Concrete pouring and vibrating integrated device

By designing the integrated device for concrete pouring and vibration, and using the combined connection of the pouring pipe and vibrating rod, the inefficiency problem caused by the separation of pouring and vibration in the existing technology is solved, and the synchronous pouring and vibration of concrete is realized. Significantly improve the pouring efficiency of the building.

CN222350258UActive Publication Date: 2025-01-14WULIAN YIHANG BUILDING MATERIALS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421189872.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-29
Publication Date
2025-01-14
Estimated Expiration
2034-05-29

AI Technical Summary

Technical Problem

In the prior art, concrete pouring and vibration are usually carried out separately and cannot be carried out simultaneously during pouring, resulting in low pouring efficiency.

Method used

A concrete pouring and vibration integrated device is designed, including pouring pipes and vibrating rods. It is fixed by connecting components. The pouring pipes and vibrating rods can be assembled and separated, and are inserted into the mold together to achieve synchronous pouring and vibration. .

Benefits of technology

Concrete pouring and vibration are achieved simultaneously, greatly improving the pouring efficiency of the building.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222350258U_ABST
    Figure CN222350258U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete pouring and vibrating integrated device which comprises a pouring pipe, a vibrating rod is installed at the end of the pouring pipe, a butt joint pipe is fixedly installed at the top of the pouring pipe, meanwhile, the outer side of the pouring pipe is covered with a first connecting piece, and a connecting base is fixedly welded to the back face of the first connecting piece. A second connecting piece is welded and fixed to the outer side of the connecting base and wraps the outer side of the vibrating rod, and meanwhile a connecting pipe is fixedly installed at the top of the vibrating rod. According to the concrete pouring and vibrating integrated device, the pouring pipe and the vibrating rod are jointly inserted into a mold needing to be poured, the pouring pipe pours concrete, meanwhile, the vibrating rod vibrates and evenly mixes the poured concrete, concrete pouring and even mixing can be conducted at the same time, and the pouring efficiency of a building is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building construction, in particular to a concrete pouring and vibrating integrated device. Background Art

[0002] How concrete pouring works:

[0003] Concrete pouring is pouring concrete mixture into the formwork to form a structure that meets the designed shape and size. The principle is to fully mix cement, aggregate, water and other materials with a specific mix ratio to form a mixture, and then use various tools and methods (such as pumping, chute, etc.) to accurately place it in the predetermined position to form a continuous and dense structure.

[0004] Working principle of concrete vibration:

[0005] The main purpose of concrete vibration is to remove bubbles from concrete, make the concrete densely combined, eliminate the honeycomb surface of concrete, and improve its strength and durability. When the vibrator is working, the concrete mixture is disturbed by high-frequency vibration or mechanical impact, and the friction between aggregate particles is reduced, so that the mixture is easier to flow and fill every corner in the formwork, and at the same time, the bubbles are discharged. For example, the insertion vibrator is inserted into the concrete for vibration, and the flat vibrator is used to vibrate the flat concrete. During the vibration process, it is necessary to reasonably control the vibration time and strength to avoid over-vibration or under-vibration to ensure the quality of the concrete.

[0006] Concrete pouring and vibration are usually carried out separately, and it is impossible to perform synchronous vibration during concrete pouring, which greatly reduces the efficiency of concrete pouring. Utility Model Content

[0007] The purpose of the utility model is to provide a concrete pouring and vibrating integrated device to solve the defects mentioned in the above background technology.

[0008] To achieve the above-mentioned purpose, a concrete pouring and vibrating integrated device is provided, including a pouring pipe, a vibrating rod is installed at the end of the pouring pipe, and a docking pipe is fixedly installed on the top of the pouring pipe, and at the same time, the outer side of the pouring pipe is covered with a first connecting piece, and a connecting seat is welded and fixed on the back side of the first connecting piece, a second connecting piece is welded and fixed on the outer side of the connecting seat, and the second connecting piece is wrapped around the outer side of the vibrating rod, and at the same time, the connecting pipe is fixedly installed on the top of the vibrating rod.

[0009] Preferably, a butt flange is welded and fixed on the top of the butt pipe, and the butt flange is screwed and fixed to a material distribution pipe of an external concrete tank truck.

[0010] Preferably, the pouring pipe and the vibrating rod are fixed by a connecting assembly, and the connecting assembly includes a connecting seat, and the first connecting piece and the second connecting piece are fixedly connected by the connecting seat.

[0011] Preferably, the first connecting piece, the connecting seat and the second connecting piece are of the same length, and the first connecting piece and the second connecting piece are both C-shaped structures made of metal material.

[0012] Preferably, the cross-sections of the casting tube and the first connecting piece are concentric circle structures, and the cross-sections of the second connecting piece and the vibrating rod are concentric circle structures.

[0013] Preferably, four sets of mounting platforms are evenly installed on the outer sides of the first connecting plate and the second connecting plate, and screw holes are opened on the outer sides of the casting pipe and the vibrating rod. At the same time, fixing bolts are inserted on the mounting platforms, and the fixing bolts pass through the mounting platforms and are screwed into the screw holes opened on the outer side wall of the casting pipe.

[0014] Compared with the prior art, the utility model has the following beneficial effects: the pouring pipe and the vibrating rod are inserted into the mold to be poured together, the pouring pipe pours the concrete, and the vibrating rod vibrates and mixes the poured concrete at the same time, the concrete pouring and mixing can be carried out at the same time, which greatly improves the pouring efficiency of the building. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a schematic diagram of the front view of the structure of the utility model;

[0016] Figure 2 The utility model structure Figure 1 Front view of

[0017] Figure 3 The utility model structure Figure 1 Side view of

[0018] Figure 4 The utility model structure Figure 1 Axonometric view of

[0019] Figure 5 The utility model structure Figure 1 Bottom view of .

[0020] Numbers in the figure: 1. Butt flange; 2. Butt pipe; 3. Casting pipe; 4. First connecting piece; 5. Connecting seat; 6. Second connecting piece; 7. Vibrating rod; 8. Connecting pipe; 9. Mounting platform; 10. Fixing bolts. DETAILED DESCRIPTION

[0021] See also Figure 1-5The utility model provides an integrated device for concrete pouring and vibrating, including a pouring pipe 3, a vibrating rod 7 is installed at the end of the pouring pipe 3, and a docking pipe 2 is fixedly installed on the top of the pouring pipe 3, and the outer side of the pouring pipe 3 is covered with a first connecting piece 4, and a connecting seat 5 is welded and fixed on the back of the first connecting piece 4, and a second connecting piece 6 is welded and fixed on the outer side of the connecting seat 5, and the second connecting piece 6 is wrapped around the outer side of the vibrating rod 7, and a connecting pipe 8 is fixedly installed on the top of the vibrating rod 7.

[0022] Working principle: The butt flange 1 is screwed to the distribution pipe of the external concrete tanker, and the pouring pipe 3 and the vibrating rod 7 are inserted into the mold to be poured. The pouring pipe 3 pours the concrete, and the vibrating rod 7 vibrates and mixes the poured concrete. Concrete pouring and mixing can be carried out at the same time, which greatly improves the pouring efficiency of the building.

[0023] As a preferred implementation, the butt flange 1 is welded and fixed to the top of the butt pipe 2, and the butt flange 1 is screwed and fixed to the material distribution pipe of the external concrete tank truck.

[0024] The pouring pipe 3 and the vibrating rod 7 are fixed by a connecting assembly, and the connecting assembly includes a connecting seat 5 , and the first connecting piece 4 and the second connecting piece 6 are fixedly connected by the connecting seat 5 .

[0025] like Figure 1-4 As shown: the pouring pipe 3 and the vibrating rod 7 are fixed by a connecting assembly, the pouring pipe 3 and the vibrating rod 7 can be assembled and separated, and the pouring pipe 3 and the vibrating rod 7 can be combined and connected and used synchronously.

[0026] As a preferred embodiment, the first connecting piece 4, the connecting seat 5 and the second connecting piece 6 have the same length, and the first connecting piece 4 and the second connecting piece 6 are both C-shaped structures made of metal material.

[0027] The cross-sections of the casting pipe 3 and the first connecting piece 4 are concentric circle structures, and the cross-sections of the second connecting piece 6 and the vibrating rod 7 are concentric circle structures.

[0028] like Figure 1-5 As shown: by setting the first connecting piece 4 and the second connecting piece 6, the pouring pipe 3 and the vibrating rod 7 can be fixedly assembled.

[0029] Four sets of mounting platforms 9 are evenly installed on the outer sides of the first connecting plate 4 and the second connecting plate 6, and screw holes are opened on the outer sides of the casting pipe 3 and the vibrating rod 7. At the same time, fixing bolts 10 are inserted into the mounting platforms 9, and the fixing bolts 10 pass through the mounting platforms 9 and are screwed into the screw holes opened on the outer side wall of the casting pipe 3.

Claims

1. A concrete pouring and vibrating integrated device, comprising a pouring pipe (3), characterized in that: A vibrating rod (7) is installed at the end of the casting pipe (3), and a butt-jointed pipe (2) is fixedly installed on the top of the casting pipe (3). At the same time, the outer side of the casting pipe (3) is covered with a first connecting piece (4), and a connecting seat (5) is welded and fixed on the back of the first connecting piece (4), and a second connecting piece (6) is welded and fixed on the outer side of the connecting seat (5), and the second connecting piece (6) is wrapped around the outer side of the vibrating rod (7), and at the same time, a connecting pipe (8) is fixedly installed on the top of the vibrating rod (7).

2. The integrated concrete pouring and vibrating device according to claim 1, characterized in that: The butt flange (1) is welded and fixed to the top of the butt pipe (2), and the butt flange (1) is screwed and fixed to the material distribution pipe of the external concrete tank truck.

3. The integrated concrete pouring and vibrating device according to claim 1, characterized in that: The pouring pipe (3) and the vibrating rod (7) are fixed via a connecting assembly, wherein the connecting assembly comprises a connecting seat (5), and the first connecting piece (4) and the second connecting piece (6) are fixedly connected via the connecting seat (5).

4. The integrated concrete pouring and vibrating device according to claim 3, characterized in that: The first connecting piece (4), the connecting seat (5) and the second connecting piece (6) are of the same length, and both the first connecting piece (4) and the second connecting piece (6) are C-shaped structures made of metal material.

5. The integrated concrete pouring and vibrating device according to claim 1, characterized in that: The cross-sections of the casting pipe (3) and the first connecting piece (4) are concentric circle structures, and the cross-sections of the second connecting piece (6) and the vibrating rod (7) are concentric circle structures.

6. The integrated concrete pouring and vibrating device according to claim 1, characterized in that: Four groups of mounting platforms (9) are evenly installed on the outer sides of the first connecting piece (4) and the second connecting piece (6), and screw holes are opened on the outer sides of the casting pipe (3) and the vibrating rod (7). At the same time, fixing bolts (10) are inserted into the mounting platforms (9), and the fixing bolts (10) pass through the mounting platforms (9) and are screwed into the screw holes opened on the outer side wall of the casting pipe (3).