Island electricity-hydrogen transmission coupling optimization scheduling method based on improved dung beetle algorithm
By improving the island-based hydrogen-electric transmission coupling optimization scheduling method using the dung beetle algorithm, a two-way coupling framework between island new energy and maritime transportation network is constructed. A hydrogen fuel cell ship transportation network is designed, solving the problems of inefficient energy supply and high carbon emissions in ocean-going islands and achieving efficient and low-carbon energy management.
Patent Information
- Application Number
- CN202410930292.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-11
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Energy supply is a prominent issue for remote islands. Existing energy management and dispatch strategies are insufficient to meet their specific needs. Traditional resupply methods are inefficient and environmentally unfriendly, and the application of new hydrogen energy storage technologies is inadequate.
An optimized scheduling method for island-based electricity-hydrogen transport coupling based on an improved dung beetle algorithm is proposed. This method constructs a two-way coupling framework between the island's new energy system and the maritime transportation network, designs a hydrogen fuel cell ship transportation network, builds an electricity-hydrogen-transportation coupling model, and uses the improved dung beetle algorithm (IDBO) to solve the optimized scheduling model. Combined with STHS and SHS, it achieves energy self-sufficiency and low carbon emissions.
It has improved the energy self-sufficiency of island regions, significantly reduced carbon emission costs, increased energy self-sufficiency rates, reduced dependence on external energy supplies, and achieved a clean and efficient energy internet.
Smart Images

Figure CN119005565A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of island integrated energy systems, and in particular to an island electricity-hydrogen transmission coupling optimization scheduling method based on an improved dung beetle algorithm. Background Art
[0002] Globally, islands have become a hot spot for development due to their unique geography and rich resources. However, the energy supply of offshore islands faces great challenges, and the instability and high cost of energy have become key issues restricting the sustainable development of islands. Although traditional diesel power generation has met the electricity demand to a certain extent, its high pollution and high cost are contrary to the development trend of green and low-carbon development.
[0003] In recent years, there have been some advances in island power supply technology, such as the integrated application of distributed microgrids and renewable energy, but these advances are mainly concentrated in offshore islands, which benefit from their geographical advantages close to the mainland and relatively convenient energy supply and transportation. The energy supply problem of offshore islands is even more severe, and the current energy management and scheduling strategies are difficult to meet their special needs. For island integrated energy systems, a variety of energy optimization configuration schemes have been proposed, but no fundamental solution has been found in energy storage and transportation. Although traditional battery swap ships and mobile energy storage systems can achieve energy scheduling to some extent, their efficiency and economy need to be improved. At the same time, new energy storage technologies, such as hydrogen energy storage, show great potential, but their application research in island energy supply is still insufficient.
[0004] In general, the energy supply challenges faced by island resource development, especially those on offshore islands, urgently need to be addressed through technological innovation. Existing technological advances can improve the energy situation on offshore islands, but energy management and transmission issues on offshore islands remain prominent. The inefficiency and environmental unfriendliness of traditional refueling methods, as well as the limited application of emerging hydrogen energy storage technologies, all point to the urgent need to find new energy solutions to promote the sustainable development of island resources. Summary of the invention
[0005] The present invention provides an island electricity-hydrogen transmission coupling optimization scheduling method based on an improved dung beetle algorithm, which can fully tap the new energy and flexible and adjustable resources in the marine transportation network, realize local energy consumption, reduce the power generation of diesel generators, and thus reduce carbon emissions.
[0006] The technical solution adopted by the present invention is:
[0007] The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm includes the following steps:
[0008] Step 1: Considering self-sufficiency and shared hydrogen storage (SHS), a two-way coupling framework is constructed to design the overall scheme of hydrogen fuel cell ship (HFCS) transportation network and island new energy system;
[0009] Step 2: Considering the operation constraints of new energy, marine transportation network, hydrogen energy storage system and short-distance transportation system, an electricity-hydrogen-transportation coupling model and an island double-layer optimization scheduling model are constructed;
[0010] Step 3: Use the improved Dung Beetle Algorithm (IDBO) to solve the electricity-hydrogen-transportation coupling model and the island two-layer optimization scheduling model constructed in step 2, and output the optimal solution.
[0011] Step 4: An improved IEEE standard 6-node grid structure is proposed to verify the feasibility of the method to improve the energy self-consistency rate and reduce the carbon emission cost of the island, as well as the effectiveness of the improved Dung Beetle Algorithm (IDBO).
[0012] In step 1, the bidirectional coupling architecture of the island energy system and the marine transportation network includes a power network based on HFCS and a marine transportation network, such as Figure 1 The bidirectional coupling architecture of the island energy system and the maritime transportation network enables the two separate systems of energy and transportation to integrate and develop together, ultimately forming a clean, low-carbon, integrated and efficient energy Internet.
[0013] In the step 1, the overall plan of the hydrogen fuel cell ship (HFCS) transportation network and the island new energy system is designed, including: the island energy system is responsible for the access of distributed new energy, power supply of power load, diesel generator interface, and power supply of water electrolysis hydrogen production equipment; the distributed new energy first supplies power to the isolated island load, and the remaining power can be converted into hydrogen energy for use by the hydrogen fuel cell ship (HFCS) or the hydrogen energy storage system; the hydrogenation main station and the substation of the marine transportation network provide energy for the hydrogen fuel cell ship (HFCS), and short-term hydrogen energy storage (STHS) and shared hydrogen storage (SHS) can make up for the lack of hydrogen energy. In addition, the hydrogen energy storage system can also supply power to the power load during peak hours.
[0014] In step 2, the constructed electricity-hydrogen-transportation coupling model includes a load center island model, which is equipped with an integrated power supply system of active power, grid power and load; during operation, it is necessary to consider constraints such as power flow constraints, line transmission power constraints, voltage over-limit, diesel generator output constraints and distributed energy output constraints;
[0015] a. Load center island model:
[0016] The load center island is equipped with a comprehensive power supply system of active power, network power and load. During operation, it is necessary to consider constraints such as power flow constraints, line transmission power constraints, voltage overlimit, diesel generator output constraints and distributed energy output constraints:
[0017] 1) Power flow constraints:
[0018]
[0019] In formula (1), P DG Refers to the active power of distributed renewable energy, Refers to the active power of the diesel generator, Refers to the active power of energy storage, Refers to the active power of the load. DG Refers to the reactive power of distributed renewable energy, Refers to the reactive power of the diesel generator, Reactive power of energy storage, Refers to the reactive power of the load; U i is the voltage amplitude at node i; U j represents the voltage amplitude at node j, θ ij is the power angle between nodes i and j; j∈i means that the source, memory and payload are correctly connected to node i; G ij Refers to the conductivity parameter of the system, B ij Refers to the system's susceptance parameter.
[0020] 2) Line power limitation:
[0021] -P l,max ≤U i U j (G ij cosθ ij +B ij sinθ ij )≤P l,max (2);
[0022] In formula (2), P l,max is the maximum transmission power (nodes i and j at both ends);
[0023] 3) Voltage constraints:
[0024] U min ≤U i ≤U max (3);
[0025] In formula (3), U min , U max are the upper and lower limits of the node voltage amplitude, which are 1.1 and 0.9 respectively.
[0026] 4) Output constraints of diesel generators:
[0027]
[0028] In formula (4), Refers to the output power of the diesel generator; It is the maximum output of the diesel generator, usually the indicated output; is the minimum output, take
[0029] 5) Wind-solar distributed energy output constraints:
[0030]
[0031] In formula (5), P WT (t) refers to the output power of wind energy; P PV (t) refers to the output power of solar energy; are the minimum outputs of wind and solar distributed energy resources, respectively; They are the maximum output of wind and solar distributed energy respectively.
[0032] The constructed electricity-hydrogen-transportation coupling model includes a hydrogen energy storage model and an operation and maintenance cost model. The hydrogen energy storage model consists of three parts: a hydrogen storage tank, a hydrogen production device and a hydrogen fuel cell. The storage tank stores hydrogen, the electrolysis hydrogen production device consumes electricity to produce hydrogen, and the battery provides electricity by burning hydrogen; the operation and maintenance cost includes the life decay cost corresponding to the power fluctuation of the hydrogen energy storage, the start-up and shutdown cost of the hydrogen production device and the fuel cell, the maintenance cost of the device and the hydrogen fuel cell, and the life decay cost corresponding to the historical operating time of the device and the fuel cell.
[0033] b. Hydrogen energy storage model:
[0034] 6) Hydrogen production model of surplus electricity from wind and solar distributed energy:
[0035]
[0036] In formula (6), P ex (t) refers to the surplus power of wind-solar distributed energy in period t; P eP2G (t) refers to the electricity used by the hydrogen electrolysis module in cycle t; P pv (t), P wind (t) are the outputs of wind energy and solar energy distributed energy in period t; P e-load (t) is the power load in period t; η P2G is the energy conversion efficiency; is the hydrogen storage capacity in period t, The upper limit of the capacity of hydrogen storage equipment.
[0037] 7) Construction of hydrogen energy storage model:
[0038] Hydrogen energy storage consists of hydrogen storage tanks, hydrogen production devices and hydrogen fuel cells; the tanks store hydrogen, the electrolytic hydrogen production device consumes electricity to produce hydrogen, and the battery provides electricity by burning hydrogen; the calculation process of the energy stored in the tank is as follows:
[0039]
[0040] In formula (7), the variable t represents the sequence number of the scheduling period; represents the energy in the energy storage in the t scheduling period; η P2G and η FC are the energy conversion efficiencies of the hydrogen production device and the battery respectively; △t represents the time span of the scheduling cycle; P eP2G (t) is the power used by the hydrogen electrolysis module in cycle t; P FC (t) is the power used by the hydrogen electrolysis module in cycle t.
[0041] c. Operation and maintenance cost model:
[0042] Lifetime attenuation cost corresponding to hydrogen energy storage power fluctuation:
[0043]
[0044] In formula (8), K λ_FL represents the lifetime decay cost corresponding to the unit fluctuating power of the device and the fuel cell; P λ_t Represents the electrical power of the hydrogen production device and hydrogen fuel cell; r λ_t Indicates the start-stop status of the device and fuel cell;
[0045] P λ_t-1 represents the electric power of the hydrogen production device and hydrogen fuel cell, r λ_t-1 Indicates the start-stop status of the equipment and fuel cell; ED stands for hydrogen production by electrolysis, and FC stands for hydrogen fuel cell; Indicates the start-stop state of the device and the fuel cell; T indicates the operating time.
[0046] The start-up and shutdown costs of the hydrogen production device and fuel cell are shown in the following formula:
[0047]
[0048] In formula (9) and formula (10), K λ_SU and K λ_SD are the unit start-stop costs of the device and the fuel cell, respectively;
[0049] r λ_SU_t and r λ_SD_tThe start-stop state of the device and the fuel cell are shown respectively; C λ_SU represents the start-up and shutdown cost of the hydrogen production device, C λ_SD represents the start-stop cost of the fuel cell;
[0050] Maintenance costs of the device and hydrogen fuel cells:
[0051]
[0052] In formula (11), K λ_OM represents the maintenance cost per unit time of the hydrogen production device and the fuel cell; C λ_OM represents the maintenance costs of the device and hydrogen fuel cells;
[0053] The lifetime decay cost corresponding to the historical operating time of the device and fuel cell is shown as follows:
[0054]
[0055] In formula (12), K λ_AGE It refers to the life decay cost corresponding to the unit operating time of the device / fuel cell; T λ_LT Indicates the expected life of the device / hydrogen fuel cell; C λ_AGE Refers to the lifetime decay cost corresponding to the historical operating time of the device and fuel cell;
[0056] The total operating cost of hydrogen energy storage is:
[0057]
[0058] The constructed electricity-hydrogen-transportation coupling model includes a maritime transportation network model, including: the probability density function of the last return time of daily users, the probability density function of the HFCS user's mileage, the hydrogenation time of HFCS, the single-station hydrogenation demand and the total hydrogenation demand of the transportation network and the hydrogen storage model.
[0059] d. Maritime transportation network model:
[0060] The hydrogen load of hydrogen fuel cell ships (HFCS) is mainly affected by mileage, return time and the supply and demand relationship of hydrogen refueling stations. The transportation network model is established as follows.
[0061] The probability density function of the last return time of daily users is:
[0062]
[0063] In formula (14), x t is the user's last return time; ψ t is the expected value, γ t is the standard deviation;
[0064] The probability density function of the mileage of hydrogen fuel cell ship (HFCS) users is defined as:
[0065]
[0066] In formula (15), x s is the user's last return time; ψ s is the expected value, γ t is the standard deviation.
[0067] The hydrogen refueling duration of a hydrogen fuel cell ship (HFCS) is:
[0068]
[0069] In formula (16), T s is the duration of hydrogenation; S refers to daily mileage; P s is the amount of hydrogenation; σ s is the hydrogenation efficiency; E refers to the hydrogen consumption per unit kilometer.
[0070] Single station hydrogenation requirements:
[0071] N m,HFCS ≤N m,H (17);
[0072] In formula (17), N m,HFCS is the amount of existing HFCS in the mth hydrogen refueling station, N m,H It refers to the amount of HFCS that the mth hydrogen refueling station can accept.
[0073] Total hydrogen refueling demand in the transportation network:
[0074]
[0075] In formula (18), M is the number of hydrogen refueling stations in the transportation network; M m,cqz is the capacity of the mth hydrogen storage station; M e,HFCS is the capacity of the e-th HFCS; N HFCS is the amount of HFCS; m refers to an element in the capacity of the hydrogen storage station; e refers to an element in HFCS.
[0076] Short-term hydrogen storage model:
[0077]
[0078] In formula (19), They are the hydrogen storage per unit time, hydrogen release per unit time and total short-term hydrogen storage; are the hydrogen storage efficiency, hydrogen release efficiency and self-release rate of STHS; C STHSis the configuration capacity of STHS; Δt is the unit time step; refers to the self-release rate of STHS; Refers to the total amount of short-term hydrogen storage at the time of the last dispatch.
[0079] Shared hydrogen energy storage mode:
[0080]
[0081] In formula (20), They are the hydrogen storage capacity per unit time, the hydrogen release capacity per unit time and the total amount of hydrogen remaining in the hydrogen storage; are the hydrogen storage efficiency, hydrogen release efficiency and self-release rate of SHS respectively; C SHS Refers to the configuration capacity of SHS. SHS is used when STHS cannot meet the hydrogen load, and its use order is: real-time hydrogen replenishment > short-term hydrogen energy storage (STHS) > shared hydrogen storage (SHS).
[0082] The hydrogenation of hydrogen fuel cell ships (HFCS) should meet certain conditions. The actual amount of hydrogen should not exceed the total capacity of the battery, but at the same time it should not be less than the amount of hydrogen expected by the user. Assuming that when the ship owner connects the HFCS to the hydrogenation pile, the user's own expected information and the expected state of hydrogen charge when leaving the hydrogenation are S h , which means that when the user decides to leave, the actual hydrogen amount of HFCS should be greater than or equal to the expected value, expressed as:
[0083]
[0084] In formula (21), S st,i is the hydrogen loading state when the i-th HFCS starts hydrogenation, S en,i is the hydrogen loading state when the i-th HFCS leaves.
[0085] The constructed island two-layer optimization scheduling model includes the island operation mode of the upper-layer transportation network and the self-consistent model of the island of the low-layer traffic network.
[0086] 1) Upper-level transportation network island operation mode:
[0087] Objective function:
[0088]
[0089] In formula (22), f1 represents the operating cost of the island, where C HS , C WT , C PV represent the energy storage and operation costs of hydrogen, wind power generation equipment and photovoltaic power generation equipment respectively; f2 represents the hydrogen refueling cost; x ijis the hydrogenation status of the i-th ship in period j, which has two values: 0 or 1, 0 means no hydrogenation, and 1 means hydrogenation; p i is the power of the ith measurement container; p j represents the price of hydrogen during period j; N represents the number of HFCS ships; △t refers to the scheduling time interval; N represents the number of HFCS ships; 24 hours a day is the scheduling cycle, the unit scheduling time is 15 minutes, so the number of scheduling times per day is 96 times.
[0090] Limiting factors: Subject to the constraints of hydrogen energy storage, power balance and HDCS.
[0091] 2) Self-consistent model of low-level traffic network islands:
[0092] Based on the two-way coupling framework of island new energy and transportation network, the objective function of low-carbon economic optimization scheduling was established, which includes two parts: one is to maximize the self-consistency rate of system electricity and hydrogen energy; the other is to minimize the carbon emission cost of the system.
[0093] The objective function is as follows:
[0094]
[0095]
[0096] In formulas (23)-(26), η refers to the daily self-consistency rate of the offshore island combined with electricity, hydrogen and transportation; F E is the electricity load on the island; F DG is the output power of distributed generation; F H is the hydrogen load of the transportation network; F q is the energy supply and output of the hydrogen refueling station; F is the carbon emission cost; α refers to the tax amount of carbon emissions; refers to the carbon emission cost; C c is the carbon trading price; c is the basic unit carbon price; β is the step-by-step price increase; v is the interval length of carbon emissions; γ represents the incentive coefficient in the carbon trading price; E g is the actual carbon emission generated by starting the diesel generator; a1, b1, c1 are the carbon emission calculation coefficients of the diesel generator; E c is the carbon emission quota of diesel generator power generation; χ is the carbon emission quota per unit of electricity; P t E It is the electricity generated by the diesel generator per unit time; △t refers to the scheduling time interval.
[0097] Restrictive factors: distribution network operation constraints, electrolyzer equipment operation constraints, hydrogen fuel cell equipment operation constraints, HFCS and hydrogen refueling station operation constraints, and hydrogen energy storage equipment operation constraints.
[0098] In step 3, an improved dung beetle algorithm (IDBO) is used to balance local optimization and global optimization capabilities using an action variation strategy based on population similarity and a reverse learning strategy.
[0099] The dung beetle optimization algorithm has fast convergence speed and strong optimization ability, but it also has defects such as uneven initial population distribution, unbalanced global exploration and local development capabilities, easy to fall into local optimization, and unable to effectively search the entire solution space, and cannot obtain the optimal solution. Therefore, the present invention proposes an improved dung beetle optimization algorithm (IDBO).
[0100] The DBO algorithm mainly consists of four steps:
[0101] Step3-1: Ball rolling behavior:
[0102] The feces behavior of dung beetles can be divided into obstacle mode and barrier-free mode. When there are no obstacles, the intensity of the light source will affect the dung beetles, and the position update during the rolling behavior is shown in the following formula 27; when encountering obstacles and unable to move forward, the tangent function is used to simulate the dance behavior, and the position update is shown in the following formula 2.
[0103]
[0104] In formula (27), x i t is the position of the i-th individual in the t-th iteration; λ is a random deflection coefficient in [0,1], which is -1 or 1 randomly; b is a random coefficient, x worst It is the worst individual position.
[0105] Step3-2: Reproductive behavior:
[0106] As shown in the following expression (28), after the spawning area is determined, the position of the young ball changes as shown in the following formula 29.
[0107] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time.
[0108]
[0109] x i t+1 =x lbest +b1×(x i t -Lb * )+b2×(x i t -Ub * ) (29);
[0110] In formulas (28) and (29), x lbestis a local optimal solution; t max is the maximum number of iterations, t is the current number of iterations; Lb is the lower bound, Ab is the upper bound; b1 and b2 are two independent random vectors of D dimension.
[0111] Step 3-3: Foraging behavior
[0112] The foraging area is simulated by using a boundary selection strategy, as shown in the following formula 30. When foraging in a local area, the position of the dung beetle is updated as shown in formula 31.
[0113]
[0114] In formulas (30) and (31), x gbest is the global optimal solution, C1 is a D-dimensional random vector with normal distribution, and C2 is a D-dimensional random vector with [0,1].
[0115] Step 3-4: Stealing behavior:
[0116] The best food sources are in the places that are best suited for competition. The locations of the oyster-stealing mantises are updated below:
[0117]
[0118] In formula (32), s is a constant and g is a D-dimensional random vector that obeys the normal distribution.
[0119] The IDBO algorithm targets the uneven distribution ratio of the four actions of the original dung beetle algorithm. Each individual can only perform one action, which may lead to insufficient search of the solution space or slow convergence. The present invention adopts an action variation strategy based on population similarity and a reverse learning strategy to improve DBO.
[0120] Improvement point 1: Dungeon action variation strategy based on population similarity:
[0121] In order to make each dung beetle perform four actions, the present invention simulates the change of time with the number of iterations, and mutates the actions of the dung beetle every m iterations, and mutates the current action into the next behavior strategy. Cosine similarity is used to measure population similarity, and population diversity is expressed as follows:
[0122]
[0123] In formula (33), Diver is an indicator to measure the degree of convergence; x i,j (t) refers to the position of the dung beetle; x glbest,j (t) refers to the global optimal solution; N refers to the number of chaotic sequences; d refers to the number of local optimal solutions;
[0124] When Diver is greater than 0.5, the population diversity is too low and may fall into a local optimum. The ability to explore the solution space and the speed of convergence are determined by the number of dung beetles rolling the ball and foraging for food.
[0125] Therefore, the individuals that perform reproduction and foraging behaviors are mutated into individuals that perform rolling behaviors, and the global search ability is enhanced to enhance species diversity, so that when the iteration threshold T of the mutated individuals is reached, max After that, it is possible to find a new best individual or restore the mutated individual to the original behavior individual to continue searching.
[0126] Improvement point 2: Reverse learning strategy:
[0127] Since the global search ability of reproduction and stealing behavior will decrease with the increase of iteration number, and the idea of the reverse learning strategy is to select a better solution by generating the reverse solution of the current feasible solution and comparing the fitness of the reverse solution with the original solution, the present invention uses the reverse learning strategy to improve the global search performance of reproduction and stealing:
[0128]
[0129]
[0130] In formula (34) and formula (35), is the inverse solution; lb and ub are D-dimensional vectors, representing the lower and upper bounds of each dimension respectively; rand() is a D-dimensional random vector, x i t is the current feasible solution; f(x i t ) refers to the objective function corresponding to the position update, Refers to the objective function corresponding to the inverse solution.
[0131] In summary, Figure 3 Shows the flow of the IDBO algorithm.
[0132] In step 4, an improved IEEE standard 6-node grid structure is proposed with a rated voltage of 10KV. The island is equipped with a diesel generator with a rated power of 400kW, a wind turbine with a rated power of 180kW, and a photovoltaic device with a power of 200kW, which represent renewable energy generation. In the transportation network, a main station and two substations are designed, and coupled through a hydrogen refueling station. Through simulation verification, it is concluded that compared with the traditional DBO algorithm, the improved dung beetle algorithm (IDBO) has higher speed and accuracy; the transportation network hydrogenation model can effectively reduce the user's hydrogenation cost and peak-to-valley difference. The details are as follows:
[0133] An island was selected as the research subject. The grid structure of the island adopted an improved IEEE standard 6-node grid model, with a rated voltage set to 10 kV and appropriately scaled according to actual needs. In order to ensure the stable operation of the grid and respond to emergencies, a diesel generator with a rated power of 400 kW was installed on the island as a backup power source. In addition, the island's energy supply also integrates two forms of renewable energy, wind energy and solar energy, which are achieved through a wind turbine with a rated power of 180 kW and a photovoltaic power generation system with a power capacity of 200 kW. The detailed system design and layout can be found in Figure 2 In the planning of the transportation network, the present invention designs a central main site and two auxiliary sites, and effectively couples the power system and the transportation system by establishing a hydrogen refueling station.
[0134] The invention provides an island electricity-hydrogen transmission coupling optimization scheduling method based on an improved dung beetle algorithm, and the beneficial effects are as follows:
[0135] 1. By building a self-consistent energy system, the present invention can make full use of new energy resources and flexible adjustment resources in the maritime transportation network, significantly improve the energy self-sufficiency of island areas, and reduce dependence on external energy supply.
[0136] 2. The present invention reveals that when the output of distributed energy is limited and hydrogen storage is insufficient, over-reliance on diesel generators will lead to an increase in the system's carbon emission costs. Through the deep integration of STHS and SHS with electricity, hydrogen and transportation systems, the self-consistency rate of energy can be greatly improved, thereby effectively reducing carbon emission costs and reducing environmental pollution.
[0137] 3. The STHS and SHS collaborative mechanism of the hydrogen refueling station realizes the multi-temporal and spatial transfer of energy. This innovative energy management strategy brings extremely high energy self-consistency and extremely low carbon emission costs, proving that improving energy self-consistency plays a key role in promoting energy coordination among systems, reducing dependence on high-carbon emission diesel generators, and achieving the dual goals of economic benefits and environmental protection.
[0138] 4. The present invention has carried out refined mathematical modeling for the new energy, maritime transportation network and hydrogen energy storage system of ocean islands, as well as the operational constraints of short-term hydrogen energy storage and SHS services, and established a two-level optimization scheduling model for electricity, hydrogen and transportation coupling, using improved dung beetle empirical verification and broad application prospects: Through example simulation analysis, the optimization scheduling method of the present invention has proved its feasibility and effectiveness, providing strong technical support and practical guidance for the low-carbon economic operation of islands and maritime transportation networks under the background of energy transformation, and also providing valuable experience and inspiration for energy management and sustainable development strategies in similar scenarios. The optimization algorithm is efficiently solved to ensure the high accuracy and practicality of the model.
[0139] 5. Through example simulation analysis, the optimization scheduling method of the present invention has proved its feasibility and effectiveness, providing strong technical support and practical guidance for the low-carbon economic operation of islands and maritime transportation networks under the background of energy transformation. It also provides valuable experience and inspiration for energy management and sustainable development strategies in similar scenarios. BRIEF DESCRIPTION OF THE DRAWINGS
[0140] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments:
[0141] Figure 1 It is a schematic diagram of the bidirectional coupling structure of the island energy system and the marine transportation network of the present invention.
[0142] Figure 2 This is a diagram of the improved IEEE 6-node system of the present invention.
[0143] Figure 3 This is a diagram of the model solving process based on IDBO of the present invention.
[0144] Figure 4(a) is a graph showing the output of landscape distributed energy in implementation;
[0145] FIG4( b ) is a graph of the power load during implementation;
[0146] FIG4( c ) is a graph showing the hydrogen load during implementation;
[0147] Figure 4(d) is a real-time hydrogen price chart during implementation.
[0148] Figure 5 It is a schematic diagram of the iteration of the basic data algorithm of the present invention;
[0149] Figure 6 This is the optimized hydrogenation data diagram of the present invention.
[0150] Figure 7 This is the operation status of the master station of scheme 4 of the present invention.
[0151] Figure 8 This is the operation status of substation 1 of scheme 4 of the present invention.
[0152] Fig. 9 This is the operation status of substation 2 of scheme 4 of the present invention. DETAILED DESCRIPTION
[0153] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.
[0154] like Figure 1 The figure shows the bidirectional coupling architecture of the island energy system and the marine transportation network, including the power network based on HFCS and the marine transportation network. Figure 3 Shows the flow of the IDBO algorithm.
[0155] In order to verify the effectiveness of the improved algorithm and the feasibility of the method for improving energy self-consistency and reducing the carbon emission cost of islands, the present invention proposes an improved IEEE standard 6-node grid structure and selects an island as the research subject for simulation experiments.
[0156] The island's power grid structure adopts an improved IEEE standard 6-node power grid model, with a rated voltage set to 10 kV and appropriately scaled according to actual needs. In order to ensure the stable operation of the power grid and respond to emergencies, a diesel generator with a rated power of 400 kW is installed on the island as a backup power source. In addition, the island's energy supply also integrates two forms of renewable energy, wind power and solar energy, which are achieved through a wind turbine with a rated power of 180 kW and a photovoltaic power generation system with a power capacity of 200 kW. The detailed system design and layout can be found in Figure 3 In the planning of the transportation network, the present invention designs a central main site and two auxiliary sites, and effectively couples the power system and the transportation system by establishing a hydrogen refueling station.
[0157] In the example of electric-hydrogen transportation coupling, the main hydrogenation station is equipped with STHS and SHS. The hydrogenation substation only has STHS, that is, the hydrogenation substation cannot transport hydrogen energy to the main hydrogenation station, and the hydrogenation substations cannot assist each other. If the wind-solar distributed energy cannot meet the demand for hydrogen load, the STHS of the hydrogenation station will make up for it first. If hydrogen energy is still in short supply, the SHS of the hydrogenation station will be called by the transport ship.
[0158] This example uses 24 hours a day as the scheduling cycle, the unit scheduling time is 15 minutes, and the landscape is 15 minutes. The output curve of landscape distributed energy is shown in Figure 4(a), and the electricity load curve is shown in Figure 4(b). The hydrogen load curve is shown in Figure 4(c). The maximum number of HFCS per day at the main hydrogen station is 10, and the maximum number of HFCS per day at sub-stations 1 and 2 is 6. The real-time hydrogen price in the area is shown in Figure 4(d). The total capacity of the hydrogen storage equipment at the main hydrogen station is 40kg, and the total capacity of the hydrogen storage system at the substation is 20kg. The transportation time of the hydrogen transport ship is 4 pm, and the diesel generator consumes 1kW·h to produce 0.96kg carbon dioxide and 25.2g hydrogen.
[0159] First, the IDBO and DBO algorithms are compared. The comparison of the main station algorithms is as follows Figure 5 As shown. Figure 5Compared with the traditional DBO algorithm, IDBO has higher speed and accuracy. Therefore, the present invention uses IDBO to optimize the original hydrogenation data. The comparison before and after optimization is shown in Table 1. The optimized hydrogenation data is shown in Table 1. Figure 6 shown.
[0160] Table 1 Optimization comparison results
[0161]
[0162] In comparison, the hydrogenation price at the port decreased by 21.4%, and the peak value decreased by 16.0% relative to the trough value. The hydrogenation rate at port 1 decreased by 38.2%, and the peak-to-valley difference decreased by 34.0%. The hydrogenation cost at substation 2 decreased by 37.4%, and the peak-to-valley difference decreased by 32%. It can be seen that the transportation network hydrogenation model can effectively reduce the user's hydrogenation cost and peak-to-valley difference.
[0163] Comparative analysis of solutions:
[0164] Taking four schemes as examples, the hydrogen energy-saving method of each scheme is shown in Table 2.
[0165] Table 2 Hydrogen energy storage solutions
[0166]
[0167] Note: indicates that the situation has been taken into account, indicates that it has not been taken into account.
[0168] According to the requirements of the power distribution system, the comprehensive power supply on the island meets the needs of the power load, and the power consumption degree is 100%. We analyze the compatibility level of hydrogen energy from the energy demand of the hydrogen load, and select the corrected hydrogenation data and the hydrogen production process of the hydrogen base. Table 3 shows the calculation results of the energy balance level and carbon cost of each system.
[0169] Table 3 Calculation results of hydrogen storage scheme
[0170]
[0171] Note: This situation is not considered.
[0172] The analysis results of the examples in Table 3 show that:
[0173] 1) In Scheme 2, the energy self-consistency rate of the hydrogen station is increased by 17.06% compared with Scheme 1, and the carbon emission cost is reduced by 91.5%. The calculation results show that STHS can effectively improve the energy self-consistency rate and reduce carbon emissions.
[0174] 2) In Scheme 3, the energy self-consistency rate of hydrogenation substation 1 increased by 12.81% and the carbon emission cost decreased by 42.3%, while that of substation 2 increased by 15.74% and the carbon emission cost decreased by 37.7%. The calculation results show that SHS can improve the energy self-consistency rate and reduce carbon emissions.
[0175] 3) By comparing Scheme 2 and Scheme 3, it can be seen that STHS is superior to SHS in the case of a single hydrogen storage configuration. Since STHS has the characteristics of local energy utilization and cross-time balance, it meets the requirements of local energy consumption and high self-consistency of the system.
[0176] 4) The four schemes were compared and analyzed, and the calculation results of Scheme 4 were the best. Therefore, the combination of STHS and SHS is the best choice to improve energy self-consistency and reduce carbon emissions. The order of hydrogen energy supply is: hydrogen production from surplus electricity of wind and light distributed energy, STHS, SHS and diesel generators.
[0177] In Scheme 4, the hydrogen refueling terminal has STHS and SHS. If the remaining hydrogen energy is less than 0.8kg, all of it is stored in STHS; if the remaining hydrogen energy is greater than 0.8kg, 0.8kg is STHS and the remaining hydrogen energy is shared energy storage, such as Figure 7 The operation of the master station and substation 1 and substation 2 is as shown. Figure 8 and Fig. 9 shown.
[0178] The above optimization results show that:
[0179] 1) In Figure 7 Among them, the energy self-consistency of Scheme 4 and Scheme 2 is 95.15%, because in these two schemes, the hydrogenation terminal only has STHS and needs to rely on diesel generators to generate electricity and produce hydrogen.
[0180] 2) In Figure 8 In the project, STHS and SHS jointly supported the operation of hydrogenation substation 1, with an energy self-consistency rate of 97.07%. It purchased electricity from the upper power grid to generate 14.28 kg of hydrogen, generating a carbon emission cost of 3.13 yuan.
[0181] 3) In Fig. 9 In the experiment, STHS and SHS jointly support the operation of hydrogenation substation 2, and the energy self-consistency rate reaches 100%, so there is no need for diesel generators to generate electricity, and there is no carbon emission cost. It can be seen that improving the energy self-consistency rate can effectively reduce carbon emission costs.
[0182] 4) In the early hours of the morning, the output of wind and solar distributed energy is small and hydrogen reserves are insufficient, so the island needs to rely on diesel generators to generate electricity.
[0183] 5) After 18:00, the output of wind and solar distributed energy decreased, but the demand for HFC hydrogenation increased, which made the hydrogen production of the surplus electricity unable to meet the demand of hydrogen load. First, the shared energy storage of the hydrogenation substation was supplemented. The above optimization results show that the self-consistent energy system is of great value in reducing carbon emissions and improving the energy self-consistency rate.
Claims
1. An island electricity-hydrogen transmission coupling optimization scheduling method based on an improved dung beetle algorithm is characterized by The following steps are involved: Step 1: Considering self-sufficiency and shared hydrogen storage (SHS), a two-way coupling framework is constructed to design the overall scheme of hydrogen fuel cell ship (HFCS) transportation network and island new energy system; Step 2: Considering the operation constraints of new energy, marine transportation network, hydrogen energy storage system and short-distance transportation system, an electricity-hydrogen-transportation coupling model and an island double-layer optimization scheduling model are constructed; Step 3: Use the improved Dung Beetle Algorithm (IDBO) to solve the electricity-hydrogen-transportation coupling model and the island two-layer optimization scheduling model constructed in step 2, and output the optimal solution.
2. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 1 is characterized by: It also includes step 4: an improved IEEE standard 6-node grid structure is proposed to verify the feasibility of the method to improve the energy self-consistency rate and reduce the carbon emission cost of the island, as well as the effectiveness of the improved dung beetle algorithm (IDBO).
3. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 1 is characterized by: In step 1, the bidirectional coupling architecture includes a power network mainly based on HFCS and a marine transportation network.
4. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 3 is characterized by: In the step 1, the overall plan of the hydrogen fuel cell ship (HFCS) transportation network and the island new energy system is designed, including: the island energy system is responsible for the access of distributed new energy, power supply of power loads, diesel generator interface, and power supply of water electrolysis hydrogen production equipment; the distributed new energy first supplies power to the isolated island load, and the remaining power can be converted into hydrogen energy for use by the hydrogen fuel cell ship (HFCS) or the hydrogen energy storage system; the hydrogenation main station and the substation of the marine transportation network provide energy for the hydrogen fuel cell ship (HFCS), and the short-term hydrogen energy storage (STHS) and shared hydrogen storage (SHS) can make up for the lack of hydrogen energy; In addition, hydrogen energy storage systems can also supply power to electrical loads during peak periods.
5. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 1 is characterized by: In step 2, the electricity-hydrogen-transportation coupling model includes a load center island model, which is as follows: The load center island is equipped with a comprehensive power supply system of active power, network power and load. During operation, power flow constraints, line transmission power constraints, voltage over-limit, diesel generator output constraints and distributed energy output constraints are considered; 1) Power flow constraints: In formula (1), P DG Refers to the active power of distributed renewable energy, Refers to the active power of the diesel generator, Refers to the active power of energy storage, Refers to the active power of the load; Q DG Refers to the reactive power of distributed renewable energy, Refers to the reactive power of the diesel generator, Reactive power of energy storage, Refers to the reactive power of the load; U i is the voltage amplitude at node i; U j represents the voltage amplitude at node j, θ ij is the power angle between nodes i and j; j∈i means that the source, storage and payload are correctly connected to node i; G ij Refers to the conductivity parameter of the system, B ij Refers to the susceptance parameter of the system; 2) Line power limitation: -P l,max ≤U i U j (G ij cosθ ij +B ij sinθ ij )≤P l,max (2); In formula (2), P l,max is the maximum transmission power; 3) Voltage constraints: IN min ≤U i ≤U max (3); In formula (3), U min , U max are the upper and lower limits of the node voltage amplitude, respectively; 4) Output constraints of diesel generators: In formula (4), Refers to the output power of the diesel generator; is the maximum output of the diesel generator; is the minimum output; 5) Wind-solar distributed energy output constraints: In formula (5), P WT (t) refers to the output power of wind energy; P PV (t) refers to the output power of solar energy; are the minimum outputs of wind and solar distributed energy resources, respectively; They are the maximum output of wind and solar distributed energy respectively.
6. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 5 is characterized by: In step 2, the electricity-hydrogen-transportation coupling model includes a hydrogen energy storage model and an operation and maintenance cost model; specifically, it includes: (1) Hydrogen production model of wind-solar distributed energy surplus power: In formula (6), P ex (t) refers to the surplus power of wind-solar distributed energy in period t; P eP2G (t) refers to the electricity used by the hydrogen electrolysis module in cycle t; P pv (t), P wind (t) are the outputs of wind energy and solar energy distributed energy in period t; P e-load (t) is the power load in period t; η P2G is the energy conversion efficiency; is the hydrogen storage capacity in period t, The upper limit of the capacity of hydrogen storage equipment; (2) Hydrogen energy storage model: Hydrogen energy storage consists of hydrogen storage tanks, hydrogen production devices and hydrogen fuel cells; the tanks store hydrogen, the electrolytic hydrogen production device consumes electricity to produce hydrogen, and the battery provides electricity by burning hydrogen; the calculation process of the energy stored in the tank is as follows: In formula (7), the variable t represents the sequence number of the scheduling period; represents the energy in the energy storage in the t scheduling period; η P2G and η FC are the energy conversion efficiencies of the hydrogen production device and the battery respectively; △t represents the time span of the scheduling cycle; P eP2G (t) is the power used by the hydrogen electrolysis module in cycle t; P FC (t) is the electricity used by the hydrogen electrolysis module in period t; (3) Operation and maintenance cost model: Lifetime attenuation cost corresponding to hydrogen energy storage power fluctuation: In formula (8), K λ_FL represents the lifetime decay cost corresponding to the unit fluctuating power of the device and the fuel cell; P λ_t Represents the electrical power of the hydrogen production device and hydrogen fuel cell; r λ_t Indicates the start-stop status of the device and fuel cell; P λ_t-1 represents the electric power of the hydrogen production device and hydrogen fuel cell, r λ_t-1 Indicates the start-stop status of the equipment and fuel cell; ED stands for hydrogen production by electrolysis, and FC stands for hydrogen fuel cell; Indicates the start-stop state of the device and the fuel cell; T indicates the running time; The start-up and shutdown costs of the hydrogen production device and fuel cell are shown in the following formula: In formula (9) and formula (10), K λ_SU and K λ_SD are the unit start-stop costs of the device and the fuel cell, respectively; r λ_SU_t and r λ_SD_t The start-stop state of the device and the fuel cell are shown respectively; C λ_SU represents the start-up and shutdown cost of the hydrogen production device, C λ_SD represents the start-stop cost of the fuel cell; Maintenance costs of the device and hydrogen fuel cells: In formula (11), K λ_OM represents the maintenance cost per unit time of the hydrogen production device and the fuel cell; C λ_OM represents the maintenance costs of the device and hydrogen fuel cells; The lifetime decay cost corresponding to the historical operating time of the device and fuel cell is shown as follows: In formula (12), K λ_AGE It refers to the life decay cost corresponding to the unit operating time of the device / fuel cell; T λ_LT Indicates the expected life of the device / hydrogen fuel cell; C λ_AGE Refers to the lifetime decay cost corresponding to the historical operating time of the device and fuel cell; The total operating cost of hydrogen energy storage is:
7. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 6 is characterized by: The electricity-hydrogen-transportation coupling model includes a maritime transportation network model, as follows: The hydrogen load of the hydrogen fuel cell ship (HFCS) is affected by mileage, return time and the supply and demand relationship of hydrogen refueling stations. The transportation network model is established as follows: The probability density function of the last return time of daily users is: In formula (14), x t is the user's last return time; ψ t is the expected value, γ t is the standard deviation; The probability density function of the mileage of hydrogen fuel cell ship (HFCS) users is defined as: In formula (15), x s is the user's last return time; ψ s is the expected value, γ t is the standard deviation; The hydrogen refueling duration of a hydrogen fuel cell ship (HFCS) is: In formula (16), T s is the duration of hydrogenation; S refers to daily mileage; P s is the amount of hydrogenation; σ s is the hydrogenation efficiency; E Refers to the hydrogen consumption per unit kilometer; Single station hydrogenation requirements: N m,HFCS ≤N m,H (17); In formula (17), N m,HFCS is the amount of existing HFCS in the mth hydrogen refueling station, N m,H It refers to the amount of HFCS that can be accepted by the mth hydrogen refueling station; Total hydrogen refueling demand in the transportation network: In formula (18), M is the number of hydrogen refueling stations in the transportation network; M m,cqz is the capacity of the mth hydrogen storage station; M e,HFCS is the capacity of the e-th HFCS; N HFCS is the amount of HFCS; m refers to an element in the capacity of the hydrogen storage station; e refers to an element in HFCS; Short-term hydrogen storage model: In formula (19), They are the hydrogen storage per unit time, hydrogen release per unit time and total short-term hydrogen storage; are the hydrogen storage efficiency, hydrogen release efficiency and self-release rate of STHS; C STHS is the configuration capacity of STHS; Δt is the unit time step; refers to the self-release rate of STHS; Refers to the total amount of short-term hydrogen storage at the time of the last dispatch; Shared hydrogen energy storage mode: In formula (20), They are the hydrogen storage capacity per unit time, the hydrogen release capacity per unit time and the total amount of hydrogen remaining in the hydrogen storage; are the hydrogen storage efficiency, hydrogen release efficiency and self-release rate of SHS respectively; C SHS Refers to the configuration capacity of SHS; SHS is used when STHS cannot meet the hydrogen load, and its use order is: real-time hydrogen replenishment > short-term hydrogen energy storage (STHS) > shared hydrogen storage (SHS); The hydrogenation of hydrogen fuel cell ships (HFCS) should meet certain conditions. The actual amount of hydrogen should not exceed the total capacity of the battery, but at the same time it should not be less than the amount of hydrogen expected by the user. When the ship owner connects the HFCS to the hydrogenation pile, the user's own expected information and the expected state of hydrogen charge when leaving the hydrogenation pile are assumed to be S. h , when the user decides to leave, the actual hydrogen amount of HFCS should be greater than or equal to the expected value, expressed as: In formula (21), S st,i is the hydrogen loading state when the i-th HFCS starts hydrogenation, S en,i is the hydrogen loading state when the i-th HFCS leaves.
8. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 7 is characterized by: The island dual-layer optimization scheduling model includes the upper-layer traffic network island operation mode and the lower-layer traffic network island self-consistent model; including: 1) Upper-level transportation network island operation mode: Objective function: In formula (22), f1 represents the operating cost of the island, where C HS , C WT , C PV represent the energy storage and operation costs of hydrogen, wind power generation equipment and photovoltaic power generation equipment respectively; f2 represents the hydrogen refueling cost; x ij is the hydrogenation status of the i-th ship in period j, which has two values: 0 or 1, 0 means no hydrogenation, and 1 means hydrogenation; p i is the power of the ith measurement container; p j represents the price of hydrogen during period j; N represents the number of HFCS ships; △t refers to the scheduling time interval; N represents the number of HFCS ships; 2) Self-consistent model of low-level traffic network islands: The objective function is as follows: In formulas (23)-(26), η refers to the daily self-consistency rate of the offshore island combined with electricity, hydrogen and transportation; F E is the electricity load on the island; F DG is the output power of distributed generation; F H is the hydrogen load of the transportation network; F q is the energy supply and output of the hydrogen refueling station; F is the carbon emission cost; α refers to the tax amount of carbon emissions; refers to the carbon emission cost; C c is the carbon trading price; c is the basic unit carbon price; β is the step-by-step price increase; v is the interval length of carbon emissions; γ represents the incentive coefficient in the carbon trading price; E g is the actual carbon emission generated by starting the diesel generator; a1, b1, c1 are the carbon emission calculation coefficients of the diesel generator; E c is the carbon emission quota of diesel generator power generation; χ is the carbon emission quota per unit of electricity; P t E It is the electricity generated by the diesel generator per unit time; △t refers to the scheduling time interval.
9. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 1 is characterized by: In step 3, an improved dung beetle algorithm (IDBO) uses an action variation strategy based on population similarity and a reverse learning strategy to balance local optimization and global optimization capabilities; The action variation strategy and reverse learning strategy based on population similarity are used to improve DBO. Improvement point 1: Dungeon action variation strategy based on population similarity: In order to make each dung beetle perform four actions, the change of time with the number of iterations was simulated, and the actions of the dung beetles were mutated every m iterations, and the current actions were mutated into the next behavior strategy; cosine similarity was used to measure population similarity, and population diversity was expressed as follows: In formula (33), Diver is an indicator to measure the degree of convergence; x i,j (t) refers to the position of the dung beetle; x glbest,j (t) refers to the global optimal solution; N refers to the number of chaotic sequences; d refers to the number of local optimal solutions; When Diver is greater than 0.5, the population diversity is too low and may fall into a local optimum; the ability to explore the solution space and the convergence speed are determined by the number of dung beetles rolling the ball and foraging for food; Therefore, the individuals that perform reproduction and foraging behaviors are mutated into individuals that perform rolling behaviors, and the global search ability is enhanced to enhance species diversity, so that when the iteration threshold T of the mutated individuals is reached, max Afterwards, it is possible to find a new best individual or restore the mutated individual to the original behavior individual to continue searching; Improvement point 2: Reverse learning strategy: Use a reverse learning strategy to improve the global search performance of breeding and stealing: In formula (34) and formula (35), is the inverse solution; lb and ub are D-dimensional vectors, representing the lower and upper bounds of each dimension respectively; rand() is a D-dimensional random vector, x i t is the current feasible solution; f(x i t ) refers to the objective function corresponding to the position update, Refers to the objective function corresponding to the inverse solution.
10. The island electricity-hydrogen transmission coupling optimization scheduling method based on the improved dung beetle algorithm according to claim 2 is characterized by: In step 4, an improved IEEE standard 6-node grid structure is proposed, with a rated voltage of 10KV, and the island is equipped with a diesel generator with a rated power of 400kW, and a wind turbine with a rated power of 180kW and a photovoltaic device with a power of 200kW representing renewable energy generation; In the transportation network, a main station and two substations are designed, and coupled through a hydrogen refueling station.