Hanging basket mounting structure for corridor bottom construction
By setting up floor slab holes and support suspension mechanisms on the corridor floor slabs, the construction difficulties of the parts below the corridor of high-rise buildings are solved, and the stable installation and construction of the hanging basket is achieved, with the advantages of simple structure and easy installation.
Patent Information
- Application Number
- CN202421132502.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-23
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2034-05-23
AI Technical Summary
The construction of the parts below the corridor of high-rise buildings is difficult, the existing hanging basket cannot be installed, and the ground conditions are limited to inconvenient construction.
A construction hanging basket installation structure at the bottom of the corridor is designed, including setting up floor slab holes and support mechanisms on the corridor floor slab. The suspension mechanism consists of a wire rope and a fixed steel plate. It extends through the floor slab holes to the bottom of the floor to connect the hanging basket, and is connected through a flexible sleeve. Tube and oblique support improve structural stability.
It has achieved stable installation and construction of hanging baskets on the corridor floor slab, adapted to different hanging basket needs, and has a simple structure and convenient installation, which has solved the problems of construction below the corridor.
Smart Images

Figure CN222350191U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hanging basket construction, in particular to a hanging basket installation structure for corridor bottom construction. Background Art
[0002] At present, high-rise buildings above the 10th floor are generally equipped with corridors, which protrude from the outer wall. During the renovation process, the part below the corridor is beyond the construction range of the hanging basket normally installed on the roof, making it impossible for the normal hanging basket to be constructed at the bottom of the corridor. In addition, due to restrictions on ground conditions, some buildings cannot be equipped with working scaffolding, resulting in difficulties in the construction of the part below the corridor. Therefore, the utility model is born. Utility Model Content
[0003] The present application provides a construction hanging basket installation structure at the bottom of a corridor to solve the problem of construction difficulties below the corridor.
[0004] In order to solve the above-mentioned technical problems, the present application provides a construction hanging basket installation structure at the bottom of a corridor, comprising: a corridor floor and a hanging basket arranged at the bottom of the corridor floor; the corridor floor is provided with floor holes in the thickness direction, and a supporting mechanism is provided at the top of the corridor floor, and a suspension mechanism is provided at the top of the supporting mechanism, and the suspension mechanism comprises a first horizontal square tube arranged at the top of the supporting mechanism, a wire rope fixing steel plate arranged on the first horizontal square tube, and a main wire rope and a secondary wire rope arranged at the bottom of the wire rope fixing steel plate, a fixing bolt is provided on the top of the wire rope fixing steel plate, the main wire rope and the secondary wire rope pass through the floor holes and extend to the bottom of the corridor floor, and the lower ends of the main wire rope and the secondary wire rope are connected to the hanging basket.
[0005] In some embodiments of the present application, the supporting mechanism includes a second horizontal square tube, a first vertical square tube arranged on the top of the first horizontal square tube, and a second vertical square tube arranged on the top of the first vertical tube, and a U-shaped groove is arranged on the top of the second vertical tube, and the U-shaped groove and the first horizontal square tube are fixed with bolts.
[0006] In some embodiments of the present application, the inner diameter of the first vertical tube and the outer diameter of the second vertical tube are the same, the second vertical tube extends into the first vertical tube, and multiple fixing holes are provided on the outer sides of the first vertical tube and the second vertical tube, and limiting bolts are provided in the fixing holes.
[0007] In some embodiments of the present application, an oblique support is provided between the first vertical square tube and the second horizontal square tube, and a rib plate is provided between the second vertical square tube and the U-shaped groove.
[0008] In some embodiments of the present application, rope clips are provided at the tops of the main steel wire rope and the auxiliary steel wire rope, and the number of rope clips is 3.
[0009] In some embodiments of the present application, a plurality of mounting holes are arranged at intervals in the length direction of the first horizontal square tube, and the steel plate for fixing the steel wire rope is bolted to any mounting hole.
[0010] In some embodiments of the present application, a flexible sleeve is provided in the floor hole.
[0011] Compared with the prior art, the utility model has the following characteristics and beneficial effects:
[0012] The utility model provides a floor hole on the corridor floor so that the main wire rope and the auxiliary wire rope can extend to the bottom of the corridor floor for connecting the hanging basket; the supporting mechanism and the hanging mechanism are provided to make the overall structure more stable, and provide installation conditions for the main wire rope and the auxiliary wire rope; the flexible sleeve is provided to prevent the main wire rope and the auxiliary wire rope from rubbing against the floor hole and protect the wire rope; the installation hole is provided to make the installation position of the steel plate fixed with the wire rope adjustable to adapt to different hanging baskets; the inclined support is provided to further improve the stability of the overall structure; the device has the advantages of simple structure and easy installation, and can meet the construction requirements of the hanging basket on the corridor floor; and the popularization and use can produce better results. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the overall structure of the embodiment of the utility model;
[0014] Figure 2 It is a side view schematic diagram of the overall structure of the embodiment of the utility model;
[0015] Figure 3 It is a schematic side view of the overall installation of the embodiment of the utility model;
[0016] Figure 4 It is a three-dimensional structural schematic diagram of an embodiment of the utility model.
[0017] In the figure, 100, corridor floor; 110, floor hole; 120, flexible sleeve; 200, hanging basket; 300, supporting mechanism; 310, second horizontal square tube; 320, first vertical square tube; 330, second vertical square tube; 340, U-shaped groove; 350, fixing hole; 360, limiting bolt; 370, oblique support; 400, hanging mechanism; 410, first horizontal square tube; 420, steel plate for fixing wire rope; 430, main wire rope; 440, auxiliary wire rope; 450, fixing bolt; 460, rope clamp. DETAILED DESCRIPTION
[0018] The following is a further detailed description of the specific implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0019] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0020] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0021] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0022] like Figure 1-4 As shown, according to some embodiments of the present application, a construction hanging basket installation structure at the bottom of a corridor includes: a corridor floor 100 and a hanging basket 200 arranged at the bottom of the corridor floor 100; a floor hole 110 is arranged in the thickness direction of the corridor floor 100, a supporting mechanism 300 is arranged at the top of the corridor floor 100, and a hanging mechanism 400 is arranged at the top of the supporting mechanism 300. The hanging mechanism 400 includes a first horizontal square tube 410 arranged at the top of the supporting mechanism 300, a steel wire rope fixing steel plate 420 arranged on the first horizontal square tube 410, and a steel wire rope fixing steel plate 420 arranged at the bottom of the steel wire rope fixing steel plate 420. The main rope 430 and the auxiliary rope 440 of the wire rope, the top of the wire rope fixing steel plate 420 is provided with a fixing bolt 450, the main wire rope 430 and the auxiliary wire rope 440 pass through the floor hole 110 and extend to the bottom of the corridor floor 100, the lower ends of the main wire rope 430 and the auxiliary wire rope 440 are connected to the hanging basket 200, the wire rope fixing steel plate 420 is made of two steel plates bent into an inverted funnel shape, holes are punched up and down, and it is fixed to the first horizontal square tube 410 by bolts, one bolt is set on the top and two bolts are set on the bottom, and the lower bolt is used to fix the main wire rope 430 and the auxiliary wire rope 440.
[0023] According to some embodiments of the present application, the support mechanism 300 includes a second horizontal square tube 310, a first vertical square tube 320 arranged on the top of the first horizontal square tube 410, and a second vertical square tube 330 arranged on the top of the first vertical tube 320. A U-shaped groove 340 is arranged on the top of the second vertical tube 330. The U-shaped groove 340 and the second vertical tube 330 are welded and connected. Bolt holes are arranged on both sides of the U-shaped groove 340. The first horizontal square tube 410 is placed in the U-shaped groove 340. Bolt holes with equal spacing as the U-shaped groove 340 are arranged on the first horizontal square tube 410. The U-shaped groove 340 and the first horizontal square tube 410 are fixed with bolts.
[0024] According to some embodiments of the present application, the inner diameter of the first vertical tube 320 and the outer diameter of the second vertical tube 330 are the same, the second vertical tube 330 extends into the first vertical tube 320, and multiple fixing holes 350 are provided on the outer sides of the first vertical tube 320 and the second vertical tube 330, and limiting bolts 360 are provided in the fixing holes 350.
[0025] According to some embodiments of the present application, an oblique support 370 is provided between the first vertical square tube 320 and the second horizontal square tube 310 , and a rib plate is provided between the second vertical square tube 330 and the U-shaped groove 340 .
[0026] According to some embodiments of the present application, rope clips 460 are provided at the tops of the main steel wire rope 430 and the auxiliary steel wire rope 440, and the number of rope clips 460 is 3.
[0027] According to some embodiments of the present application, a plurality of mounting holes are arranged at intervals in the length direction of the first horizontal square tube 410, and the wire rope fixing steel plate 420 is bolted to any mounting hole.
[0028] According to some embodiments of the present application, a flexible sleeve 120 is provided in the floor hole 110 , and the flexible sleeve 120 is an anti-shear flexible sleeve 120 , which is fixed to the corridor floor 100 by steel nails.
[0029] In summary, the utility model relates to the technical field of hanging basket construction, and discloses a hanging basket installation structure for corridor bottom construction, comprising: a corridor floor and a hanging basket arranged at the bottom of the corridor floor; the corridor floor is provided with floor holes in the thickness direction, and a supporting mechanism is provided at the top of the corridor floor, and a hanging mechanism is provided at the top of the supporting mechanism, and the hanging mechanism comprises a first horizontal square tube arranged at the top of the supporting mechanism, a wire rope fixing steel plate arranged on the first horizontal square tube, and a main wire rope and a secondary wire rope arranged at the bottom of the wire rope fixing steel plate, a fixing bolt is provided on the top of the wire rope fixing steel plate, the main wire rope and the secondary wire rope pass through the floor holes and extend to the bottom of the corridor floor, and the lower ends of the main wire rope and the secondary wire rope are connected to the hanging basket.
[0030] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principle of the present invention. These improvements and substitutions should also be regarded as the protection scope of the present invention.
Claims
1. A construction hanging basket installation structure at the bottom of a corridor, comprising: A corridor floor (100) and a hanging basket (200) arranged at the bottom of the corridor floor (100); characterized in that a floor hole (110) is arranged in the thickness direction of the corridor floor (100), a supporting mechanism (300) is arranged at the top of the corridor floor (100), a hanging mechanism (400) is arranged at the top of the supporting mechanism (300), and the hanging mechanism (400) includes a first horizontal square tube (410) arranged at the top of the supporting mechanism (300), and a first horizontal square tube (410) is arranged at the first horizontal square tube (410). A steel wire rope fixing steel plate (420) is provided on the corridor, and a main steel wire rope (430) and a secondary steel wire rope (440) are arranged at the bottom of the steel wire rope fixing steel plate (420). A fixing bolt (450) is arranged on the top of the steel wire rope fixing steel plate (420). The main steel wire rope (430) and the secondary steel wire rope (440) pass through the floor hole (110) and extend to the bottom of the corridor floor (100). The lower ends of the main steel wire rope (430) and the secondary steel wire rope (440) are connected to the hanging basket (200).
2. The corridor bottom construction hanging basket installation structure according to claim 1 is characterized in that: The support mechanism (300) comprises a second horizontal square tube (310), a first vertical square tube (320) arranged on the top of the first horizontal square tube (410), and a second vertical square tube (330) arranged on the top of the first vertical square tube (320), wherein a U-shaped groove (340) is arranged on the top of the second vertical square tube (330), and the U-shaped groove (340) and the first horizontal square tube (410) are fixed by bolts.
3. The corridor bottom construction hanging basket installation structure according to claim 2 is characterized in that: The inner diameter of the first vertical tube (320) is the same as the outer diameter of the second vertical tube (330); the second vertical tube (330) extends into the first vertical tube (320); a plurality of fixing holes (350) are arranged on the outer sides of the first vertical tube (320) and the second vertical tube (330); and limiting bolts (360) are arranged in the fixing holes (350).
4. The corridor bottom construction hanging basket installation structure according to claim 2 is characterized in that: An oblique support (370) is provided between the first vertical square tube (320) and the second horizontal square tube (310), and a rib plate is provided between the second vertical square tube (330) and the U-shaped groove (340).
5. The corridor bottom construction hanging basket installation structure according to claim 1 is characterized in that: Rope clamps (460) are provided at the tops of the main steel wire rope (430) and the auxiliary steel wire rope (440), and the number of rope clamps (460) is three.
6. The corridor bottom construction hanging basket installation structure according to claim 1 is characterized in that: The first transverse square tube (410) is provided with a plurality of mounting holes at intervals in the length direction, and the steel wire rope fixing steel plate (420) is bolted to any mounting hole.
7. The corridor bottom construction hanging basket installation structure according to claim 1 is characterized in that: A flexible sleeve (120) is arranged in the floor hole (110).