Geotechnical tunneling robot setting device and method thereof
By using the pitch collaborative mechanism and pneumatic foot design in the positioning device of the rock-ground excavation robot, the precise setting and pitch adjustment in the narrow channel is achieved, which solves the problems of starting position and angle control of the excavation robot and improves the excavation Work accuracy and safety.
Patent Information
- Application Number
- CN202411158759.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-08-22
AI Technical Summary
In urban construction, especially during the laying process of tap water pipelines, gas pipelines, communication cables, sewer pipelines, etc., the internal space of the passage is small, making it difficult to accurately control the starting position and pitch angle of the excavator robot, resulting in the excavator robot being unable to accurately position.
A rock-and-ground excavation robot positioning device is designed, including a pitch coordination mechanism unit and shell unit. The vertical installation and position adjustment of the robot is achieved through pneumatic feet and guide pulleys, and precise positioning is used for laser transmitter and camera to ensure the excavation channel. adjustment of verticality and pitch angle.
Accurate positioning and pitch adjustment in narrow underground passages is achieved, avoiding stuck situations, ensuring safe exit and efficient work of the excavator robot, and solving the problem that the excavator robot cannot accurately set and adjust the pitch angle.
Smart Images

Figure CN118933798A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a tunneling robot positioning device, and in particular to a rock and soil tunneling robot positioning device and a method thereof. Background Art
[0002] In urban construction, especially for the laying of water pipes, gas pipes, communication cables, sewer pipes, etc., it is necessary to dig channels with complex directions. When digging channels in other directions inside the channel is required, it is difficult to position the robot in place due to the small space, and the starting position of the excavation robot cannot be accurately controlled. Summary of the invention
[0003] In order to solve the problems existing in the background technology, the present invention provides a geotechnical tunneling robot positioning device and method thereof.
[0004] The technical solution adopted by the present invention is:
[0005] 1. A positioning device for a geotechnical excavation robot, comprising:
[0006] The pitch coordination mechanism unit is used for the installation of the geotechnical tunneling robot and for performing pitch adjustment when the geotechnical tunneling robot is excavating the secondary tunneling channel.
[0007] The shell unit is used for the installation and precise positioning of the pitch coordination mechanism unit, so that the secondary excavation channel of the geotechnical excavation robot is always perpendicular to the primary excavation channel; the shell unit includes a number of pneumatic supports and a pneumatic valve island, and the pneumatic valve island and the pneumatic supports are used to support the shell unit as a whole in the primary excavation channel and adjust the excavation position of the geotechnical excavation robot during excavation; each pneumatic support runs after being ventilated through the pneumatic valve island, and returns to its initial state after the ventilation is disconnected, to avoid jamming and achieve safe exit.
[0008] The shell unit also includes a shell, a plurality of supporting casters and two connecting plates. The shell unit is an arched shell. An arch-shaped installation slot is provided on one side surface of the shell in the length direction of the shell of the shell unit. The two connecting plates are vertically installed in the shell and are located on both sides of the symmetrical installation slot. The pitch coordination mechanism unit is installed between the two connecting plates and is directly opposite to the installation slot. Each supporting caster for support is installed on each side and bottom surface of the shell. A plurality of supporting leg slots are symmetrically provided on the shell on both sides of the pitch coordination mechanism unit. The top surface of the shell on each side of the pitch coordination mechanism unit and the two sides close to and far from the excavation direction are provided on the top surface of the shell. A support foot slot is provided on each side, and two support foot slots are symmetrically provided on the bottom surface of the shell on each side of the pitch coordination mechanism unit. Each pneumatic support foot and the pneumatic valve island are installed inside the shell, and each pneumatic support foot is located at a respective support foot slot. When the pneumatic valve island ventilates each pneumatic support foot through an external air pipe, each pneumatic support foot extends from a respective support foot slot and is crimped onto the channel wall of the primary excavation channel to provide overall support for the shell unit, so that the geotechnical excavation robot on the pitch coordination mechanism unit faces the excavation entrance of the secondary excavation channel perpendicular to the primary excavation channel.
[0009] The shell unit also includes several pairs of fill lights and cameras and several laser emitters. Each pair of fill lights and cameras and each laser emitter are installed on a side of the shell away from the excavation direction. Each laser emitter emits several lasers perpendicular to the primary excavation channel from the inside of the shell to the excavation entrance wall of the secondary excavation channel. The direction of each laser is parallel to the secondary excavation channel. Each pair of fill lights and cameras is directed toward the excavation entrance of the secondary excavation channel and illuminates and photographs each laser point on the excavation entrance wall of the secondary excavation channel through the gap between the pitch coordination mechanism unit and the installation groove of the shell; the pitch coordination mechanism unit is located at the center position between each laser.
[0010] The housing unit further comprises a plurality of guide pulleys, each guide pulley being installed inside the housing, and the external air pipes passing around each guide pulley are ventilated to each pneumatic support leg through the pneumatic valve island. The guide pulleys can prevent the air pipes from being torn when being pulled.
[0011] The pitch coordination mechanism unit includes a support steering cover and two pitch modules. The support steering cover is an arch-shaped plate. The geotechnical excavation robot is installed in the support steering cover. The two pitch modules are symmetrically installed on the symmetrical sides of the outer side of the support steering cover; the geotechnical excavation robot is located between the two pitch modules; the pitch module includes a cylinder, a cylinder bracket, an arc guide rail, a guide rail slide, a bearing mounting plate, a bearing, a motor mounting plate, a motor, a driving wheel and a driven wheel. The bottom end of the cylinder body of the cylinder is installed on the bottom surface of the shell through the cylinder bracket. The piston rod of the cylinder is arranged along the vertical surface. The end of the plug rod is hinged to the bottom of the vertically arranged bearing mounting plate, the central axis of the driven wheel is vertically movably connected to one side of the bearing mounting plate through the bearing, the side of the driven wheel away from the bearing mounting plate is connected to the side of the supporting steering cover, the other side of the bearing mounting plate is slidably mounted on the arc guide rail through a guide rail slide, the arc guide rail is bent upward and connected to a nearby connecting plate through a connecting frame, the body of the motor is mounted on the top surface of the bearing mounting plate through the motor mounting plate, the output shaft of the motor is horizontally connected to the central axis of the driving wheel, the driving wheel is located above the driven wheel and meshes with the driven wheel.
[0012] 2. A positioning method for a positioning device of a geotechnical excavation robot, comprising:
[0013] When the geotechnical tunneling robot positioning device is used to excavate the secondary tunneling channel, the geotechnical tunneling robot is first installed in the support steering cover of the pitch coordination mechanism unit and locked, and the positioning device is pushed into the primary tunneling channel as a whole. The pneumatic valve island ventilates each pneumatic support foot through an external air pipe, and each pneumatic support foot extends from a respective support foot slot and is crimped onto the channel wall of the primary tunneling channel to support the entire shell unit; at this time, the geotechnical tunneling robot on the pitch coordination mechanism unit faces the excavation entrance of the secondary tunneling channel perpendicular to the primary tunneling channel, and then drives the cylinder and the motor according to the preset length direction of the secondary tunneling channel to make the support steering cover move along the arc guide rail and rotate through the driven wheel until the direction of the geotechnical tunneling robot is parallel to the preset length direction of the secondary tunneling channel, thereby completing the positioning of the geotechnical tunneling robot.
[0014] When the geotechnical tunneling robot is in the process of tunneling, it emits several lasers parallel to the preset length direction of the secondary tunneling channel outside the channel and irradiates them to the channel wall in front of the geotechnical tunneling robot, and each fill light illuminates the channel wall in front of the geotechnical tunneling robot. Each camera captures the laser position on the front channel wall. When the camera captures that the geotechnical tunneling robot is not at the center position of each laser, it is judged that the geotechnical tunneling robot deviates from the tunneling direction, and the position of the geotechnical tunneling robot positioning device is adjusted by adjusting the extension of each pneumatic support foot, and then the position of the geotechnical tunneling robot is adjusted so that the tunneling robot returns to the preset length direction of the secondary tunneling channel.
[0015] When the excavation is completed, the ventilation is disconnected, and each pneumatic support leg returns to its original state inside the shell, and then the geotechnical excavation robot positioning device is pulled out of the passage through the air pipe used for ventilation to achieve a safe exit.
[0016] The beneficial effects of the present invention are:
[0017] The arc-shaped guide rail of the device of the present invention is designed with a cylinder to automatically adapt to the height change of the support steering cover during rotation. The support and excavation position can be adjusted through the pneumatic valve island and the pneumatic support foot, and it can avoid getting stuck, thereby achieving safe exit of the device. The device of the present invention can operate in a narrow underground passage, and accurately position the geotechnical excavation robot, and accurately control the initial pitch posture of the excavation robot, and adjust the pitch of the excavation robot at different angles to ensure the accuracy of subsequent excavation work. The design structure of the present invention is reasonable, easy to use, and saves labor costs. It can effectively solve the problem that the excavation robot cannot be accurately positioned in the passage and cannot adjust the pitch angle. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the overall structure of the positioning device of the tunneling robot of the present invention;
[0019] Figure 2 It is a left view of the overall structure of the positioning device of the tunneling robot of the present invention;
[0020] Figure 3 It is a schematic diagram of the pitch adjustment mechanism of the positioning device of the tunneling robot of the present invention;
[0021] Figure 4 This is a schematic diagram of the assembly of the arc-shaped guide rail and cylinder of the positioning device of the tunneling robot of the present invention;
[0022] In the figure: 1, housing, 11, fill light, 12, camera, 13, support casters, 14, pneumatic support feet, 15, pneumatic valve island, 16, guide pulley, 17, connecting plate, 21, support steering cover, 22, cylinder, 221, cylinder bracket, 222, piston rod, 23, arc guide rail, 24, guide rail slide, 25, bearing mounting plate, 251, bearing, 26, motor mounting plate, 27, motor, 271, driving wheel, 28, driven wheel. DETAILED DESCRIPTION
[0023] The following is a detailed description of an embodiment of the present invention. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific operation process are given, but the protection scope of the present invention is not limited to the following embodiment.
[0024] like Figure 1 and Figure 2As shown, the positioning device of the geotechnical tunneling robot of the present invention includes a pitch coordination mechanism unit and a shell unit. The geotechnical tunneling robot is installed on the pitch coordination mechanism unit and the pitch adjustment is performed when the geotechnical tunneling robot excavates the secondary tunneling channel; the pitch coordination mechanism unit is installed on the shell unit and is precisely positioned so that the secondary tunneling channel excavated by the geotechnical tunneling robot is always perpendicular to the primary tunneling channel; the shell unit includes a plurality of pneumatic support legs 14 and a pneumatic valve island 15, and the pneumatic valve island 14 and each pneumatic support leg 17 are used to support the shell unit as a whole in the primary tunneling channel and adjust the tunneling position when the geotechnical tunneling robot is excavating; each pneumatic support leg 14 is operated after being ventilated through the pneumatic valve island 14, and returns to the initial state after the ventilation is disconnected, so as to avoid jamming and achieve safe exit.
[0025] The shell unit also includes a shell 1, a plurality of supporting casters 13 and two connecting plates 17. The shell unit is an arched shell. An arch-shaped installation slot is provided on one side surface of the shell 1 in the length direction of the shell unit. The two connecting plates 17 are vertically installed in the shell 1 and are located on both sides of the installation slot. The pitch coordination mechanism unit is installed between the two connecting plates 17 and is directly opposite to the installation slot. Each supporting caster 13 for support is installed on each side and bottom surface of the shell 1. A plurality of supporting leg slots are symmetrically provided on the shell 1 on both sides of the pitch coordination mechanism unit. The top surface of the shell 1 on each side of the pitch coordination mechanism unit and the two sides close to and far from the excavation direction are provided on the top surface of the shell 1 on each side of the pitch coordination mechanism unit. A support foot slot is respectively provided on the side surface, and two support foot slots are symmetrically provided on the bottom surface of the shell 1 on each side of the pitch coordination mechanism unit. Each pneumatic support foot 14 and the pneumatic valve island 15 are installed inside the shell 1, and each pneumatic support foot 14 is located at a respective support foot slot. When the pneumatic valve island 15 ventilates each pneumatic support foot 14 through an external air pipe, each pneumatic support foot 14 extends from a respective support foot slot and is crimped onto the channel wall of the primary excavation channel to provide overall support for the shell unit, so that the geotechnical excavation robot on the pitch coordination mechanism unit faces the excavation entrance of the secondary excavation channel perpendicular to the primary excavation channel.
[0026] The outer shell unit also includes several pairs of fill lights 11 and cameras 12 and several laser emitters. Each pair of fill lights 11 and cameras 12 and each laser emitter are installed on a side of the outer shell 1 away from the excavation direction. Each laser emitter emits several lasers perpendicular to the primary excavation channel from the inner shell 1 to the excavation entrance wall of the secondary excavation channel. The direction of each laser is parallel to the secondary excavation channel. Each pair of fill lights 11 and cameras 12 is directed toward the excavation entrance of the secondary excavation channel and illuminates and photographs each laser point on the excavation entrance wall of the secondary excavation channel through the gap between the pitch coordination mechanism unit and the installation groove of the outer shell 1; the pitch coordination mechanism unit is located at the center position between each laser.
[0027] The housing unit further comprises a plurality of guide pulleys 16, each guide pulley 16 being mounted inside the housing 1, and the external air pipes are ventilated to the air support legs 14 through the pneumatic valve island 14 after passing through the guide pulleys 16. The guide pulleys 16 can prevent the air pipes from being torn when being pulled.
[0028] like Figure 3 and Figure 4 As shown, the pitch coordination mechanism unit includes a support steering cover 21 and two pitch modules. The support steering cover 21 is an arch-shaped plate. The geotechnical excavation robot is installed in the support steering cover 21. The two pitch modules are symmetrically installed on the symmetrical sides of the outer side of the support steering cover 21; the geotechnical excavation robot is located between the two pitch modules; the pitch module includes a cylinder 22, a cylinder bracket 221, an arc guide rail 23, a guide rail slide 24, a bearing mounting plate 25, a bearing 251, a motor mounting plate 26, a motor 27, a driving wheel 271 and a driven wheel 28. The bottom end of the cylinder body of the cylinder 22 is installed on the bottom surface inside the shell 1 through the cylinder bracket 221, and the piston rod 222 of the cylinder 22 is arranged along the vertical surface. The end of 222 is hinged to the bottom of the vertically arranged bearing mounting plate 25, and the central axis of the driven wheel 28 is vertically movably connected to one side of the bearing mounting plate 25 through the bearing 251. The side of the driven wheel 28 away from the bearing mounting plate 25 is connected to the side of the supporting steering cover 21, and the other side of the bearing mounting plate 25 is slidably mounted on the arc guide rail 23 through the guide rail slide 24. The arc guide rail 23 is bent upward and connected to a nearby connecting plate 17 through a connecting frame. The body of the motor 27 is mounted on the top surface of the bearing mounting plate 25 through the motor mounting plate 26. The output shaft of the motor 27 is horizontally connected to the central axis of the driving wheel 271. The driving wheel 271 is located above the driven wheel 28 and meshes with the driven wheel 28.
[0029] The positioning method of the rock and soil excavation robot positioning device of the present invention is specifically as follows:
[0030] When the positioning device of the geotechnical excavation robot excavates the secondary excavation channel, the geotechnical excavation robot is first installed in the support steering cover 21 of the pitch coordination mechanism unit and locked, and the positioning device is pushed into the primary excavation channel as a whole. The pneumatic valve island 15 ventilates each pneumatic support foot 14 through an external air pipe. Each pneumatic support foot 14 extends from a respective support foot slot and is crimped onto the channel wall of the primary excavation channel to support the entire shell unit; at this time, the geotechnical excavation robot on the pitch coordination mechanism unit faces the excavation entrance of the secondary excavation channel perpendicular to the primary excavation channel, and then drives the cylinder 22 and the motor 27 according to the preset length direction of the secondary excavation channel to make the support steering cover 21 move along the arc guide rail 23 and rotate through the driven wheel 28 until the direction of the geotechnical excavation robot is parallel to the preset length direction of the secondary excavation channel, thereby completing the positioning of the geotechnical excavation robot.
[0031] When the geotechnical excavation robot is in the process of excavation, it emits several lasers parallel to the preset length direction of the secondary excavation channel outside the channel and irradiates them to the channel wall in front of the geotechnical excavation robot. Each fill light 11 illuminates the channel wall in front of the geotechnical excavation robot, and each camera 12 captures the laser position on the front channel wall. When the camera 12 captures that the geotechnical excavation robot is not at the center position of each laser, it is determined that the geotechnical excavation robot deviates from the excavation direction. The position of the positioning device of the geotechnical excavation robot is adjusted by adjusting the extension amount of each pneumatic support foot 17, and then the position of the geotechnical excavation robot is adjusted so that the excavation robot returns to the preset length direction of the secondary excavation channel.
[0032] When the excavation is completed, the ventilation is disconnected, and each pneumatic support leg 17 returns to its initial state inside the shell 1, and then the geotechnical excavation robot positioning device is pulled out of the passage through the air pipe used for ventilation to achieve safe exit.
[0033] The positioning method of the positioning device of the present invention comprises the following steps:
[0034] S1: Lock the excavation robot and the supporting steering cover 21.
[0035] S2: Push the positioning device as a whole into the first-level excavation channel.
[0036] S3: After the positioning device is in place, the pneumatic support legs 14 around the arched shell 1 are lifted up to contact and lock with the inner wall of the primary excavation channel.
[0037] S4: The pitch module cooperates with the pitch angle of the tunneling robot to adjust the rotation angle of the supporting steering cover 21. At the same time, the cylinder 22 of the pitch module pushes the arc-shaped guide rail slide 24 to slide adaptively according to the rotation angle and height of the supporting steering cover 21 to complete the positioning of the tunneling robot.
[0038] In summary, the positioning device and method of the above-mentioned embodiments can effectively solve the problem of improper positioning of the excavation robot in the channel, and improve the production efficiency to a certain extent.
[0039] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A positioning device for a geotechnical excavation robot, characterized in that: include: The pitch coordination mechanism unit is used for the installation of the geotechnical tunneling robot and for making pitch adjustments when the geotechnical tunneling robot is excavating the secondary tunneling channel; The shell unit is used for the installation and precise positioning of the pitch coordination mechanism unit, so that the secondary excavation channel of the geotechnical excavation robot is always perpendicular to the primary excavation channel; the shell unit includes a plurality of pneumatic support legs (14) and a pneumatic valve island (15), and the support of the shell unit as a whole in the primary excavation channel and the adjustment of the excavation position of the geotechnical excavation robot during excavation are achieved through the pneumatic valve island (14) and each pneumatic support leg (17); each pneumatic support leg (14) is operated after being ventilated through the pneumatic valve island (14), and returns to the initial state after the ventilation is disconnected, so as to avoid being stuck and achieve safe exit.
2. The positioning device for a geotechnical excavation robot according to claim 1, characterized in that: The shell unit further comprises a shell (1), a plurality of supporting casters (13) and two connecting plates (17); the shell unit is an arched shell; an arch-shaped installation slot is provided on one side surface of the shell (1) in the longitudinal direction of the shell unit; the two connecting plates (17) are vertically installed in the shell (1) and are located on two symmetrical sides of the installation slot; the pitch coordination mechanism unit is installed between the two connecting plates (17) and is directly opposite to the installation slot; each supporting caster (13) is installed on each side and bottom surface of the shell (1); a plurality of supporting casters are symmetrically provided on the shell (1) on both sides of the pitch coordination mechanism unit; the top surface of the shell (1) on each side of the pitch coordination mechanism unit and the surfaces close to and far from the excavation A support foot slot is respectively provided on both side surfaces of the direction, and two support foot slots are symmetrically provided on the bottom surface of the shell (1) on each side of the pitch coordination mechanism unit. Each pneumatic support foot (14) and the pneumatic valve island (15) are installed inside the shell (1), and each pneumatic support foot (14) is located at a position of a respective support foot slot. When the pneumatic valve island (15) ventilates each pneumatic support foot (14) through an external air pipe, each pneumatic support foot (14) extends from a respective support foot slot and is pressed against the channel wall of the primary excavation channel to provide overall support for the shell unit, so that the geotechnical excavation robot on the pitch coordination mechanism unit faces the excavation entrance of the secondary excavation channel perpendicular to the primary excavation channel.
3. The positioning device for a geotechnical excavation robot according to claim 2, characterized in that: The housing unit further comprises a plurality of pairs of fill lights (11) and cameras (12) and a plurality of laser emitters. Each pair of fill lights (11) and cameras (12) and each laser emitter are installed on a side of the housing (1) away from the excavation direction. Each laser emitter emits a plurality of laser beams perpendicular to the primary excavation channel from the housing (1) to the excavation entrance wall of the secondary excavation channel. The direction of each laser beam is parallel to the secondary excavation channel. Each pair of fill lights (11) and cameras (12) are directed toward the excavation entrance of the secondary excavation channel and illuminate and photograph each laser point on the excavation entrance wall of the secondary excavation channel through the gap between the pitch coordination mechanism unit and the installation slot of the housing (1); the pitch coordination mechanism unit is located at the center position between each laser beam.
4. The positioning device for a geotechnical excavation robot according to claim 2, characterized in that: The housing unit further comprises a plurality of guide pulleys (16), each guide pulley (16) being installed inside the housing (1), and an external air pipe passes around each guide pulley (16) and then ventilates to each pneumatic support leg (14) through the pneumatic valve island (14).
5. The positioning device for a geotechnical excavation robot according to claim 2, characterized in that: The pitch coordination mechanism unit comprises a support steering cover (21) and two pitch modules. The support steering cover (21) is an arch-shaped plate. The geotechnical excavation robot is installed in the support steering cover (21). The two pitch modules are symmetrically installed on the symmetrical sides of the outer side of the support steering cover (21). The geotechnical excavation robot is located between the two pitch modules. The pitch module comprises a cylinder (22), a cylinder bracket (221), an arc guide rail (23), a guide rail slide (24), a bearing mounting plate (25), a bearing (251), a motor mounting plate (26), a motor (27), a driving wheel (271) and a driven wheel (28). The bottom end of the cylinder body of the cylinder (22) is installed on the bottom surface of the housing (1) through the cylinder bracket (221). The piston rod (222) of the cylinder (22) is arranged along the vertical surface. The piston rod (222) is arranged along the vertical surface. The end of the driven wheel (28) is hinged to the bottom of a vertically arranged bearing mounting plate (25), the central axis of the driven wheel (28) is vertically movably connected to one side of the bearing mounting plate (25) through a bearing (251), the side of the driven wheel (28) away from the bearing mounting plate (25) is connected to the side of the supporting steering cover (21), the other side of the bearing mounting plate (25) is slidably mounted on the arc guide rail (23) through a guide rail slide (24), the arc guide rail (23) is bent upward and connected to a nearby connecting plate (17) through a connecting frame, the body of the motor (27) is mounted on the top surface of the bearing mounting plate (25) through a motor mounting plate (26), the output shaft of the motor (27) is horizontally connected to the central axis of the driving wheel (271), the driving wheel (271) is located above the driven wheel (28) and meshes with the driven wheel (28).
6. The positioning method of the geotechnical excavation robot positioning device according to any one of claims 1 to 5, characterized in that: include: When the geotechnical tunneling robot positioning device is used to excavate the secondary tunneling channel, the geotechnical tunneling robot is first installed in the support steering cover (21) of the pitch coordination mechanism unit and locked, and the positioning device is pushed into the primary tunneling channel as a whole. The pneumatic valve island (15) ventilates each pneumatic support foot (14) through an external air pipe, and each pneumatic support foot (14) extends from a respective support foot slot and is crimped onto the channel wall of the primary tunneling channel to support the shell unit as a whole. At this time, the geotechnical tunneling robot on the pitch coordination mechanism unit faces the excavation entrance of the secondary tunneling channel perpendicular to the primary tunneling channel, and then drives the cylinder (22) and the motor (27) according to the preset length direction of the secondary tunneling channel to make the support steering cover (21) move along the arc guide rail (23) and rotate through the driven wheel (28) until the direction of the geotechnical tunneling robot is parallel to the preset length direction of the secondary tunneling channel, thereby completing the positioning of the geotechnical tunneling robot. When the geotechnical tunneling robot is in the process of tunneling, it emits several laser beams parallel to the preset length direction of the secondary tunneling channel outside the channel and irradiates the channel wall in front of the geotechnical tunneling robot, each fill light (11) irradiates the channel wall in front of the geotechnical tunneling robot, and each camera (12) photographs the laser position on the channel wall in front. When the camera (12) photographs that the geotechnical tunneling robot is not at the center position of each laser beam, it is determined that the geotechnical tunneling robot deviates from the tunneling direction, and the position of the geotechnical tunneling robot positioning device is adjusted by adjusting the extension amount of each pneumatic support foot (17), thereby adjusting the position of the geotechnical tunneling robot so that the tunneling robot returns to the preset length direction of the secondary tunneling channel; When the excavation is completed, the ventilation is disconnected, and each pneumatic support leg (17) returns to its initial state inside the housing (1), and then the geotechnical excavation robot positioning device is pulled out of the passage through the air pipe used for ventilation, thereby achieving safe exit.
Citation Information
Patent Citations
Test bed for verifying function of TBM tool changing robot
CN109085001A
TBM (Tunnel Boring Machine) shield tail frame and tunnel boring machine with same
CN116556974A
Wheel type variable-diameter multi-degree-of-freedom rock-soil duct tunneling robot
CN117231243A
Splitting tunneling equipment for tunnel construction
CN118049240A
Mechanical arm type measuring robot device and application method
US11826914B1