Lifting system and production line
By designing a lifting system for power battery processing and production, the problems of complex structure and large area of conveying line in the prior art are solved, and the effects of space saving and production cost reduction are achieved.
Patent Information
- Application Number
- CN202421145412.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-23
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2034-05-23
AI Technical Summary
The conveying line body used in the prior art for conveying vehicles has a complex structure and a large area, which leads to high requirements and high costs for the overall production system.
A lifting system is designed, including a first conveying layer, a second conveying layer and a lift, transporting the vehicle in the first direction, and transferring it between the two layers by the lift, reducing space occupancy.
By centrally arranging the conveyor layer on the same side of the elevator, space is saved and the requirements and production costs of the overall production system are reduced.
Smart Images

Figure CN222475422U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of battery processing equipment, and more specifically, to a lifting system and a production line. Background Art
[0002] In recent years, as people's awareness of energy conservation and environmental protection has increased, the application of new energy equipment and power batteries has become more and more extensive. In the processing and production of power batteries, the battery cells need to be placed on a carrier for transportation before being put into the shell.
[0003] In the prior art, the structure of the conveyor line used to convey the carriers is relatively complex and occupies a large area, which places high demands on the overall production system and is costly.
[0004] In view of this, it is necessary to propose a new technical solution to solve the above technical problems. Utility Model Content
[0005] One purpose of the present application is to provide a new technical solution for a lifting system and a production line.
[0006] According to a first aspect of the present application, a lifting system is provided, the lifting system comprising:
[0007] a first conveying layer, the first conveying layer being used to convey the carrier along a first direction;
[0008] A second conveying layer, the second conveying layer is used to convey the carrier along the first direction, and the second conveying layer is located below the first conveying layer;
[0009] an elevator, the elevator being connected to both the first conveying layer and the second conveying layer, the elevator being used to lift and lower the carrier along a second direction so as to transfer the carrier between the first conveying layer and the second conveying layer;
[0010] Along a first direction, the first conveying layer and the second conveying layer are arranged on a same side of the elevator.
[0011] Optionally, the first transport layer includes a first sublayer and a second sublayer, and the first sublayer is located above the second sublayer;
[0012] The lifting system includes a first layer changing machine, which is connected to the first conveying layer and is arranged at an end of the first conveying layer away from the lifting machine; the first layer changing machine is used to lift and lower the carrier along the second direction so that the carrier is transferred between the first sub-layer and the second sub-layer.
[0013] Optionally, the lifting system includes a supporting platform, the supporting platform is arranged between the first conveying layer and the second conveying layer, and the first layer changing machine is installed on the supporting platform.
[0014] Optionally, the second transport layer includes a third sublayer and a fourth sublayer, and the third sublayer is located above the fourth sublayer;
[0015] The lifting system includes a second layer changing machine, which is connected to the second conveying layer and is arranged at an end of the second conveying layer away from the lifting machine; the second layer changing machine is used to lift and lower the carrier along the second direction so that the carrier is transferred between the third sub-layer and the fourth sub-layer.
[0016] Optionally, the carrier has a first state and a second state, and the carrier in the first state flows in the first sub-layer and is converted into a carrier in the second state; the second sub-layer is configured to transport the carrier in the second state.
[0017] Optionally, the carrier in the second state flows in the third sub-layer and is converted into a carrier in the first state; and the fourth sub-layer is configured to transport the carrier in the first state.
[0018] According to a second aspect of the present application, a production line is provided, comprising the lifting system as described in the first aspect.
[0019] Optionally, the production line also includes a carrier and a first robot, the carrier has a first state and a second state, the first robot is set corresponding to the first sub-layer, the carrier in the first state flows in the first sub-layer and is converted into a carrier in the second state through the operation of the first robot.
[0020] Optionally, the production line further includes a second robot, which is arranged corresponding to the third sub-layer, and the carrier in the second state flows in the third sub-layer and is converted into a carrier in the first state through the operation of the second robot.
[0021] Optionally, the second sublayer is configured to only transport carriers in the second state; and the fourth sublayer is configured to only transport carriers in the first state.
[0022] The lifting system provided in the embodiment of the present application can achieve the following technical effects:
[0023] In the lifting system provided in the embodiment of the present application, since the first conveying layer and the second conveying layer are arranged on the same side of the lift along the first direction; therefore, at least in the first direction, the arrangement of the first conveying layer and the second conveying layer can save space. The first conveying layer and the second conveying layer are centrally arranged on the same side of the lift along the first direction, and on the other side of the lift along the first direction, the first conveying layer and the second conveying layer do not need to occupy position space; this can save the floor space of the lifting system, reduce the requirements for the overall production system, and save production costs.
[0024] Other features and advantages of the present application will become apparent from the following detailed description of exemplary embodiments of the present application with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The accompanying drawings, which are incorporated in and constitute a part of the specification, illustrate embodiments of the application and, together with the description, serve to explain the principles of the application.
[0026] Figure 1 Shown is a structural schematic diagram of a lifting system of the present application;
[0027] Figure 2 Shown is a schematic structural diagram of a production line of the present application.
[0028] Description of reference numerals:
[0029] 1. Lifting system; 11. First conveying layer; 111. First sub-layer; 112. Second sub-layer; 12. Second conveying layer; 121. Third sub-layer; 122. Fourth sub-layer; 13. Lifting machine; 14. First layer changing machine; 15. Second layer changing machine; 16. Support platform;
[0030] 21. Carrier in the first state; 22. Carrier in the second state; 31. First manipulator; 32. Second manipulator. DETAILED DESCRIPTION
[0031] Various exemplary embodiments of the present application will now be described in detail with reference to the accompanying drawings. It should be noted that unless otherwise specifically stated, the relative arrangement of components and steps, numerical expressions and numerical values set forth in these embodiments do not limit the scope of the present application.
[0032] The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the present application, its application, or uses.
[0033] Technologies, methods, and equipment known to ordinary technicians in the relevant art may not be discussed in detail, but where appropriate, the technologies, methods, and equipment should be considered as part of the specification.
[0034] In all examples shown and discussed herein, any specific values should be interpreted as merely exemplary and not limiting. Therefore, other examples of the exemplary embodiments may have different values.
[0035] It should be noted that like reference numerals and letters refer to similar items in the following figures, and therefore, once an item is defined in one figure, it need not be further discussed in subsequent figures.
[0036] Reference Figure 1As shown, according to an embodiment of the present application, a lifting system 1 is provided, wherein the lifting system 1 includes a first conveying layer 11, a second conveying layer 12 and an elevator 13, wherein the first conveying layer 11 is used to convey a carrier along a first direction; the second conveying layer 12 is used to convey a carrier along a first direction, and the second conveying layer 12 is located below the first conveying layer 11; the elevator 13 is connected to both the first conveying layer 11 and the second conveying layer 12, and the elevator 13 is used to lift and lower the carrier along the second direction so that the carrier can be transferred between the first conveying layer 11 and the second conveying layer 12; along the first direction, the first conveying layer 11 and the second conveying layer 12 are arranged on the same side of the elevator 13.
[0037] The lifting system provided in the embodiment of the present application can be used to transport battery cells during the production and manufacturing process of batteries. The battery cells are placed on a carrier, and the battery cells and the carrier circulate in the lifting system.
[0038] Specifically, the carrier can flow along the first direction on the first conveying layer 11, and the carrier can also flow along the first direction on the second conveying layer 12; that is, the first conveying layer 11 and the second conveying layer 12 convey the carrier along the same horizontal direction (defined as the first direction). In addition, the carrier can be transferred between the first conveying layer 11 and the second conveying layer 12 by the elevator 13; for example, by the descending action of the elevator 13, the carrier can be transferred from the first conveying layer 11 to the second conveying layer 12; by the lifting action of the elevator 13, the carrier can be transferred from the second conveying layer 12 to the first conveying layer 11.
[0039] In the lifting system provided in the embodiment of the present application, since the first conveying layer 11 and the second conveying layer 12 are arranged on the same side of the lift 13 along the first direction; therefore, at least in the first direction, the arrangement of the first conveying layer 11 and the second conveying layer 12 can save space. The first conveying layer 11 and the second conveying layer 12 are centrally arranged on the same side of the lift 13 along the first direction, and on the other side of the lift 13 along the first direction, the first conveying layer 11 and the second conveying layer 12 do not need to occupy position space; this can save the floor space of the lifting system, reduce the requirements for the overall production system, and save production costs.
[0040] Reference Figure 1 As shown, in one embodiment, the first transport layer 11 includes a first sublayer 111 and a second sublayer 112, and the first sublayer 111 is located above the second sublayer 112;
[0041] The lifting system includes a first layer changing machine 14, which is connected to the first conveying layer 11 and is arranged at an end of the first conveying layer 11 away from the elevator 13; the first layer changing machine 14 is used to lift and lower the carrier along the second direction so that the carrier is transferred between the first sub-layer 111 and the second sub-layer 112.
[0042] In this specific example, in order to further improve the efficiency of the lifting system in transporting the carrier, the first conveying layer 11 is configured to include two sub-layers, namely the first sub-layer 111 and the second sub-layer 112, wherein the first sub-layer 111 is located above the second sub-layer 112. In order to transfer the carrier between the first sub-layer 111 and the second sub-layer 112, the lifting system is provided with a first layer changer 14, which is installed at one end of the first conveying layer 11 away from the elevator 13, and the first layer changer 14 can lift the carrier in a vertical direction (defined as a second direction).
[0043] Reference Figure 1 As shown, the first direction is Figure 1 The a direction in the second direction is Figure 1 The b direction in .
[0044] Reference Figure 1 As shown, in one embodiment, the lifting system includes a support platform 16 , the support platform 16 is disposed between the first conveying layer 11 and the second conveying layer 12 , and the first layer changing machine 14 is installed on the support platform 16 .
[0045] In this specific example, in order to enhance the stability of the lifting system, the system is further provided with a support platform 16, which is located between the first conveying layer 11 and the second conveying layer 12, and the first layer changing machine 14 is installed on the support platform 16. Optionally, the support platform 16 is a steel platform.
[0046] Reference Figure 1 As shown, in one embodiment, the second transport layer 12 includes a third sublayer 121 and a fourth sublayer 122, and the third sublayer 121 is located above the fourth sublayer 122;
[0047] The lifting system includes a second layer changing machine 15, which is connected to the second conveying layer 12 and is arranged at an end of the second conveying layer 12 away from the elevator 13; the second layer changing machine 15 is used to lift and lower the carrier along the second direction so that the carrier is transferred between the third sub-layer 121 and the fourth sub-layer 122.
[0048] In this specific example, in order to further improve the efficiency of the lifting system in transporting the carrier, the second conveying layer 12 is configured to include two sublayers, namely, a third sublayer 121 and a fourth sublayer 122, wherein the third sublayer 121 is located above the fourth sublayer 122. In order to transfer the carrier between the third sublayer 121 and the fourth sublayer 122, the lifting system is provided with a second layer changer 15, which is installed at one end of the second conveying layer 12 away from the elevator 13, and the second layer changer 15 can lift the carrier in a vertical direction (defined as a second direction).
[0049] The lift 13 and the second layer-changing machine 15 can be directly installed and fixed on the bottom surface G, and there is no need to separately set up a supporting platform for installing and fixing the lift 13 and the second layer-changing machine 15 .
[0050] Reference Figure 1 As shown, in one embodiment, the carrier has a first state and a second state, and the carrier in the first state flows in the first sub-layer 111 and is converted into a carrier in the second state; the second sub-layer 112 is configured to transport the carrier in the second state.
[0051] In this specific example, since the first sublayer 111 is located above the second sublayer 112, it is convenient to operate the carrier at the position of the first sublayer 111. For example, the carrier in the first state is converted into the carrier in the second state through corresponding operations during the flow in the first sublayer 111; the carrier in the second state is transferred to the second sublayer 112 through the descending action of the first layer changing machine 14, and then the carrier in the second state flows in the second sublayer 112.
[0052] Reference Figure 1 As shown, in one embodiment, the carrier in the second state flows in the third sub-layer 121 and is converted into the carrier in the first state; the fourth sub-layer 122 is configured to transport the carrier in the first state.
[0053] In this specific example, since the third sublayer 121 is located above the fourth sublayer 122, it is convenient to operate the carrier at the position of the third sublayer 121. For example, the carrier in the second state is converted into a carrier in the first state through corresponding operations during the flow of the third sublayer 121; the carrier in the first state is transferred to the fourth sublayer 122 through the descending action of the second layer changing machine 15, and then the carrier in the first state flows in the fourth sublayer 122.
[0054] Reference Figure 2 As shown, according to another embodiment of the present application, a production line is provided, which includes the lifting system as described above.
[0055] The production line provided in the embodiment of the present application occupies a small area, has a relatively simple layout, and has a low production cost because it includes the above-mentioned lifting system.
[0056] Reference Figure 2 As shown, in one embodiment, the production line further includes a carrier and a first robot 31, the carrier having a first state and a second state (for convenience in Figure 2 The two states of carriers are distinguished in the figure, and the carriers in the first state and the carriers in the second state are respectively assigned different figure marks); the first manipulator 31 is arranged corresponding to the first sub-layer 111, and the carrier 21 in the first state flows in the first sub-layer 111 and is converted into the carrier 22 in the second state through the operation of the first manipulator 31.
[0057] In this specific example, since the first sub-layer 111 is located above the second sub-layer 112, it is convenient to operate the carrier at the position of the first sub-layer 111; specifically, a first manipulator 31 is provided at the position of the first sub-layer 111, and the carrier 21 in the first state is converted into the carrier 22 in the second state through the operation of the first manipulator 31 during the flow of the first sub-layer 111.
[0058] The first manipulator 31 is disposed at the first sub-layer 111 located above. Not only is the arrangement of the first manipulator 31 easier, but the operation of the first manipulator 31 will not be restricted by the space between the first sub-layer 111 and the second sub-layer 112, thereby avoiding the operation of the first manipulator 31 being affected by the limited space between the first sub-layer 111 and the second sub-layer 112.
[0059] Reference Figure 2 As shown, in one embodiment, the production line also includes a second robot 32, which is arranged corresponding to the third sub-layer 121, and the carrier 22 in the second state flows in the third sub-layer 121 and is converted into the carrier 21 in the first state through the operation of the second robot 32.
[0060] In this specific example, since the third sublayer 121 is located above the fourth sublayer 122, it is convenient to operate the carrier at the position of the third sublayer 121; specifically, a second manipulator 32 is provided at the position of the third sublayer 121, and the carrier 22 in the second state is converted into the carrier 21 in the first state through the operation of the second manipulator 32 during the flow of the third sublayer 121.
[0061] The second manipulator 32 is disposed at the third sub-layer 121 located above. Not only is the arrangement of the second manipulator 32 easier, but the operation of the second manipulator 32 will not be restricted by the space between the third sub-layer 121 and the fourth sub-layer 122, thereby avoiding the operation of the second manipulator 32 being affected by the limited space between the third sub-layer 121 and the fourth sub-layer 122.
[0062] Reference Figure 2 As shown, in one embodiment, the second sub-layer 112 is configured to only transport the carrier 22 in the second state; and the fourth sub-layer 122 is configured to only transport the carrier 21 in the first state.
[0063] In this specific example, the second sublayer 112 located below the first sublayer 111 is configured to only transport the carrier 22 in the second state, without the need to set a robot at the position of the second sublayer 112 to operate the carrier 22 in the second state; similarly, the fourth sublayer 122 located below the third sublayer 121 is configured to only transport the carrier 21 in the first state, without the need to set a robot at the position of the fourth sublayer 122 to operate the carrier 21 in the first state.
[0064] A complete cycle of the carrier 21 in the first state and the carrier 22 in the second state in the production line is:
[0065] The carrier 21 in the first state flows on the first sub-layer 111 and is converted into the carrier 22 in the second state through the operation of the first manipulator 31. The carrier 22 in the second state is transferred to the second sub-layer 112 through the descending action of the first layer-changing machine 14, and then the carrier 22 in the second state flows to the elevator 13 in the second sub-layer 112; under the descending action of the elevator 13, the carrier 22 in the second state is transferred to the third sub-layer 121, and then the carrier 22 in the second state flows in the third sub-layer 121 and is converted into the carrier 21 in the first state through the operation of the second manipulator 32, the carrier 21 in the first state is transferred to the fourth sub-layer 122 under the descending action of the second layer-changing machine 15, and then the carrier 21 in the first state flows to the elevator 13 in the fourth sub-layer 122; under the lifting action of the elevator 13, the carrier 21 in the first state enters the first sub-layer 111 again to participate in the next production cycle.
[0066] In a specific example, the carrier 21 in the first state is an empty tray without battery cells, and the carrier 22 in the second state is a loading tray with battery cells; Figure 1 and Figure 2 The hollow arrow A1 in the figure represents the flow direction of the empty pallet, and the solid arrow A2 represents the flow direction of the loaded pallet; the first manipulator 31 is a material unloading manipulator, and the second manipulator 32 is a material taking manipulator.
[0067] Although some specific embodiments of the present application have been described in detail by way of example, it should be understood by those skilled in the art that the above examples are only for illustration, not for limiting the scope of the present application. It should be understood by those skilled in the art that the above embodiments may be modified without departing from the scope and spirit of the present application. The scope of the present application is defined by the appended claims.
Claims
1. A lifting system, characterized in that: The lifting system comprises: A first conveying layer (11), the first conveying layer (11) being used to convey the carrier along a first direction; A second conveying layer (12), the second conveying layer (12) being used to convey the carrier along a first direction, and the second conveying layer (12) being located below the first conveying layer (11); an elevator (13), the elevator (13) being connected to both the first conveying layer (11) and the second conveying layer (12), the elevator (13) being used to lift and lower the carrier along a second direction so as to transfer the carrier between the first conveying layer (11) and the second conveying layer (12); Along a first direction, the first conveying layer (11) and the second conveying layer (12) are arranged on the same side of the elevator (13).
2. The lifting system according to claim 1, characterized in that: The first transport layer (11) comprises a first sublayer (111) and a second sublayer (112), wherein the first sublayer (111) is located above the second sublayer (112); The lifting system comprises a first layer changing machine (14), the first layer changing machine (14) being connected to the first conveying layer (11) and being arranged at an end of the first conveying layer (11) away from the lifting machine (13); the first layer changing machine (14) is used to lift and lower the carrier along a second direction so as to transfer the carrier between the first sub-layer (111) and the second sub-layer (112).
3. The lifting system according to claim 2, characterized in that: The lifting system comprises a supporting platform (16), wherein the supporting platform (16) is arranged between the first conveying layer (11) and the second conveying layer (12), and the first layer changing machine (14) is installed on the supporting platform (16).
4. The lifting system according to claim 2, characterized in that: The second transport layer (12) comprises a third sublayer (121) and a fourth sublayer (122), wherein the third sublayer (121) is located above the fourth sublayer (122); The lifting system comprises a second layer-changing machine (15), the second layer-changing machine (15) being connected to the second conveying layer (12) and being arranged at an end of the second conveying layer (12) away from the lifting machine (13); the second layer-changing machine (15) is used for lifting and lowering the carrier along a second direction so as to transfer the carrier between the third sub-layer (121) and the fourth sub-layer (122).
5. The lifting system according to claim 4, characterized in that: The carrier has a first state and a second state. The carrier in the first state flows in the first sub-layer (111) and is converted into a carrier in the second state. The second sub-layer (112) is configured to transport the carrier in the second state.
6. The lifting system according to claim 5, characterized in that: The carrier in the second state flows in the third sub-layer (121) and is converted into a carrier in the first state; and the fourth sub-layer (122) is configured to transport the carrier in the first state.
7. A production line, characterized in that: The production line comprises a lifting system as claimed in claim 4.
8. The production line according to claim 7, characterized in that: The production line also includes a carrier and a first robot (31), the carrier having a first state and a second state, the first robot (31) being arranged corresponding to the first sub-layer (111), the carrier in the first state flowing in the first sub-layer (111) and being converted into a carrier (22) in the second state through the operation of the first robot (31).
9. The production line according to claim 8, characterized in that: The production line also includes a second robot (32), which is arranged corresponding to the third sub-layer (121), and the carrier in the second state flows in the third sub-layer (121) and is converted into a carrier (21) in the first state through the operation of the second robot (32).
10. The production line according to claim 9, characterized in that: The second sub-layer (112) is configured to transport only carriers (22) in a second state; and the fourth sub-layer (122) is configured to transport only carriers (21) in a first state.