Overpass existing large karst subsidence area station foundation pit water inrush risk disposal method
By determining the groundwater leakage point in the karst-developed formation and applying water-stop walls and curtains, combined with the use of water-based polyurethane grouting materials, the problem of groundwater surge in the station foundation pit is solved, ensuring the safety and stability of foundation pit construction , avoid excessive deformation and pit collapse of the ground connecting walls.
Patent Information
- Application Number
- CN202411198931.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-29
AI Technical Summary
In the station foundation pits constructed in the karst-developed formation, the sudden surge of groundwater causes the construction quality of ground-connected walls to be difficult to ensure and the water cannot be effectively stopped, resulting in serious accidents such as sharp increase in the load-connected walls and failure of support in the foundation pit.
The groundwater leakage point is determined by determining the groundwater leakage point at the ground water outlet point in the foundation pit, forming a water stop wall and a water stop curtain, blocking the hydraulic supply, and injecting water-based polyurethane grouting material into the periphery of the leakage point to reduce the fluidity and leakage characteristics of groundwater.
It effectively reduces the risk of sudden influx of groundwater in the foundation pit, avoids excessive deformation of the ground wall and pit collapse, ensures the safety and stability of foundation pit construction, and prevents surface structures from being affected.
Smart Images

Figure CN119041465A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of foundation pit construction, and more specifically, to a method for dealing with the risk of sudden water inrush in a station foundation pit that crosses an existing large karst collapse area. Background Art
[0002] In recent years, the geological conditions and environment of deep foundation pit excavation and construction have become increasingly complex, and the number of engineering accidents has also increased, resulting in greater losses. In deep foundation pit engineering, a task that concerns the overall situation is the prevention and control of groundwater, especially in areas with poor geology such as areas with strong karst cave development. Groundwater is the natural enemy of deep foundation pit engineering and one of the most direct causes of foundation pit engineering accidents. Among the accidents caused by groundwater to foundation pits, accidents caused by bottom pressurized water account for a large part. The treatment of pressurized water is difficult, and the consequences of improper treatment are serious. It is one of the key points and difficulties in foundation pit design. When constructing a station foundation pit in a stratum with strong karst development, when karst pours into the construction range of the ground-connected wall, due to the uncontrollability of the bottom karst cave range and boundaries, there is a risk that the ground-connected wall will not be embedded in the bottom of the cave during construction, causing the ground-connected wall to be cantilevered within the karst cave range. The construction quality of the ground-connected wall is difficult to effectively guarantee, and it cannot achieve a good water-stopping effect. When there are caves with groundwater at the bottom of the foundation pit, sudden water inrush is very likely to occur during the excavation of the foundation pit. In severe cases, the stress on the diaphragm wall in the foundation pit increases sharply, and the support of the diaphragm wall fails and collapses. Due to the replenishment of groundwater in large areas of caves, large-scale ground collapse outside the pit may occur. Therefore, there is an urgent need for a method to deal with the sudden water inrush at the bottom of the pit when excavating a foundation pit with a diaphragm wall without exploring the bottom under the conditions of strongly developed karst formations, so as to avoid serious accidents. Summary of the invention
[0003] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.
[0004] In order to achieve these purposes and other advantages according to the present invention, a method for dealing with water inrush risk in a station foundation pit that crosses an existing large karst collapse area is provided, comprising the following steps:
[0005] S1. Determine the groundwater leakage point and the groundwater seepage path according to the ground water outlet point in the foundation pit;
[0006] S2. Drill holes around the groundwater leakage points and inject grout to form a water stop wall to cut off the hydraulic supply in the foundation pit;
[0007] S3. If the groundwater leakage point determined in step S1 is close to the ground-connected wall, a water-stop curtain is installed at the position corresponding to the leakage point outside the foundation pit to reduce the hydraulic supply outside the foundation pit;
[0008] S4. Drill holes around the periphery of each underground water leakage point and inject water-based polyurethane grouting material.
[0009] Preferably, in step S1, if the ground water outlet point is close to the ground-connected wall, a row of exploration holes are made along the ground-connected wall in the area where the ground water outlet point is located, and the formed exploration holes are filled with sleeve valve pipes. By drilling holes and observing the water outlet of the sleeve valve pipes, the groundwater leakage point and seepage path are determined.
[0010] Preferably, in step S1, if the ground water outlet point is far away from the ground connection wall, a circle of exploration holes are drilled with the ground water outlet point as the center, and the formed exploration holes are filled with sleeve valve pipes. By drilling holes and observing the water outlet of the sleeve valve pipes, the groundwater leakage point and seepage path are determined.
[0011] Preferably, during the drilling process of each exploration hole, when the drill rod is pulled out, if leakage occurs at the hole mouth, it is judged as a groundwater leakage point; if there is no obvious leakage at the hole mouth, it is judged as not a groundwater leakage point; the drilling position of each groundwater leakage point is recorded, and the groundwater seepage path is drawn.
[0012] Preferably, in step S2, if the underground leakage point is close to the ground-connected wall, multiple rows of water-stop holes are set along the groundwater seepage path, wherein the outermost row of U-shaped water-stop holes is combined with the ground-connected wall to enclose the underground water leakage points; grouting is performed in each formed water-stop hole, and a water-stop wall is formed after the slurry solidifies.
[0013] Preferably, in step S2, if the underground leakage point is far away from the ground-connected wall, multiple circles of O-shaped water-stopping holes are made with the underground leakage point as the center; grouting is performed in each formed water-stopping hole, and a water-stopping wall is formed after the slurry solidifies.
[0014] Preferably, each water stop hole is drilled to 1-2m below the design elevation of the foundation pit bottom and arranged in a plum blossom shape; the grouting liquid in the water stop holes is a mixture of cement slurry and water glass slurry in a volume ratio of 1:1.
[0015] Preferably, in step S3, a high-pressure rotary jet water-stopping curtain is applied along the ground-connected wall at the location corresponding to the leakage point outside the foundation pit, and the rotary jet piles are extended to 1-2 m below the bottom of the cave. The length of the water-stopping curtain is at least 0.5 m outside the groundwater seepage path.
[0016] Preferably, in step S4, a number of velocity reduction holes are made within 50 cm of the periphery of each groundwater leakage point, and water-based polyurethane grouting material is injected; and the polyurethane injection amount is determined by the groundwater flow rate and water-based polyurethane outflow conditions of adjacent groundwater leakage points.
[0017] Preferably, after the injection of the water-based polyurethane grouting material is stopped, the groundwater leakage situation at the leakage point is continuously observed after standing for a period of time. If the groundwater flow velocity does not decrease, the water-based polyurethane grouting material is continuously injected into each velocity reduction hole position corresponding to the groundwater leakage point.
[0018] The present invention has at least the following beneficial effects:
[0019] The method for dealing with the risk of sudden water inrush in a station foundation pit that crosses an existing large-scale karst collapse area provided by the present invention first determines the groundwater leakage point and the groundwater seepage path, then constructs a water-stopping wall around the groundwater leakage point to cut off the hydraulic supply in the foundation pit, so that the groundwater at the leakage point has no other hydraulic supply, and reduces the pressure-bearing characteristics of the leakage water at the leakage point; then constructs a water-stopping curtain outside the foundation pit to reduce the hydraulic supply outside the foundation pit and the scouring pressure of the groundwater outside the foundation pit on the cantilever ground-connected wall, so as to avoid excessive deformation and damage of the ground-connected wall, and even collapse of the foundation pit; Finally, holes are drilled around the periphery of each groundwater leakage point and water-based polyurethane grouting materials are injected to reduce the fluidity of groundwater and block groundwater in other leakage paths at the same time. The above process can effectively reduce the risk of groundwater leakage and sudden surges during the excavation of foundation pits in the karst cave area by finding the path, blocking and reducing the pressure of the karst cave groundwater within the foundation pit ground-connected wall within the karst cave area. At the same time, it can also effectively respond to and deal with the sudden surge problems that arise, ensure the safety and stability of subsequent foundation pit construction, and protect the safety of surface structures within the influence range of the karst cave.
[0020] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the arrangement position of the detection holes when the ground water outlet point is close to the ground connection wall in step S1 of the present invention;
[0022] Figure 2 for Figure 1 A schematic diagram of the vertical cross-section structure of the detection hole described in;
[0023] Figure 3 It is a schematic diagram of the arrangement position of the water stop holes when the ground water outlet point is close to the ground connection wall in step S2 of the present invention;
[0024] Figure 4 for Figure 3 A schematic diagram of the vertical cross-section structure of the water stop hole described in;
[0025] Figure 5 A schematic diagram of the arrangement position of the water-stop curtain in step S3 of the present invention;
[0026] Figure 6 for Figure 5 A schematic diagram of the vertical cross-section structure of the water-stop curtain;
[0027] Figure 7 It is a schematic diagram of the contour line of the speed reduction hole position distribution area in step S4 of the present invention;
[0028] In the figure: 1-ground-connected wall, 2-contour of the cave at the bottom of the ground-connected wall, 3-exploration hole position, 4-filling cofferdam, 5-water-stop hole position, 6-water-stop curtain, 7-contour of the distribution area of the speed reduction hole position; DETAILED DESCRIPTION
[0029] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0030] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0031] like Figures 1 to 7 As shown, the present invention provides a method for dealing with the risk of sudden water inrush in a station foundation pit that crosses an existing large karst collapse area, comprising the following steps:
[0032] S1. Determine the groundwater leakage point and the groundwater seepage path according to the ground water outlet point in the foundation pit;
[0033] S2. Drill holes around the groundwater leakage points and inject grout to form a water stop wall to cut off the hydraulic supply in the foundation pit;
[0034] S3. If the groundwater leakage point determined in step S1 is close to the ground-connected wall 1, a water-stop curtain 6 is installed at the position corresponding to the leakage point outside the foundation pit to reduce the hydraulic supply outside the foundation pit;
[0035] S4. Drill holes around the periphery of each underground water leakage point and inject water-based polyurethane grouting material.
[0036] In this technical solution, firstly, the groundwater leakage point is determined within a certain range of the surface water outlet point in the foundation pit, and the groundwater seepage path is clarified; then, a water stop wall is constructed around the groundwater leakage point to block the surrounding water, so that the groundwater at the leakage point has no other hydraulic supply, and the pressure-bearing characteristics of the leakage water at the leakage point are reduced; considering that the hydraulic supply sources of groundwater in large caves are extensive, if the groundwater leakage point is close to the ground connection wall 1, since the ground connection wall 1 is not embedded in the bottom of the cave, the groundwater outside the foundation pit will flow around to the inside of the foundation pit, so a water stop curtain 6 is constructed along the ground connection wall outside the foundation pit. On the one hand, the groundwater outside the foundation pit is reduced from flowing around to the inside of the foundation pit, resulting in continuous leakage of the groundwater leakage point; on the other hand, a large amount of groundwater outside the foundation pit is prevented from being lost, resulting in uneven settlement of the strata outside the foundation pit, and the scouring pressure of the groundwater outside the foundation pit on the cantilever ground connection wall is reduced, so as to avoid excessive deformation and damage of the ground connection wall, and the risk of foundation pit collapse in severe cases. Based on the above measures, the groundwater leakage points are basically in a restricted state. In order to reduce the groundwater leakage characteristics and pressure bearing capacity in the area, holes are drilled around the groundwater leakage points and water-based polyurethane grouting materials are injected. The generated polyurethane gel can reduce the fluidity of groundwater and effectively block groundwater in other leakage paths, completely reducing the risk of sudden water inrush in the foundation pit, reducing the uneven settlement that may occur in the foundation pit, and ensuring the safety and stability of the station foundation pit. By finding the path, blocking, and reducing the pressure of the cave groundwater in the foundation pit ground-connected wall within the cave area, the risk of groundwater leakage and sudden surge in the process of foundation pit excavation in the cave area can be effectively reduced. At the same time, the sudden surge problem can also be effectively responded to and handled to ensure the safety and stability of subsequent foundation pit construction, providing on-site engineering and technical personnel for prevention and response.
[0037] During construction, when a ground water outlet appears in the foundation pit, before exploring the groundwater seepage path, the foundation pit can be drained first, and then a filling cofferdam 4 is constructed in the area where the ground water outlet is located, and cotton wool and gravel are laid for counter pressure. The filling cofferdam is a circular cofferdam built within a certain range with the ground water outlet as the center. The inside of the cofferdam is filled with materials such as clay and cement mortar, and connected with a drainage pipe at the ground water outlet. On the one hand, it is used to observe whether the ground water outlet has diffused, and at the same time, it provides an operating platform for subsequent groundwater blocking.
[0038] like Figure 1 and Figure 2 As shown, if the ground water outlet point is close to the ground-connected wall 1, a row of exploration holes 3 are constructed along the ground-connected wall 1 in the area where the ground water outlet point is located. The formed exploration holes 3 are filled with sleeve valve pipes, and the groundwater leakage point and seepage path are determined by drilling holes and observing the water outlet of the sleeve valve pipes.
[0039] If the ground water outlet is far away from the ground connection wall and is located inside the foundation pit, a circle of exploration holes will be drilled with the ground water outlet as the center. The formed exploration holes will be filled with sleeve valve pipes. By drilling holes and observing the water outlet of the sleeve valve pipes, the groundwater leakage point and seepage path can be determined.
[0040] The exploration holes can be drilled with a geological drill (such as model XY-2) or a drilling and grouting machine (such as model ZLJ-650). The spacing between two adjacent exploration holes can be arranged at 1.0m, and the holes should be drilled 1-2m below the bottom elevation of the ground-connected wall 1, with a hole diameter of not less than 50mm. During the drilling process of each exploration hole, when the drill rod is raised, if there is leakage at the hole mouth, it is judged as a groundwater leakage point; if there is no obvious leakage at the hole mouth, it is judged as a non-groundwater leakage point; record the drilling points of each groundwater leakage point and draw the groundwater seepage path. In order to avoid grouting, after drilling and grouting are completed, drill the next exploration hole. During the grouting process, strengthen the monitoring of concrete axial force, surface settlement, deep displacement, etc., and adjust the construction parameters in real time and dynamically according to the monitoring results.
[0041] In step S2, Figure 3 and Figure 4 As shown, if the underground leakage point is close to the ground-connected wall 1, multiple rows of water-stop holes 5 are set up along the groundwater seepage path, among which the outermost row of U-shaped water-stop holes 5 are combined with the ground-connected wall to enclose the underground water leakage points; grouting is performed in each formed water-stop hole 5, and a water-stop wall is formed after the slurry solidifies.
[0042] If the underground leakage point is far away from the ground connection wall 1 and is located inside the foundation pit, multiple circles of O-shaped water-stop holes are constructed with the underground leakage point as the center; grouting is performed in each formed water-stop hole, and a water-stop wall is formed after the slurry solidifies.
[0043] Each water stop hole is drilled to 1-2m below the design elevation of the foundation pit bottom and arranged in a plum blossom shape; the grouting liquid in the water stop hole is mixed by cement slurry and water glass slurry in a volume ratio of 1:1; the water-cement ratio of the cement slurry is 0.8:1, and the water glass and water in the water glass slurry (Baume 35-40) are mixed in a ratio of 1:1; the grouting pressure is not more than 0.5MPa, and the grouting process strengthens the monitoring of concrete axial force, surface settlement, deep displacement, etc., and the construction parameters are adjusted dynamically in real time according to the monitoring results.
[0044] In step S3, Figure 5 and Figure 6As shown in the figure, at the location corresponding to the leakage point outside the foundation pit, a high-pressure rotary jet water-stop curtain is applied along the ground-connected wall. The rotary jet pile is probed to 1-2m below the bottom of the cave, and the length of the water-stop curtain is at least 0.5m outside the groundwater seepage path. First, the pre-drilling points are measured and laid out. The leveling points, the axis of the pile and the positioning points are determined by a total station or GPS. The layout positioning and elevation measurement work are carried out according to the provided coordinate points. The deviation between the hole position of the pile and the designed position shall not exceed 50mm. After the measurement and layout, steel bars are driven in the non-disturbance position as positioning piles and well protected. The main machine is hoisted into place by a crane, the main machine power is turned on, and the main machine position and direction are fine-tuned by its own walking device so that the bottom center of the shotcrete rod is aligned with the center of the guide hole. The deviation of the center plane should not be greater than 20mm. Before inserting the grouting pipe into the hole, water and pressure are tested on the ground to check whether the grouting equipment is normal, whether the pipeline system is unobstructed, and whether the nozzle jet morphology and injection pressure are normal. The pressure and displacement of the equipment should meet the design requirements, and the sealing of the pipeline system must be good. Assemble the drill rod in sections and drill into the formation section by section until the designed depth is reached. When the slurry reaches the designed injection pressure, the grouting nozzle should only rotate or swing at the predetermined depth for 1 to 3 minutes before lifting to remove the residual clean water in the pipeline. During the high-pressure rotary grouting construction, the grouting rod rotation speed, lifting speed, slurry, water, gas pressure and flow rate should be observed or measured and recorded at any time.
[0045] In step S4, several speed reduction holes are constructed within 50 cm of the periphery of each groundwater leakage point, such as Figure 7 As shown, water-based polyurethane grouting materials are injected; and the amount of polyurethane injected is determined by the groundwater flow rate of the adjacent groundwater leakage point and the outflow of water-based polyurethane. The general judgment standard is that it is appropriate for the groundwater to bring out a small amount of polyurethane gel when it flows out, and the injection of polyurethane grouting materials can be stopped at this time;
[0046] Furthermore, after the injection of water-based polyurethane grouting material stops, the groundwater leakage is observed after a period of time. If the groundwater flow rate does not decrease, the water-based polyurethane grouting material is continuously injected into the velocity reduction holes corresponding to the groundwater leakage point. If the groundwater flow at the groundwater leakage point gradually decreases or even stops, it indicates that the generated polyurethane gel reduces the fluidity of the groundwater and effectively blocks the groundwater in other leakage paths, completely reducing the risk of sudden water inrush in the foundation pit and ensuring the safety and stability of the station foundation pit.
[0047] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. A method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area, characterized in that: The following steps are involved: S1. Determine the groundwater leakage point and the groundwater seepage path according to the ground water outlet point in the foundation pit; S2. Drill holes around the groundwater leakage points and inject grout to form a water stop wall to cut off the hydraulic supply in the foundation pit; S3. If the groundwater leakage point determined in step S1 is close to the ground-connected wall, a water-stop curtain is installed at the position corresponding to the leakage point outside the foundation pit to reduce the hydraulic supply outside the foundation pit; S4. Drill holes around the periphery of each underground water leakage point and inject water-based polyurethane grouting material.
2. The method for dealing with water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 1, characterized in that: In step S1, if the ground water outlet point is close to the ground-connected wall, a row of exploration holes are made along the ground-connected wall in the area where the ground water outlet point is located. The formed exploration holes are filled with sleeve valve pipes. By drilling holes and observing the water outlet of the sleeve valve pipes, the groundwater leakage point and seepage path are determined.
3. The method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 1, characterized in that: In step S1, if the ground water outlet point is far away from the ground-connected wall, a circle of exploration holes is drilled with the ground water outlet point as the center. The formed exploration holes are filled with sleeve valve pipes. By drilling holes and observing the water outlet of the sleeve valve pipes, the groundwater leakage point and seepage path are determined.
4. The method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 2 or 3, characterized in that: During the drilling process of each exploration hole, when the drill rod is pulled out, if leakage occurs at the hole mouth, it is judged as a groundwater leakage point; if there is no obvious leakage at the hole mouth, it is judged as not a groundwater leakage point; the drilling positions of each groundwater leakage point are recorded, and the groundwater seepage path is drawn.
5. The method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 1, characterized in that: In step S2, if the underground leakage point is close to the ground-connected wall, multiple rows of water-stop holes are set up along the groundwater seepage path, among which the outermost row of U-shaped water-stop holes is combined with the ground-connected wall to enclose the underground water leakage points; grouting is performed in each formed water-stop hole, and a water-stop wall is formed after the slurry solidifies.
6. The method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 1, characterized in that: In step S2, if the underground leakage point is far away from the ground-connected wall, multiple circles of O-shaped water-stopping holes are made with the underground leakage point as the center; grouting is performed in each of the formed water-stopping holes, and a water-stopping wall is formed after the slurry solidifies.
7. The method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 5 or 6, characterized in that: Each water stop hole is drilled to 1-2m below the design elevation of the foundation pit bottom and arranged in a plum blossom shape; the grouting liquid in the water stop holes is a mixture of cement slurry and water glass slurry in a volume ratio of 1:
1.
8. The method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 1, characterized in that: In step S3, at the location corresponding to the leakage point outside the foundation pit, a high-pressure rotary jet water-stopping curtain is constructed along the ground-connected wall, and the rotary jet piles are extended to 1-2 m below the bottom of the cave. The length of the water-stopping curtain is at least 0.5 m outside the groundwater seepage path.
9. The method for dealing with water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 1, characterized in that: In step S4, a number of velocity reduction holes are made within 50 cm of the periphery of each groundwater leakage point, and water-based polyurethane grouting material is injected; and the polyurethane injection amount is determined by the groundwater flow rate and water-based polyurethane outflow of adjacent groundwater leakage points.
10. The method for dealing with sudden water inrush risk in a station foundation pit that crosses an existing large karst collapse area as claimed in claim 9, characterized in that: After the injection of the water-based polyurethane grouting material is stopped, the leakage of the groundwater leakage point is continued to be observed after standing for a period of time. If the groundwater flow velocity has not decreased, the water-based polyurethane grouting material is continued to be injected into each velocity reduction hole corresponding to the groundwater leakage point.