Subway tunnel construction drainage device

By designing a stirring shaft and agitation blade in the subway tunnel construction drainage device, and equipped with a shrinkage mechanism and a rotating mechanism, the problem of difficulty in filtering thin garbage ropes in groundwater is solved, and effective filtration and cleaning of rope-like garbage is achieved to prevent it Damage to the water pump.

CN222489127UActive Publication Date: 2025-02-18SUZHOU BENNING CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323391649.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-13
Publication Date
2025-02-18
Estimated Expiration
2033-12-13

AI Technical Summary

Technical Problem

During the construction of subway tunnels, groundwater may contain slender garbage ropes. These ropes are difficult to filter out through traditional filtration equipment, easily entering the water pump and causing damage, affecting the construction process.

Method used

A subway tunnel construction drainage device is designed, including components such as mobile platforms, water pumps, water inlet pipes, filter boxes and mixing shafts. By providing a stirring shaft and a stirring blade in the filter frame, and equipped with a shrinking mechanism and a rotating mechanism, it is possible to effectively filter and clean the incoming rope-like garbage.

Benefits of technology

This device can effectively filter rope-like garbage in groundwater during subway tunnel construction, prevent it from entering the water pump and causing damage, thereby ensuring the smooth progress of the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222489127U_ABST
    Figure CN222489127U_ABST
Patent Text Reader

Abstract

The utility model relates to a drainage device for subway tunnel construction, and relates to the technical field of subway tunnels. The device comprises a mobile platform, the upper end of the mobile platform is fixedly connected with a water pump, the circumferential side of the water pump is fixedly connected with a water inlet pipe and a water outlet pipe, the circumferential side of the water inlet pipe is provided with a filter box, one side wall of the filter box is fixedly connected with a filter frame, the filter frame is located at a water inlet of the filter box, and a stirring shaft is rotatably arranged in the filter frame. The stirring shaft movably penetrates through the upper end of the filtering box, two storage grooves are uniformly formed in the circumferential side of the stirring shaft, stirring blades are hinged between the side walls of the two storage grooves, contraction mechanisms are arranged on the four stirring blades, the stirring blades and the stirring shaft can wind sucked-out suction or floccules between the stirring blades and the stirring shaft, and therefore the stirring effect is improved. Rope-shaped floating objects are prevented from entering the water pump to damage the water pump.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of subway tunnels, in particular to a subway tunnel construction drainage device. Background Art

[0002] Subway tunnel refers to an underground passage used for subway operation. It is usually built of concrete or reinforced concrete structure to carry subway tracks and ensure the safe operation of trains. The tunnel is equipped with drainage systems, cable channels, emergency evacuation exits and other facilities. The construction of the tunnel needs to fully consider factors such as geological conditions, groundwater levels and surrounding environment.

[0003] Subway tunnels are generally built underground in cities. Compared with underground in the wild, there will be more garbage underground in cities. When drainage is needed during subway tunnel construction, the groundwater contains not only mud and sand, but also bags, ropes and other unoxidized garbage. Because the ropes are relatively thin and long, sometimes a simple filter basket cannot filter them out. The ropes enter the water pump, which can easily cause damage to the water pump and affect the progress of construction. Utility Model Content

[0004] In view of the deficiencies in the prior art, the purpose of the utility model is to provide a subway tunnel construction drainage device, which can filter garbage ropes in the underground water of the subway tunnel and prevent the water pump from being damaged.

[0005] The above technical objectives of the utility model are achieved through the following technical solutions:

[0006] A subway tunnel construction drainage device comprises a mobile platform, the upper end of the mobile platform is fixedly connected to a water pump, the circumferential side of the water pump is fixedly connected to a water inlet pipe and a water outlet pipe, the circumferential side of the water inlet pipe is installed with a filter box, a side wall of the filter box is fixedly connected to a filter frame, and the filter frame is located at the water inlet of the filter box, a stirring shaft is rotatably arranged in the filter frame, and the stirring shaft movably penetrates the upper end of the filter box, two receiving grooves are evenly arranged on the circumferential side of the stirring shaft, stirring blades are hinged between the side walls of the two receiving grooves, and a contraction mechanism is arranged on the four stirring blades, each group of the contraction mechanism comprises a traction rope, a spring, a guide wheel and an installation groove, the spring is fixedly connected between the stirring blade and the storage groove, the installation groove is arranged on a side wall of the storage groove, the guide wheel is rotatably connected between the side walls of the installation groove, the traction rope is fixedly connected to the lower end of the stirring blade, and the traction rope is transmission-connected to the circumferential side of the guide wheel.

[0007] By adopting the above technical scheme, the contraction mechanism, rotating rod, water pump, filter frame, water inlet pipe, filter box, stirring shaft and storage tank cooperate to filter the water sucked out of the water inlet pipe, and the stirring blade and the stirring shaft can absorb the sucked out suction or flocs can be wrapped between the stirring blade and the stirring shaft to prevent rope-like floating objects from entering the water pump and causing damage to the water pump.

[0008] In a preferred example, the utility model can be further configured as follows: a rotating groove is opened in the stirring shaft, the inner bottom wall of the rotating groove is rotatably connected to a rotating rod, and the upper end of the rotating rod movably passes through the upper end of the stirring shaft, the upper end of the stirring shaft is fixedly connected to a third motor, the output end of the third motor is fixed to the upper end of the stirring shaft, and the other side of the traction rope is fixed to the circumferential side of the rotating rod.

[0009] By adopting the above technical solution, the rotating rod rotates, and the traction rope is wrapped around the circumferential side of the rotating rod. The traction rope can pull the stirring blade so that the stirring blade can be stuck in the storage groove, which can facilitate the stirring shaft to bring the collected garbage out of the filter frame and the filter box.

[0010] In a preferred example, the utility model can be further configured as follows: an L-shaped plate is provided on the circumferential side of the stirring shaft, a rotating mechanism is provided between the L-shaped plate and the stirring shaft, the rotating mechanism includes a gear, a machine base, a second motor and a gear ring, the gear ring and the gear are both rotatably connected to the upper end of the L-shaped plate, the gear ring is fixedly connected to the circumferential side of the stirring shaft, the gear is meshed with the gear ring, the machine base is fixedly connected to the upper end of the L-shaped plate, the second motor is fixedly connected to the upper end of the machine base, and the output end of the second motor movably passes through the lower end of the machine base and is fixed to the upper end of the gear.

[0011] By adopting the above technical solution, the rotating mechanism can drive the stirring shaft to rotate for cleaning.

[0012] In a preferred example, the utility model can be further configured as follows: a mounting plate is provided on one side of the L-shaped plate, the mounting plate is fixedly connected to the upper end of the mobile platform, a debris removal mechanism is provided between the mounting plate and the L-shaped plate, the debris removal mechanism includes a rectangular groove, a screw nut, a screw and a first motor, the rectangular groove is opened on one side of the mounting plate, the screw is rotatably connected to the inner bottom wall of the rectangular groove, and the screw movably passes through the upper end of the mounting plate, the screw nut is threadedly connected to the circumferential side of the screw, the L-shaped plate is fixed to one side of the screw nut, the first motor is fixedly connected to the upper end of the mounting plate, and the output end of the first motor is fixed to the upper end of the screw.

[0013] By adopting the above technical solution, the impurity removal mechanism, the mounting plate and the sand removal frame cooperate to enable the stirring shaft to move upward, so that the stirring shaft leaves the filter frame and the filter box.

[0014] In a preferred example, the utility model can be further configured as follows: two limit rods are fixedly connected between the inner top wall and the inner bottom wall of the rectangular groove, and the screw nut is slidably connected to the circumferential sides of the two limit rods.

[0015] By adopting the above technical solution, the screw nut and the limit rod are slidably matched, which can improve the movement stability of the screw nut.

[0016] In a preferred example, the utility model can be further configured as follows: a threaded ring is threadedly connected to the circumferential side of the water inlet pipe, a filter basket is fixedly connected to one side of the threaded ring, and a handle is fixedly connected to the upper end of the mobile platform.

[0017] By adopting the above technical solution, the filter basket and the threaded ring can facilitate the connection between the filter basket and the water inlet pipe.

[0018] In a preferred example, the utility model can be further configured as follows: a sand removal frame is fixedly connected to the circumferential inner wall of the filter basket, a plurality of filter holes are provided on the circumferential inner wall and one side wall of the sand removal frame, and a stepped isolation block is fixedly connected to one side wall of the sand removal frame.

[0019] By adopting the above technical solution, the sand removal frame, stepped isolation blocks and filter holes are combined to perform preliminary filtration of sand and gravel in the water.

[0020] In summary, the present invention includes at least one of the following beneficial technical effects:

[0021] 1. A retracting mechanism, a rotating rod, a water pump, a filter frame, a water inlet pipe, a filter box, a stirring shaft, and a storage tank are provided. The water pump is started to drain water, and the water in the tunnel and garbage are sucked into the water inlet pipe. When the water and garbage pass through the filter frame, the stirring shaft rotates, and the stirring shaft can drive the stirring blade to rotate. The stirring blade can wrap the water entering the filter frame between the stirring shaft and the stirring blade, and the water sucked out of the water inlet pipe can be filtered. The stirring blade and the stirring shaft can wrap the sucked out flocs between the stirring blade and the stirring shaft to prevent rope-like floating objects from entering the water pump and damaging the water pump.

[0022] 2. A rotating rod, a rotating groove, an L-shaped plate, a debris removal mechanism and a rotating mechanism are provided. The second motor is started, and the output end of the second motor drives the gear to rotate. The gear ring is meshed with the gear ring. The gear ring drives the stirring shaft to rotate, so that the stirring shaft can rotate and the rope can be wound between the stirring shaft and the stirring blade. The third motor is started, and the output end of the third motor drives the rotating rod to rotate. The traction rope is gradually wrapped around the surface of the rotating rod, and the stirring blade rotates, so that the stirring blade approaches the receiving groove, so that the stirring blade can clamp the rope between the stirring blade and the stirring shaft. The first motor is started, and the output end of the first motor drives the screw to rotate. The screw nut moves on the circumferential side of the screw, and the screw nut drives the L-shaped plate to move upward, so that the L-shaped plate can drive the stirring shaft to leave the filter frame and the filter box to prevent the material from being wound too much on the stirring shaft and cannot be used anymore. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 is a stereogram of this embodiment;

[0024] Figure 2 This embodiment Figure 1 A partial enlarged view of the middle A;

[0025] Figure 3 is a first stereoscopic cross-sectional view of the present embodiment;

[0026] Figure 4 This embodiment Figure 3 A partial enlarged view of point B in the middle;

[0027] Figure 5 is a second stereoscopic cross-sectional view of the present embodiment;

[0028] Figure 6 This embodiment Figure 5 A partial enlarged view of point C in the middle;

[0029] Figure 7 This embodiment Figure 5 A partial enlarged view of point D in the middle.

[0030] In the figure, 1, mobile platform; 2, handle; 3, water pump; 4, filter frame; 5, water outlet pipe; 6, water inlet pipe; 7, filter box; 8, mounting plate; 9, impurity removal mechanism; 901, rectangular groove; 902, screw nut; 903, screw; 904, limit rod; 905, first motor; 10, stirring shaft; 11, rotating mechanism; 1101, gear; 1102, machine base; 1103, second motor; 1104, gear ring; 12, third motor; 13, rotating groove; 14, rotating rod; 15, stirring blade; 16, retracting mechanism; 1601, traction rope; 1602, spring; 1603, guide wheel; 1604, mounting groove; 17, L-shaped plate; 18, filter basket; 19, sand removal frame; 20, stepped isolation block; 21, filter hole; 22, storage groove; 23, threaded ring. DETAILED DESCRIPTION

[0031] The utility model is further described in detail below in conjunction with the accompanying drawings.

[0032] Example:

[0033] Reference Figure 1-7 The utility model discloses a subway tunnel construction drainage device, including a mobile platform 1, a water pump 3 is fixedly connected to the upper end of the mobile platform 1, a water inlet pipe 6 and a water outlet pipe 5 are fixedly connected to the circumferential side of the water pump 3, a filter box 7 is installed on the circumferential side of the water inlet pipe 6, a filter frame 4 is fixedly connected to one side wall of the filter box 7, and the filter frame 4 is located at the water inlet of the filter box 7, a stirring shaft 10 is rotatably arranged in the filter frame 4, and the stirring shaft 10 movably passes through the upper end of the filter box 7, two receiving grooves 22 are evenly arranged on the circumferential side of the stirring shaft 10, stirring blades 15 are hinged between the side walls of the two receiving grooves 22, and a contraction mechanism 16 is arranged on the four stirring blades 15, and each group of contraction mechanisms 16 includes a traction rope 1601, a spring 1602, a guide wheel 1603 and an installation groove 1604, and the spring 1602 is fixedly connected to the stirring blade 15 and the receiving groove 22 The installation groove 1604 is opened in one side wall of the storage groove 22, the guide wheel 1603 is rotatably connected between the side walls of the installation groove 1604, the traction rope 1601 is fixedly connected to the lower end of the stirring blade 15, and the traction rope 1601 is transmission-connected to the circumferential side of the guide wheel 1603. When drainage is needed, the water pump 3 is started to drain, and the water in the tunnel and garbage are sucked into the water inlet pipe 6. When the water and garbage pass through the filter frame 4, the stirring shaft 10 rotates, and the stirring shaft 10 can drive the stirring blade 15 to rotate. The stirring blade 15 can enter the filter frame 4 and wrap it between the stirring shaft 10 and the stirring blade 15, and the water sucked out of the water inlet pipe 6 can be filtered. The stirring blade 15 and the stirring shaft 10 can absorb the suction or floccules and wrap them between the stirring blade 15 and the stirring shaft 10 to prevent rope-shaped floating objects from entering the water pump 3 and damaging the water pump 3.

[0034] A rotating groove 13 is opened in the stirring shaft 10, and the inner bottom wall of the rotating groove 13 is rotatably connected to a rotating rod 14, and the upper end of the rotating rod 14 movably passes through the upper end of the stirring shaft 10, and the upper end of the stirring shaft 10 is fixedly connected to the third motor 12, and the output end of the third motor 12 is fixed to the upper end of the stirring shaft 10, and the other side of the traction rope 1601 is fixed to the circumferential side of the rotating rod 14. The third motor 12 is started, and the output end of the third motor 12 drives the rotating rod 14 to rotate, and the traction rope 1601 is gradually wrapped around the surface of the rotating rod 14, and the stirring blade 15 rotates, so that the stirring blade 15 approaches the storage groove 22, so that the stirring blade 15 can clamp the rope between the stirring blade 15 and the stirring shaft 10.

[0035] An L-shaped plate 17 is provided on the circumferential side of the stirring shaft 10, and a rotating mechanism 11 is provided between the L-shaped plate 17 and the stirring shaft 10. The rotating mechanism 11 includes a gear 1101, a base 1102, a second motor 1103 and a gear ring 1104. The gear ring 1104 and the gear 1101 are both rotatably connected to the upper end of the L-shaped plate 17, and the gear ring 1104 is fixedly connected to the circumferential side of the stirring shaft 10. The gear 1101 is meshed with the gear ring 1104, and the base 1102 is fixedly connected to the upper end of the L-shaped plate 17. The second motor 1103 is fixedly connected to the upper end of the base 1102, and the output end of the second motor 1103 movably passes through the lower end of the base 1102 and is fixed to the upper end of the gear 1101. The second motor 1103 is started, and the output end of the second motor 1103 drives the gear 1101 to rotate, and the gear ring 1104 is meshed with the gear ring 1104. The gear ring 1104 drives the stirring shaft 10 to rotate, so that the stirring shaft 10 can rotate, and the rope can be wrapped around the stirring shaft 10 and the stirring blade 15.

[0036] A mounting plate 8 is provided on one side of the L-shaped plate 17, and the mounting plate 8 is fixedly connected to the upper end of the mobile platform 1. A debris removal mechanism 9 is provided between the mounting plate 8 and the L-shaped plate 17, and the debris removal mechanism 9 includes a rectangular groove 901, a screw nut 902, a screw 903 and a first motor 905. The rectangular groove 901 is opened on one side of the mounting plate 8, and the screw 903 is rotatably connected to the inner bottom wall of the rectangular groove 901, and the screw 903 movably passes through the upper end of the mounting plate 8, and the screw nut 902 is threadedly connected to the circumferential side of the screw 903. The L-shaped plate 17 is fixed to one side of the screw nut 902. The first motor 905 is fixedly connected to the upper end of the mounting plate 8, and the output end of the first motor 905 is fixed to the upper end of the screw rod 903. Preferably, a sealing roll is arranged between the stirring shaft 10 and the filter box 7. The first motor 905 is started, and the output end of the first motor 905 drives the screw rod 903 to rotate. The screw nut 902 moves on the circumferential side of the screw rod 903. The screw nut 902 drives the L-shaped plate 17 to move upward, so that the L-shaped plate 17 can drive the stirring shaft 10 to leave the filter frame 4 and the filter box 7, so as to prevent the stirring shaft 10 from being entangled with too much material and being unable to be used any further.

[0037] Two limit rods 904 are fixedly connected between the inner top wall and the inner bottom wall of the rectangular groove 901, and the screw nut 902 is slidably connected to the circumferential sides of the two limit rods 904. The screw nut 902 and the limit rod 904 are slidably matched to improve the movement stability of the screw nut 902.

[0038] A threaded ring 23 is threadedly connected to the circumferential side of the water inlet pipe 6, and a filter basket 18 is fixedly connected to one side of the threaded ring 23. A handle 2 is fixedly connected to the upper end of the mobile platform 1. The filter basket 18 and the threaded ring 23 can facilitate the connection between the filter basket 18 and the water inlet pipe 6.

[0039] A sand removal frame 19 is fixedly connected to the circumferential inner wall of the filter basket 18. A plurality of filter holes 21 are provided on the circumferential inner wall and one side wall of the sand removal frame 19. A stepped isolation block 20 is fixedly connected to one side wall of the sand removal frame 19. The sand removal frame 19, the stepped isolation block 20 and the filter holes 21 cooperate to perform preliminary filtration of sand and gravel in the water.

[0040] The implementation principle of the above embodiment is as follows: start the water pump 3 to drain water, and the water in the tunnel and garbage are sucked into the water inlet pipe 6. When the water and garbage pass through the filter frame 4, start the second motor 1103, and the output end of the second motor 1103 drives the gear 1101 to rotate, and the gear ring 1104 is meshed with the gear ring 1104, and the gear ring 1104 drives the stirring shaft 10 to rotate, so that the stirring shaft 10 can rotate, and the rope can be wound between the stirring shaft 10 and the stirring blade 15, and the stirring shaft 10 can drive the stirring blade 15 to rotate, and the stirring blade 15 can enter the filter frame 4 and be wound between the stirring shaft 10 and the stirring blade 15, so that the water sucked out of the water inlet pipe 6 can be filtered, and the stirring blade 5 and the stirring shaft 10 can be sucked out or the flocs can be wound around the stirring blade 15 and the stirring blade 15. The third motor 12 is started, and the output end of the third motor 12 drives the rotating rod 14 to rotate, and the traction rope 1601 is gradually wrapped around the surface of the rotating rod 14, and the stirring blade 15 rotates, so that the stirring blade 15 approaches the storage groove 22, so that the stirring blade 15 can clamp the rope between the stirring blade 15 and the stirring shaft 10, and the first motor 905 is started. The output end of the first motor 905 drives the screw rod 903 to rotate, and the screw nut 902 moves on the circumferential side of the screw rod 903. The screw nut 902 drives the L-shaped plate 17 to move upward, so that the L-shaped plate 17 can drive the stirring shaft 10 to leave the filter frame 4 and the filter box 7, so as to prevent the stirring shaft 10 from being entangled with too much material and being unable to continue to be used.

[0041] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

[0042] The embodiments of this specific implementation method are all preferred embodiments of the utility model, and are not intended to limit the protection scope of the utility model. Therefore, all equivalent changes made based on the structure, shape, and principle of the utility model should be included in the protection scope of the utility model.

Claims

1. A drainage device for subway tunnel construction, comprising a mobile platform (1), characterized in that: The upper end of the mobile platform (1) is fixedly connected to a water pump (3), the circumferential side of the water pump (3) is fixedly connected to a water inlet pipe (6) and a water outlet pipe (5), the circumferential side of the water inlet pipe (6) is installed with a filter box (7), a side wall of the filter box (7) is fixedly connected to a filter frame (4), and the filter frame (4) is located at the water inlet of the filter box (7), a stirring shaft (10) is rotatably arranged in the filter frame (4), two receiving grooves (22) are evenly arranged on the circumferential side of the stirring shaft (10), stirring blades (15) are hinged between the side walls of the two receiving grooves (22), and the four stirring blades (15) are A retracting mechanism (16) is provided, and each group of the retracting mechanism (16) comprises a traction rope (1601), a spring (1602), a guide wheel (1603) and a mounting groove (1604), wherein the spring (1602) is fixedly connected between the stirring blade (15) and the receiving groove (22), the mounting groove (1604) is opened on a side wall of the receiving groove (22), the guide wheel (1603) is rotatably connected between the side walls of the mounting groove (1604), the traction rope (1601) is fixedly connected to the lower end of the stirring blade (15), and the traction rope (1601) is transmission-connected to the circumferential side of the guide wheel (1603).

2. A subway tunnel construction drainage device according to claim 1, characterized in that: A rotating groove (13) is provided in the stirring shaft (10), and the inner bottom wall of the rotating groove (13) is rotatably connected to a rotating rod (14), and the upper end of the rotating rod (14) movably passes through the upper end of the stirring shaft (10), and the upper end of the stirring shaft (10) is fixedly connected to a third motor (12), and the output end of the third motor (12) is fixed to the upper end of the stirring shaft (10), and the other side of the traction rope (1601) is fixed to the circumferential side of the rotating rod (14).

3. A subway tunnel construction drainage device according to claim 1, characterized in that: An L-shaped plate (17) is provided on the circumferential side of the stirring shaft (10); a rotating mechanism (11) is provided between the L-shaped plate (17) and the stirring shaft (10); the rotating mechanism (11) comprises a gear (1101), a machine base (1102), a second motor (1103) and a gear ring (1104); the gear ring (1104) and the gear (1101) are both rotatably connected to the upper end of the L-shaped plate (17); the gear ring (1104) is fixedly connected to the circumferential side of the stirring shaft (10); the gear (1101) meshes with the gear ring (1104); the machine base (1102) is fixedly connected to the upper end of the L-shaped plate (17); the second motor (1103) is fixedly connected to the upper end of the machine base (1102); and the output end of the second motor (1103) movably passes through the lower end of the machine base (1102) and is fixed to the upper end of the gear (1101).

4. A subway tunnel construction drainage device according to claim 3, characterized in that: A mounting plate (8) is provided on one side of the L-shaped plate (17), the mounting plate (8) being fixedly connected to the upper end of the mobile platform (1), a debris removal mechanism (9) being provided between the mounting plate (8) and the L-shaped plate (17), the debris removal mechanism (9) comprising a rectangular groove (901), a screw nut (902), a screw (903) and a first motor (905), the rectangular groove (901) being provided on one side of the mounting plate (8), the screw (903) being rotatably connected to the inner bottom wall of the rectangular groove (901), and the screw (903) being movably passed through the upper end of the mounting plate (8), the screw nut (902) being threadedly connected to the circumferential side of the screw (903), the L-shaped plate (17) being fixed to one side of the screw nut (902), the first motor (905) being fixedly connected to the upper end of the mounting plate (8), and the output end of the first motor (905) being fixed to the upper end of the screw (903).

5. A subway tunnel construction drainage device according to claim 4, characterized in that: Two limiting rods (904) are fixedly connected between the inner top wall and the inner bottom wall of the rectangular groove (901), and the screw nut (902) is slidably connected to the circumferential sides of the two limiting rods (904).

6. A subway tunnel construction drainage device according to claim 1, characterized in that: A threaded ring (23) is threadedly connected to the circumferential side of the water inlet pipe (6), a filter basket (18) is fixedly connected to one side of the threaded ring (23), and a handle (2) is fixedly connected to the upper end of the mobile platform (1).

7. A subway tunnel construction drainage device according to claim 6, characterized in that: A sand removal frame (19) is fixedly connected to the circumferential inner wall of the filter basket (18), a plurality of filter holes (21) are provided on the circumferential inner wall and one side wall of the sand removal frame (19), and a stepped isolation block (20) is fixedly connected to one side wall of the sand removal frame (19).