Expressway guardrail construction auxiliary device
Through the construction auxiliary device of highway guardrails, the traction rope is used to drive the railing pulley to bending the road railing, which solves the problems of inconvenience and high tension in the existing technology of multi-person cooperation, and improves construction efficiency.
Patent Information
- Application Number
- CN202420626971.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-28
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-03-28
AI Technical Summary
In the construction of highway guardrails, especially in the bend part, the existing technology requires multiple people to cooperate to bend the highway railings, which is relatively inconvenient to construction, and a large tension is required during bending, resulting in low construction efficiency.
A highway guardrail construction auxiliary device is designed, including railing mounting parts, railing pulleys, railing mounting parts and traction ropes. The railing mounting parts and railing mounting parts are disassembled and installed, and the railing pulleys are used to drive the railing pulleys to make the road railing. The plate bends, reducing the tension required for bending, thereby reducing the number of construction workers.
It effectively reduces the number of construction personnel required when bending highway railings, improves construction efficiency, and facilitates the installation and maintenance of highway guardrails.
Smart Images

Figure CN222083413U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of installation tools, and in particular to a highway guardrail construction auxiliary device. Background Art
[0002] Highway guardrails are generally provided at the edge of a highway to prevent vehicles from leaving the highway after an accident, thereby ensuring the safety of vehicle travel.
[0003] Highway guardrails include highway guardrails and highway guardrails. Highway guardrails are fixedly installed on the ground in the vertical direction, and highway guardrails are fixedly installed on highway guardrails and are arranged near the highway. Specifically, for some highway guardrails with higher specifications, the cross-section is usually arranged in a wave shape, and eight fixing holes are opened through the highway guardrail. The eight fixing holes are divided into two groups, and the two groups of fixing holes are respectively located at the two ends of the highway guardrail, and the two groups of fixing holes are arranged near the trough of the highway guardrail.
[0004] In the existing related technology, when constructing the highway guardrail with a wavy cross-section and eight fixing holes, generally a number of highway guardrails are first fixed to the ground, and then a number of highway guardrails are successively installed on the highway guardrails through the fixing holes and bolts along the extension direction of the highway.
[0005] Specifically, in the case of construction on a curved section of a highway, after one end of the highway guardrail is installed on the highway railing by means of four bolts respectively inserted through the fixing holes, it is still necessary to bend it at the construction site according to the actual bending moment of the highway to make the highway guardrail adapt to the curved section of the highway.
[0006] Generally speaking, the bending of highway guardrails needs to be completed by multiple construction workers in collaboration, that is, multiple people work together to push the free end of the highway guardrail so that the free end of the highway guardrail is bent to the position of the highway railing, and then the highway guardrail is installed on the highway guardrail through another four bolts.
[0007] With regard to the above-mentioned related technologies, it requires the cooperation of multiple persons to bend the highway guardrail to a desired position, which makes the construction inconvenient. Summary of the invention
[0008] In order to reduce the number of construction workers required when bending highway guardrails, thereby facilitating the construction of highway guardrails, the present application provides a highway guardrail construction auxiliary device.
[0009] The present application provides a highway guardrail construction auxiliary device that adopts the following technical solution:
[0010] A highway guardrail construction auxiliary device comprises a guardrail mounting part, a guardrail pulley, a guardrail mounting part, a guardrail pulley and a traction rope;
[0011] The railing mounting piece can be detachably mounted on the highway railing, and the railing pulley is rotatably matched with the railing mounting piece;
[0012] The guardrail mounting piece can be detachably mounted on the highway guardrail, and the guardrail pulley is rotatably matched with the guardrail mounting piece;
[0013] One end of the traction rope is installed on the railing installation piece, and the other end of the traction rope is wound around the guardrail pulley and the railing pulley.
[0014] By adopting the above technical solution, the railing mounting member is installed on the highway railing, and the guardrail mounting member is installed on the highway guardrail. Then, the traction rope is pulled so that the guardrail pulley acts as a movable pulley to drive the highway guardrail to bend, thereby reducing the pulling force required to bend the highway guardrail, thereby reducing the number of construction personnel required to bend the highway guardrail, and facilitating the construction of the highway guardrail.
[0015] Optionally, the railing mounting member comprises a first mounting ring, a second mounting ring, a railing screw, a railing nut and a railing wheel frame, and the first mounting ring is provided with a mounting groove;
[0016] One end of the second mounting ring is rotationally matched with the first mounting ring, the railing screw is rotationally matched with the other end of the second mounting ring, and the railing nut is threadedly matched with the railing screw;
[0017] When the railing mounting member is installed on the highway railing, the second mounting ring and the first mounting ring are both tightly fitted on the highway railing, and the railing screw is inserted into the mounting groove, and the railing nut is tightly fitted on the first mounting ring;
[0018] The railing wheel frame is installed on the first installation ring, and the railing pulley is rotatably matched with the railing wheel frame.
[0019] By adopting the above technical solution, when the railing mounting piece is installed on the highway railing, the first mounting ring and the second mounting ring are sleeved on the railing, and then the railing screw is rotated so that the railing screw is inserted into the mounting groove, and finally the railing nut is rotated and tightened so that the railing nut is tightly fitted against the first mounting ring, thereby conveniently completing the installation of the railing mounting piece.
[0020] Optionally, the railing mounting member further comprises a connecting rod, one end of which is mounted on the first mounting ring, and the railing wheel frame is mounted on the other end of the connecting rod.
[0021] By adopting the above technical solution, when the railing mounting piece is installed on the highway railing, the railing pulley is arranged away from the highway railing, so that the highway railing is more easily bent by the traction rope after approaching the highway railing.
[0022] Optionally, the connecting rod includes a horizontal connecting section and a vertical connecting section, the horizontal connecting section is installed on the first mounting ring and arranged along the horizontal direction, and the vertical connecting section is installed on the horizontal connecting section and arranged along the vertical direction.
[0023] By adopting the above technical solution, when the railing mounting piece is installed on the highway railing, the railing pulley is easier to adjust to a height position consistent with the guardrail pulley, so that the traction rope is not easy to slip off the railing pulley or the guardrail pulley.
[0024] Optionally, the guardrail mounting member includes a guardrail mounting rod, a guardrail screw, a guardrail pad, a guardrail nut and a guardrail wheel frame;
[0025] The guardrail screw is installed on the guardrail mounting rod;
[0026] When the guardrail mounting member is mounted on the highway guardrail, the guardrail mounting rod is tightly fitted on one side of the highway guardrail, the guardrail screw is passed through the fixing hole of the highway guardrail, and the guardrail pad is tightly fitted on the other side of the highway guardrail, and the guardrail nut is tightly fitted on the guardrail pad;
[0027] The fence wheel frame is installed on the fence installation rod, and the fence pulley is rotatably matched with the fence wheel frame.
[0028] By adopting the above technical solution, the guardrail pad and the guardrail mounting rod are respectively tightly fitted on both sides of the highway guardrail, so that the guardrail pulley can be stably installed on the highway guardrail with a small thickness.
[0029] Optionally, there are a plurality of the fence pulleys, and the plurality of fence pulleys are rotatably engaged with the fence mounting member, and the traction rope is wound around each fence pulley.
[0030] By adopting the above technical solution, multiple guardrail pulleys simultaneously act as movable pulleys to pull the highway guardrail, which is beneficial to further reduce the pulling force required to bend the highway guardrail, thereby further reducing the number of construction personnel required for bending the highway guardrail.
[0031] Optionally, the clapboard pulley is arranged in an hourglass shape.
[0032] By adopting the above technical solution, the hourglass-shaped guardrail pulley allows the traction rope to slide toward the middle of the guardrail pulley during movement, thereby making it difficult for the traction rope to slide from one guardrail pulley to another during movement.
[0033] Optionally, when the railing mounting piece is installed on a highway railing, the railing mounting piece is arranged close to the bottom of the highway railing.
[0034] By adopting the above technical solution, when bending the highway guardrail located on the outside of the curved part of the highway, the highway guardrail is first bent, and then the highway guardrail is lifted and bypassed around the top of the highway guardrail, so that the highway guardrail is fixedly installed on the side of the highway close to the highway, reducing the occurrence of the situation where the guardrail mounting parts hinder the lifting of the highway guardrail.
[0035] In summary, the present application includes at least one of the following beneficial technical effects:
[0036] 1. Install the railing mounting parts on the highway railing, and install the guardrail mounting parts on the public trunk plate, then pull the traction rope, so that the guardrail pulley acts as a movable pulley to drive the highway guardrail to bend, thereby reducing the tension required to bend the highway guardrail, thereby reducing the construction personnel required for bending the highway guardrail, and facilitating the construction of highway guardrails.
[0037] 2. When installing the railing mounting piece on the highway railing, put the first mounting ring and the second mounting ring on the railing, then rotate the railing screw so that the railing screw passes through the mounting groove, and finally rotate and tighten the railing nut so that the railing nut is tightly fitted on the first mounting ring, thereby conveniently completing the installation of the railing mounting piece.
[0038] 3. The guardrail pad and the guardrail mounting rod are respectively tightly fitted on both sides of the highway guardrail, so that the guardrail pulley can be stably installed on the highway guardrail with a small thickness. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 It is an overall schematic diagram of the overall structure of the embodiment of the present application.
[0040] Figure 2 It is an overall schematic diagram of the railing mounting member and the railing pulley according to an embodiment of the present application.
[0041] Figure 3 It is a cross-sectional schematic diagram of the guardrail mounting member and the guardrail pulley according to the embodiment of the present application.
[0042] Figure 4 It is a schematic diagram of the construction of the inner highway guardrail of the embodiment of the present application.
[0043] Explanation of the reference numerals in the accompanying drawings: 1. Railing mounting part; 101. Mounting groove; 11. First mounting ring; 12. Second mounting ring; 13. Railing screw; 14. Railing nut; 15. Railing wheel frame; 151. Connecting ring; 152. C-shaped handle; 16. Connecting rod; 161. Horizontal connecting section; 162. Vertical connecting section; 2. Railing pulley; 3. Guardrail mounting part; 31. Guardrail mounting rod; 32. Guardrail screw; 33. Guardrail pad; 34. Guardrail nut; 35. Guardrail wheel frame; 4. Guardrail pulley; 5. Traction rope; 51. D-shaped carabiner. DETAILED DESCRIPTION
[0044] The following is combined with Figure 1-4 This application is described in further detail.
[0045] The present application embodiment discloses a highway guardrail construction auxiliary device. Figure 1 , Figure 2 as well as Figure 3 The highway guardrail construction auxiliary device includes a guardrail mounting part 1, a guardrail pulley 2, a guardrail mounting part 3, a guardrail pulley 4 and a traction rope 5.
[0046] Reference Figure 2 In the embodiment of the present application, two railing mounting parts 1 are provided, and the two railing mounting parts 1 are distributed in the vertical direction. The railing mounting part 1 includes a first mounting ring 11, a second mounting ring 12, a railing screw 13, a railing nut 14, a railing wheel frame 15 and a connecting rod. The first mounting ring 11 is provided with a mounting groove 101 extending therethrough, and one end of the second mounting ring 12 is rotatably matched with the first mounting ring 11 and is arranged away from the mounting groove 101. The railing screw 13 is rotatably matched with the other end of the second mounting ring 12, and the railing nut 14 is threadedly matched with the railing screw 13. The railing nut 14 is integrally connected with a rotating handle, so that the construction personnel can rotate the railing nut 14 by hand.
[0047] When the railing mounting member 1 is mounted on the highway railing, the second mounting ring 12 is tightly fitted to the bottom of the highway railing, and the first mounting ring 11 is tightly fitted to the bottom of the highway railing, so that the second mounting ring 12 and the first mounting ring 11 are not easy to slide or rotate. In addition, when the railing mounting member 1 is mounted on the highway railing, the railing screw 13 is slidably inserted into the mounting groove 101, and the railing nut 14 is tightly fitted to the first mounting ring 11, so that the second mounting ring 12 is locked to the first mounting ring 11 through the railing nut 14.
[0048] Reference Figure 2 The connecting rod 16 includes a horizontal connecting section 161 and a vertical connecting section 162. The horizontal connecting section 161 is fixedly mounted on the first mounting ring and arranged in the horizontal direction. The vertical connecting section 162 is integrally connected to the horizontal connecting section 161 and arranged in the vertical direction. A reinforcing rib is provided between the horizontal connecting section 161 and the vertical connecting section 162 to ensure the stability between the horizontal connecting section 161 and the vertical connecting section 162.
[0049] Reference Figure 2, the railing wheel bracket 15 is fixedly installed at the top of the vertical connecting section 162, and the cross-section of the railing wheel bracket 15 is arranged in a "U" shape. The railing pulley 2 is rotationally fitted to the first mounting ring 11 through a bearing. The railing pulley 2 is arranged in an hourglass shape. Specifically, the diameter of the railing pulley 2 increases from the middle of the railing pulley 2 along the axial direction of the railing pulley 2 towards the edge.
[0050] Refer to Figure 2 , on one side of the first mounting ring 11, a connecting ring 151 is fixedly installed. The towing rope 5 is connected to the connecting ring 151 through a D-shaped climbing buckle 51, so that after the construction is completed, the towing rope 5 can be removed from the connecting ring 151 by pressing the block of the D-shaped climbing buckle 51.
[0051] Refer to Figure 2 , on the other side of the first mounting ring 11, a C-shaped handle 152 is fixedly installed. On the one hand, it is convenient for construction workers to take the first mounting ring 11, and on the other hand, it is convenient to fixedly wind the towing rope 5 around the C-shaped handle 152, so that the towing rope 5 is not easily pulled.
[0052] Refer to Figure 3 , the railing plate mounting member 3 includes a railing plate mounting rod 31, a railing plate screw 32, a railing plate spacer 33, a railing plate nut 34 and a railing plate wheel bracket 35. One end of the railing plate screw 32 is fixedly installed at one end of the railing plate mounting rod 31. The cross-section of the railing plate wheel bracket 35 is arranged in a "U" shape, and the railing plate wheel bracket 35 is rotationally fitted to the railing plate mounting rod 31 through a bearing, and the rotation axis of the railing plate wheel bracket 35 is coaxially arranged with the railing plate screw 32.
[0053] Refer to Figure 3 , the railing plate wheel bracket 35 is fixedly installed with a railing plate guide plate 36. The railing plate guide plate 36 is provided with a plurality of railing plate guide holes 361. In the embodiment of the present application, the number of the railing plate guide holes 361 is set to two, and the two railing plate guide holes 361 are respectively arranged corresponding to the respective railing pulleys 4.
[0054] A plurality of railing pulleys 4 are provided. In the embodiment of the present application, two railing pulleys 4 are provided. The two railing pulleys 4 are coaxially arranged. The railing pulleys 4 are arranged far away from the railing plate screw 32 and are rotationally fitted to the railing plate mounting rod 31 through a bearing, so that the rotations of the two railing pulleys 4 are not easily affected by each other, ensuring that both of the two railing pulleys 4 can rotate independently. The railing pulleys 4 are arranged in an hourglass shape. Specifically, the diameter of the railing pulleys 4 increases from the middle of the railing pulleys 4 along the axial direction of the railing pulleys 4 towards the edge.
[0055] One end of the towing rope 5 far away from the connecting ring 151 is sequentially wound around one of the railing pulleys 4, the railing pulley 2 and the other railing pulley 4, so as to reduce the force required to bend the highway railing plate through the two railing pulleys 4.
[0056] Refer to Figure 1 and Figure 2 When the guardrail mounting member 3 is installed on the highway guardrail, the guardrail mounting rod 31 is tightly fitted on one side of the highway guardrail, the guardrail screw 32 slides through the fixing hole of the highway guardrail, and the guardrail pad 33 is tightly fitted on the other side of the highway guardrail, and the guardrail nut 34 is tightly fitted on the guardrail pad 33, so that the guardrail pulley 4 can be stably installed on the highway guardrail with a small thickness.
[0057] The implementation principle of a highway guardrail construction auxiliary device in the embodiment of the present application is:
[0058] Reference Figure 4 When constructing the inner side guardrail of a highway:
[0059] S1. Install one end of the highway guardrail on the side of the highway close to the highway through its own fixing hole.
[0060] S2, install the first mounting ring 11 and the second mounting ring 12 at the bottom of the highway guardrail, and make the guardrail pulley 2 away from the highway. Then install the guardrail mounting rod 31 to the other end of the highway guardrail through the guardrail screw 32, and make the guardrail pulley 4 away from the highway.
[0061] S3, pulling the traction rope 5, so that the highway guardrail bends in the direction of the highway railing.
[0062] S4. The highway guardrail is mounted on the highway guardrail by means of bolts respectively inserted through the remaining three fixing holes.
[0063] S5, dismantle the first mounting ring 11, the second mounting ring 12 and the guardrail mounting rod 31, and stably mount the highway guardrail on the highway guardrail by means of bolts passing through the fixing holes.
[0064] When constructing the outer highway guardrail of the expressway:
[0065] S1. Install one end of the highway guardrail on the side of the highway close to the highway through its own fixing hole.
[0066] S2, install the first mounting ring 11 and the second mounting ring 12 at the bottom of the guardrail, and place the guardrail pulley 2 toward the highway. Then install the guardrail mounting rod 31 at the other end of the highway guardrail through the guardrail screw 32, and place the guardrail pulley 4 toward the highway.
[0067] S3, pulling the traction rope 5, so that the highway guardrail bends in the direction of the highway railing.
[0068] S4. Fix the traction rope 5 around the C-shaped handle 152, then lift the highway guardrail so that the highway guardrail is wrapped from the top of the highway guardrail to the inside of the high highway, and then install the highway guardrail on the highway guardrail by means of bolts respectively inserted through the remaining three fixing holes.
[0069] S5, dismantle the first mounting ring 11, the second mounting ring 12 and the guardrail mounting rod 31, and stably mount the highway guardrail on the highway guardrail by means of bolts passing through the fixing holes.
[0070] Therefore, the embodiment of the present application reduces the force required to bend the highway guardrail through the traction rope 5 and the two guardrail pulleys 2, thereby reducing the number of construction personnel required when bending the highway guardrail, thereby facilitating the construction of the highway guardrail.
[0071] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A highway guardrail construction auxiliary device, characterized in that: It comprises a railing mounting part (1), a railing pulley (2), a guardrail mounting part (3), a guardrail pulley (4) and a traction rope (5); The railing mounting member (1) is detachably mounted on a highway railing, and the railing pulley (2) is rotatably matched with the railing mounting member (1); The guardrail mounting member (3) is detachably mounted on the highway guardrail, and the guardrail pulley (4) is rotatably matched with the guardrail mounting member (3); One end of the traction rope (5) is mounted on the railing mounting member (1), and the other end of the traction rope (5) is wound around the railing pulley (4) and the railing pulley (2).
2. A highway guardrail construction auxiliary device according to claim 1, characterized in that: The railing mounting member (1) comprises a first mounting ring (11), a second mounting ring (12), a railing screw (13), a railing nut (14) and a railing wheel frame (15); the first mounting ring (11) is provided with a mounting groove (101) extending therethrough; One end of the second mounting ring (12) is rotationally matched with the first mounting ring (11), the railing screw (13) is rotationally matched with the other end of the second mounting ring (12), and the railing nut (14) is threadedly matched with the railing screw (13); When the railing mounting member (1) is mounted on a highway railing, the second mounting ring (12) and the first mounting ring (11) are both tightly fitted on the highway railing, the railing screw (13) is inserted into the mounting groove (101), and the railing nut (14) is tightly fitted on the first mounting ring (11); The railing wheel frame (15) is mounted on the first mounting ring (11), and the railing pulley (2) is rotationally matched with the railing wheel frame (15).
3. A highway guardrail construction auxiliary device according to claim 2, characterized in that: The railing mounting member (1) further comprises a connecting rod (16), one end of which is mounted on the first mounting ring (11), and the railing wheel frame (15) is mounted on the other end of the connecting rod (16).
4. A highway guardrail construction auxiliary device according to claim 3, characterized in that: The connecting rod (16) comprises a horizontal connecting section (161) and a vertical connecting section (162); the horizontal connecting section (161) is mounted on the first mounting ring (11), and the horizontal connecting section (161) is arranged in the horizontal direction; the vertical connecting section (162) is mounted on the horizontal connecting section (161), and the vertical connecting section (162) is arranged in the vertical direction.
5. The highway guardrail construction auxiliary device according to claim 1, characterized in that: The guardrail mounting member (3) comprises a guardrail mounting rod (31), a guardrail screw rod (32), a guardrail pad (33), a guardrail nut (34) and a guardrail wheel frame (35); The guardrail screw rod (32) is installed on the guardrail mounting rod (31); When the guardrail mounting member (3) is mounted on a highway guardrail, the guardrail mounting rod (31) is tightly fitted on one side of the highway guardrail, the guardrail screw (32) is inserted into a fixing hole of the highway guardrail, and the guardrail pad (33) is tightly fitted on the other side of the highway guardrail, and the guardrail nut (34) is tightly fitted on the guardrail pad (33); The fence wheel frame (35) is mounted on the fence mounting rod (31), and the fence pulley (4) is rotatably matched with the fence wheel frame (35).
6. The highway guardrail construction auxiliary device according to claim 1, characterized in that: A plurality of the fence pulleys (4) are provided, and the plurality of fence pulleys (4) are all rotatably matched with the fence mounting member (3), and the traction rope (5) is wound around each fence pulley (4).
7. The highway guardrail construction auxiliary device according to claim 6, characterized in that: The fence pulley (4) is arranged in an hourglass shape.
8. The highway guardrail construction auxiliary device according to claim 1, characterized in that: When the railing mounting member (1) is mounted on a highway railing, the railing mounting member (1) is arranged close to the bottom of the highway railing.