Composite supporting system suitable for dismantling existing tunnel in complex environment
By setting the newly built tunnel support piles on the inside of the original support pile of the existing tunnel in a complex environment, and using the detachable long steel casing and steel pipe inner support for column pile construction, the construction efficiency and cost in the existing technology is solved. High-quality problems have achieved efficient and safe tunnel renovation.
Patent Information
- Application Number
- CN202420759343.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-12
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-04-12
AI Technical Summary
In the process of renovation of existing tunnels in complex urban environments, the newly built tunnel support structure is set on the outside of the old support piles, which is prone to encounter prestressed anchor cables, which are time-consuming and labor-intensive and costly, and the bottom plate punching construction is carried out. It is difficult to install column piles, which affects construction progress and costs.
Using a composite support system, the newly built tunnel support piles are set inside the original support piles of the existing tunnel, and the column pile construction is carried out through the main structure of the tunnel to avoid conflicts between prestressed anchor cables, and Quick installation is achieved through internal steel pipe support and steel columns.
It improves the construction efficiency of newly built tunnel support piles, shortens the construction period, reduces costs, and realizes the recycling of resources, providing a safe, efficient and economical construction method.
Smart Images

Figure CN222100890U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction renewal of existing tunnels in complex urban environments, in particular to a composite support system suitable for demolishing existing tunnels in complex environments. Background Art
[0002] At present, improving the spatial structure of urban development and accelerating the renewal of urban infrastructure have become current development trends.
[0003] The existing urban infrastructure renewal includes the renewal and reconstruction of existing buried tunnels in complex urban environments. The renewal and reconstruction process of existing buried tunnels mainly includes the demolition of the existing buried section and the north open section of the tunnel, and the extension and reconstruction in situ. The general construction process of the in-situ reconstruction project is to demolish the old first and then build the new. However, because the existing tunnel is an underground structure, it is necessary to consider whether the old support system can ensure the safety of the foundation pit when demolishing the old tunnel first. In order to ensure the safety of the foundation pit during the demolition of the existing tunnel, a new tunnel support structure is usually built. The existing new tunnel support structure usually sets the new support piles on the outside of the old support piles of the original support structure of the existing tunnel, punches holes on the bottom plate of the tunnel main structure to construct column piles, and then backfills the earthwork in the tunnel main structure. The existing new tunnel support structure has the following shortcomings:
[0004] 1) Setting the new tunnel support structure outside the old support piles of the existing tunnel will cause spatial conflicts and easily touch the prestressed anchor cables. The installation and construction of the new tunnel support structure will be time-consuming and labor-intensive, and the cost will be high.
[0005] 2) Punching holes on the bottom plate to construct column piles. Due to the limited clearance of the existing tunnel, it is easy to make it impossible to install the steel columns connected to the column piles. It is also necessary to consider backfilling the tunnel frame, which is a large workload and high cost. After backfilling, it has to be excavated, which affects the construction progress, prolongs the construction period, and consumes a lot of time. Utility Model Content
[0006] The technical problem to be solved by the utility model is to provide a composite support system for installing new tunnel support piles at the fertilizer trough of an existing tunnel, setting the new tunnel support piles on the inner side of the original support piles of the existing tunnel to avoid hitting the prestressed anchor cables on the outer side of the original support piles, improving the construction efficiency of the new tunnel support pile installation, constructing column piles by passing long steel casings through the main structure of the tunnel, taking out the long steel casings for recycling after construction, and quickly completing the installation of column piles.
[0007] In order to solve the above technical problems, the utility model adopts the following technical solutions:
[0008] A composite support system suitable for demolishing existing tunnels in complex environments, the original support structure on the periphery of the existing tunnel, the original support structure comprising original support piles and a number of external anchor cables, the number of external anchor cables being installed on both sides of the tunnel main structure of the existing tunnel through the original support piles, a fat trough being formed between the tunnel main structure of the existing tunnel and the original support piles, the composite support system comprising newly-built tunnel support piles and a number of steel pipe inner supports, the newly-built tunnel support piles being installed at the fat trough of the tunnel main structure, the number of steel pipe inner supports being arranged parallel to each other, the two ends of each steel pipe inner support being respectively connected to the tunnel main structure, the tunnel main structure being penetrated from top to bottom by a detachable long steel casing.
[0009] Furthermore, the composite support system includes steel columns, which are installed inside the long steel casing.
[0010] Furthermore, the composite support system includes column piles, and the column piles are installed below the steel columns.
[0011] Furthermore, the steel column can be configured as a steel pipe column, a lattice column or an H-shaped steel pipe column.
[0012] Furthermore, the main structure of the tunnel includes a top plate and a bottom plate, the top plate is installed above the bottom plate, two side walls are installed between the top and bottom plates, the top plate is provided with a first opening, the bottom plate is provided with a second opening corresponding to the top position, and the long steel casing of the composite support system passes through the first opening of the top plate to the second opening of the bottom plate.
[0013] Furthermore, a concrete horizontal inner support is cast above the top plate of the tunnel main structure, and both sides of the concrete horizontal inner support are connected to the newly built tunnel support piles at the fat trough of the tunnel main structure.
[0014] Furthermore, steel bar connectors are pre-buried on both sides of the steel pipe inner support, and the steel pipe inner support is connected to the side wall of the tunnel main structure through the steel bar connectors on both sides.
[0015] Furthermore, the composite support system includes a water-stop curtain, which is arranged at the gap between the original support piles and the newly built tunnel support piles. The water-stop curtain and the newly built tunnel support piles are overlapped without a gap to form a reliable lateral water-stop curtain.
[0016] Furthermore, a C20 concrete layer is laid at the lower end of the base plate.
[0017] Furthermore, the width of the fertilizer trough is greater than or equal to 1m.
[0018] Compared with the prior art, the utility model has the following beneficial effects:
[0019] The composite support system of the utility model includes newly built tunnel support piles and a number of steel pipe inner supports. The newly built tunnel support piles are installed at the fat trough of the tunnel main structure. The several steel pipe inner supports are arranged in parallel with each other. The two ends of each steel pipe inner support are respectively connected to the tunnel main structure. The tunnel main structure is penetrated from top to bottom by a detachable long steel casing. The composite support structure of the utility model arranges the newly built tunnel support piles on the inner side of the old support piles of the existing tunnel, which can prevent the newly built tunnel support piles from hitting the prestressed anchor cable during the construction process, thereby improving the construction efficiency of the newly built tunnel support piles. The utility model also opens holes in the top plate and the bottom plate of the tunnel main structure, and uses long steel casings to pass through the holes in the top plate and the bottom plate to construct column piles. After the construction is completed, the steel casings are taken out for recycling, and the installation and construction of the column piles and the steel columns connected to the column piles can be completed, thereby improving the construction efficiency and shortening the construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic diagram of the relationship between the existing tunnel and the composite support system of the utility model;
[0021] Figure 2 It is a structural schematic diagram of the composite support system of the utility model.
[0022] In the figure: existing tunnel 1, tunnel main structure 11, top plate 111, bottom plate 112, side wall 113, C20 concrete layer 114, inspection port 115, concrete horizontal inner support 12, crown beam 13, original supporting structure 2, original supporting piles 21, external anchor cable 22, fertilizer trough 3, composite supporting system 4, newly built tunnel supporting piles 41, steel pipe inner support 42, steel bar connector 421, long steel casing 43, steel column 44, column pile 45, water stop curtain 46. DETAILED DESCRIPTION
[0023] The present invention is described in detail below in conjunction with the accompanying drawings, which are part of this specification and illustrate the principle of the present invention through embodiments. Other aspects, features and advantages of the present invention will become clear through the detailed description. In the drawings referred to, the same or similar parts in different figures are represented by the same reference numerals.
[0024] like Figure 1-2As shown, the first embodiment of the utility model provides a composite support system 4 suitable for dismantling an existing tunnel 1 in a complex environment, the original support structure 2 on the outer periphery of the existing tunnel 1, the original support structure 2 includes an original support pile 21 and a plurality of external anchor cables 22, the plurality of external anchor cables 22 are installed on both sides of the tunnel main structure 11 of the existing tunnel 1 through the original support pile 21, a fat trough 3 is formed between the tunnel main structure 11 of the existing tunnel 1 and the original support pile 21, the width of the fat trough 3 is greater than or equal to 1m, the composite support system 4 includes a newly built tunnel support pile 41 and a plurality of steel pipe inner supports 42, the newly built tunnel support pile 41 is installed at the fat trough 3 of the tunnel main structure 11, the plurality of steel pipe inner supports 42 are arranged parallel to each other, the two ends of each steel pipe inner support 42 are respectively connected to the tunnel main structure 11, and the tunnel main structure 11 is penetrated from the top to the bottom by a detachable long steel casing 43. In specific implementation, the newly built tunnel support pile 41 adopts a Φ1.0m@1.0m reinforced concrete cast-in-place pile. The composite support structure of the utility model sets the newly built tunnel support pile 41 inside the original support pile 21 of the existing tunnel 1, which can prevent the newly built tunnel support pile 41 from hitting the external anchor cable 22, thereby improving the construction efficiency of the newly built tunnel support pile 41. The composite support system 4 provided by the utility model can shorten the construction period of the project, and can also provide a safe, efficient and economical construction method for the renovation of urban buried tunnels under complex conditions such as large traffic volume and extremely limited construction space.
[0025] The composite support system 4 of the utility model includes a steel column 44, which is installed inside the long steel casing 43. The composite support system 4 includes a column pile 45, which is installed below the steel column 44. The long steel casing 43 is used to pass through the column pile 45 to construct the column pile, which can also avoid large-scale backfilling of the foundation pit in the main structure of the tunnel 11. After the long steel casing 43 is constructed, the column pile 45 and the steel column 44 connected to the column pile 45 can be installed and constructed, which improves the construction efficiency and shortens the construction period. The long steel casing 43 can also be taken out and recycled, which improves the resource utilization rate, saves the construction cost, and improves the environmental protection. In specific implementation, the column pile 45 of the utility model is set at a position 1.5m to the left of the center line of the main structure of the tunnel 11. The column pile 45 adopts a Φ1.0m@12m column pile 45, and the steel column 44 can be set as a steel pipe column, a lattice column or an H-shaped steel pipe column.
[0026] The main structure 11 of the tunnel of the utility model includes a top plate 111 and a bottom plate 112. The top plate 111 is installed above the bottom plate 112. Two side walls 113 are installed between the top and bottom plates 112. The top plate 111 is provided with a first opening, and the bottom plate 112 is provided with a second opening corresponding to the top position. The long steel casing 43 of the composite support system 4 passes through the first opening of the top plate 111 to the second opening of the bottom plate 112. The main structure 11 of the tunnel is connected with the steel pipe inner support 42 through the side wall 113. When the long steel casing 43 passes through the top plate 111 and the bottom plate 112 of the main structure 11 of the tunnel, the opening is finally impacted by an impact drill, thereby completing the construction of the column pile 45. The lower end of the bottom plate 112 of the bottom plate 112 is provided with a C20 concrete layer 114, and the thickness of the C20 concrete layer 114 is 40cm. The bottom of the side wall 113 of the main structure 11 of the tunnel is provided with an inspection port 115.
[0027] In specific implementation, the utility model casts a concrete horizontal inner support 12 above the top plate 111 of the tunnel main structure 11, and the two sides of the concrete horizontal inner support 12 are connected to the newly built tunnel support piles 41 at the fertilizer trough 3 of the tunnel main structure 11. A crown beam 13 can be provided at the connection between the concrete horizontal inner support 12 and the newly built tunnel support piles 41, and a steel plate is pre-embedded on the crown beam 13, and the connection between the concrete horizontal inner support 12 and the newly built tunnel support piles 41 is achieved through the steel plate.
[0028] In specific implementation, the utility model pre-buries steel bar connectors 421 on both sides of the steel tube inner support 42, and the steel tube inner support 42 is connected to the side wall 113 of the tunnel main structure 11 through the steel bar connectors 421 on both sides, thereby realizing a rigid connection between the steel tube inner support 42 and the side wall 113 of the tunnel main structure 11.
[0029] In other embodiments, the utility model can also roughen and apply interface agent on the contact surface between the steel tube inner support 42 and the side wall 113 of the tunnel main structure 11 so that the steel tube inner support 42 is connected to the side wall 113 of the tunnel main structure 11.
[0030] The composite support system 4 of the utility model includes a water-stop curtain 46, which is arranged at the gap between the original support pile 21 and the newly-built tunnel support pile 41, and the water-stop curtain 46 overlaps the newly-built tunnel support pile 41 without gap to form a reliable lateral water-stop curtain 46. The water-stop curtain 46 can prevent the peripheral groundwater from penetrating into the foundation pit of the tunnel main structure 11.
[0031] The demolition of the existing tunnel 1 of the utility model includes the following construction process:
[0032] Step 1) Drilling holes in the bottom plate 112 of the tunnel main structure 11: measuring the positions of the column piles 45 on the bottom plate 112, and using an excavator with a breaker hammer to break the pavement structure and the bottom plate 112 of the tunnel main structure 11 layer by layer from top to bottom according to the clearance of the buried section of the existing tunnel 1;
[0033] Step 2) Opening a hole in the top plate 111 of the tunnel main structure 11: excavate the soil and road surface structure above the top plate 111 of the tunnel main structure 11, measure and release the pile position of the column pile 45, draw a circle along the pile position, the circle diameter is greater than 1.3m, the diameter of the long steel casing 43 is 1.2m, and the pile diameter of the column pile 45 is 1.0m. After determining the position, use expansion bolts to install and fix the water grinding drill, and construct a circle along the pile position of the column pile 45;
[0034] Step 3) Construction of column piles 45: The crane is in place, and the long steel casing 43 is hoisted through the top plate 111 and the bottom plate 112 of the tunnel main structure 11. After checking the pile position, the excavator is used to hammer downward to stably embed the long steel casing 43 below the bottom plate 112, and the long steel casing 43 is backfilled with clay with low permeability around the long steel casing 43 at the position of the long steel casing 43 on the bottom plate 112 to prevent the subsequent punching construction mud from overflowing through the bottom of the long steel casing 43. The outer side of the long steel casing 43 at the top plate 111 is backfilled to the ground to facilitate subsequent construction. The long steel casing 43 can be taken out and reused;
[0035] Step 4) Mud preparation: Make mud with clay, and equip two mud boxes on site. The mud control indicators are as follows: viscosity 18-22 seconds; sand content ≤8%; colloid rate ≥90%. The punching drill is in place to drill holes. When drilling holes, check whether there is leakage on the outside of the long steel casing 43 at the bottom plate 112 in the buried section of the existing tunnel 1. After the light impact drilling stage, normal punching begins;
[0036] Step 5) Installation of steel cage: The steel lattice column is anchored into the foundation of the column pile 45 at a depth of 3.0m. When the steel cage is hoisted and lowered to the corresponding depth, two φ28 steel bars are used to fix the steel cage on the long steel casing 43. The lattice column is fixed on each surface. Two Φ16 steel bars are used to obliquely weld the lattice column and the main bars of the steel cage. One Φ16 horizontal steel bar is welded to the main bars of the steel cage on each side of the lattice column. The end of the horizontal steel bar has a movable amount of 20 to 30mm from each side of the lattice column, and the lattice column is set in the middle of the steel cage;
[0037] Step 6) The lattice column is hoisted into place: the steel cage is first fixed at the pile hole, and the lattice column is hoisted by a truck crane and slowly placed into the steel cage. The lattice column enters the steel cage at the top of the pile by 3m. After the lattice column is installed, the column pile 45 is cleaned for the second time, the guide tube is lowered, and underwater concrete is poured. The pile hole of the steel lattice column section is backfilled with clay to the bottom plate 112;
[0038] Step 7) Demolition of the buried section of the existing tunnel 1: After the installation of the composite support system 4 is completed, the demolition of the buried section of the existing tunnel 1 begins. The top plate 111 is demolished by crushing it longitudinally with a crusher. The side wall 113 is demolished by first drilling a hole and dividing it into blocks longitudinally. A geological drill is used to drill a hole downward at the top of the outer side of the side wall 113, and then a water-grinding drill is used to drill a horizontal hole at the corresponding vertical position at the root of the side wall 113. The side wall 113 is cut into blocks with a rope saw. After the longitudinal block seam is cut, the side wall 113 is crushed along the root of the side wall 113 with a crusher, and then the whole block is laid down. The middle wall is cut and laid down at the root with a rope saw, and the bottom plate 112 is pushed longitudinally along with the pit bottom soil while being crushed and excavated.
[0039] The above description has been a detailed description of the present invention. The above description is only a preferred embodiment of the present invention and should not limit the scope of implementation of the present application. That is, all equivalent changes and modifications made within the scope of the present application should still fall within the scope of the present invention.
Claims
1. A composite support system suitable for demolition of existing tunnels in complex environments, characterized by: The original support structure of the outer periphery of the existing tunnel comprises original support piles and a number of external anchor cables, the number of external anchor cables are installed on both sides of the tunnel main structure of the existing tunnel through the original support piles, a fat trough is formed between the tunnel main structure of the existing tunnel and the original support piles, the composite support system comprises newly-built tunnel support piles and a number of steel pipe inner supports, the newly-built tunnel support piles are installed at the fat trough of the tunnel main structure, a number of steel pipe inner supports are arranged parallel to each other, the two ends of each steel pipe inner support are respectively connected to the tunnel main structure, and a detachable long steel casing is passed through the tunnel main structure from top to bottom.
2. The composite support system for demolition of existing tunnels in complex environments according to claim 1 is characterized in that: The composite support system comprises a steel column, and the steel column is installed inside a long steel casing.
3. The composite support system suitable for demolition of existing tunnels in complex environments according to claim 1 is characterized by: The composite support system comprises column piles, and the column piles are installed below the steel columns.
4. The composite support system for demolition of existing tunnels in complex environments according to claim 3 is characterized by: The steel column can be configured as a steel pipe column, a lattice column or an H-shaped steel pipe column.
5. The composite support system suitable for demolition of existing tunnels in complex environments according to claim 1 is characterized in that: The main structure of the tunnel includes a top plate and a bottom plate, wherein the top plate is installed above the bottom plate, two side walls are installed between the top and bottom plates, the top plate is provided with a first opening, and the bottom plate is provided with a second opening corresponding to the top position, and the long steel casing of the composite support system passes through the first opening of the top plate to the second opening of the bottom plate.
6. The composite support system for demolition of existing tunnels in complex environments according to claim 5 is characterized by: A concrete horizontal inner support is cast above the top plate of the tunnel main structure, and both sides of the concrete horizontal inner support are connected to the newly built tunnel support piles at the fat trough of the tunnel main structure.
7. The composite support system for demolition of existing tunnels in complex environments according to claim 1 is characterized by: Steel bar connectors are pre-buried on both sides of the steel pipe inner support, and the steel pipe inner support is connected to the side wall of the tunnel main structure through the steel bar connectors on both sides.
8. The composite support system for demolition of existing tunnels in complex environments according to claim 1 is characterized by: The composite support system includes a water-stop curtain, which is arranged at the gap between the original support piles and the newly built tunnel support piles. The water-stop curtain and the newly built tunnel support piles are overlapped without a gap to form a reliable lateral water-stop curtain.
9. The composite support system for demolition of existing tunnels in complex environments according to claim 5 is characterized by: A C20 concrete layer is laid on the lower end of the base plate.
10. The composite support system suitable for demolition of existing tunnels in complex environments according to claim 5 is characterized by: The width of the fertilizer trough is greater than or equal to 1m.