Underpass railway general auxiliary beam buttress based on fabricated steel structure
By adopting prefabricated steel structure bore beam piers, the problems of long construction period and inability to recycle existing reinforced concrete piers are solved, and faster construction and cost reduction are achieved, while reducing interference to railway transportation.
Patent Information
- Application Number
- CN202323332355.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-07
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-07
AI Technical Summary
The existing reinforced concrete beam piers have a long construction cycle, great interference to railway transportation and cannot be recycled.
Adopt the boom beam piers based on the assembled steel structure, including the piers unit and the connecting assembly, which are composed of steel structural parts, reinforced ribs and cross-dividing plates. The support body and the connecting assembly are fixed by welding, providing convenient assembly and inspection entrance. , and a pad plate and a reinforcement plate are provided on the support body to improve support capacity.
Effectively shorten the construction cycle, reduce construction costs, reduce excavation disturbances on soil, and realize the reuse and convenient maintenance of the brace piers.
Smart Images

Figure CN222065156U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of construction assistance, and in particular relates to a general temporary beam buttress for underpass railway based on an assembled steel structure. Background Art
[0002] Underpass railway overpass projects are usually constructed using the jacking method; during the jacking period, the existing railway must be in normal operation. To ensure the safe operation of the existing railway, a temporary beam must be erected under the railway before the jacking construction; the temporary beam provides support for the railway during construction, thereby ensuring the safe operation of the railway during construction. The temporary beam is erected on the temporary beam pier, and the traditional temporary beam pier is a reinforced concrete structure; it is also large in size, has a long construction period, and has a great interference with railway transportation. In addition, the reinforced concrete structure of the temporary beam pier cannot be recycled. Summary of the invention
[0003] The utility model aims to provide a general temporary beam buttress for underpass railway based on assembled steel structure.
[0004] The utility model provides a general railway underpass beam pier based on an assembled steel structure, comprising n pier units and n-1 connection components; n≥2. The n pier units are fixedly connected in sequence through the connection components. The pier units are steel structural parts, including a support body, a reinforced rib and a diaphragm. The reinforced rib and the diaphragm are both arranged in the inner cavity of the hollow support body. A manhole is provided on the diaphragm.
[0005] Preferably, the connection assembly includes an outer connection plate, an inner connection plate and bolts. A plurality of outer connection plates surround the outer side of the end of the pier unit. Each outer connection plate corresponds to a plurality of inner connection plates. The inner connection plates are arranged in sequence along the length direction of the outer connection plate. Each inner connection plate is connected to the outer connection plate by bolts and nuts. The opposite ends of the side walls of the supporting body in two adjacent pier units extend into the opposite sides of the connection assembly respectively, and are clamped by the inner connection plate and the outer connection plate in the connection assembly. The end of the reinforced rib in the pier unit extends between the corresponding two adjacent inner connection plates.
[0006] Preferably, the end of the side wall of the supporting body extending into the connecting assembly is provided with a plurality of through holes, and the bolts in the connecting assembly pass through the through holes on the supporting body.
[0007] Preferably, a pad is provided at the position of supporting the temporary beam on the pier of the general temporary beam for underpass railway based on the assembled steel structure; the pad is located on the top surface of the supporting body.
[0008] Preferably, a reinforcing plate is provided at a position where the top of the inner side wall of the supporting body is aligned with the pad, and at a position where the bottom of the inner side wall of the supporting body is aligned with the column.
[0009] Preferably, the support body and the reinforcing ribs, the support body and the transverse partition, the transverse partition and the reinforcing ribs, and the reinforcing ribs and the reinforcement plates are all fixed by welding.
[0010] Preferably, the supporting body is in the shape of a square tube and is formed by welding four mother plates.
[0011] Preferably, the width of the upper and lower motherboards is greater than the width of the left and right motherboards.
[0012] Preferably, the reinforcing ribs on the same motherboard are arranged in sequence with equal intervals.
[0013] Preferably, the reinforcing ribs are in the shape of long strips and flat plates. The length direction of the reinforcing ribs is parallel to the length direction of the supporting body. The reinforcing ribs are arranged in sequence and at intervals along the circumferential direction of the inner side wall of the supporting body.
[0014] Preferably, the transverse partitions are arranged at equal intervals in sequence along the length direction of the support body.
[0015] Preferably, the diaphragm is provided with a clearance groove corresponding to the position of each reinforcing rib at the edges around it. Both ends of the clearance groove are provided with a through-welding hole. The reinforcing rib and the diaphragm are welded and fixed together at the through-welding hole.
[0016] The beneficial effects of the utility model are:
[0017] 1. The utility model provides a temporary beam pier of a steel structure, which can effectively shorten the construction period and reduce the time for pouring and curing of traditional concrete piers compared with the temporary beam piers of existing reinforced concrete structures.
[0018] 2. The steel structure temporary beam pier provided by the utility model adopts an assembled structure, which can be easily transported and disassembled, and can be reused, which can effectively reduce the construction cost of the underpass railway overpass project.
[0019] 3. The utility model adopts an internally reinforced steel structure, which has the advantages of smaller volume and less excavation disturbance to the soil compared with traditional concrete piers.
[0020] 4. The internal transverse partition of the utility model is provided with a manhole, so that construction personnel can easily enter the pier unit to assemble adjacent pier units, as well as conduct subsequent steel structure inspection and maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the overall structure of the utility model.
[0022] Figure 2 It is a structural schematic diagram of the buttress unit in the utility model.
[0023] Figure 3 It is a structural schematic diagram of the horizontal partition in the utility model.
[0024] Figure 4 It is a structural schematic diagram of the connecting component in the utility model.
[0025] Figure 5 A simulation diagram of a temporary beam supported by a temporary beam pier provided by the utility model.
[0026] Figure 6 A schematic diagram of stress simulation of the temporary beam pier provided by the utility model.
[0027] Figure 7 This is a schematic diagram of the first-order modal simulation of the temporary beam pier provided by the utility model.
[0028] Figure numerals: 1. pier unit; 2. connecting assembly; 3. pad; 4. reinforcing plate; 1-1. supporting body; 1-1-1. through hole; 1-2. reinforced rib; 1-3. partition; 1-3-1. clearance groove; 1-3-2. through welding hole; 2-1. outer connecting plate; 2-2. inner connecting plate; 2-3. bolt. DETAILED DESCRIPTION
[0029] The utility model is further described below.
[0030] like Figure 1 As shown, a general temporary beam pier for underpass railway based on assembled steel structure includes n pier units 1, n-1 connection components 2, multiple pads 3 and multiple reinforcement plates 4. The n pier units 1 are connected in sequence; two adjacent pier units 1 are connected by the connection component 2. n is determined by the width of the temporary beam to be supported. In this embodiment, n=3.
[0031] like Figure 2 As shown, the pier unit 1 includes a supporting body 1-1, a reinforcing rib 1-2 and a transverse partition 1-3. The supporting body 1-1 is in the shape of a square tube and includes four motherboards; the four motherboards are combined to form a structure with a rectangular longitudinal section. Two adjacent motherboards are fixed by welding; the width of the upper and lower motherboards is greater than the width of the left and right motherboards.
[0032] A plurality of reinforcing ribs 1-2 are arranged on the inner side wall of the support body 1-1; the reinforcing ribs 1-2 are in the shape of long strips and flat plates. The length direction of the reinforcing ribs 1-2 is parallel to the length direction of the support body 1-1. The reinforcing ribs 1-2 are arranged in sequence along the circumferential direction of the inner side wall of the support body 1-1, and surround the inner side wall of the support body 1-1. In some embodiments, the reinforcing ribs 1-2 on the same motherboard are arranged in sequence at equal intervals.
[0033] like Figure 2 and 3As shown, a plurality of diaphragms 1-3 are arranged in the supporting body 1-1. The diaphragms 1-3 are arranged in sequence at equal intervals along the length direction of the supporting body 1-1. The edges of the diaphragms 1-3 are provided with clearance grooves 1-3-1 corresponding to the positions of the reinforcing ribs 1-2, so that the reinforcing ribs 1-2 can pass through the diaphragms 1-3. Welding holes 1-3-2 are provided at both ends of the clearance grooves 1-3-1, so as to facilitate welding between the diaphragms 1-3 and the reinforcing ribs 1-2. A manhole 1-3-3 is provided in the middle of the diaphragm 1-3, so that the staff can enter the interior of the temporary beam pier, disassemble and assemble the connecting assembly 2, and maintain the temporary beam pier.
[0034] like Figure 4 As shown, the connection assembly 2 includes an outer connection plate 2-1, an inner connection plate 2-2 and bolts 2-3. Multiple outer connection plates 2-1 surround the outer side of the end of the pier unit 1. In this embodiment, the number of outer connection plates 2-1 in a connection assembly 2 is the same as the number of mother plates in a pier unit 1, and the lengths correspond one to one.
[0035] Each outer connecting plate 2-1 corresponds to a plurality of inner connecting plates 2-2. The inner connecting plates 2-2 are arranged in sequence along the length direction of the outer connecting plate 2-1. Each inner connecting plate 2-2 is connected to the outer connecting plate 2-1 by bolts 2-3 and nuts. The gap between two adjacent inner connecting plates 2-2 is used to provide space for the reinforcing ribs 1-2 to make way.
[0036] There is a gap between the inner connecting plate 2-2 and the outer connecting plate 2-1; the opposite ends of the side walls of the supporting bodies 1-1 in two adjacent pier units 1 extend into the opposite sides of the connecting assembly 2, and are clamped by the inner connecting plate 2-2 and the outer connecting plate 2-1 in the connecting assembly 2. The ends of each reinforcing rib 1-2 in the pier unit 1 extend into between the corresponding two adjacent inner connecting plates 2-2.
[0037] The end of the side wall of the supporting body 1-1 extending into the connecting assembly 2 is provided with a plurality of through holes 1-1-1. The bolts in the connecting assembly 2 pass through the through holes 1-1-1 on the supporting body 1-1, so as to improve the connection stability between the pier unit 1 and the connecting assembly 2.
[0038] A pad 3 is provided at the position of supporting the temporary beam on the universal temporary beam pier for underpass railway; the pad 3 is located on the top surface of the supporting body 1-1 and is provided along the width direction of the supporting body 1-1. A reinforcing plate 4 is provided at the position where the top of the inner wall of the supporting body 1-1 is aligned with the pad 3, and at the position where the bottom of the inner wall of the supporting body 1-1 is aligned with the column. The reinforcing plate 4 is provided along the width direction of each reinforced rib 1-2 to increase the strength of the stress-bearing position of the temporary beam pier.
[0039] The support body 1-1 and the reinforcing rib 1-2, the support body 1-1 and the transverse partition 1-3, the transverse partition 1-3 and the reinforcing rib 1-2, and the reinforcing rib 1-2 and the reinforcement plate 4 are all fixed by welding.
[0040] The working principle of the utility model is as follows:
[0041] Pillars are set up and guide rails are laid under the railway where a culvert is required, and the pier units are sent under the railway one by one; after each pier unit is moved into place, it is connected to the previous pier unit through a connecting component. After all the pier units are moved into place, a steel structure temporary beam pier is formed to provide support for the temporary beam under the railway.
[0042] The state of the temporary beam pier supporting the temporary beam provided by the utility model is as follows Figure 5 shown.
[0043] The utility model provides a stress simulation of the temporary beam support pier when it is subjected to load. Figure 6 As shown; its bending bearing capacity design value M γ =27930.0kN·m>M max =4536.6kN·m, design value of shear bearing capacity V γ =18480kN>V max =1807.64kN, the bearing capacity meets the requirements of the specification. Its axial stress is 168.0MPa<[σ]=200MPa; shear stress is 79.2MPa<[τ]=120MPa; the maximum effective stress σ v is 142.2MPa, and the yield strength of steel is s =345MPa, safety factor
[0044] from Figure 6 It can be seen that the overall stress of the top and bottom plates is small, and the effective stress at the top and bottom constraints of the piers increases. For the pier connection, the safety factor is 2.43, which is lower than 2.5. The temporary beam, the support constraint part and the web between the two are the weak positions of the box girder. The stress of the box girder piers is concentrated in the above positions. Safety is ensured by optimizing the stiffening ribs at the supports in the future.
[0045] The first-order modal simulation of the temporary beam pier provided by the utility model is as follows Figure 7 As shown; its overall stability verification Local stability check The calculation results of the overall deflection of the structure are shown in the following table. The total deflection is 58.34mm<60.3mm. The structural deflection meets the requirements of the specification.
[0046] The economic and social benefits of this utility model are evaluated as follows:
[0047] Traditional reinforced concrete temporary beam pier:
[0048]
[0049]
[0050] The steel structure temporary beam support provided in this embodiment:
[0051]
[0052] It can be seen from the above two tables that the cost of a pair of steel structure temporary beam piers is approximately 333,136 yuan, excluding labor. The main cost is steel material expenditure. From the above table data, it can be seen that the overall cost of steel piers during the construction phase saves about 176,647 yuan compared to concrete temporary beam piers. However, concrete piers are disposable products. From the perspective of annual use, the second use cost of a single temporary beam pier is 50% lower than the first use. Therefore, in terms of a one-year use cycle of twice, the cost of steel structure piers is about 342,870 yuan less than that of concrete piers. This is an estimate of the economic value generated by the reduction of labor and construction period, and the actual economic benefits generated are far greater than its cost construction costs.
Claims
1. A general-purpose temporary beam pier for underpass railway based on an assembled steel structure, comprising n pier units (1) and n-1 connection components (2); characterized in that: n≥2; n pier units (1) are fixedly connected in sequence through a connecting assembly (2); the pier unit (1) is a steel structure, comprising a supporting body (1-1), a reinforcing rib (1-2) and a transverse partition (1-3); the reinforcing rib (1-2) and the transverse partition (1-3) are both arranged in the inner cavity of the hollow supporting body (1-1); and a manhole (1-3-3) is provided on the transverse partition (1-3).
2. According to claim 1, a general temporary beam pier for underpass railway based on assembled steel structure, characterized in that: The connection assembly (2) comprises an outer connection plate (2-1), an inner connection plate (2-2) and bolts (2-3); a plurality of outer connection plates (2-1) surround the outer side of the end of the pier unit (1); each outer connection plate (2-1) corresponds to a plurality of inner connection plates (2-2); each inner connection plate (2-2) is arranged in sequence along the length direction of the outer connection plate (2-1); each inner connection plate (2-2) is connected to the outer connection plate (2-1) by bolts (2-3) and nuts; the opposite ends of the side walls of the supporting bodies (1-1) in two adjacent pier units (1) extend into the opposite sides of the connection assembly (2) respectively and are clamped by the inner connection plate (2-2) and the outer connection plate (2-1) in the connection assembly (2); the end of the reinforcing rib (1-2) in the pier unit (1) extends between the corresponding two adjacent inner connection plates (2-2).
3. According to claim 2, a general temporary beam pier for underpass railway based on assembled steel structure is characterized by: The end of the side wall of the supporting body (1-1) extending into the connecting assembly (2) is provided with a plurality of through holes (1-1-1); the bolts in the connecting assembly (2) pass through the through holes (1-1-1) on the supporting body (1-1).
4. The general temporary beam buttress for underpass railway based on assembled steel structure according to claim 1 is characterized by: A pad (3) is provided at the position of the supporting beam; the pad (3) is located on the top surface of the supporting body (1-1).
5. The general temporary beam buttress for underpass railway based on assembled steel structure according to claim 4 is characterized by: A reinforcing plate (4) is provided at a position where the top of the inner side wall of the supporting body (1-1) is aligned with the pad (3), and at a position where the bottom of the inner side wall of the supporting body (1-1) is aligned with the column.
6. The general temporary beam buttress for underpass railway based on assembled steel structure according to claim 1 is characterized by: The support body (1-1) and the reinforcing rib (1-2), the support body (1-1) and the transverse partition (1-3), the transverse partition (1-3) and the reinforcing rib (1-2), and the reinforcing rib (1-2) and the reinforcing plate (4) are all fixed by welding.
7. The general temporary beam buttress for underpass railway based on assembled steel structure according to claim 1 is characterized by: The supporting body (1-1) is in the shape of a square tube and is formed by welding four mother plates.
8. The general temporary beam pier for underpass railway based on assembled steel structure according to claim 1, characterized in that: The reinforcing ribs (1-2) are in the shape of long strips and flat plates; the length direction of the reinforcing ribs (1-2) is parallel to the length direction of the supporting body (1-1); and the reinforcing ribs (1-2) are sequentially spaced along the circumferential direction of the inner side wall of the supporting body (1-1).
9. The general temporary beam pier for underpass railway based on assembled steel structure according to claim 1, characterized in that: The transverse partitions (1-3) are arranged in sequence at equal intervals along the length direction of the supporting body (1-1).
10. The general temporary beam buttress for underpass railway based on assembled steel structure according to claim 1, characterized in that: The edges of the transverse partition (1-3) are provided with clearance grooves (1-3-1) corresponding to the positions of the reinforcing ribs (1-2); both ends of the clearance grooves (1-3-1) are provided with through-welding holes (1-3-2); the reinforcing ribs (1-2) and the transverse partition (1-3) are welded and fixed together at the through-welding holes (1-3-2).