Ice adding device
By designing an ice-adding device, the crushed ice is transported to the reaction tank using a screw conveyor rod and a conveying pipe. Combined with the design of the motor and pulse blowing valve, the problem of low efficiency of adding ice-adding and cooling operation in dye preparation is solved, and the production efficiency is improved. The service life of the equipment.
Patent Information
- Application Number
- CN202420784145.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-15
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-04-15
AI Technical Summary
In the prior art, the cooling operation efficiency of adding ice during dye preparation is low, and frequent handling of crushed ice is required to lead to low production efficiency.
An ice-adding device is designed, including a refrigerator, a spiral conveying rod and a conveying pipe. The broken ice in the refrigerator is gradually pushed into the conveying pipe through the spiral conveying rod, and then transported to the reaction tank by the conveying pipe, and controlled by the motor. Ice volume and pulse blow valves prevent blockage and achieve efficient cooling.
It improves the efficiency of the cooling operation of the reaction tank, reduces the operating frequency of the staff, extends the service life of the equipment, and ensures the continuous delivery of crushed ice and the efficient cooling of the reaction tank.
Smart Images

Figure CN222111786U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of dye preparation, and in particular to an ice adding device. Background Art
[0002] Ice cooling is a common process step in the dye preparation process. At high temperatures, some dyes may decompose or undergo redox reactions, resulting in changes in the color and properties of the dyes. Ice cooling can reduce the temperature of the dye and keep it within a suitable range, thereby reducing the reaction rate of the dye and improving the stability of the dye, making it easier for workers to operate and control the preparation of the dye.
[0003] The prior art is that a worker directly adds the prepared crushed ice into a reaction tank through a feeding pipe of the reaction tank. Since the reactants in the reaction tank need to be cooled during the dye preparation process, the worker needs to move the container containing the crushed ice to the reaction tank, and then manually lift the container containing the crushed ice to the feeding port of the reaction tank, and then flip the container to pour the crushed ice from the container into the reaction tank.
[0004] Since the reaction tank needs to be frequently cooled during the reaction, the staff also needs to frequently move crushed ice to the reaction tank and then put the crushed ice into the reaction tank, which makes the overall production efficiency low. Utility Model Content
[0005] In order to improve the overall production efficiency, the present application provides an ice adding device.
[0006] The ice adding device provided in this application adopts the following technical solution:
[0007] An ice adding device comprises an ice storage bin, a screw conveying rod, a conveying pipe and a reaction tank, wherein the ice storage bin is connected to the screw conveying rod, the screw conveying rod is connected to the conveying pipe, and the conveying pipe is connected to the reaction tank.
[0008] By adopting the above technical solution, when crushed ice needs to be added to the reaction tank, the spiral conveying rod can gradually push the crushed ice in the ice storage bin to the conveying pipe, and the conveying pipe then conveys the crushed ice into the reaction tank, thereby completing the cooling operation of the reaction tank and improving the overall production efficiency.
[0009] Optionally, the ice storage bin has a first feeding pipe, the spiral conveying rod has a first feeding pipe, the first feeding pipe is connected to the first feeding pipe via a flange, and a sealing gasket is provided between the first feeding pipe and the first feeding pipe.
[0010] By adopting the above technical solution, the ice storage bin and the spiral conveyor rod are connected by a flange, which can ensure the stability of the crushed ice during the transmission process. The sealing gasket is used to further enhance the sealing of the connection and reduce the damage to the flange caused by the accumulation of water generated by the melting of the crushed ice, thereby increasing the service life of the ice storage bin and the spiral conveyor rod.
[0011] Optionally, the outer circumferential surface of the first feeding tube is provided with a motor, the motor is provided with a rotating plate, and the circumferential surface of the first feeding tube is provided with an opening for the rotating plate to be plugged in.
[0012] By adopting the above technical solution, the staff starts the motor, and the motor can drive the rotating plate to rotate, so that the rotating plate can be inserted into the first feeding pipe through the opening, thereby effectively controlling the ice output in the ice storage bin, making the discharge of the ice storage bin more convenient and accurate.
[0013] Optionally, the spiral conveying rod is arranged obliquely from the ice storage bin to the conveying pipe.
[0014] By adopting the above technical solution, since the spiral conveying rod is inclined from the ice storage bin to the conveying pipe, the crushed ice can naturally slide down into the conveying pipe along the inclined spiral conveying rod under the action of gravity, thereby facilitating the spiral conveying rod to convey the crushed ice, reducing the probability of the crushed ice being blocked in the spiral conveying rod, and allowing the crushed ice to pass through the spiral conveying rod more smoothly.
[0015] Optionally, the delivery pipe includes a first pipe and a second pipe, the first pipe and the second pipe are welded, and the first pipe is vertically arranged.
[0016] By adopting the above technical solution, when the crushed ice is transported to the first pipe under the action of the spiral conveying rod, since the first pipe is vertically arranged, the crushed ice can flow smoothly from the spiral conveying rod into the first pipe, which helps the crushed ice to enter the first pipe from the spiral conveying rod.
[0017] Optionally, the second pipeline is inclined from the first pipeline to the reaction tank.
[0018] By adopting the above technical solution, when the crushed ice enters the second pipe from the first pipe, the conveying speed of the crushed ice is slowed down due to the inclined arrangement of the second pipe, thereby ensuring the efficient ice-adding process.
[0019] Optionally, a pulse blowing valve is provided on the outer peripheral surface of the first pipeline and close to the connection between the first pipeline and the second pipeline.
[0020] By adopting the above technical solution, crushed ice is prone to accumulate at the connection between the first pipe and the second pipe, so that the pulse blowing valve can blow air to the connection between the first pipe and the second pipe, which helps to push the crushed ice and reduce the incidence of crushed ice accumulation, so that the crushed ice can enter the second pipe from the first pipe more smoothly, ensuring the continuous transportation of the crushed ice.
[0021] Optionally, the pulse air blowing valve has a nozzle, and the nozzle faces the connection between the first pipe and the second pipe.
[0022] By adopting the above technical solution, when crushed ice blocks the connection between the first pipe and the second pipe, the nozzle can generate a high-speed airflow with strong impact force, so that the high-speed airflow can quickly clear the accumulation of crushed ice at the connection and keep the connection between the first pipe and the second pipe unobstructed.
[0023] Optionally, an air inlet pipe is provided on the side of the first pipeline, the pulse air blowing valve has an air blowing pipe, the air blowing pipe is connected to the air inlet pipe via a flange, and the nozzle is inserted into the air blowing pipe.
[0024] By adopting the above technical solution, since the air blowing pipe and the air inlet pipe are connected by a flange, when the pulse air blowing valve fails, the staff only needs to remove the flange to conveniently replace or repair the pulse air blowing valve.
[0025] Optionally, a baffle is provided on the inner wall of the first pipe above the air inlet pipe, and the baffle is bent toward the connection between the first pipe and the second pipe.
[0026] By adopting the above technical solution, when the crushed ice flows from the first pipe to the second pipe, since a baffle is provided on the inner wall of the first pipe above the air inlet pipe, the crushed ice will not directly rush through the nozzle into the second pipe, but will enter the second pipe along the guidance of the baffle, thereby effectively protecting the nozzle of the pulse blowing valve.
[0027] In summary, the present application includes at least one of the following beneficial technical effects:
[0028] 1. When the reaction tank needs to be cooled, the spiral conveying rod can gradually push the crushed ice in the ice storage bin to the conveying pipe, and then use the conveying pipe to transport the crushed ice into the reaction tank, thereby completing the cooling operation of the reaction tank and improving the overall production efficiency.
[0029] 2. The staff starts the motor, and the motor can drive the rotating plate to rotate, so that the rotating plate can be inserted into the first feeding pipe of the storage bin, thereby effectively controlling the amount of ice discharged from the storage bin, making the discharge of the storage bin more convenient and accurate.
[0030] 3. When the crushed ice flows from the first pipe to the second pipe, since a baffle is provided on the inner side of the first pipe above the air inlet pipe, the crushed ice will not directly rush through the nozzle of the pulse blowing valve into the second pipe, but will enter the second pipe along the guidance of the baffle, thereby effectively protecting the nozzle of the pulse blowing valve. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a schematic diagram of the overall structure of the ice adding device;
[0032] Figure 2 This is a schematic diagram of the local structure of the ice adding device. Figure 1 ;
[0033] Figure 3 This is a schematic diagram of the local structure of the ice adding device. Figure 2 ;
[0034] Figure 4 It is a schematic diagram of the cross-sectional structure of the delivery pipe and the pulse blowing valve;
[0035] Explanation of the reference numerals: 1. ice storage bin; 11. first feed pipe; 12. opening; 13. first bracket; 14. second bracket; 2. spiral conveying rod; 21. first feed pipe; 3. conveying pipe; 31. first pipeline; 311. air inlet pipe; 312. baffle; 32. second pipeline; 4. reaction tank; 41. second feed pipe; 5. flange; 51. sealing gasket; 6. motor; 61. rotating plate; 62. output shaft; 7. pulse blowing valve; 71. blowing pipe; 72. nozzle. DETAILED DESCRIPTION
[0036] The following is combined with Figure 1-4 This application is described in further detail.
[0037] The embodiment of the present application discloses an ice adding device.
[0038] Reference Figure 1 and Figure 2 An ice adding device includes an ice storage bin 1, a screw conveying rod 2, a conveying pipe 3 and a reaction tank 4. The ice storage bin 1 is located above the screw conveying rod 2. The screw conveying rod 2 is inclined from the ice storage bin 1 to the conveying pipe 3. The screw conveying rod 2 is welded to the conveying pipe 3. The conveying pipe 3 and the reaction tank 4 are connected by a flange 5.
[0039] In addition, the ice storage bin 1 has a first feeding pipe 11 , the spiral conveying rod 2 has a first feeding pipe 21 connected to the first feeding pipe 11 , the first feeding pipe 11 and the first feeding pipe 21 are connected via a flange 5 , and a sealing gasket 51 is installed between the two flanges 5 .
[0040] When the reaction tank 4 needs to be cooled, the staff starts the ice adding device, so that the crushed ice in the ice storage bin 1 can be sent out from the first feeding pipe 11 of the ice storage bin 1, and then enter the screw conveying rod 2 from the first feeding pipe 21 of the screw conveying rod 2, and at the same time, the crushed ice is transported to the conveying pipe 3 by the screw conveying rod 2, and then the crushed ice is transported to the reaction tank 4 through the conveying pipe 3, so as to achieve the cooling treatment of the reaction tank 4.
[0041] Reference Figure 2 The storage bin 1 is trapezoidal, a first bracket 13 is welded to one side of the bottom of the storage bin 1 near the first feeding pipe 11, a motor 6 is threadedly connected to one side of the first feeding pipe 11 and near the connection between the first feeding pipe 11 and the first feeding pipe 21, the motor 6 is mounted on the first bracket 13, a rotating plate 61 is clamped on the output shaft 62 of the motor 6, an opening 12 is opened on the first feeding pipe 11, the opening 12 is semicircular, the rotating plate 61 can be rotated on the first feeding pipe 11 through the opening 12, and the size and shape of the rotating plate 61 are smaller than the shape and size of the cross section of the first feeding pipe 11.
[0042] The staff starts the motor 6 and rotates the rotating plate 61 out of the opening 12 at the first feeding pipe 11, so that the crushed ice is transported from the first feeding pipe 11 of the ice storage bin 1 to the spiral conveying rod 2, and driven by the spiral conveying rod 2, the crushed ice can smoothly enter the conveying pipe 3. When the output of the crushed ice reaches the cooling effect, the staff starts the motor 6 again, rotates the rotating plate 61 from the opening 12 to the first feeding pipe 11 of the ice storage bin 1, and then the crushed ice no longer enters the spiral conveying rod 2, so that the ice output in the ice storage bin 1 can be effectively controlled.
[0043] Reference Figure 3 The delivery pipe 3 includes a first pipe 31 and a second pipe 32, which are welded to each other. The first pipe 31 is arranged in a vertical direction, and the first pipe 31 is welded to the spiral delivery rod 2, and the second pipe 32 is arranged obliquely from the first pipe 31 to the reaction tank 4. A pulse blowing valve 7 is installed on the first pipe 31 near the connection between the first pipe 31 and the second pipe 32. The installation position of the ice storage bin 1 is directly above the delivery pipe 3, and a second bracket 14 is installed by expansion bolts. The pulse blowing valve 7 is erected above the second bracket 14. At the same time, the pulse blowing valve 7 is provided with a blowing pipe 71, and an air inlet pipe 311 is provided on the outer peripheral surface of the first pipe 31. The blowing pipe 71 and the air inlet pipe 311 are connected by a flange 5.
[0044] When the crushed ice is transported to the first pipe 31 under the action of the spiral conveying rod 2, it can pass through the first pipe 31 smoothly and then enter the second pipe 32. Since part of the crushed ice will be blocked at the connection between the first pipe 31 and the second pipe 32, the pulse blowing valve 7 is started again to blow part of the crushed ice into the second pipe 32, and then the crushed ice is slowly transported in the second pipe 32 to the second feeding pipe 41 of the reaction tank 4.
[0045] Reference Figure 4 A nozzle 72 is welded on the inner wall of the air blowing pipe 71, and the nozzle 72 faces the connection between the first pipe 31 and the second pipe 32. At the same time, a baffle 312 is welded on the inner wall of the first pipe 31 near the upper part of the air inlet pipe 311, and the baffle 312 is bent toward the connection between the first pipe 31 and the second pipe 32. The shape of the baffle 312 can be changed according to the situation. Here, the baffle 312 is arc-shaped, and the size of the baffle 312 should be larger than the size of the cross section of the nozzle 72.
[0046] When the crushed ice enters the second pipe 32 from the first pipe 31, the crushed ice can enter the second pipe 32 along the guidance of the baffle 312, and part of the crushed ice will be blocked at the connection between the first pipe 31 and the second pipe 32. At this time, the nozzle 72 can generate a high-speed airflow with strong impact force, and blow part of the crushed ice blocked at the connection between the first pipe 31 and the second pipe 32 into the second pipe 32, so that the crushed ice can smoothly enter the reaction tank 4.
[0047] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. An ice adding device, characterized in that: The invention comprises a storage ice box (1), a screw conveying rod (2), a conveying pipe (3) and a reaction tank (4), wherein the storage ice box (1) is connected to the screw conveying rod (2), the screw conveying rod (2) is connected to the conveying pipe (3), and the conveying pipe (3) is connected to the reaction tank (4).
2. An ice adding device according to claim 1, characterized in that: The ice storage bin (1) is provided with a first feeding pipe (11), the spiral conveying rod (2) is provided with a first feeding pipe (21), the first feeding pipe (11) and the first feeding pipe (21) are connected via a flange (5), and a sealing gasket (51) is provided between the first feeding pipe (11) and the first feeding pipe (21).
3. An ice adding device according to claim 2, characterized in that: The outer circumferential surface of the first feeding tube (11) is provided with a motor (6), the motor (6) is provided with a rotating plate (61), and the circumferential surface of the first feeding tube (11) is provided with an opening (12) for the rotating plate (61) to be plugged in.
4. The ice adding device according to claim 1, characterized in that: The spiral conveying rod (2) is arranged obliquely from the ice storage bin (1) to the conveying pipe (3).
5. The ice adding device according to claim 1, characterized in that: The delivery pipe (3) comprises a first pipe (31) and a second pipe (32); the first pipe (31) and the second pipe (32) are welded, and the first pipe (31) is arranged vertically.
6. The ice adding device according to claim 5, characterized in that: The second pipeline (32) is arranged obliquely from the first pipeline (31) to the reaction tank (4).
7. The ice adding device according to claim 5, characterized in that: A pulse air blowing valve (7) is provided on the outer peripheral surface of the first pipeline (31) and close to the connection between the first pipeline (31) and the second pipeline (32).
8. An ice adding device according to claim 7, characterized in that: The pulse blowing valve (7) is provided with a nozzle (72), and the nozzle (72) is directed toward the connection point between the first pipe (31) and the second pipe (32).
9. The ice adding device according to claim 8, characterized in that: The side of the first pipeline (31) is provided with an air inlet pipe (311), the pulse air blowing valve (7) is provided with an air blowing pipe (71), the air blowing pipe (71) is connected to the air inlet pipe (311) via a flange (5), and the nozzle (72) is disposed inside the air blowing pipe (71).
10. The ice adding device according to claim 9, characterized in that: A baffle (312) is provided on the inner wall of the first pipe (31) above the air inlet pipe (311), and the baffle (312) is bent toward the connection between the first pipe (31) and the second pipe (32).