Gypsum board suspended ceiling mounting structure
By using alloy booms, sliding plates and magnet rods in the installation of gypsum board ceilings, the problems of low installation efficiency and poor accuracy in the existing technology are solved, convenient installation and disassembly are achieved, and work efficiency and installation accuracy are improved. .
Patent Information
- Application Number
- CN202420393976.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-29
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-02-28
AI Technical Summary
During the installation of existing gypsum board ceilings, workers have high labor intensity, low installation efficiency, and are prone to position deviations, difficulty in disassembling, which affects work efficiency and accuracy.
A structure including alloy boom, sliding plate, drawstring, spring, magnet rod and metal collar is designed to adjust the position of the gypsum board through sliding and magnetic force, and the convenience and position of the ceiling installation and disassembly are achieved using spring and magnetic force. Fine-tuning.
It improves the installation and disassembly efficiency of gypsum board ceiling, enhances installation accuracy, reduces workers' labor intensity, and simplifies the position adjustment and deviation correction process.
Smart Images

Figure CN222120693U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building decoration, and particularly relates to a gypsum board ceiling installation structure. Background Art
[0002] Gypsum board is a material made of building gypsum as the main raw material. It is a building material with light weight, high strength, thin thickness, easy processing, and good sound insulation, heat insulation and fire resistance. The ceiling has the functions of heat preservation, heat insulation, sound insulation and sound absorption. It is also a hidden layer for electrical, ventilation and air conditioning, communication and fire protection, alarm pipeline equipment and other projects.
[0003] At present, the Chinese utility model with publication number: CN219138117U discloses a gypsum board ceiling installation structure, which belongs to the field of interior decoration technology. It includes a hanging rod embedded in the roof and a keel hung under the hanging rod, and also includes a hanging rod connected to the gypsum board, a mounting beam is connected under the keel, and a clamping hole for the hanging rod to pass through is opened on the mounting beam, and a self-locking piece is arranged in the mounting beam. When the hanging rod has a tendency to move downward in the mounting beam, the self-locking piece limits and fixes the hanging rod. This application has the effect of reducing the labor intensity of workers during the installation of gypsum board ceilings.
[0004] The existing gypsum board ceiling installation usually places the gypsum board at the bottom of the hanger and temporarily fixes it on the hanger by bonding. The workers can loosen the support of the gypsum board only after they fix the hanger and the keel by bolts. The labor intensity of the workers in this installation process is high and the practicality is low. At the same time, position deviation is inevitable during the installation of the gypsum board ceiling, and this installation method is also very troublesome for the disassembly of the gypsum board, thus reducing the work efficiency of the gypsum board ceiling installation. Utility Model Content
[0005] The utility model aims to provide a gypsum board ceiling installation structure, which has the advantages of being convenient for installing and disassembling the gypsum board ceiling and being able to fine-tune and correct the position of the gypsum board after installation.
[0006] The above technical purpose of the utility model is achieved through the following technical solutions: a gypsum board ceiling installation structure, including a crossbeam, alloy hangers are arranged on both sides of the crossbeam, sliding plates slidably connected to the alloy hangers are slidably connected to both sides of the crossbeam, and pull ropes are fixedly connected to one end of the two sliding plates close to the inside of the crossbeam, and springs are respectively fixedly connected to the sliding plates and the crossbeam on the surface of the pull rope, and the end of the pull rope away from the sliding plate is fixedly connected to a connecting sleeve slidably connected to the bottom of the crossbeam, a bottom plate is installed at the bottom of the connecting sleeve, and a gypsum board is installed at the bottom of the bottom plate.
[0007] By adopting the above technical scheme, the gypsum board is pulled downward, so that the sliding plate is pulled back to the inside of the beam to compress the spring, so that the beam can be placed between the two alloy hangers for free movement, and then the gypsum board is loosened and the rebound force of the spring is used to drive the sliding plate to be inserted into the inside of the alloy hanger to fix the beam, thereby facilitating the installation and disassembly of the gypsum board ceiling and improving work efficiency; the metal ring slides on the surface of the magnet rod so that the gypsum board can slide left and right to adjust the position, and the magnetic force between the magnet rod and the metal ring fixes the position of the gypsum board, and then the sliding plate slides back and forth inside the alloy hanger to adjust the position of the gypsum board, and the magnetic force between the magnet sheet and the alloy hanger fixes the position of the gypsum board, thereby achieving the function of fine-tuning and correcting the position of the gypsum board after installation, thereby improving the installation accuracy.
[0008] The utility model is further configured as follows: a magnet rod is fixedly connected to the inside of the connecting sleeve, a metal ring fixedly connected to the top of the bottom plate is slidably sleeved on the surface of the magnet rod, and a magnet sheet magnetically connected to the alloy hanger is fixedly connected to one end of the sliding plate close to the alloy hanger.
[0009] By adopting the above technical solution, the metal ring slides on the surface of the magnet rod so that the gypsum board can slide left and right to adjust its position, and then the sliding plate slides back and forth inside the alloy hanger to adjust the position of the gypsum board, and the position of the gypsum board is fixed by magnetic force, so that the position of the gypsum board after installation can be fine-tuned and corrected to improve the installation accuracy.
[0010] The utility model is further configured as follows: a threaded rod is installed on the top of the alloy suspension rod, and a fastening bolt which is clamped with the alloy suspension rod is sleeved on the surface of the bottom of the threaded rod.
[0011] By adopting the above technical solution, the alloy suspension rod is fixedly installed at the bottom of the threaded rod by threading the surface of the threaded rod with a fastening bolt.
[0012] The utility model is further configured as follows: a sliding groove which is slidably connected with the threaded rod is provided inside the alloy suspension rod.
[0013] By adopting the above technical solution, the alloy suspension rod can be easily slid into the bottom of the threaded rod, thereby improving the installation efficiency.
[0014] The utility model is further configured as follows: an expansion bolt is installed on the top of the threaded rod.
[0015] By adopting the above technical solution, the top of the threaded rod is fixed on the ceiling, thereby improving the installation stability.
[0016] The utility model is further configured as follows: one end of the sliding plate close to the alloy suspension rod is rotatably connected to a ball which is slidably connected to the alloy suspension rod.
[0017] By adopting the above technical solution, the friction of the sliding plate sliding inside the alloy suspension rod is reduced, making movement easier.
[0018] The utility model is further configured as follows: the top of the gypsum board is bonded to the bottom of the base plate by quick-drying glue.
[0019] The above technical solution is adopted to facilitate the rapid fixing of the gypsum board to the bottom of the base plate, thereby improving work efficiency.
[0020] In summary, the utility model has the following beneficial effects:
[0021] 1. Pull the gypsum board downwards to pull the sliding plate back into the interior of the beam to compress the spring, so that the beam can be placed between the two alloy hangers for free movement. Then, by loosening the gypsum board, use the spring's rebound force to drive the sliding plate to snap into the interior of the alloy hanger to fix the beam, thereby facilitating the installation and removal of the gypsum board ceiling and improving work efficiency.
[0022] 2. The metal ring slides on the surface of the magnet rod so that the gypsum board can slide left and right to adjust its position. At the same time, the magnetic force between the magnet rod and the metal ring fixes the position of the gypsum board. Then, the sliding plate slides back and forth inside the alloy hanger to adjust the position of the gypsum board. The magnetic force between the magnet sheet and the alloy hanger fixes the position of the gypsum board, thereby achieving the function of fine-tuning and correcting the position of the gypsum board after installation, thereby improving the installation accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the structure of the utility model;
[0024] Figure 2 It is a cross-sectional view of the structure of the utility model;
[0025] Figure 3 This utility model Figure 2 Enlarged view of point A in .
[0026] Figure numerals: 1. alloy hanger; 2. crossbeam; 3. gypsum board; 4. sliding plate; 5. spring; 6. base plate; 7. connecting sleeve; 8. pull rope; 9. magnet rod; 10. metal ring; 11. magnet sheet; 12. ball bearing; 13. threaded rod; 14. fastening bolt; 15. slide groove; 16. expansion bolt. DETAILED DESCRIPTION
[0027] The utility model is further described in detail below in conjunction with the accompanying drawings.
[0028] Embodiment 1:
[0029] refer to Figure 1 , Figure 2 , Figure 3The gypsum board ceiling installation structure comprises a cross beam 2, alloy hangers 1 are arranged on both sides of the cross beam 2, and sliding plates 4 slidably connected to the alloy hangers 1 are slidably connected to the two sides of the cross beam 2, and a pull rope 8 is fixedly connected to one end of the two sliding plates 4 close to the inside of the cross beam 2, and a spring 5 fixedly connected to the sliding plate 4 and the cross beam 2 is arranged on the surface of the pull rope 8, and the end of the pull rope 8 away from the sliding plate 4 is fixedly connected to a connecting sleeve 7 slidably connected to the bottom of the cross beam 2, and a bottom plate 6 is installed at the bottom of the connecting sleeve 7, and a gypsum board 3 is installed at the bottom of the bottom plate 6; by pulling the gypsum board 3 downward, the sliding plate 4 is pulled back to the inside of the cross beam 2 to compress the spring 5, so that the cross beam 2 can be placed between the two alloy hangers 1 for free movement, and then the gypsum board 3 is loosened and the resilience of the spring 5 is used to drive the sliding plate 4 to be stuck in the inside of the alloy hanger 1 to fix the cross beam 2, thereby facilitating the installation and disassembly of the gypsum board ceiling and improving the work efficiency.
[0030] refer to Figure 1 A threaded rod 13 is installed on the top of the alloy hanger 1, and a fastening bolt 14 that is clamped with the alloy hanger 1 is threadedly sleeved on the surface of the bottom of the threaded rod 13. The fastening bolt 14 is threadedly sleeved on the surface of the threaded rod 13, so that the alloy hanger 1 is clamped and installed at the bottom of the threaded rod 13.
[0031] refer to Figure 1 A slide groove 15 is provided inside the alloy suspension rod 1 and is slidably connected to the threaded rod 13, so that the alloy suspension rod 1 can slide into the bottom of the threaded rod 13 to improve the installation efficiency.
[0032] refer to Figure 1 An expansion bolt 16 is installed on the top of the threaded rod 13 to fix the top of the threaded rod 13 on the ceiling to improve the stability of the installation.
[0033] Brief description of the usage process: Use quick-drying glue to glue the gypsum board 3 to the bottom of the base plate 6, and then pull the gypsum board 3 downward so that the gypsum board 3 pulls the sliding plate 4 back to the inside of the beam 2 through the connecting sleeve 7 and the pull rope 8, thereby compressing the spring 5 so that the beam 2 can be placed between the two alloy hangers 1, and then loosen the gypsum board 3 so that the rebound force of the spring 5 drives the sliding plate 4 to reset, thereby clamping the sliding plate 4 into the inside of the alloy hanger 1 to fix the beam 2, and re-entering the inside of the beam 2 through the connecting sleeve 7 to reset the gypsum board 3, and then fix the gypsum board 3. At the same time, when disassembling, you only need to pull the gypsum board 3 downward again to retract the sliding plate 4 back into the inside of the beam 2.
[0034] Embodiment 2:
[0035] refer to Figure 1 , Figure 2 , Figure 3, a gypsum board ceiling installation structure, the inside of the connecting sleeve 7 is fixedly connected with a magnet rod 9, the surface of the magnet rod 9 is slidably sleeved with a metal ring 10 fixedly connected to the top of the bottom plate 6, and the end of the sliding plate 4 close to the alloy suspension rod 1 is fixedly connected with a magnet sheet 11 magnetically connected to the alloy suspension rod 1; the metal ring 10 slides on the surface of the magnet rod 9, so that the gypsum board 3 can slide left and right to adjust the position, and at the same time, the magnetic force between the magnet rod 9 and the metal ring 10 fixes the position of the gypsum board 3, and then the sliding plate 4 slides back and forth inside the alloy suspension rod 1 to adjust the position of the gypsum board 3, and the magnetic force between the magnet sheet 11 and the alloy suspension rod 1 is used to fix the position of the gypsum board 3, so as to achieve the function of fine-tuning and correcting the position of the gypsum board after installation, thereby improving the installation accuracy.
[0036] refer to Figure 3 One end of the sliding plate 4 close to the alloy suspension rod 1 is rotatably connected to a ball 12 that is slidably connected to the alloy suspension rod 1, thereby reducing the friction of the sliding plate 4 sliding inside the alloy suspension rod 1 and facilitating movement.
[0037] refer to Figure 2 The top of the gypsum board 3 is bonded to the bottom of the base plate 6 by quick-drying glue, which facilitates the gypsum board 3 to be quickly fixed to the bottom of the base plate 6 and improves work efficiency.
[0038] Brief description of the usage process: by pulling the gypsum board 3, the bottom plate 6 is driven to move left and right, so that the bottom plate 6 drives the metal ring 10 to slide on the surface of the magnet rod 9, and the sliding of the gypsum board 3 is limited by the magnet rod 9, so that the gypsum board 3 can slide left and right to adjust the position, and at the same time, the position of the gypsum board 3 is fixed by the mutual magnetic attraction between the magnet rod 9 and the metal ring 10, and then the gypsum board 3 is pulled forward and backward to make the crossbeam 2 drive the sliding plate 4 to slide forward and backward inside the alloy hanger 1 to adjust the position of the gypsum board 3, and the position of the gypsum board 3 is fixed by the mutual magnetic attraction between the magnet sheet 11 and the alloy hanger 1.
[0039] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of the present invention.
Claims
1. A gypsum board ceiling installation structure, comprising a crossbeam (2), characterized in that: Alloy hangers (1) are provided on both sides of the cross beam (2), and sliding plates (4) slidably connected to the alloy hangers (1) are slidably connected to both sides of the cross beam (2), and one end of the two sliding plates (4) close to the inside of the cross beam (2) is fixedly connected to a pull rope (8), and the surface of the pull rope (8) is sleeved with a spring (5) fixedly connected to the sliding plate (4) and the cross beam (2) respectively, and the end of the pull rope (8) away from the sliding plate (4) is fixedly connected to a connecting sleeve (7) slidably connected to the bottom of the cross beam (2), and a bottom plate (6) is installed at the bottom of the connecting sleeve (7), and a gypsum board (3) is installed at the bottom of the bottom plate (6).
2. A gypsum board ceiling installation structure according to claim 1, characterized in that: The interior of the connecting sleeve (7) is fixedly connected to a magnet rod (9), the surface of the magnet rod (9) is slidably sleeved with a metal ring (10) fixedly connected to the top of the bottom plate (6), and one end of the sliding plate (4) close to the alloy suspension rod (1) is fixedly connected to a magnet sheet (11) magnetically connected to the alloy suspension rod (1).
3. A gypsum board ceiling installation structure according to claim 1, characterized in that: A threaded rod (13) is installed on the top of the alloy suspension rod (1), and a fastening bolt (14) which is clamped to the alloy suspension rod (1) is threadedly sleeved on the surface of the bottom of the threaded rod (13).
4. A gypsum board ceiling installation structure according to claim 3, characterized in that: The alloy suspension rod (1) is provided with a sliding groove (15) inside thereof which is slidably connected to the threaded rod (13).
5. The gypsum board ceiling installation structure according to claim 3, characterized in that: An expansion bolt (16) is installed on the top of the threaded rod (13).
6. A gypsum board ceiling installation structure according to claim 2, characterized in that: One end of the sliding plate (4) close to the alloy suspension rod (1) is rotatably connected to a ball (12) which is slidably connected to the alloy suspension rod (1).
7. A gypsum board ceiling installation structure according to claim 1, characterized in that: The top of the gypsum board (3) is bonded to the bottom of the base plate (6) by quick-drying glue.