Mine underground filling pipeline water guide valve
By designing a filling pipe water guide valve for underground mines, the water flow direction is controlled by rotatable valve plate assembly and rocker structure, the filling top overload and material caused by the cleaning water of underground filling pipes in mines has been solved after entering the mining site. The problem of lowering slurry concentration improves the strength of the filler and ore quality.
Patent Information
- Application Number
- CN202421291664.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2034-06-07
AI Technical Summary
After the cleaning water of the underground filling pipeline of the mine enters the mining site, the filling top is excessive and the filling slurry concentration is reduced, affecting the filling strength and ore quality.
Design a mine underground filling pipe water guide valve, adopts rotatable valve plate assembly and rocker structure, and drives the valve plate assembly to be in different positions by rotating rocker, controlling the flow direction of the filling mortar or pipe washing water to avoid unnecessary water entering The mining site.
It effectively avoids the problems of filling slurry separating and concentration reduction caused by pipe moisturizing water and pipe washing water entering the mining site, improves the filling top rate and the concentration of filling slurry, and ensures the filling body strength and ore quality.
Smart Images

Figure CN222458455U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of mining equipment and relates to a water guide valve for filling pipelines in underground mines. Background Art
[0002] In mines that adopt the mechanized downward layered horizontal approach cementation filling method, the filling of the underground goaf is generally divided into three processes: bottom filling, secondary filling and top filling. Before the filling process begins, the filling pipeline needs to be drained and lubricated with clean water for 2 to 3 minutes to ensure that the filling pipeline is unobstructed. After the filling is completed, the filling pipeline needs to be cleaned with clean water for 8 to 12 minutes to ensure that the slurry in the filling pipeline is clean.
[0003] As the mine continues to be mined deeper and deeper, the filling pipeline is laid longer, and the start and stop of filling will cause a large amount of pipe lubrication and pipe washing water to enter the mining area, which can easily cause the filling slurry to segregate to form a sand roof, reduce the concentration of the filling slurry, and thus affect the strength of the filling body, and may also cause the board wall collapse accident due to excessive filling and top connection. In addition, when the goaf is top connected, a large amount of pipe washing water used to clean the filling pipeline will squeeze the slurry that has entered the access filling top connection from the board wall exhaust port, resulting in the problem of no top connection, which has a serious impact on the safety of adjacent access mining. At the same time, the overflowing filling slurry mixed with the ore will cause ore depletion and affect the ore quality. The ore containing filling slurry entering the chute is likely to cause chute blockage and affect normal production. Utility Model Content
[0004] The utility model aims to provide a water guide valve for underground mine filling pipes to solve the problems of excessive filling top connection and reduced filling slurry concentration caused by the cleaning water of the underground mine filling pipes entering the mining area.
[0005] To this end, the utility model adopts the following technical solutions:
[0006] A water diversion valve for filling pipes in underground mines, comprising a valve body, the valve body being in a cavity shape, and a rotatable valve plate assembly being arranged inside the valve body, the valve plate assembly comprising a rocker, the rocker being in contact with an inner wall of the valve body through a valve stem, a first valve disc and a second valve disc being arranged on both sides of the rocker, the first valve disc being fixedly connected to the rocker through a first bolt, and the second valve disc being fixedly connected to the rocker through a second bolt;
[0007] The valve body is provided with a first opening, a second opening and a third opening, wherein a first sealing gasket is provided inside the valve body near the first opening and a second sealing gasket is provided near the second opening, and both the first sealing gasket and the second sealing gasket are used to limit the rotatable valve plate assembly.
[0008] Furthermore, the rocker includes a first rod body and a second rod body, and the connection angle between the two is 110-130 degrees, and a socket is provided in the middle of the first rod body.
[0009] Furthermore, the first rod body has arc-shaped sides, a semicircular bottom, and a straight-sided top, and the width of the first rod body increases from top to bottom; the second rod body is a straight rod, and its size is 13cm~15cm.
[0010] Furthermore, the first valve disc includes a second rod body, both ends of the second rod body are provided with a first protrusion, the three form a U-shape, the size of the second rod body is 18cm~22cm, and the size of the first protrusion is 1cm~2cm.
[0011] Furthermore, the second valve disc includes a third rod body, and both ends of the third rod body are provided with second protrusions, and the three form a U-shape. The size of the third rod body is 14cm~16cm, and the size of the second protrusion is 0.6cm~0.8cm.
[0012] Furthermore, a lifting ring is provided at the bottom of the valve body.
[0013] The beneficial effects of the utility model are:
[0014] The utility model drives the valve plate assembly to different positions by rotating the rocker, thereby determining the flow direction of filling mortar or pipe washing water passing through the valve body, which can avoid the problem of filling slurry being segregated to form a sand top plate after a large amount of pipe lubricating water, pipe washing water, etc. enters the mining field, and can reduce the concentration of filling slurry and solve the problem of low filling top connection rate. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the structure of the utility model;
[0016] Figure 2 It is a structural schematic diagram of the rotatable valve plate assembly of the utility model.
[0017] In the figure, 1-valve body, 1a-first opening, 1b-second opening, 1c-third opening, 2-rotatable valve plate assembly, 3-rocker, 3a-first rod body, 3b-second rod body, 3c-jack, 4-valve stem, 5-first valve disc, 5a-fourth rod body, 5b-first protrusion, 6-second valve disc, 6a-third rod body, 6b-second protrusion, 7-first bolt, 8-second bolt, 9-first sealing gasket, 10-second sealing gasket, DETAILED DESCRIPTION
[0018] The technical solution of the utility model is described below in conjunction with the accompanying drawings and implementation methods.
[0019] like Figure 1As shown, a water diversion valve for filling pipes in underground mines comprises a valve body 1, which is in the shape of a cavity and has a rotatable valve plate assembly 2 inside; the valve body 1 adopts a three-way pipe, and has a first opening 1a, a second opening 1b and a third opening 1c on the left side, the top and the right side thereof, respectively, wherein the first opening 1a is set as a slurry outlet for filling mortar, and the second opening 1b is set as a pipe washing water outlet for cleaning the filling pipe.
[0020] like Figure 2 As shown, the rotatable valve plate assembly 2 includes a rocker 3, which is connected to the inside of the valve body 1 through a valve stem 4; a first valve disc 5 and a second valve disc 6 are respectively provided on both sides of the rocker 3, the first valve disc 5 is fixedly connected to the rocker 3 through a first bolt 7, and the second valve disc 6 is fixedly connected to the rocker 3 through a second bolt 8; the end of the valve stem 4 extends out of the valve body 1 and is connected to an external drive device, specifically, the external drive device can adopt an existing screwing drive component such as an electric wrench.
[0021] It should be noted that when the first valve disc 5 is screwed to the first opening 1a, its two ends are just clamped on both sides of the first opening 1a, playing a diversion role; when the second valve disc 6 is screwed to the second opening 1b, its two ends are just clamped on both sides of the second opening 1b, also playing a diversion role.
[0022] A first sealing gasket 9 is provided inside the valve body 1 near the first opening 1a, and a second sealing gasket 10 is provided near the second opening 1b. Both the first sealing gasket 9 and the second sealing gasket 10 are used to limit the rotatable valve plate assembly 2, and both are made of metal winding.
[0023] The rocker 3 includes a first rod body 3a and a second rod body 3b, and the connection angle between the two is 110°. A plug hole 3c is provided in the middle of the first rod body 3a, and the plug hole 3c is matched with the valve stem 4; the sides of the first rod body 3a are arc-shaped, the bottom is semicircular, and the top is straight-edged. The width of the first rod body 3a increases from top to bottom. The second rod body 3b is a straight rod with a size of 13cm~15cm.
[0024] The first valve disc 5 comprises a fourth rod body 5a, both ends of which are provided with first protrusions 5b, and the three form a U-shape. Specifically, the size of the fourth rod body 5a is 18 cm to 22 cm, and the size of the first protrusion 5b is 1 cm to 2 cm.
[0025] The second valve disc 6 includes a third rod body 6a, both ends of which are provided with second protrusions 6b, and the three form a U shape. Specifically, the size of the third rod body 6a is 14cm-16cm, and the size of the second protrusion 6b is 0.6cm-0.8cm.
[0026] In addition, a lifting ring 11 is provided at the bottom of the valve body 1 , and its purpose is to facilitate the lifting of the valve body 1 .
[0027] The utility model is used in the following process:
[0028] First, connect the valve body 1 to the downhole filling pipeline through a flange. When it is necessary to use clean water to drain, lubricate and clean the filling pipeline, turn on the external drive device, such as an electric wrench, and drive the rocker 3 to rotate clockwise, so that the first valve disc 5 is located at the channel of the first opening 1a, and the pipe washing water flows to the water storage tank through the third opening 1c and the second opening 1b in turn; when performing the filling operation, turn on the external drive device and drive the rocker 3 to rotate counterclockwise, so that the second valve disc 6 is located at the channel of the second opening 1b, and the filling mortar flows to the area to be filled through the third opening 1c and the first opening 1a in turn.
[0029] Finally, the volume and properties of the cavity of the valve body 1 of the utility model can be modified according to different site conditions. Accordingly, the relative positions between the rocker 3 and the first valve disc 5 and the second valve disc 6 need to be adjusted in time to adapt to the different pipe orifice diameters of the valve body 1 and continue to play a guiding role.
Claims
1. A water guide valve for filling pipeline in underground mine, characterized in that: The valve body (1) comprises a valve body (1), the valve body (1) is in the shape of a cavity, a rotatable valve plate assembly (2) is arranged inside the valve body, the valve plate assembly (2) comprises a rocker (3), the rocker (3) is in contact with the inner wall of the valve body (1) via a valve stem (4), a first valve disc (5) and a second valve disc (6) are arranged on both sides of the rocker (3), the first valve disc (5) is fixedly connected to the rocker (3) via a first bolt (7), and the second valve disc (6) is fixedly connected to the rocker (3) via a second bolt (8); The valve body (1) is provided with a first opening (1a), a second opening (1b) and a third opening (1c), wherein a first sealing gasket (9) is provided inside the valve body (1) near the first opening (1a), and a second sealing gasket (10) is provided near the second opening (1b), and the first sealing gasket (9) and the second sealing gasket (10) are both used to limit the position of the rotatable valve plate assembly (2).
2. A water diversion valve for underground filling pipeline in a mine according to claim 1, characterized in that: The rocker (3) comprises a first rod body (3a) and a second rod body (3b), and the two are connected at an angle of 110 to 130 degrees. A plug hole (3c) is provided in the middle of the first rod body (3a).
3. A water diversion valve for underground filling pipeline in a mine according to claim 2, characterized in that: The first rod body (3a) has arc-shaped sides, a semicircular bottom and a straight-edge top, and the width of the first rod body (3a) increases from top to bottom; the second rod body (3b) is a straight rod with a size of 13 cm to 15 cm.
4. A water diversion valve for filling pipeline in underground mine according to claim 1, characterized in that: The first valve disc (5) comprises a fourth rod body (5a), and first protrusions (5b) are provided at both ends of the fourth rod body (5a), and the three form a U-shape, the size of the fourth rod body (5a) is 18 cm to 22 cm, and the size of the first protrusion (5b) is 1 cm to 2 cm.
5. The water diversion valve for underground filling pipeline in a mine according to claim 1, characterized in that: The second valve disc (6) comprises a third rod body (6a), and second protrusions (6b) are provided at both ends of the third rod body (6a), so that the three form a U-shape, the size of the third rod body (6a) is 14 cm to 16 cm, and the size of the second protrusion (6b) is 0.6 cm to 0.8 cm.
6. A water diversion valve for underground filling pipeline in a mine according to claim 1, characterized in that: The openings of the first valve disc (5) and the second valve disc (6) are arranged back to back.
7. The water diversion valve for underground filling pipeline in a mine according to claim 1, characterized in that: A lifting ring (11) is provided at the bottom of the valve body (1).