Superheater hoisting structure
Through the design of clamp and clamp structures, combined with screws and screws, the problems of inconvenient installation and disassembly of superheater lifting structures and difficulty in fixing snake-shaped pipes in the prior art are solved, and the simplicity and stability of the structure are achieved, and different pipe diameters are adapted to and spacing requirements.
Patent Information
- Application Number
- CN202420919993.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-29
- Publication Date
- 2024-12-17
- Estimated Expiration
- 2034-04-29
AI Technical Summary
The existing superheater hoisting structure is inconvenient to install and disassemble, and it is difficult to fix the snake-shaped tube to prevent deformation.
Using a clamp and clamp structure, a fan-shaped groove is installed on the inner side of the clamp and a snake-shaped tube to fit tightly. The clamp and clamp are connected by screws, and the screws and double nuts are combined to achieve fixing and lifting, which is convenient for installation and disassembly, and the clamp position is adjusted. Meet different pipe diameters and spacing.
The superheater lifting structure is realized simply installed and disassembled, and the serpentine tube is fixed to prevent deformation, and lifting and fixing is achieved through lifting lugs and screws to adapt to different pipe diameters and spacings.
Smart Images

Figure CN222181509U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of superheaters, in particular to a superheater hoisting structure. Background Art
[0002] The superheater includes a serpentine tube, and the hoisting structure of the superheater usually includes two clamping plates, which have a semicircular arc with the same diameter as the serpentine tube, and the two clamping plates are closed to fix the serpentine tube. In this technical solution, the connection between the two clamping plates is fixed by welding, which is inconvenient to install and disassemble.
[0003] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present disclosure, and therefore may include information that does not constitute the prior art known to ordinary technicians in the field. Utility Model Content
[0004] In view of the deficiencies in the prior art, the embodiment of the utility model discloses a superheater hoisting structure to solve the problem that the prior hoisting structure is inconvenient to install and disassemble.
[0005] The technical solution adopted by the utility model is as follows:
[0006] A superheater hanging structure is used for a superheater, wherein the superheater has a serpentine tube; the hanging structure comprises: a clamping plate having two pieces; a clamping block having a plurality of groups, wherein each group of the clamping blocks is symmetrically arranged between the two clamping plates, and each group of the clamping blocks is arranged at intervals along the length direction of the clamping plates at the upper end and the lower end of the serpentine tube, and comprises: a groove, which is opened at the upper end and the lower end of the inner side of the clamping block, is fan-shaped, and has a radius the same as that of the serpentine tube; wherein the grooves located around the serpentine tube are in close contact with the outer surface of the serpentine tube, and the clamping plate and the clamping blocks located at the same height are screwed.
[0007] A further technical solution is that the clamp includes: first through holes, which are spaced apart along the length direction of the clamp; the clamp block includes: second through holes, which are located corresponding to the first through holes; and the lifting structure includes: a first screw, which threadably connects the first through hole and the second through hole.
[0008] A further technical solution is that the hoisting structure further includes: a connecting block, which is arranged at the upper end between the two clamping plates; wherein the clamping plates and the connecting block are connected by screws.
[0009] A further technical solution is that the lifting structure includes: a top plate; the connecting block includes: a screw rod, which is arranged on the upper end of the connecting block and passes through the top plate; and a double nut, which is screwed into the upper end of the screw rod to fix the clamping plate on the top plate.
[0010] A further technical solution is that the connection block includes: a third through hole, the position of which corresponds to the first through hole; and the lifting structure includes: a second screw, threadedly connecting the first through hole and the third through hole.
[0011] A further technical solution is that the lifting structure further includes: a lifting lug, which is threadedly connected to the screw rod.
[0012] The beneficial effects of the embodiments of the present utility model are as follows:
[0013] (I) The superheater hoisting structure of the utility model comprises two clamping plates and a clamping block arranged between the two clamping plates. The upper and lower ends of the inner sides of the clamping block are provided with fan-shaped grooves. The radius of the grooves is the same as the radius of the serpentine tube. The clamping blocks are symmetrically inserted between adjacent serpentine tubes so that the grooves around the serpentine tubes are closely attached to the outer surface of the serpentine tubes. The clamping plates and the clamping blocks at the same height are connected by screws to fix the clamping plates and the clamping blocks together. The structure is simple and easy to install and disassemble. At the same time, the serpentine tube is fixed in the inscribed circle enclosed by the grooves to prevent the serpentine tube from deformation. Different pipe diameters and pipe spacings can be met by adjusting the position and size of the clamping blocks.
[0014] (ii) Furthermore, a connecting block is screwed to the upper ends of the two clamping plates, and a screw rod is arranged on the connecting block. When lifting is required, the lifting lugs on the screw rod can be connected to the superheater by a crane. When lifting and fixing is required, the screw rod passes through the top plate, and the double nuts are screwed into the top of the screw rod and tightened to fix the connecting block and the top plate together, thereby realizing the lifting of the superheater. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a front view structural schematic diagram of the superheater lifting structure of the utility model.
[0016] Figure 2 It is a cross-sectional view of the superheater hoisting structure of the utility model.
[0017] Figure 3 It is an axonometric view of the clamping block in the superheater lifting structure of the utility model.
[0018] In the figure:
[0019] 1. Serpentine tube; 2. Clamp; 21. First through hole; 3. Clamp block; 31. Groove; 32. Second through hole; 4. Connecting block; 41. Screw; 42. Double nut; 43. Third through hole; 5. Lifting ear; 51. Ring body; 52. Connecting part; 6. First screw; 7. Second screw; 8. Top plate. DETAILED DESCRIPTION
[0020] The specific implementation of the present utility model is described below in conjunction with the accompanying drawings.
[0021] In order to make the purpose, technical scheme and advantages of the utility model clearer, the device proposed in the utility model is further described in detail below in combination with the accompanying drawings and specific implementation methods. According to the following description, the advantages and features of the utility model will be clearer. It should be noted that the accompanying drawings adopt a very simplified form and use non-precise proportions, which are only used to conveniently and clearly assist in explaining the purpose of the implementation method of the utility model. In order to make the purpose, features and advantages of the utility model more obvious and easy to understand, please refer to the accompanying drawings. It should be noted that the structure, proportion, size, etc. illustrated by the accompanying drawings of this specification are only used to match the content disclosed in the specification, so that people familiar with this technology can understand and read, and are not used to limit the limiting conditions for the implementation of the utility model, so it has no technical substantive significance. Any modification of the structure, change of the proportional relationship or adjustment of the size, without affecting the effect that the utility model can produce and the purpose that can be achieved, should still fall within the scope of the technical content disclosed by the utility model.
[0022] First embodiment:
[0023] This embodiment discloses a superheater hoisting structure.
[0024] like Figure 1 As shown, the superheater hoisting structure is used for the superheater, and the superheater has a serpentine tube 1. Those skilled in the art can know that the technical solution of this embodiment can also be used for other heat exchange equipment with a serpentine tube 1, such as an economizer and a reheater.
[0025] like Figure 1 to Figure 3 As shown, the lifting structure includes a clamping plate 2 and a clamping block 3. The clamping plates 2 have two pieces, and the clamping blocks 3 have several groups. Each group of clamping blocks 3 is symmetrically arranged between the two clamping plates 2, and each group of clamping blocks 3 is arranged at intervals at the upper end and the lower end of the serpentine tube 1 along the length direction of the clamping plates 2. The clamping block 3 includes a groove 31, and the groove 31 is opened at the upper end and the lower end of the inner side of the clamping block 3, and the inner side refers to the side adjacent to the two symmetrical clamping blocks 3. The groove 31 is fan-shaped, and the radius is the same as the radius of the serpentine tube 1. Among them, the grooves 31 located around the serpentine tube 1 are close to the outer surface of the serpentine tube 1, and the clamping plates 2 and the clamping blocks 3 located at the same height are screwed.
[0026] like Figure 2As shown, exemplarily, two clamps 2 are arranged vertically and in parallel. First through holes 21 are provided on the clamps 2 at intervals along the length direction of the clamps 2. The clamping blocks 3 are provided at the upper and lower ends of all parallel pipes in the serpentine tube 1. The clamping block 3 includes a second through hole 32, which is transversely penetrated and provided in the middle of the clamping block 3, and when the clamping block 3 is fixed, the position of the second through hole 32 corresponds to the first through hole 21. The lifting structure also includes a first screw 6, which is threadedly connected to the first through hole 21 and the second through hole 32. Preferably, the angle corresponding to the fan shape of the groove 31 is 90°, so that the grooves 31 located around the serpentine tube 1 can completely surround the outer surface of the serpentine tube 1, and the supporting effect on the serpentine tube 1 is good.
[0027] During installation of this embodiment:
[0028] The clamping block 3 is symmetrically inserted into the upper and lower ends of all parallel pipes in the serpentine tube 1, so that the grooves 31 located around the serpentine tube 1 are close to the outer surface of the serpentine tube 1, and the clamping plates 2 are placed on both sides of the serpentine tube 1, and the first through hole 21 of the clamping plate 2 is aligned with the second through hole 32 of the clamping block 3. The first screw 6 is threadedly connected to the first through hole 21 and the second through hole 32, and the clamping plate 2 and the clamping block 3 are fixed together, and at the same time, the serpentine tube 1 is fixed in the inscribed circle enclosed by the groove 31.
[0029] The lifting structure of this embodiment connects the clamping plate 2 and the clamping block 3 at the same height by screws, has a simple structure, and is easy to install and disassemble. The serpentine tube 1 is fixed in the inscribed circle enclosed by the groove 31, which can prevent the serpentine tube 1 from deformation, and the position and size of the clamping block 3 can be adjusted to meet different pipe diameters and pipe spacings.
[0030] Second embodiment:
[0031] Based on the first embodiment, the second embodiment is further optimized and refined.
[0032] like Figure 2 As shown, further, the hoisting structure also includes a connecting block 4, which is arranged at the upper end between the two clamping plates 2. The clamping plates 2 and the connecting block 4 are screwed.
[0033] Exemplarily, the connection block 4 includes a third through hole 43, which runs transversely through the connection block 4. When the connection block 4 is fixed, the position of the third through hole 43 corresponds to the first through hole 21, and the connection block 4 is flush with the upper end of the clamping plate 2. The lifting structure includes a second screw 7, which is threadedly connected to the first through hole 21 and the third through hole 43. The connection block 4 can also be arranged at the lower end between the two clamping plates 2 to facilitate the placement of the superheater.
[0034] like Figure 2As shown, further, the hanging structure includes a top plate 8, and the top plate 8 is located at the upper end of the hanging structure. The connecting block 4 includes a screw rod 41 and a double nut 42. The screw rod 41 is arranged at the upper end of the connecting block 4 and passes through the top plate 8. The double nut 42 is screwed into the upper end of the screw rod 41 to fix the clamping plate 2 on the top plate 8.
[0035] Further, the lifting structure also includes a lifting lug 5, which is threadedly connected to the screw rod 41. Exemplarily, the lifting lug 5 includes a ring body 51 and a connecting portion 52 connected to the lower end of the ring body 51, a fourth through hole (not marked in the figure) is provided in the connecting portion 52, and the screw rod 41 is threadedly connected to the fourth through hole.
[0036] In this embodiment, when lifting is required, the threaded lifting ear 5 on the screw 41 can be used to lift the superheater through a crane. When lifting and fixing is required, the screw 41 passes through the top plate 8, and the double nut 42 is screwed into the top of the screw 41 and tightened to fix the connecting block 4 and the top plate 8 together to achieve the lifting of the superheater.
[0037] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0038] The above-mentioned embodiments only express several implementation methods of the utility model, and the description is relatively specific and detailed, but it cannot be understood as limiting the scope of the utility model patent. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the utility model, which all belong to the protection scope of the utility model. Therefore, the protection scope of the utility model patent shall be based on the attached claims.
Claims
1. Superheater hoisting structure, It is characterized in that Used for a superheater, the superheater having a serpentine tube; the hoisting structure comprises: The splint has two pieces; The clamping blocks have several groups, each group of the clamping blocks is symmetrically arranged between two clamping plates, and each group of the clamping blocks is spaced apart at the upper end and the lower end of the serpentine tube along the length direction of the clamping plates, including: The groove is provided at the upper end and the lower end of the inner side of the clamping block, is fan-shaped, and has the same radius as that of the serpentine tube; The grooves located around the serpentine tube are closely attached to the outer surface of the serpentine tube, and the clamping plate is screw-connected to the clamping block located at the same height.
2. The superheater hoisting structure according to claim 1, It is characterized in that The splint comprises: First through holes are provided at intervals along the length direction of the clamping plate; The clamping block comprises: a second through hole, located corresponding to the first through hole; The hoisting structure comprises: A first screw is threadedly connected to the first through hole and the second through hole.
3. The superheater hoisting structure according to claim 2, It is characterized in that The hoisting structure also includes: A connecting block, arranged at the upper end between the two clamping plates; Wherein, the clamping plate and the connecting block are connected by screws.
4. The superheater hoisting structure according to claim 3, It is characterized in that The hoisting structure comprises: a top plate; The connection block comprises: A screw rod is arranged at the upper end of the connecting block and passes through the top plate; A double nut is screwed into the upper end of the screw rod to fix the clamping plate to the top plate.
5. The superheater hoisting structure according to claim 3, It is characterized in that The connection block comprises: a third through hole, located corresponding to the first through hole; The hoisting structure comprises: The second screw is threadedly connected to the first through hole and the third through hole.
6. The superheater hoisting structure according to claim 4, Features: The hoisting structure also includes: A lifting lug is threadedly connected to the screw rod.