Pouring thickness real-time monitoring device for concrete pouring

By using transparent film and U-frame plywood structures in the concrete casting device to isolate the concrete from contact with the vertical pole, and using the second threaded rod to drive the moving plate and pressure sensor to adjust the casting thickness, the problem of concrete solidification and thickness adjustment is solved, and the device is realized multiple uses and thickness monitoring accuracy.

CN222298687UActive Publication Date: 2025-01-03HANGZHOU HENGLIAN CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421162308.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-24
Publication Date
2025-01-03
Estimated Expiration
2034-05-24

AI Technical Summary

Technical Problem

The existing real-time monitoring device for pouring concrete in a long time can easily cause concrete to solidify on the vertical poles, affecting the visibility of the scale lines, and it is difficult to adjust the reasonable range of concrete pouring thickness.

Method used

The transparent film and U-frame clamp structure are adopted to prevent the concrete from contacting the vertical pole, and the moving plate and pressure sensor are driven to move through the second threaded pole, real-time monitoring and adjustment of the concrete cast thickness is achieved.

Benefits of technology

It effectively avoids the problem of concrete solidification on the vertical poles, which is convenient for cleaning and multiple use, and allows real-time adjustment of the concrete pouring thickness to avoid waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222298687U_ABST
    Figure CN222298687U_ABST
Patent Text Reader

Abstract

The utility model discloses a pouring thickness real-time monitoring device for concrete pouring, and relates to the technical field of constructional engineering. The device comprises a vertical rod, a monitoring assembly is arranged below the outer wall of the vertical rod, and a warning assembly is arranged above the outer wall of the vertical rod. A floating plate in the monitoring assembly is movably arranged below the outer wall of the vertical rod in a sleeving mode, a winding roller is rotationally connected to the floating plate, a transparent film is wound around the outer wall of the winding roller, and U-shaped frames are arranged on the periphery of the bottom end of the vertical rod. The bottom end of the transparent film is clamped on the outer side face of the vertical rod through a U-shaped frame and a clamping plate in the monitoring assembly, and the top end of the transparent film is driven to move through a floating plate and a winding roller, so that the problem that concrete is not conveniently prevented from being solidified on the vertical rod in the prior art is solved; and a second threaded rod in the warning assembly drives a movable plate and a pressure sensor to move relative to a fixed plate, and the problem that in the prior art, the warning range of the concrete pouring thickness is inconvenient to adjust is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of construction engineering, and particularly relates to a pouring thickness real-time monitoring device for concrete pouring. Background Art

[0002] With the development of construction engineering, the emergence of various construction equipment or instruments has greatly facilitated the construction process. Among them, the pouring thickness real-time monitoring device is a new type of construction equipment. Through the use of the pouring thickness real-time monitoring device, construction personnel can monitor the pouring thickness of concrete in real time, thereby improving the accuracy of concrete pouring and avoiding the waste of concrete.

[0003] The existing document with announcement number CN217716230U discloses a device for independently measuring the thickness of concrete pouring in real time, including a vertically arranged upright pole and a horizontally arranged floating plate, a sleeve is sleeved on the upright pole, the lower end of the sleeve is integrally connected to the floating plate, and the floating plate contacts the upper surface of the concrete. The upright pole is provided with a scale, and when the sleeve is at the lowest end of the upright pole, the upper end of the sleeve corresponds to the zero scale line of the scale;

[0004] However, it still has the following disadvantages in actual use:

[0005] 1. The above-mentioned device for independently measuring the pouring thickness of concrete in real time has a scale on the vertical pole, and when the sleeve is located at the lowest end of the vertical pole, the upper end of the sleeve corresponds to the zero scale line of the scale, and the pouring thickness of the concrete is indicated by the scale line. However, during the pouring process, the concrete will adhere to the vertical pole, and the concrete will solidify on the vertical pole during long-term use, thereby blocking the scale line, thereby affecting the next use of the device;

[0006] 2. The above-mentioned device for independently measuring the thickness of poured concrete in real time has an upper marking line and a lower marking line arranged in parallel on its vertical pole, and the upper marking line and the lower marking line are both red tape or green tape. The upper marking line and the lower marking line are used to display the reasonable design range of the concrete thickness. However, since the upper marking line and the lower marking line are both red tape or green tape, it is not convenient to change the reasonable range of the concrete pouring thickness in real time according to the construction requirements during the construction process.

[0007] To this end, we provide a real-time monitoring device for pouring thickness of concrete pouring to solve the above-mentioned problems. Utility Model Content

[0008] The utility model aims to provide a real-time monitoring device for the pouring thickness of concrete pouring, wherein the bottom end of a transparent film is clamped on the outer side of a vertical pole by a U-shaped frame and a clamping plate in a monitoring component, and the top end of the transparent film is driven to move by a floating plate and a winding roller, thereby solving the existing problem that it is inconvenient to prevent concrete from solidifying on the vertical pole, and the second threaded rod in the warning component drives the movable plate and the pressure sensor to move relative to the fixed plate, thereby solving the existing problem that it is inconvenient to adjust the warning range of the concrete pouring thickness.

[0009] In order to solve the above technical problems, the utility model is realized by the following technical solutions:

[0010] The utility model is a real-time monitoring device for pouring thickness of concrete, comprising a vertical pole, a monitoring component is arranged below the outer wall of the vertical pole, and a warning component is arranged above the outer wall of the vertical pole;

[0011] The floating plate in the monitoring component is movably sleeved under the outer wall of the vertical pole, and a winding roller is rotatably connected to the floating plate, and a transparent film is wound around the outer wall of the winding roller. A U-shaped frame is arranged around the bottom end of the vertical pole, and a clamping plate is movably connected inside the U-shaped frame.

[0012] The fixed plate in the warning component is sleeved on the outer wall of the vertical pole, and a movable plate is movably connected below the fixed plate. Pressure sensors are fixedly connected on all sides of the lower surface of the movable plate. The front end thread of the surface of the fixed plate passes through the second threaded rod, and the bottom end of the second threaded rod is rotatably connected to the front end of the upper surface of the movable plate.

[0013] The utility model is further configured as follows: scale lines are engraved and drawn on the outer walls around the vertical pole at equal intervals.

[0014] The utility model is further configured as follows: support rods are welded around the bottom ends of the vertical rods, and bottom plates are welded to the bottom ends of the support rods.

[0015] The utility model is further configured as follows: grooves are provided around the surface of the floating plate, mounting holes are provided on the inner walls on both sides of the grooves, both ends of the winding roller are fixedly connected with a rotating shaft, and the end of the rotating shaft away from the winding roller is rotatably connected to the inside of the mounting hole.

[0016] The utility model is further configured as follows: a first threaded rod is threaded through a group of vertical arms of the U-shaped frame, one end of the first threaded rod located on the outside of the U-shaped frame is fixedly connected to a first knob, and one end of the first threaded rod located on the inside of the U-shaped frame is rotatably connected to the outer wall of the movable plate away from the transparent film.

[0017] The utility model is further configured as follows: a protective shell is clamped on the outer side of the U-shaped frame.

[0018] The utility model is further configured as follows: limiting rods are movably penetrated around the surface of the fixed plate, the bottom ends of the limiting rods are respectively welded around the upper surface of the movable plate, and limiting nuts are threadedly sleeved on the top ends of the limiting rods.

[0019] The utility model is further configured as follows: mounting grooves are provided around the lower surface of the movable plate, and the pressure sensors are fixedly connected inside the mounting grooves.

[0020] The utility model is further configured as follows: the top end of the second threaded rod is fixedly connected with a second knob, and the second knob is located above the fixing plate.

[0021] The utility model has the following beneficial effects:

[0022] 1. The utility model provides a monitoring component, clamps the lower end of the transparent film above the outer side surface of the vertical pole through a U-shaped frame and a clamping plate, and drives the upper end of the transparent film to move through a floating plate and a winding roller, so that the transparent film is attached to the outer side surface of the vertical pole. The provision of the transparent film prevents the concrete from directly contacting the scale line on the end surface of the vertical pole, thereby facilitating the cleaning of the vertical pole and facilitating repeated use.

[0023] 2. The utility model sets a warning component, and through the threaded connection between the second threaded rod and the fixed plate, the second threaded rod drives the movable plate and the pressure sensor to move, and limits the thickness of concrete pouring through the movable plate and the pressure sensor, so as to avoid the waste of concrete caused by excessive concrete pouring.

[0024] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0026] Figure 1 The figure is a schematic diagram of the overall structure of a device for real-time monitoring of pouring thickness of concrete pouring;

[0027] Figure 2 It is a structural schematic diagram of the utility model upright pole;

[0028] Figure 3 This is a schematic diagram of the structure of the monitoring component of the utility model;

[0029] Figure 4This is a structural disassembly diagram of the floating plate of the utility model;

[0030] Figure 5 This is a schematic diagram of the installation between the U-shaped frame and the clamping plate of the utility model;

[0031] Figure 6 This is a schematic diagram of the structure of the warning component of the utility model;

[0032] Figure 7 It is a structural schematic diagram of the movable plate of the utility model.

[0033] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0034] 1-vertical pole, 101-scale line, 102-support rod, 103-bottom plate, 2-monitoring component, 201-floating plate, 201a-groove, 201b-mounting hole, 202-winding roller, 202a-rotating shaft, 203-transparent film, 204-U-shaped frame, 204a-first threaded rod, 204b-first knob, 205-clamping plate, 206-protective shell, 3-warning component, 301-fixed plate, 302-movable plate, 302a-limiting rod, 302b-limiting nut, 302c-mounting slot, 303-pressure sensor, 304-second threaded rod, 304a-second knob. DETAILED DESCRIPTION

[0035] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model. Specific embodiment 1

[0037] See also Figure 1-4 As shown, it is the first embodiment of the utility model, which provides a real-time monitoring device for pouring thickness of concrete pouring, including a vertical pole 1 and a monitoring component 2, and the monitoring component 2 includes a floating plate 201, a winding roller 202, a transparent film 203, a U-shaped frame 204 and a clamping plate 205. The upper end of the transparent film 203 is driven to move by the floating plate 201 and the winding roller 202, and the lower end of the transparent film 203 is fixed by the U-shaped frame 204 and the clamping plate 205. At the same time, the transparent film 203 is used to isolate the concrete and the vertical pole 1, thereby solving the existing problems of being inconvenient to clean the solidified concrete on the vertical pole 1 and being inconvenient to reuse for multiple times.

[0038] Specifically, the floating plate 201 is movably sleeved under the outer wall of the vertical pole 1, and a winding roller 202 is rotatably connected to the floating plate 201. The outer wall of the winding roller 202 is wrapped with a transparent film 203, and the U-shaped frame 204 is respectively arranged around the bottom end of the vertical pole 1. The inside of the U-shaped frame 204 is movably connected with a clamping plate 205. The floating plate 201 is set to display the pouring thickness of the concrete in real time, and the winding roller 202 is set to roll up the transparent film 203, and the concrete and the vertical pole 1 are isolated by the transparent film 203, and the lower end of the transparent film 203 is fixed by the U-shaped frame 204 and the clamping plate 205.

[0039] Furthermore, scale lines 101 are engraved on the outer walls of the four sides of the vertical pole 1 at equal intervals, support rods 102 are welded around the bottom end of the vertical pole 1, and bottom plates 103 are welded at the bottom ends of the support rods 102. The scale lines 101 are used to display the pouring thickness of the concrete in real time, and the support rods 102 and the bottom plates 103 are used to install the vertical pole 1;

[0040] Grooves 201a are provided on all sides of the surface of the floating plate 201, and mounting holes 201b are provided on the inner walls of both sides of the grooves 201a. The two ends of the winding roller 202 are fixedly connected with a rotating shaft 202a, and the end of the rotating shaft 202a away from the winding roller 202 is rotatably connected to the inside of the mounting hole 201b. The setting of the groove 201a is used to rotatably install the winding roller 202 on the floating plate 201, and the setting of the mounting hole 201b and the rotating shaft 202a realizes the rotatable installation of the winding roller 202 on the inner side of the groove 201a.

[0041] A first threaded rod 204a is threadedly penetrated on a group of vertical arms of the U-shaped frame 204, and one end of the first threaded rod 204a located on the outside of the U-shaped frame 204 is fixedly connected to a first knob 204b, and one end of the first threaded rod 204a located on the inside of the U-shaped frame 204 is rotatably connected to the outer wall of the moving plate 302 away from the transparent film 203. The first threaded rod 204a is used to drive the moving plate 302 to move, and the first knob 204b is used to facilitate the rotation of the first threaded rod 204a;

[0042] A protective shell 206 is clamped on the outer side of the U-shaped frame 204. The protection shell 206 is provided to prevent the U-shaped frame 204, the clamping plate 205 and other structures from contacting with concrete.

[0043] The operation process of this embodiment is as follows: first, remove the protective shell 206, and place the lower end of the transparent film 203 between the clamping plate 205 and the vertical pole 1, and turn the first knob 204b, so that the first knob 204b drives the first threaded rod 204a to rotate synchronously, and under the action of the threaded connection between the first threaded rod 204a and the vertical arm of the U-shaped frame 204, the first threaded rod 204a drives the clamping plate 205 to move, so that the lower end of the transparent film 203 is clamped under the outer side surface of the vertical pole 1 through the clamping plate 205, and the protective shell 206 is re-engaged. After being clamped on the U-shaped frame 204, the vertical pole 1 is then placed at the place where concrete needs to be poured through the support rod 102 and the bottom plate 103, and the concrete pouring work is carried out. During the concrete pouring process, the floating plate 201 is driven by the concrete to move on the outer wall of the vertical pole 1, and the pouring thickness of the concrete is obtained by comparing the positional relationship between the scale line 101 and the floating plate 201. At the same time, during the movement of the floating plate 201, the winding roller 202 and the upper end of the transparent film 203 are driven to move synchronously, so that the transparent film 203 is attached to the outer surface of the vertical pole 1. Specific embodiment 2

[0045] See also Figure 6-7 As shown, it is the second embodiment of the utility model, which is based on the previous embodiment, but is different from the previous embodiment in that: a warning component 3 is arranged above the outer wall of the vertical pole 1, and the warning component 3 includes a fixed plate 301, a movable plate 302, a pressure sensor 303 and a second threaded rod 304. The movable plate 302 and the pressure sensor 303 are driven by the second threaded rod 304 to move relative to the fixed plate 301, and the maximum thickness of the concrete pouring is warned by the pressure sensor 303, which solves the existing problem of inconvenience in real-time adjustment of the maximum thickness of the concrete pouring.

[0046] Specifically, the fixed plate 301 is sleeved on the outer wall of the vertical pole 1, and the movable plate 302 is movably connected to the lower part of the fixed plate 301. The lower surface of the movable plate 302 is fixedly connected with pressure sensors 303 on all sides. The front end thread of the surface of the fixed plate 301 passes through the second threaded rod 304, and the bottom end of the second threaded rod 304 is rotatably connected to the front end of the upper surface of the movable plate 302. The setting of the fixed plate 301 is used to install structures such as the movable plate 302. The setting of the movable plate 302 is used to drive the pressure sensor 303 to move, and the setting of the pressure sensor 303 is used to warn the maximum thickness of concrete pouring. At the same time, the setting of the second threaded rod 304 is used to drive the movable plate 302 to move relative to the fixed plate 301.

[0047] Furthermore, the surface of the fixed plate 301 is movably penetrated by the limiting rods 302a, the bottom ends of the limiting rods 302a are respectively welded to the upper surface of the movable plate 302, and the top thread sleeve of the limiting rods 302a is provided with limiting nuts 302b. The setting of the limiting rods 302a and the limiting nuts 302b realizes the movable installation of the movable plate 302 below the fixed plate 301, and limits the movement of the movable plate 302.

[0048] The lower surface of the movable plate 302 is provided with mounting grooves 302c all around, and the pressure sensors 303 are fixedly connected inside the mounting grooves 302c. The mounting grooves 302c are used to install the pressure sensors 303;

[0049] A second knob 304 a is fixedly connected to the top end of the second threaded rod 304 . The second knob 304 a is located above the fixing plate 301 . The second knob 304 a is arranged to facilitate the rotation of the second threaded rod 304 .

[0050] The rest of the structure is the same as that of the first embodiment.

[0051] The operation process of this embodiment is: turn the second knob 304a, the second knob 304a drives the second threaded rod 304 to rotate synchronously, and under the action of the threaded connection between the second threaded rod 304 and the fixed plate 301, the second threaded rod 304 drives the movable plate 302 to move, thereby driving the pressure sensor 303 to move through the movable plate 302, and by adjusting the height of the pressure sensor 303, the maximum thickness of the concrete pouring is warned.

[0052] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0053] The preferred embodiments of the utility model disclosed above are only used to help explain the utility model. The preferred embodiments do not describe all the details in detail, nor do they limit the utility model to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the utility model, so that technicians in the relevant technical field can well understand and use the utility model. The utility model is limited only by the claims and their full scope and equivalents.

Claims

1. A device for real-time monitoring of pouring thickness of concrete pouring, comprising a vertical pole (1), characterized in that: A monitoring assembly (2) is arranged below the outer wall of the vertical pole (1), and a floating plate (201) in the monitoring assembly (2) is movably sleeved below the outer wall of the vertical pole (1), a winding roller (202) is rotatably connected to the floating plate (201), and a transparent film (203) is wound around the outer wall of the winding roller (202), and a U-shaped frame (204) is arranged around the bottom end of the vertical pole (1), and a clamping plate (205) is movably connected inside the U-shaped frame (204); A warning component (3) is arranged above the outer wall of the vertical pole (1), and a fixed plate (301) in the warning component (3) is sleeved above the outer wall of the vertical pole (1), a movable plate (302) is movably connected below the fixed plate (301), and pressure sensors (303) are fixedly connected around the lower surface of the movable plate (302), a front end thread of the surface of the fixed plate (301) penetrates the second threaded rod (304), and the bottom end of the second threaded rod (304) is rotatably connected to the front end of the upper surface of the movable plate (302).

2. A real-time monitoring device for pouring thickness of concrete pouring according to claim 1, characterized in that: The outer walls of the vertical pole (1) are all engraved with scale lines (101) at equal intervals in the vertical direction.

3. A real-time monitoring device for pouring thickness of concrete pouring according to claim 2, characterized in that: Support rods (102) are welded around the bottom end of the vertical rod (1), and bottom plates (103) are welded at the bottom ends of the support rods (102).

4. A real-time monitoring device for pouring thickness of concrete pouring according to claim 1, characterized in that: The surface of the floating plate (201) is provided with grooves (201a) on all sides, and mounting holes (201b) are provided on the inner walls on both sides of the grooves (201a); both ends of the winding roller (202) are fixedly connected to a rotating shaft (202a), and the end of the rotating shaft (202a) away from the winding roller (202) is rotatably connected to the inside of the mounting hole (201b).

5. A real-time monitoring device for pouring thickness of concrete pouring according to claim 1, characterized in that: A first threaded rod (204a) is threadedly penetrated on a group of vertical arms of the U-shaped frame (204), and one end of the first threaded rod (204a) located on the outside of the U-shaped frame (204) is fixedly connected to a first knob (204b), and one end of the first threaded rod (204a) located on the inside of the U-shaped frame (204) is rotatably connected to the outer wall of the movable plate (302) away from the transparent film (203).

6. A real-time monitoring device for pouring thickness of concrete pouring according to claim 5, characterized in that: A protective shell (206) is clamped on the outer side of the U-shaped frame (204).

7. A real-time monitoring device for pouring thickness of concrete pouring according to claim 1, characterized in that: The surface of the fixed plate (301) is movably penetrated by limiting rods (302a), and the bottom ends of the limiting rods (302a) are respectively welded to the upper surface of the movable plate (302) and the top end of the limiting rods (302a) is threadedly sleeved with limiting nuts (302b).

8. A real-time monitoring device for pouring thickness of concrete pouring according to claim 1, characterized in that: The lower surface of the movable plate (302) is provided with mounting grooves (302c) on all sides, and the pressure sensors (303) are fixedly connected inside the mounting grooves (302c).

9. A real-time monitoring device for pouring thickness of concrete pouring according to claim 1, characterized in that: A second knob (304a) is fixedly connected to the top end of the second threaded rod (304), and the second knob (304a) is located above the fixing plate (301).