Tower crane foundation structure utilizing engineering piles

By using side-by-side distributed engineering piles and cast-in piles in the tower crane foundation, combining the middle-connected components and reinforced steel plates to form a rectangular distributed tower crane foundation structure, the problem of insufficient bearing capacity of the tower crane foundation is solved, and rapid installation and reduction of construction costs are achieved. Effect.

CN222275539UActive Publication Date: 2024-12-31ZHONGXIN CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420845855.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-23
Publication Date
2024-12-31
Estimated Expiration
2034-04-23

AI Technical Summary

Technical Problem

During the construction of the project, the soil layer distribution in the site of the tower crane is uneven, resulting in insufficient bearing capacity. The conventional four-hole cast-injected pile foundation is costly and has a long construction period, which consumes a lot of manpower and material resources.

Method used

Two engineering piles distributed side by side and two cast-in-place piles distributed side by side are used, combined with the middle-connected components and reinforced steel plates to form a rectangular tower crane foundation structure. The concrete cast layer is integrated with the engineering foundation to enhance the connection strength of the pile head and reduce the Number of cast piles and concrete construction area.

Benefits of technology

While meeting the bearing capacity requirements of the tower crane foundation, the number of cast piles and concrete construction area are reduced, the pile head connection strength is improved, the tower crane is quickly installed, and the construction cost and construction period are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222275539U_ABST
    Figure CN222275539U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of tower crane foundations, in particular to a tower crane foundation structure utilizing engineering piles. The tower crane foundation structure utilizing the engineering piles comprises the two engineering piles which are distributed side by side, and the two engineering piles are arranged on a poured engineering foundation; the tower crane foundation structure further comprises two cast-in-place piles distributed side by side, a concrete pouring layer is poured on the peripheries of the two cast-in-place piles, and the concrete pouring layer and the engineering foundation on the engineering piles are integrally formed in a pouring mode and flush with each other. The pile heads of the engineering piles and the pile heads of the cast-in-place piles extend out of the pouring layer and are provided with middle connecting assemblies. According to the tower crane foundation structure utilizing the engineering piles, the reinforcing steel plates are erected between the adjacent engineering piles, between the adjacent cast-in-place piles and between the adjacent engineering piles and the cast-in-place piles, so that the connecting strength of the socketed pipes on the pile heads is greatly enhanced, and then the first layer of a tower crane standard knot is located on the standard knot connector columns.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tower crane foundations, in particular to a tower crane foundation structure utilizing engineering piles. Background Art

[0002] When installing a tower crane in a construction project, it is often encountered that the soil layer in the site is unevenly distributed and its bearing capacity is less than the minimum requirement of the tower foundation for the foundation bearing capacity. The tower crane foundation needs to be selected as a pile foundation. Conventional tower crane pile foundations generally select four piles, but because they use bored cast-in-place piles, their cost is high and the construction period is long, which consumes a lot of manpower and material resources in the construction preparation stage.

[0003] Therefore, it is necessary to provide a new tower crane foundation structure using engineering piles to solve the above technical problems. Utility Model Content

[0004] In order to solve the above technical problems, the utility model provides a tower crane foundation structure using engineering piles.

[0005] The tower crane foundation structure using engineering piles provided by the utility model comprises two engineering piles distributed side by side, and the two engineering piles are arranged on the poured engineering foundation;

[0006] The tower crane foundation structure also includes two bored piles arranged side by side, the two bored piles and the two engineering piles are arranged in a rectangular shape on a horizontal plane, and a concrete pouring layer is poured around the two bored piles, the concrete pouring layer and the engineering foundation on the engineering piles are integrally formed and level with each other;

[0007] The pile heads of the engineering piles and the cast-in-place piles extend out of the casting layer and are provided with a central joint assembly, the central joint assembly comprising a sleeve pipe, a plurality of connecting plates distributed in an annular manner and used for connecting to the foundation are fixedly installed at the bottom of the sleeve pipe, and a fixing plate is fixedly installed at the top of the sleeve pipe, and a standard joint column for connecting the standard section of the tower crane is fixedly welded on the fixing plate;

[0008] Reinforcement steel plates are also installed between adjacent sleeve pipes.

[0009] Preferably, two side seats distributed in an angle are fixedly welded on the side wall of the sleeve tube, and a mounting groove is provided on the side seat, and side holes are provided on both side walls of the mounting groove.

[0010] Preferably, mounting plate heads are fixedly mounted on both ends of the reinforcing steel plate, and each mounting plate head is provided with a through hole.

[0011] Preferably, the mounting plate heads at both ends of the reinforcing steel plate are respectively inserted into mounting grooves provided on the corresponding side seats on the adjacent sleeve pipes, and the mounting plate heads are fixedly connected to the side seats by bolts.

[0012] Preferably, the connecting plate is provided with a plurality of mounting holes and is fixedly connected to the ground by long screws.

[0013] Preferably, bolt holes are provided on the standard joint column.

[0014] Compared with the related art, the tower crane foundation structure using engineering piles provided by the utility model has the following beneficial effects:

[0015] After the engineering piles and cast-in-place piles are arranged, the utility model sequentially installs the middle link assembly, specifically, the sleeve pipe is sleeved on the pile head extending out of the foundation surface, and then the long screw is passed through the installation hole provided in the connecting plate to be fixedly connected with the foundation, the side seats on the adjacent pile bodies are kept relatively arranged, and the reinforcing steel plates are installed on the side seats on the adjacent pile bodies by bolts, so that the reinforcing steel plates are all arranged between the adjacent engineering piles, between the adjacent cast-in-place piles, and between the adjacent engineering piles and cast-in-place piles, thereby greatly enhancing the connection strength of the sleeve pipes on each pile head, and subsequently the first layer of the tower crane standard section can be placed on the standard section joint column, so the tower crane can be quickly installed;

[0016] The utility model utilizes two engineering piles on the already cast engineering foundation, and subsequently adds two bored piles distributed side by side, and then casts the concrete casting layer and the engineering foundation into one, which can not only meet the bearing capacity requirements of the tower crane for the foundation, but also reduce the number of bored piles. The concrete casting layer is matched with the already cast engineering foundation, which also reduces the construction area of ​​the concrete casting layer. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A structural schematic diagram of a preferred embodiment of a tower crane foundation structure using engineering piles provided by the utility model;

[0018] Figure 2 for Figure 1 The schematic diagram of the distribution structure of engineering piles and cast-in-place piles shown;

[0019] Figure 3 for Figure 1 The structural schematic diagram of the mid-link assembly shown;

[0020] Figure 4 for Figure 1 Schematic diagram of the structure of the reinforced steel plate shown.

[0021] Numbers in the figure: 1, engineering pile; 2, cast-in-place pile; 3, concrete pouring layer; 4, central joint assembly; 41, sleeve pipe; 42, connecting plate; 42a, mounting hole; 43, fixing plate; 44, standard joint column; 44a, bolt hole; 45, side seat; 45a, mounting groove; 45b, side hole; 5, reinforcement steel plate; 51, mounting plate head; 51a, through hole. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.

[0023] The specific implementation of the present utility model is described in detail below in conjunction with specific embodiments.

[0024] See also Figures 1 to 4 The embodiment of the utility model provides a tower crane foundation structure using engineering piles, and the tower crane foundation structure using engineering piles includes: two engineering piles 1 distributed side by side and two cast-in-place piles 2 distributed side by side.

[0025] In the embodiments of the present invention, please refer to Figure 1 and Figure 2 The two engineering piles 1 are arranged on the already cast engineering foundation, and the two cast-in-place piles 2 and the two engineering piles 1 are distributed in a rectangular shape on a horizontal plane, and a concrete casting layer 3 is cast around the two cast-in-place piles 2, and the concrete casting layer 3 is cast integrally with the engineering foundation on the engineering piles 1 and is level with each other.

[0026] It should be noted that by utilizing two engineering piles 1 on the already cast engineering foundation and subsequently adding two bored piles 2 distributed side by side, the cast concrete casting layer 3 is cast as one with the engineering foundation, which not only meets the bearing capacity requirements of the tower crane for the foundation, but also reduces the number of bored piles. The concrete casting layer 3 is combined with the already cast engineering foundation, which also reduces the construction area of ​​the concrete casting layer 3.

[0027] In the embodiments of the present invention, please refer to Figure 1 , Figure 3 and Figure 4The pile heads of the engineering pile 1 and the cast-in-place pile 2 extend out of the casting layer and are both provided with a central joint assembly 4, the central joint assembly 4 comprising a sleeve pipe 41, a plurality of connecting plates 42 distributed in an annular manner and used for connecting to the foundation are fixedly installed at the bottom of the sleeve pipe 41, and a plurality of mounting holes 42a are provided on the connecting plate 42 and fixedly connected to the ground through long screws, and a fixing plate 43 is fixedly installed on the top of the sleeve pipe 41, a standard joint column 44 for connecting the standard section of the tower crane is fixedly welded on the fixing plate 43, and a bolt hole 44a is provided on the standard joint column 44, two side seats 45 distributed at 90° are fixedly welded on the side wall of the sleeve pipe 41, and a carrying groove 45a is provided on the side seat 45, and side holes 45b are provided on both side walls of the carrying groove 45a, and a reinforcing steel plate 5 is also installed between adjacent sleeve pipes 41;

[0028] Specifically, both ends of the reinforcing steel plate 5 are fixedly installed with mounting plate heads 51, and each of the mounting plate heads 51 is provided with a through hole 51a, and the mounting plate heads 51 at both ends of the reinforcing steel plate 5 are respectively inserted into the mounting grooves 45a opened on the corresponding side seats 45 on the adjacent sleeve pipes 41, and the mounting plate heads 51 are fixedly connected to the side seats 45 by bolts.

[0029] It should be noted that after the engineering piles 1 and the bored piles 2 are set up, the middle link assembly 4 is installed in turn. Specifically, the sleeve 41 is sleeved on the pile head extending out of the foundation surface, and then the long screws are passed through the mounting holes 42a opened in the connecting plate 42 to fix it to the foundation (the connecting plate 42 on the engineering pile 1 is fixed on the already cast engineering foundation, and the connecting plate 42 on the bored pile 2 is fixed on the later cast concrete casting layer 3). The side seats 45 on the adjacent pile bodies are kept relatively arranged, and the reinforcing steel plates 5 are installed on the side seats 45 on the adjacent pile bodies by bolts. Therefore, reinforcing steel plates 5 are installed between adjacent engineering piles 1, between adjacent bored piles 2, and between adjacent engineering piles 1 and bored piles 2, thereby greatly enhancing the connection strength of the sleeves 41 on each pile head. Subsequently, the first layer of the standard section of the tower crane can be placed on the standard section joint column 44, so the tower crane can be installed quickly.

[0030] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A tower crane foundation structure using engineering piles, comprising two engineering piles (1) arranged side by side, wherein the two engineering piles (1) are arranged on a poured engineering foundation, and characterized in that: The tower crane foundation structure further comprises two bored piles (2) arranged side by side, the two bored piles (2) and the two engineering piles (1) being arranged in a rectangular shape on a horizontal plane, and a concrete pouring layer (3) being poured around the two bored piles (2), the concrete pouring layer (3) being integrally formed with the engineering foundation on the engineering piles (1) and being flush with each other; The pile heads of the engineering pile (1) and the cast-in-place pile (2) both extend out of the casting layer and are both provided with a central joint assembly (4), the central joint assembly (4) comprising a sleeve pipe (41), a plurality of connecting plates (42) distributed in an annular manner and used for connecting to the foundation being fixedly mounted on the bottom of the sleeve pipe (41), and a fixing plate (43) being fixedly mounted on the top of the sleeve pipe (41), and a standard joint column (44) for connecting to a tower crane standard joint being fixedly welded on the fixing plate (43); A reinforcing steel plate (5) is also installed between adjacent sleeve tubes (41).

2. The tower crane foundation structure using engineering piles according to claim 1 is characterized in that: Two side mounts (45) are fixedly welded to the side wall of the sleeve tube (41) and are distributed at 90 degrees. The side mounts (45) are provided with a mounting groove (45a), and side holes (45b) are provided on both side walls of the mounting groove (45a).

3. The tower crane foundation structure using engineering piles according to claim 2 is characterized in that: Both ends of the reinforcing steel plate (5) are fixedly mounted with mounting plate heads (51), and each mounting plate head (51) is provided with a through hole (51a).

4. The tower crane foundation structure using engineering piles according to claim 3 is characterized in that: The mounting plate heads (51) at both ends of the reinforcing steel plate (5) are respectively inserted into mounting grooves (45a) provided on the corresponding side mounts (45) on the adjacent sleeve pipes (41), and the mounting plate heads (51) are fixedly connected to the side mounts (45) by bolts.

5. The tower crane foundation structure using engineering piles according to claim 1, characterized in that: The connection plate (42) is provided with a plurality of mounting holes (42a) and is fixedly connected to the ground via long screws.

6. The tower crane foundation structure using engineering piles according to claim 1, characterized in that: The standard joint column (44) is provided with a bolt hole (44a).