evenly distributed on the contact surface between the plug and the tube blank, reducing the friction between the plug and the tube blank.

[0011] The utility model provides a steel pipe hot perforation plug through improvement, which has the following improvements and advantages compared with the prior art:

[0012] First, the utility model sets a tapered structure at the end of the plug to reduce friction and resistance during the punching process, and then the first reinforcing rod and the second reinforcing rod form a triangular structure to evenly support the inner wall of the plug body through the support block, ensuring that the inner wall of the plug body is evenly supported in all directions, which helps to reduce deformation or damage of the plug caused by uneven force during operation, can effectively disperse the pressure from the tube blank, reduce the stress concentration of the plug during the punching process, thereby improving the durability of the plug, and the triangular structure is a very stable structural form, which can effectively resist forces from all directions.

[0013] Second: In the utility model, the first cooling pipe and the second cooling pipe are in a flow structure, which is used for cold water to enter the first cooling pipe and then be discharged through the second cooling pipe, so as to facilitate the removal of internal heat, effectively reduce the temperature of the plug during operation, improve its thermal stability and durability, and reduce the thermal stress and thermal fatigue of the plug body, thereby extending its service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The utility model is further explained below in conjunction with the accompanying drawings and embodiments:

[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0016] Figure 2 This is a schematic diagram of the connection structure of the plug body of the utility model;

[0017] Figure 3 It is a schematic diagram of the internal structure of the plug body of the utility model.

[0018] Explanation of the accompanying drawings: 1. head end; 2. head body; 201. limit block; 202. support block; 203. first reinforcement rod; 204. second reinforcement rod; 3. first cooling pipe; 4. second cooling pipe; 5. threaded groove; 6. locking plate; 7. mounting hole; 8. threaded bolt; 9. mounting plate; 10. punch connecting rod; 11. connecting shaft; 12. locking bracket; 13. locking bolt; 14. lubrication groove. DETAILED DESCRIPTION

[0019] The following will be combined with the attached Figures 1 to 3The utility model is described in detail, and the technical solutions in the embodiments of the utility model are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0020] The utility model provides a steel pipe hot perforation plug through improvement, such as Figure 1-Figure 3 As shown, it includes a head end 1, a head body 2 is installed at the right end of the head end 1, a limit block 201 is installed on the inner wall of the head body 2, a support block 202 is installed on the left wall of the limit block 201, a first reinforcing rod 203 is installed on the upper end surface of the support block 202, a second reinforcing rod 204 is installed on the inner wall of the first reinforcing rod 203, a first cooling pipe 3 passes through the interior of the head body 2, a second cooling pipe 4 flows through the left end of the first cooling pipe 3, the first reinforcing rod 203 and the second reinforcing rod 204 form a triangular structure, and the first reinforcing rod 203 and the second reinforcing rod 204 are evenly distributed along the outer wall of the support block 202.

[0021] In this embodiment: the plug end 1 is provided with a tapered structure to reduce friction and resistance during the punching process, and then the first reinforcing rod 203 and the second reinforcing rod 204 form a triangular structure to uniformly support the inner wall of the plug body 2 through the support block 202, ensuring that the inner wall of the plug body 2 is uniformly supported in all directions, which helps to reduce the deformation or damage of the plug due to uneven force during operation, can effectively disperse the pressure from the tube blank, reduce the stress concentration of the plug during the punching process, thereby improving the durability of the plug, and the triangular structure is a very stable structural form, which can effectively resist forces from all directions, and then the first cooling pipe 3 and the second cooling pipe 4 are connected through the inside of the plug body 2, and the first cooling pipe 3 and the second cooling pipe 4 are in a flow structure, which is used for the entry of cold water into the first cooling pipe 3 and then discharged through the second cooling pipe 4, so as to facilitate the removal of internal heat, which can effectively reduce the temperature of the plug during operation, improve its thermal stability and durability, and reduce the thermal stress and thermal fatigue of the plug body 2, thereby extending its service life.

[0022] In a preferred embodiment, a threaded groove 5 is opened inside the right end of the head body 2, a threaded bolt 8 is installed inside the threaded groove 5, a mounting plate 9 is installed at the end of the threaded bolt 8, and a puncher connecting rod 10 is installed on the right side wall of the mounting plate 9. The threaded groove 5 is connected to the puncher connecting rod 10 on the mounting plate 9 through the threaded bolt 8.

[0023] In a preferred embodiment, a locking plate 6 is installed on the right side wall of the plug body 2, a mounting hole 7 is opened inside the locking plate 6, a connecting shaft 11 is installed on the outer wall of the mounting plate 9, a locking bracket 12 is installed on the outer surface of the connecting shaft 11, and a locking bolt 13 is installed inside the locking bracket 12. When the plug body 2 is connected to the punching machine connecting rod 10, the locking bracket 12 is rotated along the connecting shaft 11 to align the locking bracket 12 with the locking plate 6, and then the locking bolt 13 is rotated to connect with the mounting hole 7, and the installed plug body 2 is further locked to ensure that it is not easy to loosen or fall off during the punching process, thereby improving the stability of the entire punching process.

[0024] In a preferred embodiment, lubrication grooves 14 are evenly formed on the outer wall of the plug body 2. Lubrication grooves 14 are formed on the outer surface or a lubrication coating is applied so that the lubricant can be evenly distributed on the contact surface between the plug and the tube blank, thereby reducing the friction between the plug and the tube blank.

[0025] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A hot perforation plug for a steel pipe, characterized in that: The invention comprises a mandrel end (1), a mandrel body (2) being installed at the right end of the mandrel end (1), a limit block (201) being installed on the inner wall of the mandrel body (2), a support block (202) being installed on the left side wall of the limit block (201), a first reinforcing rod (203) being installed on the upper end surface of the support block (202), a second reinforcing rod (204) being installed on the inner wall of the first reinforcing rod (203), a first cooling pipe (3) passing through the interior of the mandrel body (2), and a second cooling pipe (4) flowing through the left end of the first cooling pipe (3).

2. A hot perforation plug for a steel pipe according to claim 1, characterized in that: The first reinforcing rod (203) and the second reinforcing rod (204) form a triangular structure, and the first reinforcing rod (203) and the second reinforcing rod (204) are evenly distributed along the outer wall of the support block (202).

3. The hot perforation plug for steel pipe according to claim 1, characterized in that: A thread groove (5) is provided inside the right end of the plug body (2).

4. A hot perforation plug for a steel pipe according to claim 3, characterized in that: A threaded bolt (8) is installed inside the threaded groove (5), a mounting plate (9) is installed at the end of the threaded bolt (8), and a punching machine connecting rod (10) is installed on the right side wall of the mounting plate (9).

5. The hot perforation plug for steel pipe according to claim 1, characterized in that: A locking plate (6) is installed on the right side wall of the mandrel body (2), and a mounting hole (7) is provided inside the locking plate (6).

6. A hot perforation plug for a steel pipe according to claim 4, characterized in that: A connecting shaft (11) is installed on the outer wall of the mounting plate (9), a locking bracket (12) is installed on the outer surface of the connecting shaft (11), and a locking bolt (13) is installed inside the locking bracket (12).

7. The hot perforation plug for steel pipe according to claim 1, characterized in that: The outer wall of the plug body (2) is evenly provided with lubrication grooves (14).