Fabricated diagonal-bracing-free building green construction enclosing wall
Through the design of the prefabricated oblique-free building green construction fence, locking components and threaded connections are used to achieve rapid installation and disassembly, solving the problems of long construction cycles and great environmental impact of traditional walls, and improving construction efficiency and material utilization.
Patent Information
- Application Number
- CN202420835007.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-22
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-04-22
AI Technical Summary
The construction period of traditional building construction walls is long, has a great environmental impact, and is difficult to recycle, especially when it is necessary to quickly build and demolish it, showing obvious limitations.
Adopt prefabricated green construction fence, including the wall body, columns, connecting sleeves, locking components, butt holes, locking sliding interfaces, support blocks and reinforcement rods, and quickly install and Disassemble and reduce unnecessary tilting structures through fitting columns, bases and reinforcement plates.
The rapid installation and disassembly of the fence is achieved, the connection stability is enhanced, the installation practicality is improved, and the environmental impact is reduced through galvanized steel sheet materials and reasonable structure.
Smart Images

Figure CN222140912U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to an assembled green construction fence free of diagonal bracing. Background Art
[0002] Construction refers to the production activities in the implementation stage of engineering construction. It is the construction process of various buildings. It can also be said that it is the process of turning various lines on the design drawings into physical objects at designated locations. In order to prevent accidental injuries caused by falling objects from high altitudes and to prevent criminals from entering the construction site to steal equipment and workers' property and cause unnecessary losses, walls are usually built at the construction site. In modern construction, walls, as temporary or permanent enclosure structures, undertake multiple functions such as safety protection, construction area division, and noise control.
[0003] Traditional building construction fences mainly use masonry or prefabricated concrete panels. Although these methods meet the construction needs to a certain extent, they have disadvantages such as long construction period, great impact on the environment, and difficulty in recycling. Especially in occasions where rapid construction and dismantling are required, the limitations of these fence panels are more obvious. Therefore, the utility model proposes an assembled green construction fence without diagonal bracing. Utility Model Content
[0004] The purpose of the utility model is to provide an assembled green construction fence without diagonal bracing, so as to solve the problem that the traditional construction fence mainly adopts masonry or prefabricated concrete slabs, which meet the construction needs to a certain extent, but have the disadvantages of long construction period, great impact on the environment, and difficulty in recycling. Especially in occasions where rapid construction and dismantling are required, the limitations of these fences are more obvious.
[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0006] An assembled green construction fence without diagonal bracing, comprising:
[0007] A wall body, wherein an upper connecting plate and a lower connecting plate are respectively installed on the top and the bottom of the wall body, and the upper connecting plate and the lower connecting plate are used to position the wall body;
[0008] The upright posts are arranged at the left and right ends of the wall body;
[0009] Connecting sleeves, two groups of connecting sleeves are provided, and the connecting sleeves are provided at the upper and lower ends of the left side of the left end column;
[0010] A locking assembly, which is arranged between the connecting sleeves;
[0011] Docking holes, which are opened at the upper and lower ends of the right side of the column at the right end corresponding to the connecting sleeve;
[0012] A locking sliding interface, the locking sliding interface is opened on the right side of the column at the right end corresponding to the locking component, and the left side of the locking sliding interface is connected with a threaded hole;
[0013] Support blocks, which are arranged inside the wall body and distributed at four diagonal corners, and first reinforcing rods and second reinforcing rods are cross-arranged between the support blocks;
[0014] Wherein, the locking assembly includes a handle, a first gear, a second gear, a threaded rod and a connecting threaded sleeve. The handle is connected to the first gear through a rotating shaft. The first gear and the second gear perform meshing motion. The second gear is fixedly connected to a threaded rod, and the outer part of the threaded rod is sleeved with a connecting threaded sleeve.
[0015] Optionally, the wall body is made of galvanized steel plate.
[0016] Optionally, a stopper is provided at the top of the column, and a base is provided at the bottom of the column.
[0017] Optionally, a reinforcement plate is provided between the column and the base, and four positioning bolts are evenly distributed on the upper surface of the base.
[0018] Optionally, a connecting fastener is provided on the upper connecting plate, and the connecting fastener is arranged in an L shape, and one side of the connecting fastener is detachably connected to the column, and the other side of the connecting fastener is detachably connected to the upper connecting plate.
[0019] The beneficial effects of the utility model are:
[0020] In the utility model, through the cooperation of the connecting sleeve and the docking hole, it is possible to facilitate the installers to quickly install and disassemble. In order to increase the stability of the connection, a locking assembly is set, and the handle is turned. Through the engagement between the first gear and the second gear, the movement of the handle shaft is transmitted to the threaded rod, thereby driving the connecting threaded sleeve to move linearly on the threaded rod, and then fixedly connected with the corresponding threaded hole, so that the splicing between the fences is more secure, and the practicability of the installation between the fences is further improved. In addition, through the cooperation of the column, the base, the reinforcement plate and the positioning bolts, the structure is reasonable and firm, and unnecessary tilting support structure is reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 This is a structural schematic diagram of an assembled green construction fence without diagonal bracing of the utility model;
[0022] Figure 2 It is a structural schematic diagram of another viewing angle in the utility model;
[0023] Figure 3 It is a cross-sectional view in the present utility model.
[0024] The numbers in the figure are:
[0025] 1. Wall body; 2. Column; 3. Upper connecting plate; 4. Lower connecting plate; 5. Connecting fastener; 6. Stopper; 7. Base; 8. Reinforcement plate; 9. Positioning bolt; 10. Connecting sleeve;
[0026] 11. Locking assembly; 1101. Handle; 1102. First gear; 1103. Second gear; 1104. Threaded rod; 1105. Connecting threaded sleeve;
[0027] 12. Docking hole; 13. Locking sliding interface; 14. Threaded hole; 15. Support block; 16. First reinforcement rod; 17. Second reinforcement rod. DETAILED DESCRIPTION
[0028] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0029] The following is an explanation of the preferred embodiments of the device of the utility model.
[0030] See also Figure 1-3As shown, the assembled green construction fence without diagonal bracing includes a fence body 1, which serves as the main fence structure and provides protection and isolation functions. The fence body 1 is a galvanized steel plate with anti-corrosion and anti-rust properties. An upper connecting plate 3 and a lower connecting plate 4 are respectively installed on the top and bottom of the fence body 1. The upper connecting plate 3 and the lower connecting plate 4 are used to position the fence body 1. A connecting fastener 5 is arranged on the upper connecting plate 3. The connecting fastener 5 is arranged in an L shape, and one side of the connecting fastener 5 is detachably connected to the column 2, and the other side of the connecting fastener 5 is detachably connected to the upper connecting plate 3. The columns 2 are arranged at the left and right ends of the fence body 1, a stopper 6 is arranged on the top of the column 2, a base 7 is arranged on the bottom of the column 2, and a reinforcing plate 8 is arranged between the column 2 and the base 7 to increase the stability of the column 2. Four positioning plates are evenly distributed on the upper surface of the base 7. Bolts 9 and connecting sleeves 10 are provided in two groups. The connecting sleeves 10 are arranged at the upper and lower ends of the left side of the left end column 2, and the locking assembly 11 is arranged between the connecting sleeves 10. The docking holes 12 are opened at the upper and lower ends of the right side of the right end column 2 corresponding to the connecting sleeves 10. Through the cooperation of the connecting sleeves 10 and the docking holes 12, it is convenient for the installers to quickly install and disassemble. The locking sliding interface 13 is opened at the right side of the right end column 2 corresponding to the locking assembly 11, and the left side of the locking sliding interface 13 is connected with a threaded hole 14. The setting of the locking sliding interface 13 facilitates the connection of the threaded sleeve 1105 to align with the connecting threaded hole 14. The support blocks 15 are arranged inside the wall body 1 and distributed on four diagonals. The first reinforcement rod 16 and the second reinforcement rod 17 are cross-arranged between the support blocks 15 to increase the stability of the wall body 1.
[0031] Among them, the locking assembly 11 includes a handle 1101, a first gear 1102, a second gear 1103, a threaded rod 1104 and a connecting threaded sleeve 1105. The handle 1101 is connected to the first gear 1102 through a rotating shaft. The first gear 1102 and the second gear 1103 perform meshing motion. The second gear 1103 is fixedly connected to the threaded rod 1104, and the outer part of the threaded rod 1104 is sleeved with a connecting threaded sleeve 1105. Specifically, through the mutual cooperation of the handle 1101, the first gear 1102, the second gear 1103, the threaded rod 1104 and the connecting threaded sleeve 1105, convenient locking between the left end column 2 and the right end column 2 can be achieved, thereby ensuring the stability and safety of the connection between several wall bodies 1.
[0032] Working principle: During installation, the staff first assembles and connects the column 2, the upper connecting plate 3, the lower connecting plate 4, the connecting fastener 5, the block 6, the base 7 and the fence body 1, and then the staff splices and assembles several assembled fence bodies 1, inserts the connecting sleeve 10 into the docking hole 12 accordingly, twists the handle 1101, and transmits the movement of the rotating shaft of the handle 1101 to the threaded rod 1104 through the engagement between the first gear 1102 and the second gear 1103, thereby driving the connecting threaded sleeve 1105 to move linearly on the threaded rod 1104, and then fixedly connected with the corresponding threaded hole 14, so that the splicing between the fences is more secure, and finally the positioning bolt 9 on the base 7 is sunk and positioned.
[0033] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and the specification only describe the principles of the utility model. The utility model may be subject to various changes and improvements without departing from the spirit and scope of the utility model. These changes and improvements fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. An assembled green construction fence without diagonal bracing, characterized in that: include: A wall body (1), wherein an upper connecting plate (3) and a lower connecting plate (4) are respectively installed on the top and the bottom of the wall body (1), and the upper connecting plate (3) and the lower connecting plate (4) are used to position the wall body (1); The upright posts (2) are arranged at the left and right ends of the enclosure body (1); A connecting sleeve (10), wherein two groups of the connecting sleeve (10) are provided, and the connecting sleeve (10) is provided at the upper and lower ends of the left side of the left end column (2); A locking assembly (11), the locking assembly (11) being arranged between the connecting sleeves (10); A docking hole (12), the docking hole (12) is opened at the upper and lower ends of the right side of the column (2) at the right end corresponding to the connecting sleeve (10); A locking sliding interface (13), the locking sliding interface (13) is arranged on the right side of the upright column (2) at the right end corresponding to the locking assembly (11), and the left side of the locking sliding interface (13) is connected to a threaded hole (14); Support blocks (15), the support blocks (15) are arranged inside the enclosure body (1) and distributed at four diagonal corners, and first reinforcing rods (16) and second reinforcing rods (17) are cross-arranged between the support blocks (15); The locking assembly (11) comprises a handle (1101), a first gear (1102), a second gear (1103), a threaded rod (1104) and a connecting threaded sleeve (1105); the handle (1101) is connected to the first gear (1102) via a rotating shaft; the first gear (1102) and the second gear (1103) perform meshing motion; the second gear (1103) is fixedly connected to the threaded rod (1104); and the outer portion of the threaded rod (1104) is sleeved with a connecting threaded sleeve (1105).
2. The assembled green construction fence without diagonal bracing according to claim 1 is characterized in that: The enclosure body (1) is made of galvanized steel plate.
3. The assembled green construction fence without diagonal bracing according to claim 1 is characterized in that: A stopper (6) is provided at the top of the column (2), and a base (7) is provided at the bottom of the column (2).
4. The assembled green construction fence without diagonal bracing according to claim 3 is characterized in that: A reinforcing plate (8) is provided between the upright column (2) and the base (7), and four positioning bolts (9) are evenly distributed on the upper surface of the base (7).
5. The assembled green construction fence without diagonal bracing according to claim 3 is characterized in that: The upper connecting plate (3) is provided with a connecting fastener (5), which is arranged in an L shape, and one side of the connecting fastener (5) is detachably connected to the column (2), and the other side of the connecting fastener (5) is detachably connected to the upper connecting plate (3).