Liquid chromatography system and control system
The control method for liquid chromatography systems dynamically adjusts flow rates during idle periods to minimize pump damage and consumption, ensuring efficient operation by aligning flow rate changes with equilibration times, thus addressing the challenges of idle periods in multi-stream systems.
Patent Information
- Application Number
- PCT/JP2024/010997
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-04-17
- Filing Date
- 2024-03-21
- Publication Date
- 2024-10-24
AI Technical Summary
Liquid chromatography systems with multiple streams face challenges in reducing pump damage and mobile phase consumption during idle periods without compromising analysis efficiency, as continuous flow is necessary to prevent pump damage but increases consumption, and lowering flow rates during idle periods prolongs analysis restart times.
A control method that adjusts the mobile phase flow rate to a lower rate during idle periods and determines whether to revert to the original flow rate based on the equilibration time, allowing for flow rate reduction without delaying analysis start times, thus minimizing pump damage and mobile phase consumption.
This approach effectively reduces pump damage and mobile phase consumption while maintaining analysis efficiency by dynamically controlling flow rates based on idle periods and equilibration times, optimizing system performance during both analysis and idle phases.
Smart Images

Figure JP2024010997_24102024_PF_FP_ABST
Abstract
Description
Liquid chromatograph system and control system
[0001] The present disclosure relates to a liquid chromatography system having multiple streams and a control method for controlling the liquid chromatography system.
[0002] Liquid chromatography is a technique for separating components contained in a sample by introducing the sample to be analyzed into a column together with an eluent, which is a mobile phase. The components of the sample separated by liquid chromatography are then analyzed using a detector such as a mass spectrometer.
[0003] International Publication No. 2017 / 216934 (Patent Document 1), "Nexera QX," and Shimadzu Corporation (Non-Patent Document 1) disclose liquid chromatographic systems that include a plurality of liquid chromatographic analytical systems (hereinafter referred to as "streams"), an injection device that injects a sample into each of the plurality of streams, a detector, and a valve that selectively connects one of the plurality of streams to the detector.
[0004] International Publication No. 2017 / 216934
[0005] "Nexera QX", [online], [searched December 14, 2022], Shimadzu Corporation, Internet <URL: https: / / www.ssi.shimadzu.com / products / liquid-chromatography-mass-spectrometry / ultrafast-multiplex-lcms-nexera-qx.html>
[0006] The liquid chromatograph systems described in Patent Document 1 and Non-Patent Document 1 can improve analytical efficiency by using multiple streams to perform parallel sample separation and continuous mass analysis. However, such liquid chromatograph systems may experience idle periods during which no analysis is being performed in any of the streams.
[0007] Although there is no need to flow the mobile phase during idle periods, it is preferable to keep the mobile phase flowing at all times to avoid damage to the pump, etc. However, if the mobile phase continues to flow at the same flow rate as during analysis, there is a problem in that a large amount of mobile phase is consumed.
[0008] One method is to reduce the flow rate during idle periods, but if the flow rate is reduced, it will be necessary to increase the flow rate again when starting analysis. However, if the flow rate is increased, it is preferable to increase the flow rate in stages to prevent damage to the pump, which results in the problem of taking time to restart analysis.
[0009] An object of the present disclosure is to reduce pump damage and mobile phase consumption in a liquid chromatography system having multiple streams without reducing analytical efficiency.
[0010] The liquid chromatography system disclosed herein includes multiple streams for separating components contained in a sample, multiple pumps that supply a mobile phase to each of the multiple streams, and a control device that controls each device to perform parallel separation of the components in the sample using each of the multiple streams. The control device is capable of controlling each device so that multiple analyses are performed in a first stream of the multiple streams at a first flow rate, with one analysis being defined as the period from when a sample is injected into a stream until the stream becomes ready to accept the next sample. The control device is capable of controlling, for each of the multiple streams, a pump that supplies mobile phase to the stream so that the flow rate of the mobile phase supplied to the stream is a second flow rate that is lower than the first flow rate during an idle period in which no analysis is being performed. The control device controls a first pump that supplies mobile phase to the first stream to change from the first flow rate to the second flow rate when a first idle period between a first analysis of multiple analyses performed in the first stream and a second analysis performed after the first analysis is longer than the equilibration time from when switching from the second flow rate to the first flow rate begins to when the first flow rate becomes the first flow rate, and controls the first pump to maintain the first flow rate without changing to the second flow rate when the first idle period is shorter than the equilibration time.
[0011] A control method disclosed herein is a method for controlling a liquid chromatograph system. The liquid chromatograph system includes a plurality of streams for separating components contained in a sample and a plurality of pumps for supplying a mobile phase to each of the plurality of streams. The control method includes the steps of controlling each apparatus to perform separation of the components in the sample in parallel using each of the plurality of streams; controlling each apparatus to perform multiple analyses in a first stream of the plurality of streams at a first flow rate, with one analysis being defined as a period from when a sample is injected into a stream until the stream is ready to inject a next sample; and controlling a pump that supplies a mobile phase to each of the plurality of streams during an idle period in which no analysis is being performed, so that the flow rate of the mobile phase supplied to the stream is a second flow rate that is lower than the first flow rate. determining whether a first idle period between a first analysis and a second analysis performed after the first analysis among a plurality of analyses performed in the first stream will be longer than an equilibration time required from when switching from the second flow rate to the first flow rate begins until the first flow rate is reached; controlling a first pump that supplies mobile phase to the first stream to change the flow rate from the first flow rate to the second flow rate when it is determined that the first idle period will be longer than the equilibration time; and controlling the first pump to maintain the first flow rate without changing to the second flow rate when it is determined that the first idle period will be shorter than the equilibration time.
[0012] According to the present disclosure, the first pump is controlled during a first idle period between a first analysis and a second analysis depending on whether the first idle period is longer than the equilibration time, and therefore, if the flow rate can be reduced without delaying the start timing of the second analysis, the flow rate can be reduced, thereby reducing pump damage and mobile phase consumption without reducing analytical efficiency.
[0013] FIG. 1 is a schematic diagram of an LC system. FIG. 2 is a schematic diagram of a stream. FIG. 3 is an example of a setting screen for setting an idle flow rate and an equilibration time. FIG. 4 is a timing chart showing an example of an analysis schedule and pump control. FIG. 5 is a timing chart showing an example of an analysis schedule and pump control when the analysis schedule is changed from the analysis schedule shown in FIG. 4. FIG. 6 is a flowchart showing an example of processing executed by a processor 182. FIG. 7 is a flowchart showing processing according to a modified example. FIG. 8 is an example of a setting screen for accepting a change in the number of streams.
[0014] Hereinafter, embodiments of the present disclosure will be described in detail with reference to the drawings. In the drawings, the same or corresponding parts are designated by the same reference numerals, and description thereof will not be repeated.
[0015] [Overall System Configuration] The schematic configuration of a liquid chromatography system (hereinafter referred to as an LC (Liquid Chromatography) system) in which the setting of analysis conditions is assisted by the assistance device according to this embodiment will be described with reference to Fig. 1. Fig. 1 is a schematic configuration diagram of the LC system.
[0016] The LC system 1 separates and analyzes components contained in a sample. The LC system 1 includes a sample injector 10, multiple streams 12A to 12D, a divert valve 14, and a detector 16. In the following description, when there is no need to distinguish between the streams 12A to 12D, they will be referred to as "streams 12."
[0017] The sample injection device 10 injects a sample into each of the multiple streams 12A to 12D. The sample injection device 10 is, for example, an autosampler, and includes a sample plate capable of accommodating one or more samples and a needle, both of which are not shown. The sample injection device 10 typically includes multiple sample plates. The needle aspirates the sample from the sample plate and injects the aspirated sample into a predetermined stream 12 according to set analysis conditions.
[0018] The stream 12 is an analytical flow path provided for separating components contained in a sample, and a mobile phase flows through it. Each of the streams 12A to 12D is connected to a detector 16 via a divert valve 14.
[0019] The diverter valve 14 includes ports 141 to 146. The streams 12A to 12D are connected to the ports 141 to 144, respectively. The detector 16 is connected to the port 145. A drain pipe (not shown) is connected to the port 146. The diverter valve 14 fluidly connects one of the streams 12A to 12D to the detector 16 by switching the connection destinations of the ports 141 to 144 between the port 145 and the port 146, respectively.
[0020] Detector 16 is disposed downstream of streams 12A-12D and analyzes the components separated by passing through each of streams 12A-12D. In one embodiment, detector 16 is a mass spectrometer. However, detector 16 is not limited to a mass spectrometer and may be an absorbance detector, a fluorescence detector, a differential refractive index detector, an electrical conductivity detector, an evaporative light scattering detector, or the like, without any particular limitation.
[0021] The control device 18 includes a processor 182 and a memory 184. The processor 182 is, for example, a CPU, which is an arithmetic circuit that executes predetermined arithmetic processing described in a program. The memory 184 includes non-volatile or volatile memory such as a read-only memory (ROM) or a random access memory (RAM), and / or a large-capacity storage device such as a hard disk drive (HDD) or a solid state drive (SSD). The processor 182 reads the programs and data stored in the memory 184 to control the sample injection device 10, the pump, valves and mixers included in the stream 12, the divert valve 14, and the detector 16 that constitute the LC system 1, and executes predetermined processing based on the detection results from the detector 16 and the operating status of each device.
[0022] An input device 171 and a display device 172 are connected to the control device 18. The input device 171 is, for example, a keyboard, a mouse, a pointing device, a touch panel, or the like, and accepts user operations. The display device 172 is, for example, a liquid crystal display (LCD) or an organic electroluminescence (EL) display. The control device 18 accepts user operations accepted via the input device 171. The control device 18 also outputs a video signal to the display device 172. The display device 172 displays an image corresponding to the video signal output from the control device 18.
[0023] As described above, in the LC system 1, multiple streams 12A to 12D are connected in parallel and connected to the detector 16 via the divert valve 14, so that separation of components in a sample can be performed in parallel using each of the streams 12A to 12D.
[0024] 2 is a schematic diagram of the stream. Stream 12 includes a supply device 126, a valve 124, and a column 122. A mobile phase is sent from supply device 126 to column 122, and the mobile phase passes through column 122 and is sent to divert valve 14.
[0025] The supply device 126 supplies the mobile phase flowing in the stream 12. The supply device 126 includes a plurality of solvent containers S1 and S2, a mixer 261, and a mobile phase pump 262.
[0026] The plurality of solvent containers S1, S2 contain solvents. The types of solvents contained in the solvent containers S1, S2 may be different from each other or may be the same. In this embodiment, the description will be given assuming that the types of solvents contained in the solvent containers S1, S2 are different from each other.
[0027] The mixer 261 mixes the solvents supplied from the solvent containers S1 and S2 at a predetermined ratio. The mixed solution mixed by the mixer 261 is sent as a mobile phase to the column 122 by a mobile phase pump 262. Note that the predetermined ratio includes 0:100. The mixing ratio may be set to be constant during the analysis of the sample, or may be set to change over time during the analysis.
[0028] The mobile phase pump 262 sends the mixed liquid obtained by the mixer 261 as a mobile phase toward the valve 124 .
[0029] The valve 124 switches the flow path connected to the supply device 126 between a flow path that passes through the sample injection device 10 and is connected to the column 122, and a flow path that is connected to the column 122 without passing through the sample injection device 10. If the flow path in which the supply device 126, the sample injection device 10, and the column 122 are connected in series in this order is called the "injection flow path," and the flow path in which the supply device 126 and the column 122 are connected in series in this order without passing through the sample injection device 10 is called the "direct flow path," then it can be said that the valve 124 switches between the injection flow path and the direct flow path.
[0030] The column 122 separates the components contained in the sample injected from the sample injection device 10. The column 122 is filled with a stationary phase for separating the components contained in the sample.
[0031] As described above, the stream 12 is configured to separate components contained in the sample injected from the sample injection device 10 .
[0032] 2 is merely an example and is not particularly limited. For example, the stream 12 may further include a flow path for delivering a cleaning solution. Alternatively, the stream 12 may be configured to include one solvent container and deliver only one type of solvent, without including the mixer 261.
[0033] The streams 12A to 12D may have the same structure or may have different structures, but in this embodiment, the streams 12A to 12D will be described as having the same structure.
[0034] In addition, even if the configurations of the streams 12A to 12D are different from each other, all of the streams 12A to 12D are configured to be switchable between a direct connection flow path and an injection flow path, and only need to be equipped with a supply device 126 and at least one column 122.
[0035] The configurations of the supply devices 126 included in the streams 12A to 12D may be different from each other or may be the same. By configuring the supply devices 126 to be different from each other, the type of mobile phase can be changed. Furthermore, by configuring the types of mobile phase pumps 262 included in the supply devices 126 to be different from each other, the settable range of flow rates and the type of usable column 122 can be changed for each stream 12. Furthermore, the types and / or numbers of the columns 122 included in the streams 12A to 12D may be different. Furthermore, the streams 12A to 12D may further include a column oven for maintaining the temperature of the column 122.
[0036] [Flow Rate Control During Idle Periods] As described above, the LC system 1 can perform parallel separation of components in a sample using each of the streams 12A to 12D by connecting multiple streams 12A to 12D in parallel and connecting them to the detector 16. For example, the LC system 1 can perform parallel separation of components in a sample using each of the streams 12A to 12D by staggering the timing of sample injection into the streams 12A to 12D, while switching the stream 12 connected to the detector 16 to continuously detect the components separated by the streams 12A to 12D, thereby improving analysis efficiency.
[0037] In the LC system 1, analysis efficiency can be further improved by designing analysis conditions so as to shorten idle periods during which no analysis is being performed in each stream 12. In this embodiment, the term "idle period" includes the period from the end of one analysis in one stream 12 to the execution of the next analysis. In this embodiment, the term "one analysis in one stream 12" refers to the period from the injection of a sample into one stream 12 to the time when the stream 12 is ready to inject the next sample.
[0038] During the idle period, it is not necessary to flow the mobile phase, but it is preferable to keep the mobile phase flowing at all times to avoid damage to the pump. a If the mobile phase continues to flow at the analysis flow rate F during the idle period, the amount of mobile phase consumed will increase. a Idle flow rate F i The pump is controlled so that the mobile phase consumption can be reduced.
[0039] Furthermore, when increasing the flow rate, the control device 18 controls the pump so that the flow rate is increased in stages to prevent damage to the pump. i to analysis flow rate F a When the flow rate is increased to restart the analysis, it is preferable to provide an equilibration time so that the flow rate is increased stepwise. i to analysis flow rate F a After starting the switch to the analysis flow rate F a This is the time it takes for the
[0040] However, if the equilibration time is longer than the idle period, the analysis flow rate F a From idle flow rate F i If the flow rate is reduced to 0.5, it will take longer to resume the next analysis than if the flow rate were not reduced, since an equilibration time must be provided before the next analysis can be resumed.
[0041] The control device 18 according to the present embodiment adjusts the flow rate to the analysis flow rate F during analysis depending on whether the idle period is longer or shorter than the equilibration time. a This prevents the analysis start timing from being delayed and suppresses a decrease in analysis efficiency.
[0042] In addition, the idle flow rate F i The idle flow rate and the equilibration time can be set arbitrarily by the user. Fig. 3 shows an example of a setting screen for the idle flow rate and the equilibration time. A screen 400 is displayed on the display device 172. The screen 400 includes an input field 401 for the idle flow rate, an input field 402 for the equilibration time, an OK button 403, and a cancel button 404.
[0043] The user can input a predetermined numerical value into the input field 401 and / or the input field 402 via the input device 171. When the numerical value is input into the input field 401 and the input field 402 and the OK button 403 is operated, the processor 182 sets the idle flow rate F i and equilibration time.
[0044] [Timing Chart] Fig. 4 is a timing chart showing an analysis schedule and an example of pump control. In Fig. 4, the analysis schedule is shown in the upper part for each stream, and an example of pump control is shown in the lower part.
[0045] In stream 1, multiple analyses are performed. Specifically, in the period T from 0 to timing t3 a1 Analysis 1 is performed during the period T a5 Analysis 5 is performed on stream 1 during the period T from timing t3 to timing t10. i4 The period from timing t12 onwards is an idle period.
[0046] The control device 18 i4 is the equilibration time T e Since the flow rate is longer than the analysis flow rate F a From idle flow rate F iThe control device 18 controls the pump 1 of the stream 1 to reduce the idle flow rate F to 0 at time t7 so that the switching is completed by time t10 when the analysis 5 can be started. i to analysis flow rate F a After timing t12 when no analysis is performed, the control device 18 controls the pump 1 so that the flow rate is switched to the analysis flow rate F a From idle flow rate F i Pump 1 of stream 1 is controlled to lower the pressure to
[0047] In stream 2, the period T from timing t2 to timing t6 a2 Analysis 2 is performed during the period T from timing t0 to timing t2. i1 The period from timing t6 onwards is an idle period. i1 is the equilibration time T e Since the flow rate is shorter than the idle flow rate F i Instead, the analytical flow rate F a After timing t6 when no analysis is performed, the control device 18 controls the flow rate to the analysis flow rate F a From idle flow rate F i Pump 1 of stream 1 is controlled to lower the pressure to
[0048] In stream 3, the period T from timing t5 to timing t9 a3 Analysis 3 is performed during the period T from timing t0 to timing t5. i2 The period from timing t9 onwards is an idle period. i2 is the equilibration time T e Since the flow rate is longer than the idle flow rate F i The control device 18 controls the pump 3 of the stream 3 so that the analysis flow rate F a At timing t1, the idle flow rate F i to analysis flow rate F a After timing t9 when no analysis is performed, the control device 18 controls the pump 3 to start switching the flow rate to the analysis flow rate F a From idle flow rate Fi Pump 3 of stream 3 is controlled to lower the pressure to
[0049] In stream 4, the period T from timing t8 to timing t11 a4 Analysis 4 is performed during the period T from timing t0 to timing t8. i3 The period from timing t11 onwards is an idle period. i3 is the equilibration time T e Since the flow rate is longer than the idle flow rate F i The control device 18 controls the pump 4 of the stream 4 so that the analysis flow rate F a At timing t4, the idle flow rate F i to analysis flow rate F a After timing t11 when no analysis is performed, the control device 18 controls the pump 4 to start switching the flow rate to the analysis flow rate F a From idle flow rate F i Pump 4 of stream 4 is controlled to lower the pressure to
[0050] As described above, the controller 18 adjusts the flow rate to the analysis flow rate F depending on whether the idle period is longer or shorter than the equilibration time. a The system determines whether to lower the pressure from the starting point and controls each pump accordingly, thereby reducing pump damage and mobile phase consumption without reducing analytical efficiency.
[0051] [Timing chart when the analysis schedule is changed] The control device 18 can change the analysis schedule so that an analysis scheduled to be performed in one stream is executed in another stream. For example, if the control device 18 determines that one stream cannot be used, the control device 18 changes the analysis schedule so that the analysis scheduled to be performed in the one stream is executed in another stream. Furthermore, the control device 18 accepts a change in the number of streams to be used via the input device 171, and if the number of available streams decreases, changes the analysis schedule so that the analysis scheduled to be performed in one stream is executed in another analysis.
[0052] If the analysis schedule is changed so that an analysis that was scheduled to be performed in one stream is performed in another stream, the number of analyses performed in one stream will increase and the idle period will also decrease, so the control device 18 may change the control of the pump in accordance with the shortened idle period.
[0053] Figure 5 is a timing chart showing an example of the analysis schedule and pump control when the analysis schedule is changed from that shown in Figure 4. In the example shown in Figure 4, the control device 18 changes the analysis schedule so that analyses 3 and 4, which were scheduled to be performed in streams 3 and 4 among streams 1 to 4 to be used, are instead performed in stream 1 or 2.
[0054] The control device 18 changes the analysis schedule so that analysis 3, which was scheduled to be performed in stream 3, is now performed in stream 1, and analysis 4, which was scheduled to be performed in stream 4, is now performed in stream 2.
[0055] Analysis 3 is the period T from timing t5 to timing t9 between Analysis 1 and Analysis 5. a3 The analysis schedule is set so that analysis 3 is executed in stream 1 between analysis 1 and analysis 5. By changing the analysis schedule so that analysis 3 is executed between analysis 1 and analysis 5, the idle period is extended to period T i4 From period T i4-1 and period T i4-2 The period T i4-1 and period T i4-2 In both cases, the equilibration time T e Since the flow rate is shorter than the analysis flow rate F a From idle flow rate F i without changing the analytical flow rate F a Pump 1 of stream 1 is controlled so that:
[0056] Before the analysis schedule is changed, the control device 18 temporarily sets the flow rate to the analysis flow rate F a From idle flow rate F i After the flow rate is reduced to , at timing t10, the flow rate reaches the analysis flow rate F aAfter the analysis schedule is changed, the control device 18 controls the pump 1 so that the flow rate does not change between timing t3 and timing t10.
[0057] Analysis 4 is the period T from timing t8 to timing t11 after analysis 2. a4 The analysis is scheduled to be performed in stream 2 at 10:00. The period T i3 The period T i3 ' is the equilibration time T e Since the flow rate is shorter than the analysis flow rate F a From idle flow rate F i without changing the analytical flow rate F a Pump 2 of stream 2 is controlled so that:
[0058] The analysis schedule change causes the controller 18 to adjust the flow rate in stream 2 to the analysis flow rate F a From idle flow rate F i The timing of changing the setting is delayed from timing t6 to timing t11.
[0059] As described above, if the analysis schedule is changed so that an analysis that was scheduled to be performed in one stream is performed in another stream, the number of analyses performed in one stream increases and the idle period also becomes shorter. Therefore, the control device 18 also changes the control of the pump in accordance with the shortened idle period.
[0060] [Flowchart] Fig. 6 is a flowchart showing an example of processing executed by processor 182. Processor 182 executes the processing shown in Fig. 5 by reading and executing a program stored in memory 184. Processor 182 executes the processing shown in Fig. 6 at a predetermined cycle.
[0061] In S100, the processor 182 determines whether one analysis has been completed. Whether one analysis has been completed is determined, for example, based on whether a predetermined analysis period has elapsed since the sample was injected by the sample injection device 10.
[0062] If it is determined that one analysis has not been completed (NO in S100), the processor 182 ends the process. If it is determined that one analysis has been completed (YES in S100), the processor 182 proceeds to S102.
[0063] In S102, the processor 182 determines whether the idle period is longer than the balancing time. More specifically, for a stream whose analysis was determined to have ended in S100, the processor 182 calculates the time (idle period) until the start of the next analysis, and determines whether the calculated idle period is longer than the predetermined balancing time.
[0064] If it is determined that the idle period is not longer than the equilibration time (NO in S102), the processor 182 ends the process without changing the flow rate, i.e., leaving the flow rate at the analysis flow rate.
[0065] If it is determined that the idle period is longer than the equilibration time (YES in S102), the processor 182 sets the flow rate to the idle flow rate and ends the process.
[0066] As described above, the processor 182 determines whether or not to set the flow rate to the idle flow rate each time an analysis is completed.
[0067] The processor 182 may set the flow rate in advance in accordance with the analysis schedule. An example of the processing executed by the processor 182 in such a case will be described with reference to FIG. 7. FIG. 7 is a flowchart showing processing according to a modified example. The processor 182 executes the processing shown in FIG. 7 by reading and executing a program stored in the memory 184. The processor 182 executes the processing shown in FIG. 7 at a predetermined cycle.
[0068] In S100A, the processor 182 determines whether the number of available streams has changed. As described above, when the processor 182 determines that one stream cannot be used or when the processor 182 receives a change in the number of streams to be used via the input device 171, the processor 182 determines that the number of available streams has changed.
[0069] A change to the number of streams is accepted, for example, via the setting screen shown in Fig. 8. Fig. 8 is an example of a setting screen for accepting a change to the number of streams. Screen 500 is displayed on display device 172. Screen 500 includes an input field 501 for the number of streams, an OK button 502, and a cancel button 503. The user inputs the number of streams they wish to use in input field 501 via input device 171. The input field corresponds to a reception unit that accepts a change to the number of streams. When a numerical value is entered in input field 501 and OK button 502 is operated, processor 182 accepts the change to the number of streams.
[0070] 7, if it is determined that the number of available streams has not changed (NO in S100A), the processor 182 ends the process. If it is determined that the number of available streams has changed (YES in S100A), the processor 182 proceeds to S102A.
[0071] In S102A, the processor 182 changes the analysis schedule in accordance with the changed number of streams. For example, if the number of available streams is reduced, the processor 182 changes the analysis schedule so that an analysis scheduled to be performed on one stream is performed on another stream.
[0072] In S104A, the processor 182 resets the flow rate of the mobile phase in accordance with the changed analysis schedule.
[0073] The processor 182 controls the pumps included in each stream so that the flow rates of the mobile phases are set to the values reset in S104A.
[0074] As described above, even when the flow rate control method is set in advance in accordance with the analysis schedule, the processor 182 changes the flow rate control method in response to changes in the analysis schedule.
[0075] [Aspects] It will be understood by those skilled in the art that the above-described embodiments and modifications are specific examples of the following aspects.
[0076] (Item 1) A liquid chromatograph system according to one aspect includes multiple streams for separating components contained in a sample, multiple pumps that supply a mobile phase to each of the multiple streams, and a control device that controls each device to perform parallel separation of the components in the sample using each of the multiple streams. The control device is capable of controlling each device so that multiple analyses are performed in a first stream of the multiple streams at a first flow rate, with one analysis being defined as the period from when a sample is injected into a stream until the stream becomes ready to accept the next sample. The control device is capable of controlling a pump that supplies mobile phase to each of the multiple streams during an idle period in which no analysis is being performed, so that the flow rate of the mobile phase supplied to that stream is a second flow rate that is lower than the first flow rate. The control device controls a first pump that supplies mobile phase to the first stream to change from the first flow rate to the second flow rate when a first idle period between a first analysis of multiple analyses performed in the first stream and a second analysis performed after the first analysis is longer than the equilibration time from when switching from the second flow rate to the first flow rate begins to when the first flow rate becomes the first flow rate, and controls the first pump to maintain the first flow rate without changing to the second flow rate when the first idle period is shorter than the equilibration time.
[0077] According to the liquid chromatography system described in paragraph 1, the control device controls the first pump depending on whether the first idle period between the first and second analyses is longer than the equilibration time. Therefore, if the flow rate can be reduced without delaying the start timing of the second analysis, the flow rate can be reduced, thereby reducing pump damage and mobile phase consumption without reducing analytical efficiency.
[0078] (2) In the liquid chromatograph system described in (1), the control device can change the analysis schedule so that an analysis scheduled to be performed in a second stream of the multiple streams is performed in a first stream. The control device controls the first pump to change from the first flow rate to the second flow rate when the first idle period is longer than the equilibration time in the changed analysis schedule. The control device controls the first pump to maintain the first flow rate without changing to the second flow rate when the first idle period is shorter than the equilibration time in the changed analysis schedule.
[0079] According to the liquid chromatography system described in paragraph 2, even if the analysis schedule is changed so that an analysis that was scheduled to be performed in the second stream is now performed in the first stream, thereby changing the first idle period, the first pump is controlled in accordance with the changed first idle period. Therefore, even if the analysis schedule is changed, damage to the pump and consumption of mobile phase can be reduced without reducing analysis efficiency.
[0080] (3) In the liquid chromatography system described in paragraph 2, when the control device determines that the second stream cannot be used, it changes the analysis schedule so that the analysis scheduled to be performed in the second stream is performed in the first stream.
[0081] According to the liquid chromatography system described in paragraph 3, the analysis schedule can be changed flexibly because the analysis schedule is changed when it is determined that the second stream cannot be used. Furthermore, the first pump is controlled according to the changed first idle period, so that damage to the pump and consumption of mobile phase can be reduced without reducing analysis efficiency while the analysis schedule is changed flexibly.
[0082] (4) The liquid chromatograph system described in paragraph 2 further includes a reception unit that receives a change in the number of streams to be used. When the change received by the reception unit reduces the number of available streams, the control device changes the analysis schedule so that an analysis scheduled to be performed in the second stream is performed in the first stream.
[0083] According to the liquid chromatography system described in paragraph 4, the number of streams to be used can be flexibly changed, and the analysis schedule is changed in accordance with the change, while the first pump is controlled in accordance with the changed first idle period. Therefore, it is possible to flexibly change the number of streams to be used, without reducing the analysis efficiency, and to reduce damage to the pump and consumption of mobile phase.
[0084] (5) In the liquid chromatograph system described in any one of paragraphs 1 to 4, the control device determines whether the first idle period will be longer than the equilibration time when the first analysis is completed. If the first idle period is longer than the equilibration time, the control device controls the first pump to change the flow rate from the first to the second. If the first idle period is shorter than the equilibration time, the control device controls the first pump to maintain the first flow rate without changing the flow rate to the second.
[0085] According to the liquid chromatography system described in paragraph 5, it is determined whether the first idle period will be longer than the equilibration time when the first analysis is completed, and therefore the pump can be controlled according to the latest analysis schedule at the time the first analysis is completed.
[0086] (Item 6) A control method according to one aspect is a control method for controlling a liquid chromatography system. The liquid chromatography system includes a plurality of streams for separating components contained in a sample and a plurality of pumps for supplying a mobile phase to each of the plurality of streams. The control method includes the steps of controlling each device to perform separation of the components in the sample in parallel using each of the plurality of streams; controlling each device to perform multiple analyses in a first stream of the plurality of streams at a first flow rate, with one analysis being defined as a period from when a sample is injected into a stream until the stream is ready to inject a next sample; and controlling a pump that supplies mobile phase to each of the plurality of streams during an idle period in which no analysis is being performed so that the flow rate of the mobile phase supplied to the stream is a second flow rate that is lower than the first flow rate. determining whether a first idle period between a first analysis and a second analysis performed after the first analysis among a plurality of analyses performed in the first stream will be longer than an equilibration time required from when switching from the second flow rate to the first flow rate begins until the first flow rate is reached; controlling a first pump that supplies mobile phase to the first stream to change the flow rate from the first flow rate to the second flow rate when it is determined that the first idle period will be longer than the equilibration time; and controlling the first pump to maintain the first flow rate without changing to the second flow rate when it is determined that the first idle period will be shorter than the equilibration time.
[0087] (7) A control program according to one aspect is a program for causing a computer to execute the control method described in 8.
[0088] (Item 8) A computer-readable medium according to one aspect stores the control program described in item 7.
[0089] According to the control method, control program, and computer-readable medium described in paragraphs 6 to 8, the first pump is controlled depending on whether the first idle period between the first and second analyses is longer than the equilibration time. Therefore, if the flow rate can be reduced without delaying the start timing of the second analysis, the flow rate can be reduced, thereby reducing pump damage and mobile phase consumption without reducing analytical efficiency.
[0090] The embodiments disclosed herein are intended to be combined as appropriate within the scope of any technical inconsistency. The embodiments disclosed herein should be considered to be illustrative and not restrictive in all respects. The scope of the present invention is defined by the claims, not by the description of the above-mentioned embodiments, and is intended to include all modifications within the meaning and scope of the claims.
[0091] 1 LC system, 10 sample injection device, 12, 12A to 12D stream, 14 divert valve, 16 detector, 18 control device, 122 column, 124 valve, 126 supply device, 141 to 146 port, 171 input device, 172 display device, 182 processor, 184 memory, 261 mixer, 262 mobile phase pump, 400, 500 screen, 401, 402, 501 input field, 403, 502 OK button, 404, 503 cancel button, F a Analysis flow rate, F i Idle flow rate, S1, S2 Solvent container, T e Equilibration time.
Claims
1. A system comprising: a plurality of streams for separating components contained in a sample; a plurality of pumps for supplying a mobile phase to each of the plurality of streams; and a control device for controlling each device to perform separation of the components in the sample in parallel using each of the plurality of streams, wherein the control device is capable of controlling each device so that a plurality of analyses are performed in a first stream of the plurality of streams at a first flow rate, with one analysis being defined as a period from when a sample is injected into a stream to when the stream is in a state where a next sample can be injected; and is capable of controlling a pump for supplying mobile phase to each of the plurality of streams so that the flow rate of the mobile phase supplied to the stream is a second flow rate that is lower than the first flow rate during an idle period in which no analysis is being performed; and, for a first idle period between a first analysis and a second analysis performed following the first analysis, controls a first pump for supplying mobile phase to the first stream to change the flow rate from the first flow rate to the second flow rate when the first idle period is longer than an equilibration time from when switching from the second flow rate to the first flow rate begins to when the flow rate reaches the first flow rate; a liquid chromatograph system that controls the first pump to maintain the first flow rate without changing to the second flow rate when the first idle period is shorter than the equilibration time; 2. The liquid chromatograph system of claim 1, wherein the control device is capable of changing an analysis schedule so that an analysis scheduled to be performed in a second stream of the plurality of streams is performed in the first stream; and when, in the changed analysis schedule, the first idle period becomes longer than the equilibration time, the control device controls the first pump to change from the first flow rate to the second flow rate; and when, in the changed analysis schedule, the first idle period becomes shorter than the equilibration time, the control device controls the first pump to maintain the first flow rate without changing to the second flow rate.
3. The liquid chromatography system of claim 2, wherein the control device, when determining that the second stream is unavailable, changes the analysis schedule so that the analysis scheduled to be performed in the second stream is performed in the first stream.
4. A liquid chromatography system as described in claim 2, further comprising a reception unit that receives a change to the number of streams to be used, and when the number of available streams is reduced due to the change received by the reception unit, the control device changes the analysis schedule so that the analysis scheduled to be performed in the second stream is performed in the first stream.
5. A liquid chromatograph system as claimed in any one of claims 1 to 4, wherein the control device determines whether or not the first idle period will be longer than the equilibration time when the first analysis is completed, controls the first pump to change from the first flow rate to the second flow rate if the first idle period is longer than the equilibration time, and controls the first pump to maintain the first flow rate without changing to the second flow rate if the first idle period is shorter than the equilibration time.
6. A method for controlling a liquid chromatograph system, the liquid chromatograph system including: a plurality of streams for separating components contained in a sample; and a plurality of pumps for supplying a mobile phase to each of the plurality of streams, the method comprising the steps of: controlling each device to perform separation of components in the sample in parallel using each of the plurality of streams; controlling each device to perform a plurality of analyses at a first flow rate in a first stream among the plurality of streams, with one analysis being defined as a period from when a sample is injected into a stream until the stream is in a state in which the next sample can be injected; controlling a pump for supplying mobile phase to each of the plurality of streams such that the flow rate of the mobile phase supplied to the stream is a second flow rate lower than the first flow rate during an idle period in which no analysis is being performed; and determining whether a first idle period between a first analysis among the plurality of analyses performed in the first stream and a second analysis performed following the first analysis is longer than an equilibration time from when switching from the second flow rate to the first flow rate begins until the flow rate reaches the first flow rate. a step of controlling a first pump supplying a mobile phase to the first stream to change from the first flow rate to the second flow rate when it is determined that the first idle period will be longer than the equilibration time; and a step of controlling the first pump to maintain the first flow rate without changing to the second flow rate when it is determined that the first idle period will be shorter than the equilibration time.
Citation Information
Patent Citations
Glycohemoglobin analyzer
JP1995120447A
Automatic analyzer
JP2000304751A
Gas chromatograph apparatus
JP2011095072A
Gas chromatography apparatus
JP2013044647A
Gas chromatograph apparatus
US20140352406A1