Prefabricated aqueduct hoisting structure
By designing a prefabricated aqueduct lifting structure and fixing the aqueduct using positioning piers and adjustment components, the aqueduct shake and friction problems caused by rope instability are solved, and lifting safety and efficiency are improved.
Patent Information
- Application Number
- CN202420132775.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-19
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-01-19
AI Technical Summary
During the hoisting construction of existing aqueducts, the instability of the rope causes the aqueduct to shake and friction, which easily causes damage and rope breakage, which poses certain dangers.
A prefabricated aqueduct hoisting structure is designed, including positioning pier, side plate, rotating seat, rotating plate, hoisting ring and adjustment assembly, which passes through the hoist through the hoist through the hoist through the hoist through the rope, and the positioning pier and side are used to use the rotating plate and adjustment assembly. The plate is fixed to the aqueduct to avoid collision with objects and adapt to aqueducts of different sizes through the adjustment components.
The stable fixation and rapid separation of the aqueduct are achieved, avoiding rope wear and breakage, and improving lifting safety and efficiency.
Smart Images

Figure CN222138440U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, in particular to a prefabricated aqueduct hoisting structure. Background Art
[0002] An aqueduct is an overhead channel that conveys water across rivers, valleys, depressions, and roads. It is commonly used for irrigation, flood control, and sediment removal, and large aqueducts can also be navigable. Constructed primarily of stone masonry, concrete, and reinforced concrete, aqueducts, as water-conveying structures, are widely used in civil engineering. Prefabricated aqueducts, owing to their high efficiency and ease of construction, are widely used in aqueduct projects.
[0003] Announcement No. CN217296921U discloses a prefabricated aqueduct hoisting structure for hoisting prefabricated aqueducts, including a hanger base plate, a hanger upright plate and a hoisting top plate, wherein the limit piers are placed on the hanger base plate, at least two hanger upright plates are placed on both end sides of the hoisting base plate, the hanger top plate is placed on the top of two mirror-opposite hanger upright plates, the segment clamping bolts pass through the hanger top plate and are arranged in the direction of the limit piers, and the hoisting top plate is provided with external hoisting equipment, which can not only reduce the difficulty of aqueduct hoisting construction, but also improve the quality of aqueduct hoisting construction.
[0004] In the existing aqueduct hoisting construction, rope hoisting is usually adopted, and the rope is directly connected to the aqueduct, and the hoisting stability is poor. The aqueduct hoisted by the rope is swaying in the air, which is easy to collide with the aqueduct and cause damage to the aqueduct. In addition, when the rope is used to hoist the prefabricated aqueduct, the rope hoisting the aqueduct in the air causes the rope to cause the aqueduct to shake, resulting in friction at the connection between the rope and the aqueduct. Using a rope to hoist the aqueduct multiple times is easy to cause the rope to break, which is easy to cause production accidents, which is dangerous. For this reason, we propose a prefabricated aqueduct hoisting structure to solve the above problems. Utility Model Content
[0005] The purpose of the utility model is to provide a prefabricated aqueduct hoisting structure to solve the problem proposed in the above-mentioned background technology that when using ropes to hoist the prefabricated aqueduct, the ropes will cause the aqueduct to shake because the ropes are hoisted in the air, resulting in friction at the connection between the ropes and the aqueduct. Using one rope to hoist the aqueduct multiple times can easily cause the rope to break, thereby easily causing production accidents and posing certain risks.
[0006] To achieve the above-mentioned object, the present utility model provides the following technical solutions: a prefabricated aqueduct hoisting structure, comprising a bottom plate for hoisting;
[0007] Positioning piers, wherein two groups of positioning piers are provided, and the two groups of positioning piers are symmetrically installed on the bottom plate;
[0008] Side panels, wherein two groups of side panels are provided and the two groups of side panels are mounted on the upper ends of the two groups of positioning piers;
[0009] Rotating seats, the rotating seats are provided in four groups, and the four groups of rotating seats are fixedly mounted on the upper ends of the two groups of side plates;
[0010] Rotating plates, wherein the rotating plates are provided in four groups, and the four groups of rotating plates are rotatably installed in four groups of rotating seats;
[0011] The lifting rings are provided in four groups, and the four groups of lifting rings are fixedly mounted on the upper sides of opposite ends of the four groups of rotating plates;
[0012] An adjusting component is movably mounted on the base plate and the positioning piers, and is used to adjust the distance between the two groups of positioning piers.
[0013] Preferably, the adjustment component includes a slide groove, which is opened in the base plate, and opposing screw rods are rotatably installed in the slide groove. Slide blocks are fixedly installed on the lower sides of the two groups of positioning piers, and the two groups of slide blocks are sleeved on the left and right ends of the opposing screw rods.
[0014] Preferably, two groups of second screw rods are installed in the upper ends of the two groups of positioning piers, three groups of synchronous wheels are rotatably installed in the lower ends of the two groups of side panels, four groups of synchronous wheels at the front and rear ends of the two groups of side panels are fixedly connected to the upper ends of the four groups of second screw rods, two groups of synchronous belts are sleeved on the six groups of synchronous wheels, and two groups of synchronous wheels are installed in the middle of the two groups of side panels, and rotating handles are fixedly installed on them respectively.
[0015] Preferably, the two groups of positioning piers are L-shaped, and the inner walls of the lower ends of the two groups of positioning piers are arc-shaped.
[0016] Preferably, rubber pads are glued to the inner walls of the lower ends of the two groups of positioning piers.
[0017] Preferably, the middle positions of the four groups of rotating plates are rotatably connected to the four groups of rotating seats, the opposite ends of the four groups of rotating plates protrude from the inner wall of the positioning pier, and the opposite ends of the four groups of rotating plates are located between the two groups of positioning piers.
[0018] The present invention has the following advantages compared with the prior art: the present invention first places the prefabricated aqueduct on the two groups of positioning piers, passes ropes through the four groups of lifting rings to connect with the crane, and pulls the four groups of lifting rings by the crane to lift the opposite ends of the four groups of rotating plates, so that the opposite ends of the four groups of rotating plates are downwardly fitted on the prefabricated aqueduct, and the prefabricated aqueduct can be fixedly installed in the two groups of positioning piers, which is convenient for quickly separating the two groups of positioning piers from the prefabricated aqueduct after the prefabricated aqueduct is installed, and the two groups of positioning piers are separated from the prefabricated aqueduct in a way that does not require manual disassembly, and the prefabricated aqueduct can be avoided from collision with objects during lifting, and there is no need for ropes to be connected to the prefabricated aqueduct, which avoids wear and breakage of the ropes and the prefabricated aqueduct hammock. When lifting prefabricated aqueducts of different sizes, the two groups of positioning piers and the two groups of side plates can be moved closer or farther away by rotating the opposing screw rods and the rotating handle, which is convenient for fixing prefabricated aqueducts of different sizes. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0020] Figure 1 It is a schematic front view of the structure of the utility model;
[0021] Figure 2 This is a schematic diagram of a left-side cross-section of the structure of the present invention;
[0022] Figure 3 This is a schematic front cross-sectional view of the structure of the present invention;
[0023] Figure 4 For this utility model Figure 2 A partial enlarged schematic diagram of the middle A.
[0024] In the figure: 1. Base plate; 2. Positioning pier; 3. Side plate; 4. Rotating seat; 5. Rotating plate; 6. Lifting ring; 7. Slide groove; 8. Opposite screw rod; 9. Slider; 10. Second screw rod; 11. Synchronous pulley; 12. Synchronous belt; 13. Rotating handle; 14. Rubber pad. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0026] See also Figure 1-4 , the utility model provides an embodiment: a prefabricated aqueduct hoisting structure, comprising a bottom plate 1 for hoisting;
[0027] Positioning piers 2, there are two groups of positioning piers 2, and the two groups of positioning piers 2 are symmetrically installed on the bottom plate 1;
[0028] Side panels 3, there are two sets of side panels 3, the two sets of side panels 3 are installed on the upper ends of the two sets of positioning piers 2;
[0029] The rotating seat 4 is provided with four groups, and the four groups of rotating seats 4 are fixedly mounted on the upper ends of the two groups of side plates 3;
[0030] The rotating plates 5 are provided with four groups, and the four groups of rotating plates 5 are rotatably installed in the four groups of rotating seats 4;
[0031] The lifting rings 6 are provided in four groups, and the four groups of lifting rings 6 are fixedly mounted on the upper sides of the opposite ends of the four groups of rotating plates 5;
[0032] The adjusting component is movably mounted on the bottom plate 1 and the positioning pier 2. The adjusting component is used to adjust the distance between the two groups of positioning piers 2. The device places the prefabricated aqueduct in the two groups of positioning piers 2, and then connects it to the four groups of lifting rings 6 through ropes. The ropes drive the opposite ends of the four groups of rotating plates 5 to rise, and the opposite ends of the four groups of rotating plates 5 are lowered to fit the upper end of the prefabricated aqueduct, so that the prefabricated aqueduct can be fixed. Then, the adjusting component can be used to adapt and place prefabricated aqueducts of different widths.
[0033] Furthermore, the adjustment component includes a slide groove 7, which is opened in the base plate 1, and an opposing screw rod 8 is rotatably installed in the slide groove 7. Slide blocks 9 are fixedly installed on the lower sides of the two groups of positioning piers 2. The two groups of slide blocks 9 are sleeved on the left and right ends of the opposing screw rod 8. This structure drives the connected slide blocks 9 to slide in the slide groove 7 by rotating the opposing screw rod 8, so that the two groups of positioning piers 2 can be moved closer or farther away.
[0034] Furthermore, two groups of second screw rods 10 are installed in the upper ends of the two groups of positioning piers 2, and three groups of synchronous wheels 11 are rotatably installed in the lower ends of the two groups of side panels 3. The four groups of synchronous wheels 11 at the front and rear ends of the two groups of side panels 3 are fixedly connected to the upper ends of the four groups of second screw rods 10, and two groups of synchronous belts 12 are sleeved on the six groups of synchronous wheels 11. Two groups of synchronous wheels 11 are installed in the middle of the two groups of side panels 3, and rotating handles 13 are fixedly installed on them. This structure drives the three groups of synchronous wheels 11 and the synchronous belts 12 to rotate by rotating the rotating handles 13. The rotation of the synchronous wheels 11 drives the second screw rod 10 to rotate in the positioning pier 2, so that the side panels 3 can be raised on the positioning pier 2, which is convenient for fixing prefabricated aqueducts of different heights.
[0035] Furthermore, the two groups of positioning piers 2 are L-shaped, and the inner walls of the lower ends of the two groups of positioning piers 2 are arc-shaped. This structure makes the lower end of the prefabricated aqueduct fit with the inner walls of the lower ends of the two groups of positioning piers 2 according to the shape of the two groups of positioning piers 2.
[0036] Furthermore, rubber pads 14 are glued to the inner walls of the lower ends of the two groups of positioning piers 2. This structure prevents wear and damage to the prefabricated aqueduct and the inner walls of the positioning piers 2 when the prefabricated aqueduct is placed in the two groups of positioning piers 2 through the rubber pads 14 on the inner walls of the two groups of positioning piers 2.
[0037] Furthermore, the middle positions of the four groups of rotating plates 5 are rotatably connected to the four groups of rotating seats 4, and the opposite ends of the four groups of rotating plates 5 protrude from the inner wall of the positioning pier 2. The opposite ends of the four groups of rotating plates 5 are located between the two groups of positioning piers 2. This structure is based on the installation position of the four groups of rotating plates 5, so that when the opposite ends of the four groups of rotating plates 5 are raised, the opposite ends of the four groups of rotating plates 5 are attached to the upper edge of the prefabricated aqueduct.
[0038] Working principle: When hoisting the prefabricated aqueduct, Figure 2 、 Figure 3 and Figure 4 As shown, first rotate the opposing screw rod 8, and the opposing screw rod 8 rotates to drive the two sets of sliders 9 to slide in the slide groove 7. The two sets of sliders 9 slide and drive the two sets of positioning piers 2 to move closer or farther away, and then the prefabricated aqueduct is placed in the two sets of positioning piers 2. According to the height of the prefabricated aqueduct, rotate the rotating handle 13. The rotating handle 13 rotates and drives the two sets of synchronous wheels 11 to rotate. The two sets of synchronous wheels 11 rotate and drive the two sets of synchronous belts 12 and rotate the four sets of synchronous wheels 11 in the front and rear ends of the two sets of positioning piers 2. The four sets of synchronous wheels 11 rotate and drive the four sets of second screw rods 10 to rotate. The four sets of second screw rods 10 rotate and slide out from the two sets of positioning piers 2,
[0039] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention. Therefore, the embodiments should be considered in all respects as illustrative and non-restrictive, and the scope of the present invention is defined by the appended claims, not the foregoing description, and all variations within the meaning and range of equivalents of the claims are intended to be encompassed within the present invention. Any reference sign in a claim should not be construed as limiting the claim to which it relates.
Claims
1. A prefabricated aqueduct hoisting structure, comprising a bottom plate (1) for hoisting; Features: Positioning piers (2), wherein two groups of the positioning piers (2) are provided, and the two groups of the positioning piers (2) are symmetrically installed on the bottom plate (1); Side panels (3), wherein two groups of the side panels (3) are provided, and the two groups of the side panels (3) are installed on the upper ends of the two groups of positioning piers (2); A rotating seat (4), wherein the rotating seat (4) is provided in four groups, and the four groups of the rotating seats (4) are fixedly mounted on the upper ends of the two groups of side plates (3); Rotating plates (5), wherein four groups of rotating plates (5) are provided, and the four groups of rotating plates (5) are rotatably installed in four groups of rotating seats (4); Lifting rings (6), wherein four groups of the lifting rings (6) are provided, and the four groups of the lifting rings (6) are fixedly mounted on the upper sides of opposite ends of the four groups of rotating plates (5); An adjustment component is movably mounted on the base plate (1) and the positioning piers (2), and is used to adjust the distance between the two groups of positioning piers (2).
2. The prefabricated aqueduct hoisting structure according to claim 1, characterized in that: The adjustment assembly comprises a slide groove (7), the slide groove (7) is arranged in the bottom plate (1), a counter screw rod (8) is rotatably installed in the slide groove (7), and a slider (9) is fixedly installed on the lower side of the two groups of positioning piers (2), and the two groups of sliders (9) are sleeved on the left and right ends of the counter screw rod (8).
3. The prefabricated aqueduct hoisting structure according to claim 1, characterized in that: Two groups of second screw rods (10) are installed in the upper ends of the two groups of positioning piers (2), three groups of synchronous wheels (11) are rotatably installed in the lower ends of the two groups of side plates (3), four groups of synchronous wheels (11) at the front and rear ends of the two groups of side plates (3) are fixedly connected to the upper ends of the four groups of second screw rods (10), two groups of synchronous belts (12) are sleeved on the six groups of synchronous wheels (11), and rotating handles (13) are fixedly installed on the two groups of synchronous wheels (11) installed in the middle of the two groups of side plates (3).
4. The prefabricated aqueduct hoisting structure according to claim 1, characterized in that: The two groups of positioning piers (2) are L-shaped, and the inner walls of the lower ends of the two groups of positioning piers (2) are both arc-shaped.
5. The prefabricated aqueduct hoisting structure according to claim 1, characterized in that: Rubber pads (14) are glued to the inner walls of the lower ends of the two groups of positioning piers (2).
6. The prefabricated aqueduct hoisting structure according to claim 1, characterized in that: The middle positions of the four groups of rotating plates (5) are rotatably connected to the four groups of rotating seats (4), and the opposite ends of the four groups of rotating plates (5) protrude from the inner wall of the positioning pier (2), and the opposite ends of the four groups of rotating plates (5) are located between the two groups of positioning piers (2).