Pneumatic conveying device for dried sludge
By designing the pneumatic conveying device for drying sludge, the air pressure push and clear airflow are used to solve the odor and high maintenance costs in the conveying method of the drying sludge scraper, and the smooth transportation and efficiency of the drying sludge are achieved. Clearing the blockage improves the transmission efficiency and speed of clearing the blockage.
Patent Information
- Application Number
- CN202323662501.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-29
AI Technical Summary
The existing scraper conveying methods of dry sludge have problems such as high odor, complex configuration of dust fan, and inability to achieve vertical conveying and high construction and maintenance costs.
A pneumatic conveying device for drying sludge is designed, including a drying sludge silo, crusher, silo, rotary feeder and drying sludge front silo. The drying sludge is pushed to the conveying pipeline by air pressure, and the use of The tracheal replenishment pipe, clearing and blocking tracheal and pressure gauge achieves smooth delivery and blocking, reducing the accumulation of bonds.
It realizes smooth transportation and efficient blocking of dry sludge, reduces construction and maintenance costs, avoids odor leakage, and improves conveying efficiency and blocking speed.
Smart Images

Figure CN222063426U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of pneumatic conveying, in particular to a pneumatic conveying device for drying sludge. Background Art
[0002] As my country accelerates the pace of building a resource-saving and environmentally friendly society, in order to solve the dilemma of "sludge siege" and the pain points of urban development, the harmless and resource-based disposal of sludge has become imminent. At present, the disposal method of sludge coupled power generation is becoming more and more mature. The harmless and resource-based disposal process of sludge generally first dries the wet sludge with a high humidity content. The humidity of the dried sludge after drying is generally below 45%. The dried sludge discharged from the dryer is generally transported to the dry sludge bin near the dryer by a scraper, and then transported by car to the dry sludge furnace warehouse near the boiler front coal conveying system, or transported from the dry sludge bin to the dry sludge furnace warehouse by a scraper, and finally unloaded from the dry sludge furnace warehouse to the coal conveying system and enter the boiler for incineration to achieve harmless and resource-based disposal of sludge.
[0003] However, due to the strong odor of dried sludge, a dust extraction fan must be installed when conveying it by a scraper conveyor to exhaust air from the scraper conveyor to prevent odor leakage. At the same time, the scraper arrangement is complex, vertical conveying cannot be achieved, there are many rotating parts, and the construction and maintenance costs are high. Utility Model Content
[0004] The purpose of the utility model is to provide a pneumatic conveying device for dried sludge to solve the problems raised in the above background technology.
[0005] In order to solve the above technical problems, the utility model adopts the following technical solutions.
[0006] The utility model provides a pneumatic conveying device for dried sludge, comprising a dried sludge bin, a crusher, a silo, a rotary feeder and a dried sludge front bin which are sequentially connected along a conveying direction, the dried sludge bin receives the dried sludge conveyed by the dryer, a feed valve is arranged between the crusher and the silo, and a pipeline between the rotary feeder and the dried sludge front bin is a conveying pipeline; the pneumatic conveying device for dried sludge also comprises a silo air inlet pipe, a conveying air inlet pipe and a clearing air inlet pipe, the silo air inlet pipe The pipe is connected to the silo, and the silo air valve is provided on the silo air inlet pipe, the conveying air inlet pipe is connected to the head end of the conveying pipeline, and the conveying air inlet pipe is provided with a conveying air valve, the clearing air inlet pipe is connected to the end of the conveying pipeline, and the clearing air inlet pipe is provided with a clearing air valve, the end of the conveying pipeline is also provided with a clearing material valve, and the clearing material valve is arranged downstream of the clearing air inlet pipe; the pneumatic conveying device for dried sludge also includes a pressure gauge for detecting the pressure of the conveying pipeline.
[0007] In some embodiments of the present application, the rotary feeder is of variable frequency type, so that the rotary feeder can control the conveying speed of the dried sludge by changing the rotation speed.
[0008] In some embodiments of the present application, the portion of the conveying pipeline close to the head end is the starting section; the pneumatic conveying device for dried sludge also includes an air supply pipe, which is connected to the starting section of the conveying pipeline, and an air supply valve is provided on the air supply pipe; there are multiple air supply pipes, and the connection positions of each of the air supply pipes are arranged at intervals on the starting section.
[0009] In some embodiments of the present application, the pressure gauge is connected to the starting section.
[0010] In some embodiments of the present application, the pneumatic conveying device for dried sludge also includes a balancing air pipe; the balancing air pipe connects the top of the dried sludge bin and the top of the silo, and a balancing air valve is provided on the balancing air pipe.
[0011] In some embodiments of the present application, the bottom of the drying sludge bin is a horizontally arranged bottom plate; the pneumatic conveying device also includes a unloading slide; the unloading slide is arranged in the drying sludge bin and close to the bottom plate of the drying sludge bin.
[0012] In some embodiments of the present application, a drop pipe is also connected to the bottom of the drying sludge bin, and a drop valve is provided on the drop pipe.
[0013] In some embodiments of the present application, the pipeline between the dried sludge bin and the crusher is a feed pipe; the feed pipe is connected to the bottom of the dried sludge bin, and a gate valve is provided on the feed pipe.
[0014] In some embodiments of the present application, the pneumatic conveying device for dried sludge also includes a feeder air inlet pipe; the feeder air inlet pipe is connected to the rotary feeder, and a feeder air valve is provided on the feeder air inlet pipe.
[0015] In some embodiments of the present application, a bag dust collector is connected to the top of the dried sludge front bin.
[0016] It can be seen from the above technical solutions that the embodiments of the utility model have at least the following advantages and positive effects:
[0017] In the pneumatic conveying device for dried sludge in the embodiment of the utility model, a dried sludge bin can be used to receive and store the dried sludge conveyed by the dryer.
[0018] Silo feeding process: open the feed valve, start the crusher, and the dried sludge bin transports the dried sludge crushed by the crusher to the silo, and the crusher breaks the dried sludge into pieces for easy transportation.
[0019] Conveying process: open the clearing valve, silo air valve, and conveying air valve, and close the clearing valve. Start the rotary feeder, which works at the set frequency to convey the dried sludge in the dried sludge silo to the conveying pipeline. The material is pushed forward by the air pressure provided by the silo air inlet pipe and the conveying air inlet pipe, ensuring that the dried sludge can be smoothly conveyed to the front bin of the dried sludge furnace.
[0020] During the transportation process, when the pressure gauge detects that the pressure in the conveying pipeline is lower than the lower limit setting value of the conveying pressure, it means that all the dry ash sludge in the silo has been fed into the conveying pipeline. However, due to the high humidity and viscosity of the dried sludge, there is a certain degree of adhesion, which inevitably forms a certain degree of adhesion in the conveying pipeline and silo. At this time, close the clearing valve and open the clearing air valve. The airflow enters from the end of the conveying pipeline to the silo. At the same time, start the clearing air intake timer. When the clearing air intake timer is up, close the clearing air valve and open the clearing valve. The high-pressure airflow in the silo pump and the conveying pipeline is instantly depressurized to the front warehouse of the drying sludge furnace. The high-speed airflow at the moment of pressure relief can effectively clean the dried sludge adhered in the conveying pipeline and silo to avoid it becoming thicker and stickier, thereby ensuring smooth transportation.
[0021] During the conveying process, when the pressure gauge detects that the pressure in the conveying pipeline is lower than the conveying end pressure setting value, the rotary feeder is stopped, the silo air inlet valve and the conveying air inlet valve are closed, and the conveying process ends. Then the silo feeding process can be run again.
[0022] Blockage clearing process (blockage clearing process is enabled when the conveying pipeline is blocked): close the blockage clearing valve, silo gas valve and conveying gas valve, open the blockage clearing valve, and the air flow enters from the end of the conveying pipeline to the silo blockage outlet, and starts the blockage clearing gas pressure charging timer at the same time. When the blockage clearing gas pressure charging timer is up, close the blockage clearing valve and open the blockage clearing valve for end back extraction. Thus, a high negative pressure is generated at the blockage to loosen the blockage. At the same time, since there is still a high positive pressure in the conveying pipeline between the blockage and the silo and in the silo, when back extraction is performed from the tail, once the sludge at the blockage is loosened, it will be pressed by the positive pressure to move to the front bin of the dried sludge. In this way, the blockage clearing method of front pressure and back extraction of the conveying pipeline greatly improves the blockage clearing speed and has high blockage clearing efficiency because the pressure difference between the front and rear ends of the blockage during the blockage clearing process is larger than that of the conventional back extraction method. If it is detected that the pressure in the conveying pipeline is less than the set value of the conveying end pressure, the blockage clearing valve is closed and the blockage clearing valve is opened. The system enters the waiting process and the blockage clearing is completed automatically.
[0023] If the pressure in the conveying pipeline is not less than the set value of the conveying end pressure, the system will close the clearing valve, open the clearing air valve, and continue to clear the blockage automatically.
[0024] It should be noted that in the entire clearing process, in order to ensure that a certain positive pressure is always maintained in the conveying pipeline between the blockage and the silo, when the pressure in the conveying pipeline between the blockage and the silo is less than the clearing positive pressure setting value, usually the clearing positive pressure setting value is greater than or equal to 0.2Mpa, the conveying air valve will be opened to supplement the pressure in the conveying pipeline between the blockage and the silo, and the conveying air valve will be closed when the pressure is not less than the clearing positive pressure setting value. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The various objects, features and advantages of the present invention will become more apparent by considering the following detailed description of the preferred embodiments of the present invention in conjunction with the accompanying drawings. The accompanying drawings are only exemplary illustrations of the present invention and are not necessarily drawn to scale. In the accompanying drawings, the same reference numerals always represent the same or similar parts. Among them:
[0026] Figure 1 It is a schematic diagram of the connection structure of a pneumatic conveying device for dried sludge in one embodiment of the utility model.
[0027] Figure 2 It is a flow chart of the silo feeding process.
[0028] Figure 3 It is a flow chart of the conveying process.
[0029] Figure 4 It is a flow chart of the clearing process.
[0030] The accompanying drawings are marked as follows: 1. Drying sludge bin; 11. Feeding pipe; 111. Feeding valve; 112. Gate valve; 2. Crusher; 3. Silo; 4. Rotary feeder; 5. Drying sludge front bin; 51. Bag filter; 6. Conveying pipeline; 61. Clearing valve; 71. Silo air inlet pipe; 711. Silo air valve; 72. Conveying air inlet pipe; 721. Conveying air valve; 73. Clearing air inlet pipe; 731. Clearing air valve; 74. Balancing air pipe; 741. Balancing air valve; 75. Feeder air inlet pipe; 751. Feeder air valve; 76. Air supply pipe; 761. Air supply valve; 77. Air supply main pipe; 771. Air supply main valve; 8. Pressure gauge; 9. Unloading slide. DETAILED DESCRIPTION
[0031] Although the present invention can be easily embodied as embodiments of different forms, only some of the specific embodiments are shown in the drawings and described in detail in this specification. It should be understood that this description should be regarded as an exemplary description of the principles of the present invention and is not intended to limit the present invention to that described herein.
[0032] Thus, a feature indicated in this specification will be used to illustrate one of the features of an embodiment of the utility model, rather than implying that each embodiment of the utility model must have the described feature. In addition, it should be noted that this specification describes many features. Although some features can be combined together to illustrate possible system designs, these features can also be used in other combinations that are not explicitly described. Thus, unless otherwise stated, the described combinations are not intended to be limiting.
[0033] In the embodiments shown in the drawings, the indications of directions (such as up, down, left, right, front and back) used to explain the structure and movement of various elements of the utility model are not absolute but relative. These descriptions are appropriate when these elements are in the positions shown in the drawings. If the descriptions of the positions of these elements change, the indications of these directions also change accordingly.
[0034] See also Figure 1 A pneumatic conveying device for dried sludge provided in one embodiment of the utility model includes a dried sludge bin 1, a crusher 2, a silo 3, a rotary feeder 4 and a dried sludge front bin 5 which are sequentially connected along the conveying direction. The dried sludge bin 1 receives the dried sludge conveyed by the dryer, a feed valve 111 is provided between the crusher 2 and the silo 3, and a pipeline between the rotary feeder 4 and the dried sludge front bin 5 is a conveying pipeline 6.
[0035] The pneumatic conveying device for dried sludge also includes a silo air inlet pipe 71, a conveying air inlet pipe 72 and a clearing air inlet pipe 73. The silo air inlet pipe 71 is connected to the silo 3, and a silo air valve 711 is provided on the silo air inlet pipe 71. The conveying air inlet pipe 72 is connected to the head end of the conveying pipeline 6, and a conveying air valve 721 is provided on the conveying air inlet pipe 72. The clearing air inlet pipe 73 is connected to the end of the conveying pipeline 6, and a clearing air valve 731 is provided on the clearing air inlet pipe 73. A clearing valve 61 is also provided at the end of the conveying pipeline 6, and the clearing valve 61 is provided downstream of the clearing air inlet pipe 73.
[0036] The pneumatic conveying device for dried sludge further comprises a pressure gauge 8 for detecting the pressure of the conveying pipeline 6 .
[0037] Through the above structural design, the dried sludge bin 1 can be used to receive and store the dried sludge transported by the dryer.
[0038] Feeding process of silo 3: open the feed valve 111, start the crusher 2, and the dried sludge silo 1 conveys the dried sludge crushed by the crusher 2 to the silo 3, and the dried sludge is crushed by the crusher 2 for easy transportation.
[0039] Conveying process: open the clearing valve 61, the silo air valve 711, and the conveying air valve 721, and close the clearing valve 731. Start the rotary feeder 4, which works at a set frequency to convey the dried sludge in the dried sludge silo 1 to the conveying pipeline 6. And by relying on the air pressure provided by the silo air inlet pipe 71 and the conveying air inlet pipe 72 to push the material forward, it is ensured that the dried sludge can be smoothly conveyed to the front bin of the dried sludge furnace.
[0040] During the transportation process, when the pressure gauge 8 detects that the pressure in the conveying pipeline 6 is lower than the lower limit setting value of the conveying pressure, it means that the dry ash sludge in the silo 3 has been completely fed into the conveying pipeline 6. However, due to the high humidity and viscosity of the dried sludge, there is a certain degree of adhesion, which inevitably forms a certain degree of adhesion in the conveying pipeline 6 and the silo 3. At this time, the clearing valve 61 is closed and the clearing air valve 731 is opened. The airflow enters from the end of the conveying pipeline 6 to the silo 3, and the clearing air intake timer is started at the same time. When the clearing air intake timer is up, the clearing air valve 731 is closed and the clearing valve 61 is opened. The high-pressure airflow in the silo pump and the conveying pipeline 6 is instantly depressurized to the front silo of the dried sludge furnace. The high-speed airflow at the moment of pressure relief is flushed to effectively clean the dried sludge adhered in the conveying pipeline 6 and the silo 3 to avoid getting thicker and thicker, thereby ensuring smooth transportation.
[0041] During the conveying process, when the pressure gauge 8 detects that the pressure in the conveying pipeline 6 is lower than the conveying end pressure setting value, the rotary feeder 4 is stopped, the silo 3 air inlet valve and the conveying air inlet valve are closed, and the conveying process ends. Then the silo 3 feeding process can be run again.
[0042] Blockage clearing process (blockage clearing process is enabled when the conveying pipeline 6 is blocked): close the blockage clearing valve 61, the silo gas valve 711 and the conveying gas valve 721, open the blockage clearing valve 731, and the airflow enters from the end of the conveying pipeline 6 to the silo 3 to block the outlet. At the same time, start the blockage clearing gas pressure charging timer. When the blockage clearing gas pressure charging timer is up, close the blockage clearing valve 731, and open the blockage clearing valve 61 to perform end back-drawing. Thus, a high negative pressure is generated at the blockage to loosen the blockage. At the same time, since there is still a high positive pressure in the conveying pipeline 6 and the silo 3 between the blockage and the silo 3, when back-drawing is performed from the tail, once the sludge at the blockage is loosened, it will be pressed by the positive pressure to move toward the drying sludge front bin 5. In this way, the blockage clearing method of front pressure and back-drawing through the conveying pipeline 6 is greatly improved in the blockage clearing process because the pressure difference between the front and rear ends of the blockage is larger than that of the conventional back-drawing method, and the blockage clearing speed is greatly improved, and the blockage clearing efficiency is high. If it is detected that the pressure in the conveying pipeline 6 is lower than the set value of the conveying end pressure, the air valve 731 is closed and the material valve 61 is opened, and the system enters the waiting process and the automatic clearing is completed.
[0043] If the pressure in the delivery pipeline 6 is not less than the delivery end pressure setting value, the system closes the clearing valve 61, opens the clearing air valve 731, and the system continues to automatically clear the blockage.
[0044] It should be noted that during the entire unblocking process, in order to ensure that a certain positive pressure is always maintained in the conveying pipe 6 between the blocked point and the silo 3, when the pressure in the conveying pipe 6 between the blocked point and the silo 3 is less than the clearing positive pressure setting value, usually the clearing positive pressure setting value is greater than or equal to 0.2Mpa, the conveying air valve 721 is opened to supplement the pressure of the conveying pipe 6 between the blocked point and the silo 3, and the conveying air valve 721 is closed when the pressure is not less than the clearing positive pressure setting value.
[0045] The pneumatic conveying device for dried sludge further includes a balancing air pipe 74. The balancing air pipe 74 connects the top of the dried sludge bin 1 and the top of the silo 3, and a balancing air valve 741 is provided on the balancing air pipe 74. During the feeding process of the silo 3, the dried sludge bin 1 conveys the dried sludge crushed by the crusher 2 to the silo 3 by opening the balancing air valve 741, and the balancing air pipe 74 can balance the air pressure between the dried sludge bin 1 and the silo 3, so that the conveying of the dried sludge is smoother.
[0046] The pipeline between the dried sludge bin 1 and the crusher 2 is a feed pipe 11, which is connected to the bottom of the dried sludge bin 1 and is provided with a gate valve 112. The gate valve 112 can control the dried sludge bin 1 to convey the dried sludge to the crusher 2 or stop conveying the dried sludge. The gate valve 112 can be a manual gate valve 112 that can be manually controlled.
[0047] The bottom of the drying sludge bin 1 is also connected to a feeding pipe, and a feeding valve is provided on the feeding pipe. The feeding pipe is used to discharge the high-water content sludge with a moisture content greater than 45% that appears when the sludge dryer is abnormal. The feeding valve can control the drying sludge bin 1 to transport the high-water content sludge through the feeding pipe or stop transporting the high-water content sludge.
[0048] The bottom of the dried sludge bin 1 is a horizontally arranged bottom plate, and the pneumatic conveying device further comprises a discharge slide 9, which is arranged in the dried sludge bin 1 and close to the bottom plate of the dried sludge bin 1. During the feeding process of the silo 3, the discharge slide 9 can avoid the problems of the dried sludge in the dried sludge bin 1 not being discharged and arching, thereby ensuring that the dried sludge bin 1 smoothly conveys the dried sludge to the silo 3.
[0049] The rotary feeder 4 is of variable frequency type, so that the rotary feeder 4 can control the conveying speed of the dried sludge by changing the rotation speed. During the conveying process, if the pressure gauge 8 detects that the pressure in the conveying pipeline 6 is higher than the high conveying pressure setting value, the frequency setting value of the rotary feeder 4 is reduced to reduce the conveying speed. When the pressure gauge 8 detects that the pressure in the conveying pipeline 6 is lower than the low conveying pressure setting value, the frequency setting value of the rotary feeder 4 is increased to increase the conveying speed.
[0050] It should be noted that when the pressure gauge 8 detects that the pressure in the conveying pipe 6 is higher than the high set value of the conveying pressure, it means that there is a certain amount of dried sludge accumulation in the conveying pipe 6. Therefore, the set frequency of the rotary feeder 4 should be immediately reduced at this time to prevent the silo 3 from feeding a large amount of material to the conveying pipe 6 to avoid causing drastic fluctuations in the conveying pressure, pipe blockage and other problems.
[0051] In this embodiment, the crusher 2 and the feed valve 111 are both connected to the top of the silo 3 , and the rotary feeder 4 is connected to the bottom of the silo 3 .
[0052] The pneumatic conveying device for dried sludge further includes a feeder air inlet pipe 75, which is connected to the rotary feeder 4 and is provided with a feeder air valve 751. The airflow provided by the feeder air inlet pipe 75 can drive the rotary feeder 4 to convey the dried sludge.
[0053] The part of the conveying pipeline 6 close to the head end is the starting section. The pneumatic conveying device for dried sludge also includes an air supply pipe 76, which is connected to the starting section of the conveying pipeline 6, and an air supply valve 761 is provided on the air supply pipe 76. There are multiple air supply pipes 76, and the connection positions of each air supply pipe 76 on the starting section are arranged at intervals. Due to the low conveying speed in the conveying pipeline 6 in the starting section, and the high moisture content and viscosity of the dry ash sludge, it is easier to produce material-gas separation in the conveying pipeline 6 and cause accumulation. Therefore, the starting section is air-supplemented through multiple air supply pipes 76, and the air pressure is used to push the dried sludge in the starting section to accelerate the transportation and avoid accumulation. In this embodiment, the starting section refers to the conveying pipeline 6 within 50 meters from the head end of the conveying pipeline 6 to the front warehouse of the dried sludge furnace. The connection positions of each air supply pipe 76 on the starting section are spaced 1.5 meters to 10 meters apart. The pressure gauge 8 is connected to the starting section.
[0054] The air supply valve 761 includes an air inlet valve, an orifice plate and a check valve which are connected in sequence along the gas flow direction, and the air supply valve 761 has a built-in pressure measuring device. The built-in pressure measuring device of each air supply valve 761 always automatically detects the pressure at the connection position of the air supply pipe 76 on the starting section. When the pressure in the starting section is higher than the air inlet pressure setting value of the air supply valve 761, the air supply valve 761 is automatically opened to supply air to the delivery pipeline 6. When the pressure at the connection position of the air supply pipe 76 is lower than the air inlet pressure setting value of the air supply valve 761, the air supply valve 761 is automatically closed to stop supplying air to the delivery pipeline 6.
[0055] The silo gas valve 711 includes a manual ball valve, an air intake valve and a check valve connected in sequence along the gas flow direction. The feeder gas valve 751 includes a manual ball valve, an air intake valve and a check valve connected in sequence along the gas flow direction. The conveying gas valve 721 includes a manual ball valve, an air intake valve and a check valve connected in sequence along the gas flow direction. The pneumatic conveying device for dried sludge also includes an air supply main pipe 77, and one end of a plurality of air supply pipes 76 away from the air supply main pipe 77 of the conveying pipeline 6 is commonly connected to the air supply main pipe 77. The air supply main pipe 77 is also provided with an air supply main valve 771, and the air supply main valve 771 includes a manual ball valve, an air intake valve and a check valve connected in sequence along the gas flow direction. The blockage clearing gas valve 731 includes a manual ball valve, a pressure regulating valve, an air intake valve and a check valve connected in sequence along the gas flow direction.
[0056] In this embodiment, the silo air inlet pipe 71, the feeder air inlet pipe 75, the transport air inlet pipe 72, the air supply main pipe 77 and the clearing air pipe are connected to an air source for air supply.
[0057] A bag dust collector 51 is connected to the top of the dried sludge front chamber 5. The gas in the dried sludge front chamber 5 is filtered and dusted by the bag dust collector 51 and then discharged to avoid polluting the environment.
[0058] The following describes the use of the pneumatic conveying device for dried sludge in combination with the above embodiments.
[0059] See also Figure 2 , Feeding process of silo 3: Starting from the waiting stage, the balancing valve and feed valve 111 are opened and the feed timer is started, the unloading slide 9 and the crusher 2 are started, and the dried sludge silo 1 conveys the dried sludge crushed by the crusher 2 to the silo 3, and the dried sludge is crushed by the crusher 2 for easy transportation. When the set value of the waiting feeding time is reached, the unloading slide 9 and the crusher 2 are stopped, the feed valve 111 and the balancing valve are closed, and then the conveying process is turned on.
[0060] See also Figure 3 , Conveying process: open the clearing valve 61, open the silo air valve 711, the feeder air valve 751, the conveying air valve 721 and the air supply valve 761, start the rotary feeder 4 at the designed frequency setting value, and the rotary feeder 4 works at the set frequency to convey the dried sludge in the dried sludge silo 1 to the conveying pipeline 6. And by relying on the air pressure provided by the silo air inlet pipe 71, the feeder air inlet pipe 75, the conveying air inlet pipe 72 and the air supply pipe 76 to push the material forward, it is ensured that the dried sludge can be smoothly conveyed to the front bin of the dried sludge furnace.
[0061] During the conveying process, when the pressure gauge 8 detects that the pressure in the conveying pipeline 6 is higher than the high set value of the conveying pressure, it means that there is a certain amount of dried sludge accumulation in the conveying pipeline 6, and the frequency setting value of the rotary feeder 4 is reduced to reduce the conveying speed. When the conveying pressure is lower than the low set value of the conveying pressure, the frequency setting value of the rotary feeder 4 is increased to increase the conveying speed.
[0062] During the transportation process, when the pressure gauge 8 detects that the pressure in the transportation pipeline 6 is lower than the lower limit setting value of the transportation pressure, it means that the dried sludge in the silo 3 has been completely fed into the transportation pipeline 6. Close the clearing valve 61, open the clearing air valve 731, start the clearing air intake timer, wait for the clearing air intake timer to expire, close the clearing air valve 731, open the clearing valve 61, and the high-pressure airflow in the silo pump and the transportation pipeline 6 is instantly depressurized to the front bin of the dried sludge furnace. Through the flushing of the high-speed airflow at the moment of pressure relief, the dried sludge stuck in the transportation pipeline 6 and the silo 3 is effectively cleaned to avoid getting thicker and stickier, thereby ensuring smooth transportation.
[0063] During the conveying process, when the pressure gauge 8 detects that the pressure in the conveying pipeline 6 is lower than the conveying end pressure setting value, the rotating feeder 4 is stopped, the silo air valve 711, the feeder air valve 751, the conveying air valve 721 and the air supply valve 761 are closed, and the conveying process ends. Then, the waiting stage is entered, and the silo 3 feeding process can be run again.
[0064] See also Figure 4 , clearing process (clearing process is enabled when the conveying pipeline 6 is blocked): first determine whether the pipe is blocked, close the clearing valve 61, the silo air valve 711, the feeder air valve 751, the conveying air valve 721 and the air supply valve 761, open the clearing air valve 731, start the clearing pressure timer, and the air flow enters from the end of the conveying pipeline 6 to the silo 3 to block the outlet. When the clearing air pressure timer is up, close the clearing air valve 731, open the clearing valve 61 to perform end back pumping. Thus, a high negative pressure is generated at the blocked part to loosen the blocked part. At the same time, since there is still a high positive pressure in the conveying pipeline 6 and the silo 3 between the blocked part and the silo 3, when back pumping from the tail, once the sludge at the blocked part is loosened, it will be pressed by the positive pressure to move to the drying sludge front bin 5. In this way, the clearing method of front pressure and back pumping of the conveying pipeline 6 is used. Since the pressure difference between the front and rear ends of the blocked part is larger than that of the conventional back pumping method during the clearing process, the clearing speed is greatly improved, and the clearing efficiency is high. If it is detected that the pressure in the conveying pipeline 6 is lower than the set value of the conveying end pressure, the air valve 731 is closed and the material valve 61 is opened, and the system enters the waiting process and the automatic clearing is completed.
[0065] If the pressure in the delivery pipeline 6 is not less than the delivery end pressure setting value, further determine whether the pressure is less than the clearing positive pressure setting value. If the pressure is less than the clearing positive pressure setting value, open the delivery air valve 721 and the air supply valve 761 to supply air until the pressure in the delivery pipeline 6 is greater than the clearing positive pressure setting value, and then close the delivery air valve 721 and the air supply valve 761.
[0066] If the pressure is greater than the clearing positive pressure setting value, the clearing material valve 61 is closed, the clearing air valve 731 is opened, the clearing pressure charging timer is started, and the system continues to automatically clear the blockage.
[0067] Although the utility model has been described with reference to several typical embodiments, it should be understood that the terms used are illustrative and exemplary, rather than restrictive. Since the utility model can be implemented in a variety of forms without departing from the spirit or essence of the utility model, it should be understood that the above-mentioned embodiments are not limited to any of the aforementioned details, but should be widely interpreted within the spirit and scope defined by the attached claims, so all changes and modifications falling within the scope of the claims or their equivalents should be covered by the attached claims.
Claims
1. A pneumatic conveying device for dried sludge, characterized in that: It includes a dried sludge bin, a crusher, a silo, a rotary feeder and a dried sludge front bin which are sequentially connected along the conveying direction, the dried sludge bin receives the dried sludge conveyed by the dryer, a feed valve is provided between the crusher and the silo, and a pipeline between the rotary feeder and the dried sludge front bin is a conveying pipeline; The pneumatic conveying device for dried sludge further comprises a silo air inlet pipe, a conveying air inlet pipe and a clearing air inlet pipe, wherein the silo air inlet pipe is connected to the silo, and a silo air valve is provided on the silo air inlet pipe, the conveying air inlet pipe is connected to the head end of the conveying pipeline, and a conveying air valve is provided on the conveying air inlet pipe, the clearing air inlet pipe is connected to the end of the conveying pipeline, and a clearing air valve is provided on the clearing air inlet pipe, and a clearing valve is also provided at the end of the conveying pipeline, and the clearing valve is provided downstream of the clearing air inlet pipe; The pneumatic conveying device for dried sludge also includes a pressure gauge for detecting the pressure of the conveying pipeline.
2. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The rotary feeder is of variable frequency type, so that the rotary feeder can control the conveying speed of the dried sludge by changing the rotation speed.
3. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The portion of the delivery pipeline close to the head end is the starting section; The pneumatic conveying device for dried sludge further comprises an air supply pipe, which is connected to the starting section of the conveying pipeline and is provided with an air supply valve; There are a plurality of air supply pipes, and the connection positions of the air supply pipes are arranged at intervals on the starting section.
4. The pneumatic conveying device for dried sludge according to claim 3, characterized in that: The pressure gauge is connected to the starting section.
5. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The pneumatic conveying device for dried sludge also includes a balance air pipe; The balancing air pipe connects the top of the drying sludge bin and the top of the silo, and a balancing air valve is provided on the balancing air pipe.
6. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The bottom of the drying sludge bin is a horizontally arranged bottom plate; The pneumatic conveying device also includes a discharge slide; The unloading slide is arranged in the dried sludge bin and is close to the bottom plate of the dried sludge bin.
7. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The bottom of the drying sludge bin is also connected with a drop pipe, and the drop pipe is provided with a drop valve.
8. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The pipeline between the dried sludge bin and the crusher is a feed pipe; The feed pipe is connected to the bottom of the drying sludge bin, and a gate valve is provided on the feed pipe.
9. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The pneumatic conveying device for dried sludge also includes a feeder air inlet pipe; The feeder air inlet pipe is connected to the rotary feeder, and a feeder air valve is arranged on the feeder air inlet pipe.
10. The pneumatic conveying device for dried sludge according to claim 1, characterized in that: The top of the dried sludge front bin is connected with a bag dust collector.