Nuclear power overhaul night shift plan management and control system

By designing a nuclear power plant overhaul night shift planning and control system, the problem of night shift planning engineers not understanding the handover data was solved, and the data was digitized and visualized, improving the execution efficiency of night shift plans and data sharing capabilities.

CN119048060APending Publication Date: 2024-11-29CNNC NUCLEAR POWER OPERATION MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411215415.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

During nuclear power plant overhauls, night shift planning engineers are unfamiliar with daytime plans, leading to a lack of timely, comprehensive, and accurate data handover. This results in data handover errors and issues with data sharing, experience feedback, and skills transfer.

Method used

Design a nuclear power plant overhaul night shift planning and control system, including data acquisition, display, storage and recording modules, to realize the digitization and visualization of overhaul night shift plan handover data and duty data, support real-time tracking and early warning of critical paths, nodes and status information, and have query and feedback functions.

Benefits of technology

This enabled night shift planning engineers to have timely, comprehensive, and accurate control over handover data, avoiding human error, improving data sharing and skills transfer, and ensuring the smooth execution of night shift plans.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119048060A_ABST
    Figure CN119048060A_ABST
Patent Text Reader

Abstract

The invention specifically relates to a nuclear power overhaul night shift plan management and control system, and the system comprises a data obtaining module which is used for obtaining overhaul night shift plan handover data; the data display module is used for displaying overhaul night shift plan handover data and overhaul night shift plan on-duty data; the data storage module is used for storing overhaul night shift plan handover data and overhaul night shift plan on-duty data; and the data recording module is used for recording overhaul night shift plan on-duty data. According to the invention, the digitalization and visualization of the overhaul night shift plan handover data and the overhaul night shift plan on-duty data, and the query, experience feedback and skill inheritance of the overhaul night shift plan handover data and the overhaul night shift plan on-duty data are realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of nuclear power overhaul night shift plan control, and in particular to a nuclear power overhaul night shift plan control system. Background Art

[0002] In the current nuclear power plant overhaul planning and control work, the number of overhaul planning engineers is limited, and overload operation is required during the entire overhaul period, but it is impossible to meet the 24-hour planning and control requirements of the overhaul plan, especially in the second half of the night, and night shift planning engineers need to be arranged for uninterrupted control.

[0003] Because the night shift planning engineers do not participate in the daytime planning control, they do not understand the daytime overhaul site, overhaul key paths, overhaul important decisions and overhaul important matters, which poses a great challenge to the seamless connection of the site. The current practice is to send emails and write notes, and each planning engineer hands over to the night shift planning engineer face-to-face in the office, which has the following problems:

[0004] 1. The night shift planning engineer cannot fully understand and track the unit status, critical path, and key nodes;

[0005] 2. The handover data of the night shift plan is prone to language and other human errors;

[0006] 3. Deviations in critical path work cannot be adjusted and controlled in a timely manner;

[0007] 4. Night shift schedule duty records cannot be shared for query, experience feedback, and skill inheritance. Summary of the invention

[0008] One of the purposes of the present invention is to provide a nuclear power overhaul night shift plan control system to solve the problem that the existing nuclear power overhaul night shift plan control method cannot timely, comprehensively and accurately grasp the overhaul night shift plan handover data, realize the digitization and visualization of the overhaul night shift plan handover data, and facilitate night shift plan engineers to timely, comprehensively and accurately grasp the overhaul night shift plan handover data.

[0009] The second purpose of the present invention is to provide a nuclear power overhaul night shift plan management and control system to solve the problem that the overhaul night shift plan duty data cannot be shared, queried, experience fed back and skills inherited in the existing nuclear power overhaul night shift plan management and control method, and to realize the query, experience feedback and skills inheritance of the overhaul night shift plan duty data.

[0010] In order to solve the above problems, the present invention provides a nuclear power overhaul night shift plan control system, comprising:

[0011] Data acquisition module, used to obtain overhaul night shift plan handover data;

[0012] Data display module, used to display the overhaul night shift plan handover data and overhaul night shift plan duty data;

[0013] A data storage module, used to store overhaul night shift plan handover data and overhaul night shift plan duty data;

[0014] The data recording module is used to record the planned duty data of the overhaul night shift.

[0015] As one of the feasible ways, the overhaul night shift plan handover data includes today's critical path information, today's key node information, today's maintenance retention information and today's important unit status information of the overhaul main line plan, nuclear island plan and conventional island plan.

[0016] As one of the feasible ways, today's critical path information includes the critical path information of the past 24 hours, the critical path information of the current overhaul and the critical path information of the next 24 hours; the critical path information of the past 24 hours and the critical path information of the current overhaul both include the following field information: work number, work name, responsible department and plan execution deviation; the critical path information of the next 24 hours includes the following field information: work number, work name, responsible department and whether it is ready.

[0017] As one of the feasible ways, today's key node information includes key node information of the past 24 hours, key node information of the current overhaul and key node information of the next 24 hours; the key node information of the past 24 hours and the key node information of the current overhaul both include the following field information: work number, work name, responsible department and plan execution deviation; the key node information of the next 24 hours includes the following field information: work number, work name, responsible department and whether it is ready.

[0018] As one of the feasible ways, the nuclear power overhaul night shift planning control system also includes:

[0019] The data sending module is used to notify the responsible departments in advance of the key node information of the overhaul main line plan, nuclear island plan and conventional island plan in the next 24 hours.

[0020] As one of the feasible ways, today's important status information of the unit includes important status information of the unit in the past 24 hours, important status information of the unit in the current overhaul, and important status information of the unit in the next 24 hours; important status information of the unit in the past 24 hours, important status information of the unit in the current overhaul, and important status information of the unit in the next 24 hours all include system equipment switch status information, system equipment interlocking status information, overhaul dynamic switching point information, and overhaul static switching point information.

[0021] As one of the feasible ways, the data display module intuitively displays the system equipment switch status information and system equipment interlocking status information in today's important unit status information of the overhaul main line plan, nuclear island plan and conventional island plan through graphics.

[0022] As one of the feasible ways, today's maintenance retention information includes today's critical path retention information and today's fixed retention information; today's critical path retention information and today's fixed retention information both include the following field information: major, name, contact number and standby location; among them, today's critical path retention information of the overhaul main line plan, nuclear island plan and conventional island plan is set in the data acquisition module by professional engineers according to the critical path work of the night shift overhaul main line plan, nuclear island plan and conventional island plan issued by the overhaul plan engineer; today's fixed retention information of the overhaul main line plan, nuclear island plan and conventional island plan is set in the data acquisition module by professional engineers according to the scaffolding and insulation work of the night shift overhaul main line plan, nuclear island plan and conventional island plan issued by the overhaul plan engineer.

[0023] As one of the feasible ways, the overhaul night shift plan duty data includes the night's key path information, key node information, unit important status information, maintenance execution information and abnormal situation handling information, as well as the next 24 hours key path activity plan adjustment and work order approval.

[0024] As one of the feasible ways, the nuclear power overhaul night shift plan management and control system is equipped with a search engine, which has the function of querying the overhaul night shift plan handover data and the overhaul night shift plan duty data.

[0025] Beneficial technical effects of the present invention:

[0026] The nuclear power overhaul night shift plan control system of the present invention automatically obtains and displays the overhaul night shift plan handover data, realizes the visualization and digitization of the overhaul night shift plan handover data, and facilitates the night shift plan engineers to grasp the overhaul night shift plan handover data in a timely, comprehensive and accurate manner; records the overhaul night shift plan duty data and saves and displays it, realizes the visualization and digitization of the overhaul night shift plan duty data; has the query function of the overhaul night shift plan handover data and the overhaul night shift plan duty data, realizes the query, experience feedback and skill inheritance of the overhaul night shift plan handover data and the overhaul night shift plan duty data. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a structural schematic diagram of an embodiment of a nuclear power overhaul night shift planning control system of the present invention. DETAILED DESCRIPTION

[0028] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which this application belongs; the terms used in the specification of the application are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned figure descriptions are intended to cover non-exclusive inclusions.

[0029] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0030] The technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings and specific embodiments.

[0031] The job responsibilities of the night shift plan engineer are to comprehensively track, coordinate and correct the safety, quality and progress of the overhaul site, focus on controlling the progress of the on-site work of the overhaul main line plan, nuclear island plan and conventional island plan, coordinate and solve problems in a timely manner, report problems that require decision-making to the overhaul project department immediately, and keep detailed and accurate records of night shift plan duty.

[0032] The night shift planning engineer arrives at the post at 19:00 to conduct work handover. The content of the handover includes today's key path information of the overhaul main line plan, nuclear island plan and conventional island plan, today's key node information, today's maintenance retention information and today's important unit status information.

[0033] The present invention provides a nuclear power overhaul night shift plan control system, which realizes the visualization and digitization of overhaul night shift plan handover data and overhaul night shift plan duty records, facilitates night shift plan engineers to grasp the overhaul night shift plan handover data in a timely, comprehensive and accurate manner, avoids the inability to grasp the overhaul night shift plan handover data in a timely, comprehensive and accurate manner during face-to-face handover of the overhaul night shift plan, and eliminates the lengthy overhaul night shift plan handover process.

[0034] See also Figure 1 , shows a schematic structural diagram of an embodiment of a nuclear power overhaul night shift plan control system, the nuclear power overhaul night shift plan control system comprising:

[0035] Data acquisition module, used to obtain overhaul night shift plan handover data;

[0036] Data display module, used to display the overhaul night shift plan handover data and overhaul night shift plan duty data;

[0037] A data storage module, used to store overhaul night shift plan handover data and overhaul night shift plan duty data;

[0038] The data recording module is used to record the planned duty data of the overhaul night shift.

[0039] In this embodiment, as one of the feasible methods, the overhaul night shift plan handover data includes today's critical path information, today's key node information, today's maintenance retention information and today's important unit status information of the overhaul main line plan, nuclear island plan and conventional island plan.

[0040] In this embodiment, as one of the feasible ways, today's critical path information includes the critical path information of the past 24 hours, the critical path information of the current overhaul and the critical path information of the next 24 hours; the critical path information of the past 24 hours and the critical path information of the current overhaul both include the following field information: work number, work name, responsible department and plan execution deviation; the critical path information of the next 24 hours includes the following field information: work number, work name, responsible department and whether it is ready.

[0041] In this embodiment, as one of the feasible ways, today's key node information includes key node information of the past 24 hours, key node information of the current overhaul in progress, and key node information of the next 24 hours; the key node information of the past 24 hours and the key node information of the current overhaul in progress both include the following field information: work number, work name, responsible department, and plan execution deviation; the key node information of the next 24 hours includes the following field information: work number, work name, responsible department, and whether it is ready.

[0042] In this embodiment, as one of the achievable methods, the nuclear power overhaul night shift planning control system further includes:

[0043] The data sending module is used to notify the responsible department one hour in advance of the key node information of the overhaul main line plan, nuclear island plan and conventional island plan for the next 24 hours.

[0044] In this embodiment, as one of the feasible ways, today's important status information of the unit includes important status information of the unit in the past 24 hours, important status information of the unit currently in overhaul, and important status information of the unit in the next 24 hours; important status information of the unit in the past 24 hours, important status information of the unit currently in overhaul, and important status information of the unit in the next 24 hours all include system equipment switch status information, system equipment interlocking status information, overhaul dynamic switching point information, and overhaul static switching point information; system equipment includes fuel operation room, personnel gate, equipment gate, biological shielding door, nuclear detection detector cover, evaporator plugging plate, water gate and transmission well valve.

[0045] In this embodiment, as one of the feasible ways, the data display module intuitively displays the system equipment switch status information and system equipment interlocking status information in today's important status information of the overhaul main line plan, nuclear island plan and conventional island plan through graphics.

[0046] In this embodiment, as one of the feasible ways, today's maintenance retention information includes today's critical path retention information and today's fixed retention information; today's critical path retention information and today's fixed retention information both include the following field information: major, name, contact number and standby location; among them, today's critical path retention information of the overhaul main line plan, nuclear island plan and conventional island plan is set in the data acquisition module by professional engineers according to the night shift overhaul main line plan, nuclear island plan and conventional island plan critical path work issued by the overhaul plan engineer; today's fixed retention information of the overhaul main line plan, nuclear island plan and conventional island plan is set in the data acquisition module by professional engineers according to the night shift overhaul main line plan, nuclear island plan and conventional island plan scaffolding and insulation work issued by the overhaul plan engineer; the night shift issued by the overhaul plan engineer is from 20:00 tonight to 8:00 the next morning.

[0047] In this embodiment, as one of the feasible methods, the overhaul night shift plan duty data includes nighttime critical path information, critical node information, important unit status information, execution information of maintenance retention and abnormal condition handling information, as well as planned adjustments and work order approvals for critical path activities in the next 24 hours.

[0048] In this embodiment, as one of the feasible methods, the nuclear power overhaul night shift plan management and control system is provided with a search engine, which has the function of querying the overhaul night shift plan handover data and the overhaul night shift plan duty data, so as to realize the query, experience feedback and skill inheritance of the overhaul night shift plan handover data and the overhaul night shift plan duty data.

[0049] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A nuclear power overhaul night shift planning control system, characterized in that: include: Data acquisition module, used to obtain overhaul night shift plan handover data; Data display module, used to display the overhaul night shift plan handover data and overhaul night shift plan duty data; A data storage module, used to store overhaul night shift plan handover data and overhaul night shift plan duty data; The data recording module is used to record the planned duty data of the overhaul night shift.

2. The nuclear power overhaul night shift planning control system according to claim 1 is characterized in that: The overhaul night shift plan handover data includes today's critical path information, today's key node information, today's maintenance retention information and today's important unit status information of the overhaul main line plan, nuclear island plan and conventional island plan.

3. The nuclear power overhaul night shift planning control system according to claim 2 is characterized in that: Today's critical path information includes the critical path information of the past 24 hours, the critical path information of the current overhaul and the critical path information of the next 24 hours; the critical path information of the past 24 hours and the critical path information of the current overhaul both include the following field information: work number, work name, responsible department and plan execution deviation; the critical path information of the next 24 hours includes the following field information: work number, work name, responsible department and whether it is ready.

4. The nuclear power overhaul night shift planning control system according to claim 2 is characterized in that: Today's key node information includes the key node information of the past 24 hours, the key node information of the current overhaul and the key node information of the next 24 hours; the key node information of the past 24 hours and the key node information of the current overhaul both include the following field information: work number, work name, responsible department and plan execution deviation; the key node information of the next 24 hours includes the following field information: work number, work name, responsible department and whether it is ready.

5. The nuclear power overhaul night shift planning control system according to claim 4 is characterized in that: The nuclear power overhaul night shift planning control system also includes: The data sending module is used to notify the responsible departments in advance of the key node information of the overhaul main line plan, nuclear island plan and conventional island plan in the next 24 hours.

6. The nuclear power overhaul night shift planning control system according to claim 2 is characterized in that: Today's important unit status information includes the important unit status information of the past 24 hours, the important unit status information of the unit currently undergoing overhaul, and the important unit status information of the next 24 hours; the important unit status information of the past 24 hours, the important unit status information of the unit currently undergoing overhaul, and the important unit status information of the next 24 hours all include system equipment switch status information, system equipment interlocking status information, overhaul dynamic switching point information, and overhaul static switching point information.

7. The nuclear power overhaul night shift planning control system according to claim 6 is characterized in that: The data display module intuitively displays the system equipment switch status information and system equipment interlocking status information in today's important unit status information of the overhaul main line plan, nuclear island plan and conventional island plan through graphics.

8. The nuclear power overhaul night shift planning control system according to claim 2 is characterized in that: Today's maintenance retention information includes today's critical path retention information and today's fixed retention information; today's critical path retention information and today's fixed retention information both include the following field information: major, name, contact number and standby location; among them, today's critical path retention information of the overhaul main line plan, nuclear island plan and conventional island plan is set in the data acquisition module by professional engineers according to the critical path work of the night shift overhaul main line plan, nuclear island plan and conventional island plan issued by the overhaul plan engineer; today's fixed retention information of the overhaul main line plan, nuclear island plan and conventional island plan is set in the data acquisition module by professional engineers according to the scaffolding and insulation work of the night shift overhaul main line plan, nuclear island plan and conventional island plan issued by the overhaul plan engineer.

9. The nuclear power overhaul night shift planning control system according to claim 1, characterized in that: The overhaul night shift plan duty data includes the night's key path information, key node information, unit important status information, maintenance execution information and abnormal situation handling information, as well as the next 24 hours key path activity plan adjustment and work order approval.

10. The nuclear power overhaul night shift planning control system according to claim 1, characterized in that: The nuclear power overhaul night shift plan control system is equipped with a search engine, which has the function of querying the overhaul night shift plan handover data and the overhaul night shift plan duty data.