Construction method of cast-in-place cover beam

A construction method and cast-in-place beam covering technology, which are applied in chemical instruments and methods, clay preparation devices, cement mixing devices, etc., can solve the problems of low concrete efficiency, long time consumption, and construction delays, etc.

CN108858771AInactive Publication Date: 2018-11-23陈佳佳
0 Cites 2 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Publication Date
2018-11-23
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
Patent Text Reader

Abstract

The invention discloses a construction method of a cast-in-place cover beam. Construction equipment is used. The construction equipment comprises a box body, a first transmission cavity is formed in the box body, a first motor is fixedly arranged in the upper end wall of the first transmission cavity, the lower end of an output shaft of the first motor is in power connection with a power shaft stretching downwards, a sun wheel is fixedly arranged on the outer surface of the power shaft, planet wheels are symmetrically engaged with the left side and the right side of the sun wheel, stirring shafts stretching downwards are fixedly arranged on the inner surfaces of the planet wheels, the outer sides of the planet wheels are engaged with gear rings, the gear rings are fixedly connected with the inner wall of the first transmission cavity, first containing cavities are formed in the lower end wall of the first transmission cavity in a left-and-right-symmetry manner, and a stirring cavity communicates with the portions below the left first containing cavity and the right first containing cavity. By means of the equipment, the preparation efficiency of concrete can be improved, and the preparation time of the concrete can be effectively shortened.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the field of construction, in particular to a construction method for a cast-in-place cap beam. Background technique

[0002] With the development of science and technology and the progress of society, the country has been promoting the development of high technology. A large amount of concrete needs to be used in the construction process of cast-in-place cap beams. The existing concrete preparation equipment is not efficient and takes a lot of time, which may lead to Construction was delayed, so a new type of equipment was urgently needed. Contents of the invention

[0003] The object of the present invention is to provide a construction method for cast-in-place cap beams, which can overcome the above-mentioned defects of the prior art.

[0004] According to the present invention, a cast-in-place cover beam construction method of the equipment of the present invention uses a construction equipment, the construction equipmen...

Examples

Embodiment Construction

[0014] All features disclosed in this specification, or steps in all methods or processes disclosed, may be combined in any manner, except for mutually exclusive features and / or steps.

[0015] Any feature disclosed in this specification (including any appended claims, abstract and drawings), unless expressly stated otherwise, may be replaced by alternative features which are equivalent or serve a similar purpose. That is, unless expressly stated otherwise, each feature is one example only of a series of equivalent or similar features.

[0016] like Figure 1-2 As shown, a cast-in-place cover beam construction method of the present invention uses a construction equipment, the construction equipment includes a box body 100, a first transmission chamber 101 is arranged inside the box body 100, and the first transmission chamber 101 A first motor 102 is fixed in the upper end wall of the chamber 101, and the lower end of the output shaft of the first motor 102 is connected to a ...