Efficient buffering hanging cage device
By designing a high-efficiency buffering hoisting device with double-layer bottom, the problems of pipeline elbow wear and inconvenient maintenance are solved, the equipment operation time is extended and the maintenance efficiency is improved, and the structure of slurry conveying elbows is improved for mineral processing enterprises.
Patent Information
- Application Number
- CN202421042545.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-14
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2034-05-14
AI Technical Summary
The original pipeline elbows are prone to wear during the graded sand deposition process, resulting in the leakage of ore sand, and inconvenient installation and maintenance, affecting production continuity.
A high-efficiency buffering hoisting device was designed, adopting a double-layer bottom structure, including the main body of the hoisting tank, A pipe, B pipe, flange, buffer bottom and spare bottom. The materials are Φ377 and Φ159 steel pipes, and the buffer bottom and spare bottom are The 375mm diameter 20mm steel plate forms a erosion buffer layer and a spare layer, extending the equipment operation time and simplifying maintenance.
It improves the erosion resistance of the equipment and the interchangeability of spare parts, reduces the pipe damage rate, enhances maintenance efficiency and quality, and ensures the continuous operation of the equipment.
Smart Images

Figure CN222351696U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of buffer hanging tanks, and in particular relates to a high-efficiency buffer hanging tank device. Background Art
[0002] The original pipe elbows are subjected to great impact during the classification and sedimentation process, especially at the bottom of the elbows, which are easily worn and cause sand leakage, so they need to be frequently welded and replaced. The original elbow structure will cause corrosion of the pipe wall due to the long-term impact of the sand during use, and the weld will leak after the wear. The system equipment must be stopped before welding and replacement, affecting production continuity; in addition, the installation and disassembly are inconvenient and the workload is large. Utility Model Content
[0003] The technical problem to be solved by the utility model is to solve the problem of inconvenient maintenance.
[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0005] A high-efficiency buffer hanging tank device comprises a hanging tank body, the top of which is fixedly connected to a tube A, one side of which is fixedly connected to a tube B, one side of each of which is fixedly connected to a flange, the bottom of the hanging tank body is fixedly connected to a spare bottom, and one end of the hanging tank body close to the spare bottom is fixedly connected to a buffer bottom.
[0006] The A pipe and the B pipe are both connected to the hanging pot body, and the hanging pot body is made of Φ377 steel pipe.
[0007] The materials of the A tube and the B tube are both Φ159 steel tubes.
[0008] The buffer bottom and the spare bottom are both circular steel plates with a diameter of 375 mm and a thickness of 20 mm.
[0009] Compared with the prior art, the utility model has the following beneficial effects:
[0010] The manufacturing process of the double-layer bottom hanging tank is simple and of low difficulty; it not only ensures its scour resistance, but also reduces the damage rate of pipes; it enhances the interchangeability of spare parts and improves the quality and efficiency of maintenance. After actual production tests, this patent can be widely used in the improvement of the slurry conveying elbow structure of mineral processing enterprises, with good results. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a structural schematic diagram of an embodiment of the utility model.
[0012] Serial numbers and names of the accompanying drawings: flange 1, B pipe 2, hanging tank body 3, buffer bottom 4, spare bottom 5, A pipe 6. DETAILED DESCRIPTION
[0013] The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments. The illustrative embodiments and descriptions of the present invention are used to explain the present invention, but are not intended to limit the present invention.
[0014] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0015] Example 1
[0016] like Figure 1 As shown, the utility model describes an efficient buffer hanging tank device, including a hanging tank body 3, the top of the hanging tank body 3 is fixedly connected with an A tube 6, one side of the hanging tank body 3 is fixedly connected with a B tube 2, one side of the A tube 6 and the B tube 2 are fixedly connected with a flange 1, the bottom of the hanging tank body 3 is fixedly connected with a spare bottom 5, and the end of the hanging tank body 3 near the spare bottom 5 is fixedly connected with a buffer bottom 4; the A tube 6 and the B tube 2 are both connected to the hanging tank body 3, and the material of the hanging tank body 3 is Φ377 steel pipe; the materials of the A tube 6 and the B tube 2 are both Φ159 steel pipe; the buffer bottom 4 and the spare bottom 5 are both circular steel plates with a diameter of 375 mm and a thickness of 20 mm.
[0017] The structure of the utility model is a double-layer bottom hanging tank. Compared with the previous elbow structure, the original structure is mainly optimized: a Φ377 steel pipe is used as the hanging tank body 3, and A tube 6 and B tube 2 are welded on the upper part and the right side of the hanging tank body 3, respectively. The angle between A tube 6 and B tube 2 is 90°, and flanges 1 are provided on A tube 6 and B tube 2. Two circular steel plates with a diameter of 375mm and a thickness of 20mm are cut and welded on the hanging tank body 3 as a buffer bottom 4 and a spare bottom 5. The hanging tank is designed to have a double-layer bottom. The first layer of buffer bottom 4 is used as a scouring buffer layer, and the second layer of bottom is a spare bottom 5. When the first layer of bottom is scour and worn, the slurry leaks into the second layer of bottom and settles to form a buffer protection layer, thereby slowing down the wear time of the second layer of bottom, and while increasing the service life, it also ensures the continuous operation of the equipment. This not only prolongs the operation time of the equipment, but also saves the consumption of pipes, and improves the maintenance efficiency and quality.
[0018] The manufacturing process of the double-layer bottom hanging tank is simple and of low difficulty; it not only ensures its scour resistance, but also reduces the damage rate of pipes; it enhances the interchangeability of spare parts and improves the quality and efficiency of maintenance. After actual production tests, this patent can be widely used in the improvement of the slurry conveying elbow structure of mineral processing enterprises, with good results.
[0019] The technical solutions provided by the embodiments of the present invention are introduced in detail above. Specific examples are used herein to illustrate the principles and implementation methods of the embodiments of the present invention. The description of the embodiments above is only applicable to help understand the principles of the embodiments of the present invention.
Claims
1. An efficient buffer hanging tank device, comprising a hanging tank body (3), characterized in that: The top of the hanging pot body (3) is fixedly connected to a tube A (6), one side of the hanging pot body (3) is fixedly connected to a tube B (2), one side of the tube A (6) and the tube B (2) are fixedly connected to a flange (1), the bottom of the hanging pot body (3) is fixedly connected to a spare bottom (5), and one end of the hanging pot body (3) close to the spare bottom (5) is fixedly connected to a buffer bottom (4).
2. The high-efficiency buffer hanging tank device according to claim 1 is characterized in that: The A pipe (6) and the B pipe (2) are both connected to the hanging pot body (3), and the material of the hanging pot body (3) is Φ377 steel pipe.
3. The high-efficiency buffer tank device according to claim 2 is characterized in that: The material of the A tube (6) and the B tube (2) are both Φ159 steel tubes.
4. The high-efficiency buffer hanging tank device according to claim 3 is characterized in that: The buffer bottom (4) and the spare bottom (5) are both circular steel plates with a diameter of 375 mm and a thickness of 20 mm.