External scaffold through-wall type tying device

By designing the wall-through-type pulling device of the external scaffolding, using three-stage wall connecting parts and adjustable roof support, the problems of waste of steel pipes and fasteners and concrete cracks in traditional construction are solved, and efficient and economic pulling effect is achieved. Suitable for shear wall structures, improving construction safety and standardization and tooling.

CN222276134UActive Publication Date: 2024-12-31YUNNAN CONSTR ENG GENERAL CONTRACTING
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323330070.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-07
Publication Date
2024-12-31
Estimated Expiration
2033-12-07

AI Technical Summary

Technical Problem

The pre-embedded knotting device used in traditional construction wastes steel pipes and fasteners, which has poor economic benefits, and may cause cracks when under premature stress on concrete. It is not suitable for shear wall structures, which have safety hazards and do not comply with standardized tools. development trend.

Method used

A wall-through-type pulling device for external scaffolding is designed, using three-stage wall connecting parts, adjustable top support and connecting steel pipes, and is connected to the fastening part through the connecting parts to avoid pre-embedding and rear anchoring, which is suitable for shear walls. Structure, providing adjustable pull-on points, using standard parts, reducing the use of disposable consumables.

Benefits of technology

The device saves time and effort, avoids point deviation, eliminates waste of steel pipes and fasteners, has a wide range of application and good economicality. It is suitable for secondary structure decoration and decoration construction, improving construction safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222276134U_ABST
    Figure CN222276134U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of scaffolds, in particular to an external scaffold through-wall type tying device which comprises a fastening part and a tying part connected with the fastening part through a connecting piece, the fastening part comprises an adjustable jacking, one end of the adjustable jacking is provided with a jacking supporting plate, and the other end of the adjustable jacking is provided with a jacking screw. A jacking connecting steel pipe is sleeved on the jacking screw rod, the tying part is a wall connecting piece steel pipe, one end of the wall connecting piece steel pipe is fixedly connected with the jacking connecting steel pipe, and the other end of the wall connecting piece steel pipe is fixedly connected with a cross rod of the double-row scaffold vertical rod. According to the through-wall type pulling and connecting device for the external scaffold, the building construction external scaffold is pulled and connected through the three-section type wall connecting piece, pre-burying or post-anchoring is not needed any more, a working face is provided for secondary structure decoration construction in advance, time and labor are saved, and the phenomenon of point position deviation is eradicated. Meanwhile, disposable consumables are not used in the method, all accessories are not prone to being damaged, the wall connecting piece can be manufactured into a standard piece, and the whole wall connecting piece can be recycled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of scaffolding, in particular to a wall-penetrating type tie-tying device for an external scaffolding. Background Art

[0002] The scaffolding system traditionally used in construction needs to be reliably connected to the building through wall ties. The traditional method of pre-embedded steel pipes is to pre-embed vertical steel pipes inside the concrete, and the wall ties are connected to the pre-embedded steel pipes through fasteners to form a rigid connection. This method requires a large amount of steel pipes and fasteners to be wasted, which is not economically efficient. In addition, premature stress on concrete will cause cracks and other quality problems. In case of a rush project, the pre-embedded Ala nodes must be removed in advance before the secondary structure construction can be interspersed. In this case, the tie points will be removed too early, which will leave major safety hazards to the entire frame. In addition, the pre-embedded tie is not suitable for shear wall structures, which does not conform to the development trend of standardization and tooling in the construction industry. Utility Model Content

[0003] The utility model aims to provide an external scaffolding through-the-wall anchoring device to solve the quality problems proposed in the above background technology, such as the need to waste a large number of steel pipes and fasteners, poor economic benefits, and the premature stress on concrete causing cracks and the like.

[0004] To achieve the above-mentioned purpose, the utility model provides an external scaffolding through-wall tensioning device, including a fastening part and a tensioning part connected to the fastening part through a connecting piece, the fastening part includes an adjustable top support, one end of the adjustable top support is equipped with a top support support plate, the other end is a top support screw, a top support connecting steel pipe is mounted on the top support screw, the tensioning part is a wall connecting steel pipe, one end of the wall connecting steel pipe is connected and fixed to the top support connecting steel pipe, and the other end of the wall connecting steel pipe is connected and fixed to the cross bar of the double-row scaffolding uprights.

[0005] Preferably, a jacking nut is installed near the end of the jacking screw connecting the steel pipe.

[0006] Preferably, one end of the adjustable jacking support passes through the shear wall, and the surface of the jacking support plate is attached to the outer wall of the shear wall.

[0007] Preferably, one end of the wall connecting member steel pipe is connected to the top supporting connecting steel pipe through a plurality of cross fasteners.

[0008] Preferably, a vertical pole is installed at one end of the wall connecting member steel pipe, the upper end of the vertical pole is connected to the wall connecting member steel pipe, and the lower end of the vertical pole is connected to the top supporting connecting steel pipe.

[0009] Preferably, a vertical pole is installed at one end of the wall connecting member steel pipe, the lower end of the vertical pole is connected to the wall connecting member steel pipe, and the upper end of the vertical pole is connected to the top supporting connecting steel pipe.

[0010] Preferably, the inner wall of the jacking support connecting steel pipe is provided with an internal thread, one end of the adjustable jacking support is provided with an external thread, and the jacking support connecting steel pipe is threadedly connected to the adjustable jacking support.

[0011] Compared with the prior art, the utility model has the following beneficial effects:

[0012] In the external scaffolding through-the-wall tie-up device, a three-section wall tie is used to tie up the external scaffolding of the building construction, and no pre-embedding or post-anchoring is required, so that a working surface is provided in advance for the secondary structure decoration and renovation construction, which saves time and effort, and eliminates the phenomenon of point deviation. At the same time, this method does not use disposable consumables, all accessories are not easily damaged, the wall tie can be made into a standard part, and the whole can be used in a turnover manner, which is economical. The wall tie of the present invention has various structures and a wide range of applications. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 This is one of the overall structural diagrams of the utility model;

[0014] Figure 2 This is the second schematic diagram of the overall structure of the utility model;

[0015] Figure 3 This is the third schematic diagram of the overall structure of the utility model.

[0016] The meaning of each number in the figure is:

[0017] 1. Adjustable top support; 1-1. Top support plate; 1-2. Top support screw; 1-3. Top support nut; 2. Top support connecting steel pipe; 3. Cross fastener; 4. Wall connecting steel pipe. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0019] Example 1

[0020] The utility model provides a wall-penetrating type tie-tying device for an external scaffolding, such as Figure 1As shown, it includes a fastening part and a pulling part connected to the fastening part through a connecting piece, the fastening part includes an adjustable top support 1, one end of the adjustable top support 1 is equipped with a top support support plate 1-1, and the other end is a top support screw 1-2, and a top support connecting steel pipe 2 is mounted on the top support screw 1-2, and the pulling part is a wall connecting steel pipe 4, one end of the wall connecting steel pipe 4 is connected and fixed to the top support connecting steel pipe 2, and the other end of the wall connecting steel pipe 4 is connected and fixed to the cross bar of the double-row scaffolding uprights.

[0021] In this embodiment, a supporting nut 1-3 is installed near the end of the supporting screw 1-2 and the supporting connecting steel pipe 2, which is used to lock and fix the end of the supporting screw 1-2.

[0022] Specifically, one end of the adjustable jacking support 1 passes through the shear wall, and the surface of the jacking support plate 1 - 1 is attached to the outer wall of the shear wall, so as to fix one end of the adjustable jacking support 1 .

[0023] Furthermore, the inner wall of the jacking support connecting steel pipe 2 is provided with an internal thread, one end of the adjustable jacking support 1 is provided with an external thread, and the jacking support connecting steel pipe 2 is threadedly connected to the adjustable jacking support 1 .

[0024] Further, such as Figure 1 As shown, when the tie-joint wall-connecting steel pipe 4 is close to the top-supporting connecting steel pipe 2, one end of the wall-connecting steel pipe 4 is connected to the top-supporting connecting steel pipe 2 through a plurality of cross fasteners 3, so as to facilitate the connection and fixation of the wall-connecting steel pipe 4 and the top-supporting connecting steel pipe 2.

[0025] Example 2

[0026] The utility model provides a wall-penetrating type tie-tying device for an external scaffolding, such as Figure 2 As shown, it includes a fastening part and a pulling part connected to the fastening part through a connecting piece, the fastening part includes an adjustable top support 1, one end of the adjustable top support 1 is equipped with a top support support plate 1-1, and the other end is a top support screw 1-2, and a top support connecting steel pipe 2 is mounted on the top support screw 1-2, and the pulling part is a wall connecting steel pipe 4, one end of the wall connecting steel pipe 4 is connected and fixed to the top support connecting steel pipe 2, and the other end of the wall connecting steel pipe 4 is connected and fixed to the cross bar of the double-row scaffolding uprights.

[0027] In this embodiment, a supporting nut 1-3 is installed near the end of the supporting screw 1-2 and the supporting connecting steel pipe 2, which is used to lock and fix the end of the supporting screw 1-2.

[0028] Specifically, one end of the adjustable jacking support 1 passes through the shear wall, and the surface of the jacking support plate 1 - 1 is attached to the outer wall of the shear wall, so as to fix one end of the adjustable jacking support 1 .

[0029] Furthermore, the inner wall of the jacking support connecting steel pipe 2 is provided with an internal thread, one end of the adjustable jacking support 1 is provided with an external thread, and the jacking support connecting steel pipe 2 is threadedly connected to the adjustable jacking support 1 .

[0030] Further, such as Figure 2 As shown, when the tie-part wall-connecting steel pipe 4 is located above the top-supporting connecting steel pipe 2, the spacing between the tie-points must meet the two-step and three-span setting requirements of the scheme. A vertical pole is installed at one end of the wall-connecting steel pipe 4, and the upper end of the vertical pole is connected to the wall-connecting steel pipe 4, and the lower end of the vertical pole is connected to the top-supporting connecting steel pipe 2. In this way, the connection between the wall-connecting steel pipe 4 and the top-supporting connecting steel pipe 2 is achieved.

[0031] Example 3

[0032] The utility model provides a wall-penetrating type tie-tying device for an external scaffolding, such as Figure 3 As shown, it includes a fastening part and a pulling part connected to the fastening part through a connecting piece, the fastening part includes an adjustable top support 1, one end of the adjustable top support 1 is equipped with a top support support plate 1-1, and the other end is a top support screw 1-2, and a top support connecting steel pipe 2 is mounted on the top support screw 1-2, and the pulling part is a wall connecting steel pipe 4, one end of the wall connecting steel pipe 4 is connected and fixed to the top support connecting steel pipe 2, and the other end of the wall connecting steel pipe 4 is connected and fixed to the cross bar of the double-row scaffolding uprights.

[0033] In this embodiment, a supporting nut 1-3 is installed near the end of the supporting screw 1-2 and the supporting connecting steel pipe 2, which is used to lock and fix the end of the supporting screw 1-2.

[0034] Specifically, one end of the adjustable jacking support 1 passes through the shear wall, and the surface of the jacking support plate 1 - 1 is attached to the outer wall of the shear wall, so as to fix one end of the adjustable jacking support 1 .

[0035] Furthermore, the inner wall of the jacking support connecting steel pipe 2 is provided with an internal thread, one end of the adjustable jacking support 1 is provided with an external thread, and the jacking support connecting steel pipe 2 is threadedly connected to the adjustable jacking support 1 .

[0036] Further, such as Figure 3 As shown, when the tie-joint wall-connecting steel pipe 4 is located below the top-supporting connecting steel pipe 2, a vertical pole is installed at one end of the wall-connecting steel pipe 4, the lower end of the vertical pole is connected to the wall-connecting steel pipe 4, and the upper end of the vertical pole is connected to the top-supporting connecting steel pipe 2. In this way, the connection between the wall-connecting steel pipe 4 and the top-supporting connecting steel pipe 2 is achieved.

[0037] When using the external scaffolding through-the-wall tie-down device of the utility model, materials and tools are first prepared: materials such as fastening parts, connectors and tie-down parts, as well as tools for installation and fixing, such as screwdrivers, cross fasteners, etc. First, the adjustable top support 1 is fixed to one side of the shear wall, and the top support support plate 1-1 is attached to the outer wall of the shear wall to fix one end of the adjustable top support 1. Then, the top support screw 1-2 is inserted into the shear wall from the other side, and the top support nut 1-3 is tightened to lock and fix the end of the top support screw 1-2. One end of the wall connecting piece steel pipe 4 is connected and fixed to the top support connecting steel pipe 2, and the other end of the wall connecting piece steel pipe 4 is connected and fixed to the cross bar of the double-row scaffolding uprights. The connecting part can be connected by a number of cross fasteners 3 to facilitate the connection and fixation of the wall connecting piece steel pipe 4 and the top support connecting steel pipe 2. As needed, the height of the supporting connecting steel pipe 2 can be adjusted by rotating the supporting screw rod 1-2 to adapt to external scaffolds of different heights and lengths. After the adjustment is completed, the supporting nut 1-3 is tightened again to lock and fix the end of the supporting screw rod 1-2.

[0038] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the utility model and are not used to limit the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection of the utility model is defined by the attached claims and their equivalents.

Claims

1. An external scaffolding through-the-wall tie-down device, characterized in that: The invention comprises a fastening part and a pulling part connected to the fastening part through a connecting piece, wherein the fastening part comprises an adjustable top support (1), one end of the adjustable top support (1) is provided with a top support support plate (1-1), and the other end is a top support screw (1-2), a top support connecting steel pipe (2) is sleeved on the top support screw (1-2), and the pulling part is a wall connecting steel pipe (4), one end of the wall connecting steel pipe (4) is connected and fixed to the top support connecting steel pipe (2), and the other end of the wall connecting steel pipe (4) is connected and fixed to the cross bar of the double-row scaffolding uprights.

2. The external scaffolding through-the-wall tie-down device according to claim 1 is characterized in that: A jacking nut (1-3) is installed on the end of the jacking screw rod (1-2) close to the jacking connection steel pipe (2).

3. The external scaffolding through-the-wall tie-down device according to claim 1 is characterized in that: One end of the adjustable top support (1) passes through the shear wall, and the surface of the top support plate (1-1) is attached to the outer wall of the shear wall.

4. The external scaffolding through-the-wall tie-down device according to claim 1 is characterized in that: One end of the wall connecting member steel pipe (4) is connected to the top supporting connecting steel pipe (2) via a plurality of cross fasteners (3).

5. The external scaffolding through-the-wall tie-down device according to claim 1 is characterized in that: A vertical pole is installed at one end of the wall connecting member steel pipe (4), the upper end of the vertical pole is connected to the wall connecting member steel pipe (4), and the lower end of the vertical pole is connected to the top supporting connecting steel pipe (2).

6. The external scaffolding through-the-wall tie-down device according to claim 1 is characterized in that: A vertical pole is installed at one end of the wall connecting member steel pipe (4), the lower end of the vertical pole is connected to the wall connecting member steel pipe (4), and the upper end of the vertical pole is connected to the top supporting connecting steel pipe (2).

7. The external scaffolding through-the-wall tie-down device according to claim 1 is characterized in that: The inner wall of the jacking support connecting steel pipe (2) is provided with an internal thread, one end of the adjustable jacking support (1) is provided with an external thread, and the jacking support connecting steel pipe (2) is threadedly connected to the adjustable jacking support (1).