Drainage structure with floor drain overhauling function
By setting up spaced connecting parts and maintenance box on the drainage pipe, efficient dredging of the drainage pipe and replacement of the connecting parts is achieved, solving the problems of low dredging efficiency and high maintenance costs in the existing technology, and improving the maintenance efficiency of the drainage pipe and The practicality of the structure.
Patent Information
- Application Number
- CN202323424993.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2033-12-14
AI Technical Summary
The dredging and maintenance efficiency of existing drainage pipes in tunnels and basements is low, and it is difficult to replace the connecting parts, resulting in high maintenance costs.
A drainage structure with floor drain maintenance is designed, including a spaced connecting parts and a maintenance pipe opening on the drainage pipe. A maintenance box body is arranged above the maintenance pipe opening. The maintenance box body can be detached in the pit and the floor drain port is passed through. The sewer pipe is connected to the maintenance pipe opening, which is convenient for dredging and replacing the connecting parts, and the structural reinforcement of the maintenance box body and the sealing layer prevent leakage.
It improves the dredging efficiency of the drainage pipe, reduces maintenance costs, simplifies the construction and secondary repair processes, and enhances the practicality of the structure.
Smart Images

Figure CN222349882U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building waterproof equipment, and in particular relates to a drainage structure with floor drain maintenance function. Background Art
[0002] Drainage pipe is a kind of pipe with the function of inverted filtration and water permeability. Drainage pipe has strong drainage and water seepage effect, and has no special requirements for geology and terrain. Therefore, drainage pipe is widely used in tunnels, basements and other places. Tunnels, basements and other places are prone to water leakage problems. The traditional method is to break the ground to make grooves, and then lay drainage pipes for drainage. However, ordinary groove drainage mostly uses semi-circular pipes with inverted buckles. This method is easy to enter fine sand, causing blockage inside the drainage pipe, and the dredging and maintenance of the drainage pipe is quite labor-intensive and time-consuming.
[0003] In the prior art, a Chinese patent document with publication number CN208701722U discloses a basement floor groove drainage repair structure, including a groove located at the basement crack, a drainage pipe buried in the groove, a downpipe on the side wall of the drainage pipe, and the downpipe is connected to the side wall of the drainage pipe; the downpipe extends upward to form an inspection port. The drainage repair structure is provided with an inspection port, through which the drainage pipe can be dredged, which solves the problem of clogging and dredging of the drainage pipe to a certain extent. However, in order to effectively drain water, the drainage pipe needs to be buried below the ground, and the inspection port is connected to the drainage pipe through a narrow pipe. Due to the branching of the pipeline and the small inspection port, it is difficult to use ordinary mechanical dredging equipment for dredging, and the dredging efficiency is low; in addition, the connection between the pipeline extending from the inspection port and the drainage pipe is prone to wear and leakage. Once leakage occurs, the corresponding connecting piece needs to be replaced in time. The connecting piece cannot be replaced with the help of the inspection port, and the floor needs to be chiseled open, and the secondary repair cost is high.
[0004] Therefore, in view of the problems existing in the prior art, it is urgently necessary to provide a drainage structure with floor drain maintenance. Summary of the invention
[0005] In view of the problems in the related technology, the utility model proposes a drainage structure with floor drain repair function to overcome the technical problems of low dredging efficiency and difficulty in replacing connecting parts of the existing drainage repair structure.
[0006] The technical solution of the utility model is implemented as follows: a drainage structure with floor drain maintenance includes a groove located underground, the groove is filled with a gravel layer, and a drainage pipe is buried in the gravel layer;
[0007] The drainage pipe is provided with a plurality of connecting pieces at intervals along its extension direction, and the drainage pipe is connected with another adjacent drainage pipe through the connecting pieces; the upper end opening of the connecting piece forms an inspection pipe opening, and an inspection box body is provided above each inspection pipe opening; a through hole is provided at the lower part of the inspection box body, and the through hole and the inspection pipe opening are adapted to each other; a floor drain is provided at the middle position of the top of the inspection box body, and the floor drain is connected to a sewer pipe, and the sewer pipe passes through the inspection box body and extends into the inspection pipe opening;
[0008] A cement mortar layer is provided on the upper part of the gravel sub-layer, and a pit is provided on the cement mortar layer near the inspection pipe opening of the connecting piece, and the inspection box body is detachably placed in the pit;
[0009] When the inspection box body is lifted out of the pit, the sewer pipe is separated from the inspection pipe opening along with the inspection box body, and the inspection pipe opening is exposed; when the inspection box body is placed in the pit, the sewer pipe is connected to the inspection pipe opening, and the upper end surface of the inspection box body is flush with the ground plane.
[0010] The utility model provides an inspection pipe opening on the drainage pipe, and the inspection pipe openings are distributed at intervals along the extension direction of the drainage pipe. An inspection box body is provided above the inspection pipe opening, and a floor drain is provided in the middle of the top of the inspection box body, and the floor drain extends into the inspection pipe opening through the pipeline. If a blockage occurs in the drainage pipe, the inspection pipe opening can be exposed by simply lifting out the inspection box body, and ordinary mechanical dredging equipment can be used to quickly dredge the branches at the inspection pipe opening; in addition, if the branch connecting parts of the inspection pipe opening need to be further inspected or replaced, the inspection box body is disassembled to expose the corresponding connecting parts, and the ground does not need to be excavated, which can greatly improve the inspection efficiency.
[0011] As a further improvement of the above scheme, the maintenance box body is a square structure with a hollow cavity, and a plurality of ribs are provided in the hollow cavity of the maintenance box body. The plurality of ribs are arranged between the upper and lower end surfaces of the maintenance box body in the form of mechanical support; in order to further improve the structural strength of the maintenance box body, a plurality of ribs are arranged inside the maintenance box body, which can effectively prevent the maintenance box body from being stepped on and deformed.
[0012] As a further improvement of the above scheme, the upper part of the maintenance box body protrudes along its circumference to form an annular boss, and the pit is provided with a stepped groove matched with the annular boss. When the maintenance box body is placed in the pit, the annular boss and the stepped groove are engaged with each other. The pit is provided to adapt to the maintenance box body, so that the maintenance box body can be easily lifted out of the pit, which is convenient for clearing and maintenance of the drainage pipe.
[0013] As a further improvement of the above solution, a sealing layer is further provided between the annular boss and the stepped groove; the provision of the sealing layer can effectively prevent ground water from seeping into the pit through the gap between the inspection box body and the pit, thereby avoiding odor.
[0014] As a further improvement of the above solution, grooves are provided on both sides of the top of the inspection box body, and handles are rotatably connected in the grooves; the provision of the handles helps maintenance personnel to lift and place the inspection box body.
[0015] As a further improvement of the above scheme, the wall of the drainage pipe is provided with multiple pairs of penetration holes, and the axes of the multiple pairs of penetration holes are respectively arranged in a cross-shaped manner with the axis of the drainage pipe; the wall of the drainage pipe is coated with a non-woven fabric layer. The provision of the penetration holes allows groundwater to enter the drainage pipe through the penetration holes and be discharged; in addition, wrapping the non-woven fabric layer on the drainage pipe can preliminarily prevent fine sand and the like from entering the drainage pipe.
[0016] As a further improvement of the above scheme, the diameter of the inspection pipe opening is larger than the diameter of the sewer pipe. By setting the diameter of the inspection pipe opening larger than the diameter of the sewer pipe, on the one hand, the large-diameter inspection pipe opening makes it convenient for maintenance personnel to effectively clear the branches of the drainage pipe through the inspection pipe opening; on the other hand, it is also convenient for the sewer pipe to smoothly extend into and connect with the inspection pipe opening when the inspection box is placed.
[0017] As a further improvement of the above scheme, the floor drain is covered with a square sieve plate, which includes a plurality of sieve bars distributed side by side, and the plurality of sieve bars are connected into one by a plurality of ribs, and the gaps between the two sieve bars form strip-shaped sieve holes; by arranging the square sieve plate to cover the floor drain, impurities in the accumulated water can be isolated to avoid blockage of the sewer pipe and the drainage pipe; in addition, the plurality of sieve bars distributed side by side also have an anti-slip effect, which can effectively prevent people from slipping when passing.
[0018] As a further improvement of the above scheme, a slot is further provided at the lower part of the floor drain, and a sleeve is connected to the slot. The middle part of the sleeve is vertically penetrated, and the sewer pipe extends into the sleeve from top to bottom and is engaged with the sleeve; the top of the sewer pipe is also covered with a circular sieve plate.
[0019] As a further improvement of the above scheme, a limiting groove is provided on the inner wall of the sleeve, and a corresponding limiting portion is provided on the upper side wall of the sewer pipe. When the sewer pipe extends into the sleeve from top to bottom, the limiting portion and the limiting groove cooperate with each other.
[0020] Beneficial effects:
[0021] The utility model provides an inspection pipe opening on the drainage pipe, and the inspection pipe openings are distributed at intervals along the extension direction of the drainage pipe. An inspection box body is provided above the inspection pipe opening, and a floor drain is provided in the middle of the top of the inspection box body, and the floor drain extends into the inspection pipe opening through the pipeline. If a blockage occurs in the drainage pipe, the inspection pipe opening can be exposed by simply lifting out the inspection box body, and ordinary mechanical dredging equipment can be used to quickly dredge the branches at the inspection pipe opening; in addition, if the branch connecting parts of the inspection pipe opening need to be further inspected or replaced, the inspection box body is disassembled to expose the corresponding connecting parts, and there is no need to dig the ground, which can greatly improve the inspection efficiency. The utility model has a simple structure, convenient construction, good grooving drainage effect, convenient secondary repair, and is very practical. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the structure of the utility model;
[0023] Figure 2 It is a side view of the utility model;
[0024] Figure 3 It is a cross-sectional schematic diagram of the utility model;
[0025] Figure 4 It is an exploded schematic diagram of the utility model;
[0026] Figure 5 This is a working principle diagram of the utility model;
[0027] Reference numerals:
[0028] 1. Drainage tube; 11. Infiltration hole;
[0029] 2. Inspection box; 21. Floor drain; 21a. Slot; 22. Through hole; 23. Drain pipe; 23a. Limiting part; 24. Rib plate; 25. Annular boss; 26. Groove; 27. Handle;
[0030] 3. Connecting parts; 31. Inspection pipe opening;
[0031] 4. Gravel layer;
[0032] 5. Cement mortar layer; 51. Pit; 52. Step groove; 53. Sealing layer;
[0033] 6. Square sieve plate;
[0034] 7. Cylinder sleeve; 71. Limiting groove;
[0035] 8. Round sieve plate;
[0036] C1. Groove. DETAILED DESCRIPTION
[0037] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0038] like Figure 1-Figure 5 As shown, a drainage structure with floor drain maintenance includes a trench C1 located underground, the trench C1 is filled with a gravel layer 4, a drainage pipe 1 is buried in the gravel layer 4, and in this embodiment, a plurality of pairs of penetration holes 11 are arranged on the pipe wall of the drainage pipe 1, and the axes of the plurality of pairs of penetration holes 11 are arranged in a cross with the axis of the drainage pipe 1; the pipe wall of the drainage pipe 1 is coated with a non-woven fabric layer. The provision of the penetration holes 11 allows groundwater to enter the drainage pipe 1 through the penetration holes 11 and be discharged; in addition, wrapping the non-woven fabric layer on the drainage pipe 1 can preliminarily prevent fine sand and the like from entering the drainage pipe 1.
[0039] The drainage pipe 1 is provided with a plurality of connecting pieces 3 at intervals along its extension direction, and the drainage pipe 1 is connected with another adjacent drainage pipe 1 through the connecting piece 3; in the present embodiment, the connecting piece 3 is a three-way pipe, and the upper end opening of the connecting piece 3 forms an inspection pipe opening 31, and an inspection box body 2 is provided above each inspection pipe opening 31.
[0040] The lower part of the inspection box body 2 is provided with a through hole 22, and the through hole 22 is adapted to the inspection pipe opening 31; the middle position of the top of the inspection box body 2 is provided with a floor drain 21, and the floor drain 21 is connected to a sewer pipe 23, and the sewer pipe 23 passes through the inspection box body 2 and extends into the inspection pipe opening 31; the upper part of the gravel layer 4 is provided with a cement mortar layer 5, and the cement mortar layer 5 is provided with a pit 51 near the inspection pipe opening 31 of the connecting piece 3, and the inspection box body 2 is detachably placed in the pit 51. When the inspection box body 2 is lifted out of the pit 51, the sewer pipe 23 is separated from the inspection pipe opening 31 along with the inspection box body 2, and the inspection pipe opening 31 is exposed; when the inspection box body 2 is placed in the pit 51, the sewer pipe 23 is connected to the inspection pipe opening 31, and the upper end surface of the inspection box body 2 is flush with the ground plane.
[0041] In this embodiment, the floor drain opening 21 is covered with a square sieve plate 6, and the square sieve plate 6 includes a plurality of sieve bars arranged side by side, and the plurality of sieve bars are connected into one by a plurality of ribs, and the gaps between the two sieve bars form strip-shaped sieve holes; by arranging the square sieve plate 6 to cover the floor drain opening 21, impurities in the accumulated water can be isolated, and blockage of the sewer pipe 23 and the drainage pipe 1 can be avoided; in addition, the plurality of sieve bars arranged side by side also have an anti-slip effect, which can effectively prevent people from slipping when passing.
[0042] In this embodiment, a slot 21a is further provided at the lower part of the floor drain 21, and a sleeve 7 is connected to the slot 21a, and the middle part of the sleeve 7 is vertically penetrated, and the sewer pipe 23 extends into the sleeve 7 from top to bottom, and is engaged with the sleeve 7; the top of the sewer pipe 23 is also covered with a circular sieve plate 8. Specifically, a limiting groove 71 is provided on the inner wall of the sleeve 7, and a corresponding limiting portion 23a is provided on the upper side wall of the sewer pipe 23. When the sewer pipe 23 extends into the sleeve 7 from top to bottom, the limiting portion 23a cooperates with the limiting groove 71.
[0043] In this embodiment, the inspection box body 2 is a square structure with a hollow cavity, and a plurality of ribs 24 are provided in the hollow cavity of the inspection box body 2. The plurality of ribs 24 are provided between the upper and lower end surfaces of the inspection box body 2 in the form of mechanical support; specifically, there are 4 to 6 ribs 24, which are distributed circumferentially with the inspection pipe opening 31 as the center, and the thickness of the ribs 24 ranges from 4 mm to 6 mm. In order to further improve the structural strength of the inspection box body 2, a plurality of ribs 24 are provided inside the inspection box body 2, which can effectively prevent the inspection box body 2 from being deformed by being stepped on.
[0044] In this embodiment, the upper portion of the inspection box body 2 protrudes along its circumference to form an annular boss 25, and the recess 51 is provided with a stepped groove 52 adapted to the annular boss 25. When the inspection box body 2 is placed in the recess 51, the annular boss 25 is engaged with the stepped groove 52. The recess 51 is provided to adapt to the inspection box body 2, so that the inspection box body 2 can be easily lifted out of the recess 51, so as to facilitate the unblocking and inspection of the drainage pipe 1.
[0045] In this embodiment, a sealing layer 53 is provided between the annular boss 25 and the stepped groove 52, and the sealing layer 53 is made of rubber. The provision of the sealing layer 53 can effectively prevent ground water from penetrating into the pit 51 from the gap between the inspection box body 2 and the pit 51, thereby preventing odor. In this embodiment, grooves 26 are provided on both sides of the top of the inspection box body 2, and handles 27 are rotatably connected in the grooves 26; the provision of the handles 27 helps maintenance personnel to lift and place the inspection box body 2.
[0046] In this embodiment, the diameter of the inspection pipe opening 31 is larger than the diameter of the sewer pipe 23; the diameter of the inspection pipe opening 31 is set to be larger than the diameter of the sewer pipe 23. On the one hand, the large-diameter inspection pipe opening 31 is convenient for maintenance personnel to effectively clear the branches of the drainage pipe 1 through the inspection pipe opening 31; on the other hand, it is also convenient for the sewer pipe 23 to smoothly extend into and connect with the inspection pipe opening 31 when the inspection box body 2 is placed.
[0047] Through the above scheme of the utility model, in specific applications: a connecting piece 3 is provided on the drainage pipe 1, the upper end opening of the connecting piece 3 forms a maintenance pipe opening 31, an inspection box body 2 is provided above the inspection pipe opening 31, and a floor drain 21 is provided in the middle of the top of the inspection box body 2, and the floor drain 21 extends into the inspection pipe opening 31 through a pipeline. If a blockage occurs in the drainage pipe 1, it is only necessary to lift out the inspection box body 2 to expose the inspection pipe opening 31, thereby removing the narrow pipe between the floor drain 21 and the drainage pipe 1, and facilitating the use of common mechanical unclogging equipment, such as a manual winch or a motorized winch, to unblock the drainage pipe 1; at the same time, since the inspection pipe opening 31 is directly arranged on the connecting piece 3 of the drainage pipe 1, the maintenance personnel can extend the scraper of the manual winch or the motorized winch along the branches at the inspection pipe opening 31 in turn to quickly unblock the blocks, thereby avoiding the difficulty in unblocking the blocks due to the bifurcation of the branches of the drainage pipe 1, and greatly improving the unblocking efficiency of the drainage pipe 1; in addition, if the branch connecting piece 3 of the inspection pipe opening 31 needs further inspection or replacement, the inspection box body 2 is disassembled to expose the corresponding connecting piece 3, without the need to dig the ground, and the secondary repair is convenient, which has strong practicality.
[0048] According to the disclosure and teaching of the above specification, the technicians in the field of the utility model can also change and modify the above implementation. Therefore, the utility model is not limited to the specific implementation methods disclosed and described above, and some modifications and changes to the utility model should also fall within the scope of protection of the claims of the utility model. In addition, although some specific terms are used in this specification, these terms are only for the convenience of explanation and do not constitute any limitation to the utility model.
Claims
1. A drainage structure with floor drain maintenance, comprising a trench located underground, the trench is filled with a gravel layer, a drainage pipe is buried in the gravel layer, and the characteristics are: The drainage pipe is provided with a plurality of connecting pieces at intervals along its extension direction, and the drainage pipe is connected with another adjacent drainage pipe through the connecting pieces; the upper end opening of the connecting piece forms an inspection pipe opening, and an inspection box body is provided above each inspection pipe opening; a through hole is provided at the lower part of the inspection box body, and the through hole and the inspection pipe opening are adapted to each other; a floor drain is provided at the middle position of the top of the inspection box body, and the floor drain is connected to a sewer pipe, and the sewer pipe passes through the inspection box body and extends into the inspection pipe opening; A cement mortar layer is provided on the upper part of the gravel sub-layer, and a pit is provided on the cement mortar layer near the inspection pipe opening of the connecting piece, and the inspection box body is detachably placed in the pit; When the inspection box is lifted out of the pit, the sewer pipe is separated from the inspection pipe opening along with the inspection box, and the inspection pipe opening is exposed; When the inspection box body is placed in the pit, the sewer pipe is connected to the inspection pipe opening, and the upper end surface of the inspection box body is flush with the ground plane.
2. A drainage structure with floor drain maintenance according to claim 1, characterized in that: The inspection box body is a square structure with a hollow cavity. A plurality of ribs are arranged in the hollow cavity of the inspection box body. The plurality of ribs are arranged between the upper and lower end surfaces of the inspection box body in the form of mechanical support.
3. A drainage structure with floor drain maintenance according to claim 2, characterized in that: The upper part of the inspection box body protrudes along its circumference to form an annular boss, and the pit is provided with a stepped groove adapted to the annular boss. When the inspection box body is placed in the pit, the annular boss is engaged with the stepped groove.
4. A drainage structure with floor drain maintenance according to claim 3, characterized in that: A sealing layer is also provided between the annular boss and the stepped groove.
5. A drainage structure with floor drain maintenance according to claim 4, characterized in that: Grooves are also provided on both sides of the top of the inspection box body, and handles are rotatably connected in the grooves.
6. The drainage structure with floor drain maintenance according to claim 1, characterized in that: The wall of the drainage tube is provided with a plurality of pairs of penetration holes, and the axes of the plurality of pairs of penetration holes are respectively arranged to cross with the axis of the drainage tube; the wall of the drainage tube is coated with a non-woven fabric layer.
7. The drainage structure with floor drain maintenance according to claim 1, characterized in that: The diameter of the inspection pipe opening is larger than the diameter of the sewer pipe.
8. The drainage structure with floor drain maintenance according to claim 1, characterized in that: The floor drain opening is covered with a square sieve plate, which includes a plurality of sieve bars distributed side by side, the plurality of sieve bars are connected into one body through a plurality of ribs, and the gaps between the two sieve bars form strip-shaped sieve holes.
9. A drainage structure with floor drain maintenance according to claim 8, characterized in that: A slot is also provided at the bottom of the floor drain, and a sleeve is connected to the slot. The middle of the sleeve is vertically penetrated, and the sewer pipe extends into the sleeve from top to bottom and is engaged with the sleeve. The top of the sewer pipe is also covered with a circular sieve plate.
10. A drainage structure with floor drain maintenance according to claim 9, characterized in that: A limiting groove is arranged on the inner wall of the sleeve, and a corresponding limiting portion is arranged on the upper side wall of the sewer pipe. When the sewer pipe extends into the sleeve from top to bottom, the limiting portion and the limiting groove cooperate with each other.
Citation Information
Patent Citations
Basement bottom plate fluting drainage repair structure
CN208701722U