Pipeline butt joint structure and movable dust removal system
By setting up installation gaps and sealing tapes in the pipe docking structure of the mobile dust collector, the sealing effect is achieved by using negative pressure, which solves the problem of cumbersome pipe connections in the prior art, and improves the speed of construction and sealing performance.
Patent Information
- Application Number
- CN202421541674.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2025-03-21
- Estimated Expiration
- 2034-07-01
AI Technical Summary
The existing mobile dust collector needs to be aligned and connected at the pipe connections, resulting in more cumbersome construction operations on site.
By setting up installation gaps and sealing tapes in the pipe docking structure, the sealing tape is blocked by negative pressure to achieve the sealing effect at the docking and simplifying the docking operation.
The sealing performance at the pipe docking point is realized, while simplifying the connection operation and improving the speed and convenience of on-site construction.
Smart Images

Figure CN222650826U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of dust removal equipment, and more specifically relates to a pipeline docking structure and a mobile dust removal system. Background Art
[0002] With the improvement of national environmental protection requirements, manufacturing enterprises are required to recycle and centrally treat the harmful substances such as smoke and dust generated during the production process that damage the environment. At present, the more common method is to enclose the equipment that generates smoke and dust with a dust hood, and set a vent on the top of the dust hood to suck the smoke, dust and other harmful substances generated during the production process into the ventilation duct, and transport them to the equipment through the ventilation duct for centralized treatment, so as to achieve the standard of qualified emissions.
[0003] The specific settings of the dust hood are divided into fixed and mobile types. Among them, the advantages of the fixed dust hood are simple equipment, small capital investment, and good dust removal effect. It is often used for small and medium-sized production equipment, ventilation duct collection, convenient layout, and material output or output from the side. However, this fixed dust hood also has certain limitations. For example, in some metallurgical, chemical and other industries, when materials need to be loaded or lifted out from the top, this layout cannot meet the needs. At this time, a mobile dust hood is needed. That is, when the material needs to be loaded or lifted out from the top, the dust hood needs to be removed, and when production is required, the dust hood is moved above the production equipment. At this time, it is necessary to re-dock the mobile air duct and the fixed air duct of the dust removal system. In order to ensure the sealing performance after docking, it is often necessary to align and connect the ends of the two air ducts, which increases the difficulty of on-site construction.
[0004] After searching, the patent CN204265037U discloses a dust removal duct docking and disconnecting device for a mobile unloading vehicle. The application includes a preset fixed duct, a mobile duct of the unloading vehicle, a spring, a driving device, a bracket, flange one, and flange two. The preset fixed duct is docked with the mobile duct of the unloading vehicle; the upper end of the preset fixed duct is connected to the main duct, and the lower end is connected to flange one. The preset fixed duct is provided with an electric valve, and the flange one is provided with a soft rubber cushion pad; the upper end of the mobile duct of the unloading vehicle is connected to flange two, and the lower end is connected to the upper end of the telescopic sleeve, flange two is connected to a spring, and the lower end of the telescopic sleeve is connected to the dust hood, and flange two is provided with a soft rubber cushion pad; the dust hood is fixedly connected to the bracket arranged on the unloading vehicle. The application uses a soft rubber cushion pad to ensure the sealing during docking, prevent dust from overflowing, and prevent mechanical damage caused by hard connection.
[0005] For another example, the patent CN219221558U discloses a mechanical sealing device for connecting a mobile air duct. The application includes a fixed air duct, a sliding air duct slidably sleeved in the fixed air duct, a first pair of joints arranged at one end of the fixed air duct, the first pair of joints connected to the sliding air duct, a second pair of joints abutting the first pair of joints, a docking dust suction pipe arranged on the second pair of joints, the docking dust suction pipe connects the sliding air duct and the fixed air duct, and one end of a plurality of tightening devices arranged on the fixed air duct, the other end of the tightening device abuts the first pair of joints, and the tightening device is located on the side of the first pair of joints away from the second pair of joints. The application solves the problem in the prior art that the dust removal effect is poor because the gap at the splicing of the dust removal duct is too large and the sealing performance is too poor.
[0006] Although the above applications can ensure the sealing performance of the pipeline joints, they still require alignment and connection operations at the joints, which is not convenient for rapid construction work on site. Utility Model Content
[0007] 1. Problems to be solved
[0008] In view of the problem that existing mobile dust hoods need to be aligned and connected at the pipe joints, which makes on-site construction operations more complicated, the utility model provides a pipe docking structure, which can ensure the sealing performance of the docking point and simplify the connection operation of the docking point through the mutual cooperation of the installation gap and the sealing belt.
[0009] In addition, the utility model also provides a mobile dust removal system, which can make the construction operation at the pipeline joint more convenient and quick.
[0010] 2. Technical solution
[0011] In order to solve the above problems, the technical solution adopted by the utility model is as follows:
[0012] The utility model discloses a pipe docking structure, comprising a first connecting pipe and a second connecting pipe, wherein the ends of the two connecting pipes close to each other are respectively provided with a first docking port and a second docking port, an installation gap is left between the first docking port and the second docking port, and a sealing belt is provided at the installation gap;
[0013] When suction is performed to remove dust, negative pressure is generated at the installation gap, forcing the sealing belt to block the installation gap, thereby achieving a sealing effect on the gap.
[0014] Furthermore, there are multiple sealing belts, one end of which is formed into a shape matching the first docking interface, and the other end is formed into a shape matching the second docking interface; and one end of the sealing belt is arranged on one docking interface, and the other end is overlapped on the other docking interface.
[0015] Furthermore, the first pair of interfaces and the second pair of interfaces are both square interfaces.
[0016] Furthermore, two sealing belts are provided, each sealing belt is bent to form an L-shaped structure, and the two L-shaped sealing belts are respectively provided on different docking interfaces.
[0017] Furthermore, among two adjacent sealing belts, the width of one sealing belt is greater than the width of the other, so as to form an overlapping portion at the junction of the two sealing belts, and the overlapping portion can be tightly fitted on the other sealing belt under the action of negative pressure.
[0018] Furthermore, a stopper is provided at the edge of the first and second docking interfaces where no sealing belt is provided; during sealing, the free end of the sealing belt fits against the stopper.
[0019] Furthermore, the sealing belt is a rubber belt.
[0020] The utility model discloses a mobile dust removal system, comprising a dust removal hood, a mobile air duct and a fixed air duct; wherein one end of the mobile air duct is connected to the dust removal hood, and the mobile air duct and the fixed air duct are connected via the above-mentioned pipe docking structure; wherein the mobile air duct is connected to a first connecting pipe, and the fixed air duct is connected to a second connecting pipe.
[0021] Furthermore, the dust removal hood is connected to a horizontal moving mechanism, and the first connecting pipe is driven by the moving mechanism to move from one side of the second connecting pipe to its end surface.
[0022] Furthermore, the vertical sections of the L-shaped sealing belts on the two docking interfaces are arranged away from each other.
[0023] 3. Beneficial effects
[0024] Compared with the prior art, the beneficial effects of the utility model are:
[0025] (1) The utility model provides a pipe docking structure, in which an installation gap is left at the docking interface of two connecting pipes. By setting the installation gap, the two connecting pipes do not need to be directly connected, thereby simplifying the assembly operation between the two connecting pipes; at the same time, a sealing belt is provided at the installation gap. When air is sucked to remove dust, negative pressure is generated at the installation gap, forcing the sealing belt to block the installation gap, thereby achieving a good sealing effect.
[0026] (2) The utility model provides a pipe docking structure, in which one end of the sealing tape is fixedly arranged on a docking interface, which can effectively prevent it from being sucked into the pipe; the other end is a free end overlapped on another docking interface, and can be tightly attached to the outer wall of the interface through negative pressure adsorption, thereby achieving a sealing effect.
[0027] (3) The utility model provides a pipe docking structure, in which the first pair of interfaces and the second pair of interfaces are both square interfaces. Compared with the traditional circular interfaces, the docking operation of the directional interfaces is more convenient; at the same time, an overlapping portion is formed at the junction of adjacent sealing strips, and the overlapping portion can be tightly fitted on the other sealing strip under the action of negative pressure to form surface contact, thereby improving the sealing effect.
[0028] (4) The utility model provides a mobile dust removal system, which ensures the sealing effect by means of the mutual cooperation between the installation gap and the sealing belt, while making the construction operation at the pipe joint more convenient and quick, which is conducive to the rapid construction work on site; at the same time, the dust removal system has a simple structure and low cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a structural schematic diagram of a mobile dust removal system of the utility model;
[0030] Figure 2 This is a connection diagram of the first connecting pipe in the utility model;
[0031] Figure 3 This is a schematic diagram of the structure of the first pair of interfaces in the utility model;
[0032] Figure 4 This is a connection diagram of the second connecting pipe in the utility model;
[0033] Figure 5 This is a schematic diagram of the structure of the second pair of interfaces in the utility model;
[0034] Figure 6 It is a schematic diagram of the structure after two docking ports in the utility model are docked.
[0035] In the figure: 1, first connecting pipe; 11, first pair of interfaces; 2, second connecting pipe; 21, second pair of interfaces;
[0036] 3. Sealing tape; 31. Overlapping portion; 4. Stopper; 5. Movable air duct; 6. Fixed air duct. DETAILED DESCRIPTION
[0037] In order to further understand the content of the utility model, the utility model is described in detail in conjunction with the accompanying drawings.
[0038] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0039] The utility model is further described below in conjunction with specific embodiments.
[0040] refer to Figure 1 As shown, a mobile dust removal system of this embodiment includes a mobile air duct 5 and a fixed air duct 6. One end of the mobile air duct 5 is connected to a dust removal cover (not shown in the figure), and the other end is sealed and connected to the fixed air duct 6 through a pipe docking structure.
[0041] At the same time, the mobile air duct 5 needs to be equipped with a horizontal moving mechanism (not shown in the figure), which drives the dust cover and the mobile air duct 5 thereon to move horizontally, that is, to move from the side of the fixed air duct 6, thereby completing the sealed connection between the mobile air duct 5 and the fixed air duct 6.
[0042] It is worth mentioning that the above-mentioned moving mechanism and dust cover are both existing structures. At the same time, the above-mentioned lateral movement refers to the movement perpendicular to Figure 1 Direction of the paper.
[0043] In this embodiment, as a specific implementation of the pipeline docking structure, the pipeline docking structure includes a first connecting pipe 1 and a second connecting pipe 2. One end of the first connecting pipe 1 is used to connect to the mobile air duct 5, and the other end is provided with a first docking port 11; one end of the second connecting pipe 2 is used to connect to the fixed air duct 6, and the other end is provided with a second docking port 21.
[0044] The first docking interface 11 and the second docking interface 21 are arranged front and back, and when the two docking interfaces are moved to an aligned state, an installation gap is left between the two docking interfaces. At the same time, in order to ensure the sealing performance at the two interfaces, a sealing belt 3 is provided at the installation gap. Among them, there are multiple sealing belts 3, one end of the multiple sealing belts 3 is surrounded by a shape matching the first docking interface 11, and the other end is surrounded by a shape matching the second docking interface 21. And one end of the sealing belt 3 is fixedly set on one docking interface, and the other end is overlapped on the other docking interface. Under the action of the negative pressure generated at the installation gap, the sealing belt 3 seals the installation gap.
[0045] In the mobile dust removal system of this embodiment, a pipe docking structure is provided so that an installation gap is left between the two pipes, and strict corresponding operation is not required, thereby facilitating the docking operation between the two pipes. At the same time, through the provision of a sealing belt, when air suction and dust removal are performed, negative pressure is generated at the installation gap, forcing the sealing belt to block the installation gap, thereby achieving a good sealing effect.
[0046] In this embodiment, as an implementation method of the sealing method at the docking interface, the first docking interface 11 and the second docking interface 21 are both square interfaces. At the same time, two sealing strips 3 are provided, each sealing strip 3 is bent to form an L-shaped structure, and the two L-shaped sealing strips 3 are respectively provided on different docking interfaces.
[0047] For the convenience of description, the sealing belt 3 on the first docking port 11 is called the first sealing belt, and the sealing belt 3 on the second docking port 21 is called the second sealing belt. The side of the sealing belt connected to the docking port is the fixed end, the side overlapping the docking port is the free end, and the other two sides are the side ends.
[0048] Specifically, refer to Figure 2 , Figure 3 As shown, the horizontal section of the L-shaped first sealing strip is arranged at the bottom of the first docking port 11, and the vertical section thereof is arranged at one side of the first docking port 11 ( Figure 3 The fixed ends of the first sealing tape are fixed to the corresponding sides of the first docking port 11 by clamps.
[0049] refer to Figure 4 , Figure 5 As shown, the horizontal section of the L-shaped second sealing tape is arranged on the top of the second docking port 21, and the vertical section thereof is arranged on the other side of the second docking port 21 ( Figure 5 The fixed ends of the second sealing tape are fixed to the corresponding sides of the second docking port 21 by clamps.
[0050] It should be noted that the vertical sections of the L-shaped sealing tapes 3 on the two docking ports are arranged away from each other to prevent the sealing tape 3 on the second docking port 21 from hindering the movement of the sealing tape 3 on the first docking port 11 .
[0051] In this embodiment, the square interface is more convenient to connect than the traditional circular interface. At the same time, with the arrangement of the two L-shaped sealing strips 3, only two junctions are formed between the end sides of the entire sealing strip 3, which is conducive to ensuring the sealing effect at the installation gap.
[0052] In order to improve the sealing effect of the end of the sealing belt 3, a stopper 4 is provided at the edge of the first and second docking ports 11 and 21 where the sealing belt 3 is not provided. During sealing, the free end of the sealing belt 3 fits against the stopper 4 to form a surface contact, thereby ensuring the sealing effect.
[0053] In addition, in order to ensure the sealing effect of the two sealing strips 3 at the contact point of the side ends, in this embodiment, the width of one of the side ends of the two adjacent sealing strips 3 is greater than the width of the other, so as to form an overlap portion 31 at the junction of the two. The overlap portion 31 can be tightly attached to the other sealing strip 3 under the action of negative pressure to form a surface contact, thereby improving the sealing effect at this point.
[0054] Specifically in this embodiment, refer to Figure 3 , Figure 5 , Figure 6 As shown, the width of the horizontal section and the vertical section of the first sealing belt is consistent with the length of the corresponding side of the butt joint. The width of the horizontal section and the vertical section of the second sealing belt is longer than the length of the corresponding side of the butt joint. In other words, when the two sealing belts 3 are butt jointed with each other, the two side ends of the first sealing belt are respectively located inside the horizontal section and the vertical section of the second sealing belt, and the side ends of the horizontal section and the vertical section of the second sealing belt extend out of the junction between the two.
[0055] It should be noted that the width of the horizontal section and the vertical section refers to the length of the sealing tape 3 extending along the corresponding side of the butt joint. In other words, the ends of the horizontal section and the vertical section of the second sealing tape extend out of their respective butt joints, and the extended section is the overlapped portion 31 mentioned above.
[0056] At the same time, in order to enable the overlapping portion 31 to be bent after being adsorbed so as to overlap the side wall of another sealing belt 3, the overlapping portion 31 is a free extension of the end of the sealing belt and is not fixed by other components.
[0057] This embodiment also provides a pipeline docking method, which includes the following steps:
[0058] The first connecting pipe 1 and the second connecting pipe 2 are arranged front and back, and when the two connecting pipes are moved to the aligned position, a gap is left between the two docking ports;
[0059] The first docking port 11 moves from one side of the second docking port 21 to the end of the second docking port 21; at this time, the free end of the first sealing belt overlaps the second docking port 21, and the free end of the second sealing belt overlaps the first docking port 11; the side end of the horizontal section of the first sealing belt abuts against the inner wall of the vertical section of the second sealing belt, and the side end of the second sealing vertical section extends outward to form an overlap portion 31; the side end of the vertical section of the first sealing belt abuts against the inner wall of the horizontal section of the second sealing belt, and the side end of the second sealing horizontal section also extends outward to form an overlap portion 31;
[0060] During dust removal by suction, negative pressure is generated in the gap, so that the free end of the sealing belt 3 is tightly attached to the outer wall of the corresponding interface; at the same time, the overlapping part 31 is tightly attached to the side wall of the corresponding sealing belt 3 to complete the sealed connection in the two pipes.
[0061] The above schematically describes the present invention and its implementation methods, which are not restrictive. The drawings show only one implementation method of the present invention, and the actual structure is not limited thereto. Therefore, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the present invention, they should all fall within the protection scope of the present invention.
Claims
1. A pipe docking structure, comprising a first connecting pipe (1) and a second connecting pipe (2), wherein the ends of the two connecting pipes close to each other are respectively provided with a first docking port (11) and a second docking port (21), characterized in that: An installation gap is left between the first pair of interfaces (11) and the second pair of interfaces (21), and a sealing belt (3) is provided at the installation gap; When the air is sucked to remove dust, negative pressure is generated at the installation gap, forcing the sealing belt (3) to block the installation gap, thereby achieving a sealing effect on the gap.
2. A pipe docking structure according to claim 1, characterized in that: The sealing belts (3) are provided in plurality, one end of the plurality of sealing belts (3) is surrounded into a shape matching the first docking interface (11), and the other end is surrounded into a shape matching the second docking interface (21); and one end of the sealing belt (3) is provided on one docking interface, and the other end is overlapped on the other docking interface.
3. A pipe docking structure according to claim 2, characterized in that: The first pair of interfaces (11) and the second pair of interfaces (21) are both square interfaces.
4. A pipe docking structure according to claim 3, characterized in that: Two sealing belts (3) are provided, each sealing belt (3) is bent to form an L-shaped structure, and the two L-shaped sealing belts (3) are respectively arranged on different docking interfaces.
5. A pipe docking structure according to claim 4, characterized in that: Among two adjacent sealing belts (3), the width of one sealing belt (3) is greater than the width of the other, so as to form an overlapping portion (31) at the junction of the two, and the overlapping portion (31) can be tightly fitted on the other sealing belt (3) under the action of negative pressure.
6. A pipe docking structure according to any one of claims 1 to 5, characterized in that: A stopper (4) is provided at the edge of the first mating interface (11) and the second mating interface (21) where the sealing belt (3) is not provided; during sealing, the free end of the sealing belt (3) fits against the stopper (4).
7. A pipe docking structure according to claim 6, characterized in that: The sealing belt (3) is a rubber belt.
8. A mobile dust removal system, comprising a dust removal hood, a mobile air duct (5) and a fixed air duct (6); wherein: One end of the movable air duct (5) is connected to the dust hood, and is characterized in that: the movable air duct (5) and the fixed air duct (6) are connected via a pipe docking structure according to any one of claims 1 to 7; wherein the movable air duct (5) is connected to the first connecting pipe (1), and the fixed air duct (6) is connected to the second connecting pipe (2).
9. A mobile dust removal system according to claim 8, characterized in that: The dust removal hood is connected to a horizontal moving mechanism, and the first connecting pipe (1) is driven by the moving mechanism to move from one side of the second connecting pipe (2) to its end surface.
10. The mobile dust removal system according to claim 8, characterized in that: The vertical sections of the L-shaped sealing belts (3) on the two butting interfaces are arranged away from each other.
Citation Information
Cited By
Pipeline butt joint structure, butt joint mode and movable dust removal system
CN118564748A