Hoisting device and hoisting construction method

By designing a lifting device including tracks, tooling trolleys, lifting systems and leveling systems, the problems of low economy, large investment and low efficiency in the lifting operation of roof systems of large venues are solved, and high economy and high efficiency are achieved lifting construction and suitable for a variety of scenarios.

CN119240513APending Publication Date: 2025-01-03SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411323077.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

The existing large-scale stadium roof system hoisting operation methods have problems such as low economics, large investment and low efficiency.

Method used

Design a lifting device, including tracks, tooling trolleys, lifting systems and leveling systems, using roof steel structures as the rail load, tooling trolleys can be detached and installed on the track, and lifting systems and leveling systems are used for the installation of lifting unit plates. and angle adjustment to avoid occupying tower cranes and other hoisting equipment.

Benefits of technology

High economical and efficient lifting construction has been achieved. The lifting device components can be used multiple times without occupying the tower crane. They are good inappropriate and do not affect the construction of the lower floors of the roof, saving construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119240513A_ABST
    Figure CN119240513A_ABST
Patent Text Reader

Abstract

The invention provides a hoisting device and a hoisting construction method, and the hoisting device comprises a track which is laid on the surface of a roof steel structure; the tool trolley is detachably arranged on the track and can move along the track; the lifting system is arranged on the tool trolley so as to lift and hoist the unit plate; and the two leveling systems are suspended at the top of the tool trolley and are respectively arranged on the two sides of the lifting system so as to adjust the mounting angle of the hoisting unit plate. When the hoisting device is used for hoisting construction, normal use of a tower crane is not occupied, other hoisting work is not affected, and benefits are high; building construction of floors under the roof is not affected, simultaneous operation can be achieved, and the construction period is shortened; and the method is not limited by application scenes, high requirements on the flatness and the bearing capacity of a traveling surface when a truck crane and a crawler crane are used for hoisting are avoided, and the applicability is good.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a hoisting device and a hoisting construction method. Background Art

[0002] The roof system of large venues usually uses a long-span steel structure as the structural force system, and a canopy is set on it to realize the building function. At present, the vertical transportation of the canopy panels usually adopts the following two methods:

[0003] The first is to use a tower crane for hoisting. This method uses a tower crane throughout the entire process from hoisting of components to installation completion, which has low construction efficiency and affects the development of other hoisting work, and has low economic efficiency;

[0004] The second method is to use machinery such as truck cranes or crawler cranes for lifting. This method requires the placement of truck cranes or crawler cranes under the roof for lifting. The construction efficiency is low and the applicable scenarios are relatively limited. If the elevation of the vehicle surface under the roof changes greatly or the bearing capacity is low, a large amount of reinforcement measures will be required. In addition, since the lower working surface of the roof needs to be occupied, the subsequent work will be affected.

[0005] In summary, the current hoisting operation methods of large venue roof systems all have the problems of low economy, large investment and low efficiency. To this end, those skilled in the art have been looking for solutions. Summary of the invention

[0006] The object of the present invention is to provide a hoisting device and a hoisting construction method to solve the problems of low economy, large investment and low efficiency in the existing hoisting operation methods.

[0007] In order to solve the above technical problems, the present invention provides a lifting device, which comprises:

[0008] A track is laid on the surface of the roof steel structure;

[0009] A tooling trolley, which can be detachably mounted on the track and can move along the track;

[0010] a lifting system, arranged on the tooling trolley, to lift the hoisting unit plate;

[0011] Two leveling systems are both suspended on the top of the tooling trolley and are respectively arranged on both sides of the lifting system to adjust the installation angle of the hoisting unit plate.

[0012] Optionally, in the hoisting device, the tooling trolley includes:

[0013] The support frame comprises: an upper chord, four triangular support reinforcement frames and two lower chords, the upper chord and the two lower chords are parallel to each other; the four triangular support reinforcement frames are parallel to each other, arranged at intervals in the space formed by the upper chord and the two lower chords, and the three are connected as one; two leveling systems are suspended on the upper chord, and the lifting system is arranged on the two triangular support reinforcement frames located inside the support frame;

[0014] The supporting legs are vertically arranged at the bottom of the supporting frame, and include two first supporting column legs, two second supporting column legs, four movable wheels and two anti-tilt components. One end of the four supporting column legs is vertically arranged at the bottom of the supporting frame, and the other end is connected to a movable wheel; the first supporting column leg is shorter than the second supporting column leg, one end of the two first supporting column legs is vertically arranged at the bottom of the same lower chord, and an anti-tilt component is sleeved on the outer side of the other end connected to the movable wheel; each second supporting column leg includes two relatively retractable column legs; the tooling trolley is detachably arranged on the track based on the movable wheels.

[0015] Optionally, in the lifting device, the movable wheel includes: a first flat iron frame and a first wheel arranged at the bottom of the first flat iron frame, and the top of the first flat iron frame is welded and fixed to the bottom of a supporting column leg.

[0016] Optionally, in the lifting device, the track includes: two sub-tracks parallel to each other, each sub-track includes an I-beam and a C-shaped steel channel, and the web of the C-shaped steel channel is welded to the upper flange of the I-beam.

[0017] Optionally, in the lifting device, the anti-tilt component includes: a second flat iron frame and two second wheels, the two second wheels are respectively arranged on the opposite inner sides of the second flat iron frame, the second flat iron frame is sleeved on the outer side of the first flat iron frame on the other end of the first support column leg, the two second wheels are located below the first wheel and on both sides of the web of the sub-track, and can move along both sides of the web of the same sub-track; the first wheel can move along the upper flange of the same sub-track.

[0018] Optionally, in the hoisting device, each component of the tooling trolley is a rectangular steel square tube, and the two relatively retractable column legs of the second supporting column legs are fastened and fixed by bolts.

[0019] Optionally, in the hoisting device, each triangular support reinforcement frame includes: two oblique support reinforcement rods and one transverse support reinforcement rod, and the three are connected end to end to form a triangle.

[0020] Optionally, in the lifting device, each leveling system includes: a lifting ring, a hand winch, a wire rope and a shoulder pole beam, the lifting ring is suspended on the upper chord of the work trolley; one end of the hand winch is connected to the lifting ring, and the other end is connected to the middle of the wire rope; the two ends of the wire rope are respectively connected to the two ends of the shoulder pole beam.

[0021] Optionally, in the lifting device, the lifting system is a winch.

[0022] The present invention also provides a hoisting construction method, which comprises:

[0023] S1: According to the roof system and the lifting unit plate, process the components of the lifting device as described above into appropriate sizes;

[0024] S2: Select a suitable track installation method and lay the track of the hoisting device on the roof steel structure;

[0025] S3: Use a tower crane or a truck crane to assemble the whole structure of the work trolley, the lifting system and the leveling system of the lifting device and install it on a track laid on the roof steel structure;

[0026] S4: Accept the lifting device and conduct a pre-lifting test on the lifting device that has passed the acceptance test;

[0027] S5: Adjust the length of the two second support column legs of the tooling trolley in the lifting device to meet the inclination of the tooling trolley and the installation requirements of the lifting unit plate;

[0028] S6: The lifting device of the lifting device lifts the lifting unit plate to above the installation position;

[0029] S7: adjusting the angle of the hoisting unit plate hoisted by the lifting device based on the leveling system of the hoisting device, and installing the hoisting unit plate after the adjustment is completed;

[0030] S8: Adjust the length of the two second support column legs of the tooling trolley in the lifting device to the shortest, and move the tooling trolley along the track to the vicinity of the installation position of the next lifting unit plate;

[0031] S9: Repeat S5 to S7 until all the hoisting unit panels of this track are installed;

[0032] S10: Use a tower crane or a truck crane to hoist the entire structure assembled in S3 onto the next track laid on the roof steel structure, and remove the previous track in S9;

[0033] S11: Repeat S3 to S10 until all the hoisting unit panels of all the tracks are installed;

[0034] S12: The entire lifting device is dismantled and the lifting construction is completed.

[0035] The hoisting device and hoisting construction method provided by the present invention have the following beneficial effects compared with the prior art:

[0036] 1) The roof steel structure is used as the bearing of the track. It is only necessary to assemble the remaining components of the lifting device, and move the remaining components as a whole on the track to continuously complete the lifting of the lifting units (such as the canopy) on the same axis (corresponding to the same track), which is highly economical, low-investment and high-efficiency;

[0037] 2) The components of the lifting device can be used repeatedly, which is highly economical;

[0038] 3) The hoisting device is used for hoisting construction, which will not occupy the normal use of the tower crane (that is, it will not occupy the tower crane to hoist the hoisting unit plate), and will not affect the development of other hoisting work, which is highly efficient;

[0039] 4) The hoisting construction is performed by using the hoisting device of the present invention, which does not affect the construction of the floors under the roof, and can be operated at the same time, thus saving construction time;

[0040] 5) The lifting device of the present invention is not limited by applicable scenarios, and does not have high requirements on the flatness and bearing capacity of the driving surface when using a truck crane or a crawler crane for lifting, and has good applicability. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] The above and other objects, features and advantages of the present disclosure will become more apparent through a more detailed description of exemplary embodiments of the present disclosure in conjunction with the accompanying drawings, wherein like reference numerals generally represent like components throughout the exemplary embodiments of the present disclosure.

[0042] Figure 1 is a schematic diagram of a hoisting device in one embodiment of the present invention;

[0043] Figure 2a is a partial enlarged schematic diagram of a supporting leg arranged on a track in one embodiment of the present invention;

[0044] Figure 2b yes Figure 2a Schematic diagram of the splitting;

[0045] Figure 2c yes Figure 2b Schematic diagram of local splitting;

[0046] Figure 3 is a schematic diagram of a tooling trolley in one embodiment of the present invention;

[0047] Figure 4 is a schematic diagram of a leveling system in one embodiment of the present invention;

[0048] Figure 5 It is a flow chart of a hoisting construction method in one embodiment of the present invention.

[0049] In the figure:

[0050] 1-track; 11-subtrack;

[0051] 2- tooling trolley; 21- upper chord rod; 22- moving wheel; 23- lower chord rod; 24- anti-tilt component; 25- triangular support reinforcement frame; 251- oblique support reinforcement rod; 252- transverse support reinforcement rod; 26- first support column leg; 27- second support column leg;

[0052] 3- Lifting system;

[0053] 4-leveling system; 41-lifting ring; 42-hand chain hoist; 43-wire rope; 44-shoulder beam;

[0054] 5-Lifting unit plate. DETAILED DESCRIPTION

[0055] The hoisting device and the hoisting construction method proposed by the present invention are further described in detail below in conjunction with the accompanying drawings and specific embodiments. The advantages and features of the present invention will become clearer according to the following description and claims. It should be noted that the accompanying drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.

[0056] Please refer to Figure 1 The hoisting device includes: a track 1, a tooling trolley 2, a lifting system 3 and two leveling systems 4, the track 1 is laid on the surface of the roof steel structure; the tooling trolley 2 is detachably arranged on the track 1 and can move along the track 1; the lifting system 3 is arranged on the tooling trolley 2 to lift the hoisting unit plate; the two leveling systems 4 are both suspended on the top of the tooling trolley 2, and are respectively arranged on both sides of the lifting system 3 to adjust the installation angle of the hoisting unit plate.

[0057] Based on the structural design of the lifting device, the roof steel structure is used as the carrier of the track. It is only necessary to assemble the remaining components of the lifting device and move the remaining components as a whole on the track to continuously complete the lifting of the lifting units (such as the canopy) on the same axis (corresponding to the same track). It is highly economical, requires little investment, and is highly efficient.

[0058] Please refer to Figures 1 to 3The tooling trolley 2 includes: a support frame and support legs, the support frame includes: an upper chord 21, four triangular support reinforcement frames 25 and two lower chords 23, the upper chord 21 and the two lower chords 23 are parallel to each other; the four triangular support reinforcement frames 25 are parallel to each other, and are arranged at intervals in the space formed by the upper chord 21 and the two lower chords 23, and the three are connected as one; two leveling systems are suspended on the upper chord 21, and the lifting system 3 is arranged on the two triangular support reinforcement frames 25 located inside the support frame, specifically, on the transverse support reinforcement rods 252 of the two triangular support reinforcement frames located in the middle; the support legs are vertically arranged at the bottom of the support frame, including two first support column legs 26 , two second support column legs 27, four moving wheels 22 and two anti-tilt components 24, one end of the four support column legs are vertically arranged at the bottom of the support frame, and the other end is connected to a moving wheel 22; the first support column leg 26 is shorter than the second support column leg 27, one end of the two first support column legs 26 are vertically arranged at the bottom of the same lower chord 23, and an anti-tilt component 24 is sleeved on the outer side of the other end connected to the moving wheel 22; each second support column leg 27 includes two sections of relatively retractable column legs, specifically, the two sections of the second support column legs 27 are rectangular steel square tubes with a size difference of 1-2 wall thickness; the tooling trolley 2 is detachably arranged on the track 1 based on the moving wheel 22.

[0059] Specifically, Figure 1 As shown, each triangular support reinforcement frame includes: two oblique support reinforcement rods 251 and one transverse support reinforcement rod 252, which are connected end to end to form a triangle.

[0060] In this embodiment, Figure 1 As shown, each lower chord 23 is preferably a U-shaped rod, and the two chords 23 are arranged back to back in parallel, and a pair of support column legs are arranged in parallel at both ends of the bottom of each lower chord 23, wherein two first support column legs 26 are vertically arranged at the bottom of one lower chord 23, and two second support column legs 27 are vertically arranged at the bottom of the other lower chord 23. It can be understood that the lower chord 23 is not limited to a U-shaped rod, and can also be other shapes, as long as it can form a stable structure with other components to support the hoisting construction.

[0061] Please refer to Figure 2a and Figure 2b The track 1 comprises: two sub-tracks 11 parallel to each other, each sub-track comprises an I-beam and a C-shaped steel channel, and the web of the C-shaped steel channel is welded to the upper flange of the I-beam.

[0062] Please refer to Figure 1 , Figure 2a to Figure 2cThe moving wheel 22 includes: a first flat iron frame and a first wheel arranged at the bottom of the first flat iron frame, the top of the first flat iron frame is welded and fixed to the bottom of a support column leg (the first support column leg 26 or the second support column leg 27). The anti-tilt component 24 includes: a second flat iron frame and two second wheels, the two second wheels are respectively arranged on the opposite inner sides of the second flat iron frame, the second flat iron frame is sleeved on the outer side of the first flat iron frame on the other end of the first support column leg 26, the two second wheels are located below the first wheel and on both sides of the web of the sub-track 11, and can move along both sides of the web of the same sub-track 11; the first wheel can move along the upper flange of the same sub-track 11.

[0063] In this embodiment, please refer to Figure 1 The lifting system 3 is a winch. The winch is firmly connected to the transverse support reinforcement rod 252 of the tooling trolley 2 by welding, and the model of the winch is selected according to the weight of the hoisting unit plate.

[0064] Each component of the tooling trolley 2 is a rectangular steel square tube connected by welding; the two relatively telescopic column legs of the second support column leg 27 are fastened and fixed by bolts. Specifically, the length of the second support column leg 27 is adjusted according to the inclination angle that needs to be adjusted of the tooling trolley 2. After the length adjustment is completed, the bolts are passed through the pin holes on the two relatively telescopic column legs to fasten and fix the length of the second support column leg 27.

[0065] Please refer to Figure 4 Each leveling system 4 includes: a lifting ring 41, a hand chain hoist 42, a steel wire rope 43 and a shoulder pole beam 44. The lifting ring 41 is suspended on the upper chord 21 of the tooling trolley 2; one end of the hand chain hoist 42 is connected to the lifting ring 41, and the other end is connected to the middle of the steel wire rope 43; the two ends of the steel wire rope 43 are respectively connected to the two ends of the shoulder pole beam 44. In this embodiment, the shoulder pole beam 44 is a rectangular steel square tube, and the model of the rectangular steel square tube is the same as the model of the square tube used in the tooling trolley 2.

[0066] It can be understood that the above examples are merely examples listed for a better understanding of the technical solutions of the embodiments of the present application, and are not intended to be the sole limitation to the embodiments.

[0067] Accordingly, this embodiment also provides a hoisting construction method. Figures 1 to 5 The hoisting construction method described in this embodiment is described in detail.

[0068] First, step S1 is performed to process the components of the hoisting device described above with appropriate sizes according to the roof system and the hoisting unit panels, so that the processed hoisting device can be sufficient to hoist the hoisting unit panels.

[0069] Next, execute step S2, select a suitable track installation method, and lay the track 1 in the hoisting device on the roof steel structure;

[0070] Next, execute step S3, use a tower crane or a truck crane to hoist and install the assembled overall structure of the tooling trolley 2, the lifting system 3 and the leveling system 4 of the lifting device onto a track 1 laid on the roof steel structure; it can be understood that the assembly of the tooling trolley 2, the lifting system 3 and the leveling system 4 is carried out on the ground to ensure the firmness of the assembled structure.

[0071] Next, executing step S4, the hoisting device is inspected and accepted, and a pre-hoisting test is performed on the hoisting device after the inspection and acceptance;

[0072] Next, step S5 is executed to adjust the lengths of the two second support column legs 27 of the tooling trolley 2 in the lifting device to meet the inclination of the tooling trolley 2 and the installation requirements of the lifting unit plate 5;

[0073] Next, step S6 is executed, where the lifting device 3 of the lifting device lifts the lifting unit plate 5 to above the installation position;

[0074] Next, step S7 is executed to adjust the angle of the hoisting unit plate 5 hoisted by the lifting device 3 based on the leveling system 4 of the hoisting device, and after the adjustment is completed, the hoisting unit plate 5 is installed;

[0075] Next, execute step S8, adjust the length of the two second support column legs 27 of the tooling trolley 2 in the lifting device to the shortest, and move the tooling trolley 2 along the track 1 to the vicinity of the installation position of the next lifting unit plate 5; here, the movement of the tooling trolley 2 along the track 1 is mainly manual.

[0076] Next, execute step S9, and repeatedly execute steps S5 to S7 until the installation of all the hanging unit panels of the track 1 is completed;

[0077] Next, step S10 is executed, using a tower crane or a truck crane to hoist the entire structure assembled in S3 onto the next track 1 laid on the roof steel structure, and the previous track 1 in S9 is removed;

[0078] Next, step S11 is executed, and steps S3 to S10 are repeatedly executed until the installation of all the hanging unit panels of all the tracks is completed.

[0079] Next, step S12 is executed to dismantle the entire hoisting device, and the hoisting construction is completed.

[0080] It should be noted that, for the sake of simplicity of description, the aforementioned method embodiments are all expressed as a series of action combinations, but those skilled in the art should know that the present application is not limited to the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously.

[0081] Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.

[0082] As for the method disclosed in the embodiment, since it corresponds to the structure disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the description of the structure part.

[0083] The hoisting device and hoisting construction method provided by the present invention have the following beneficial effects compared with the prior art:

[0084] 1) The roof steel structure is used as the bearing of the track. It is only necessary to assemble the remaining components of the lifting device, and move the remaining components as a whole on the track to continuously complete the lifting of the lifting units (such as the canopy) on the same axis (corresponding to the same track), which is highly economical, low-investment and high-efficiency;

[0085] 2) The components of the lifting device can be used repeatedly, which is highly economical;

[0086] 3) The hoisting device is used for hoisting construction, which will not occupy the normal use of the tower crane (that is, it will not occupy the tower crane to hoist the hoisting unit plate), and will not affect the development of other hoisting work, which is highly efficient;

[0087] 4) The hoisting construction is performed by using the hoisting device of the present invention, which does not affect the construction of the floors under the roof, and can be operated at the same time, thus saving construction time;

[0088] 5) The lifting device of the present invention is not limited by applicable scenarios, and does not have high requirements on the flatness and bearing capacity of the driving surface when using a truck crane or a crawler crane for lifting, and has good applicability.

[0089] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of protection of the claims.

Claims

1. A lifting device, characterized in that: include: A track (1) is laid on the surface of the roof steel structure; A tooling trolley (2) which is detachably mounted on the track (1) and can move along the track (1); a lifting system (3) arranged on the tooling trolley (2) to lift the hoisting unit plate; Two leveling systems (4) are both suspended on the top of the tooling trolley (2) and are respectively arranged on both sides of the lifting system (3) to adjust the installation angle of the lifting unit plate.

2. The lifting device according to claim 1, characterized in that: The tooling trolley (2) comprises: The support frame comprises: an upper chord rod (21), four triangular support reinforcement frames (25) and two lower chord rods (23), wherein the upper chord rod (21) and the two lower chord rods (23) are parallel to each other; the four triangular support reinforcement frames are parallel to each other, arranged at intervals in the space formed by the upper chord rod (21) and the two lower chord rods (23), and the three are connected as one; two leveling systems are suspended on the upper chord rod (21), and the lifting system (3) is arranged on the two triangular support reinforcement frames (25) located inside the support frame; The support legs are vertically arranged at the bottom of the support frame, and include two first support column legs (26), two second support column legs (27), four moving wheels (22) and two anti-tilt components (24); one end of each of the four support column legs is vertically arranged at the bottom of the support frame, and the other end is connected to a moving wheel (22); the first support column leg (26) is shorter than the second support column leg (27); one end of each of the two first support column legs (26) is vertically arranged at the bottom of the same lower chord (23), and an anti-tilt component (24) is sleeved on the outer side of the other end connected to the moving wheel (22); each second support column leg (27) includes two relatively retractable column legs; the tooling trolley (2) is detachably arranged on the track (1) based on the moving wheel (22).

3. The lifting device according to claim 2, characterized in that: The movable wheel (22) comprises: a first flat iron frame and a first wheel arranged at the bottom of the first flat iron frame, and the top of the first flat iron frame is welded and fixed to the bottom of a supporting column leg (26, 27).

4. The lifting device according to claim 3, characterized in that: The track (1) comprises: two mutually parallel sub-tracks (11), each sub-track comprising an I-beam and a C-shaped steel channel, the web of the C-shaped steel channel being welded to the upper flange of the I-beam.

5. The lifting device according to claim 4, characterized in that: The anti-tilt component (24) comprises: a second flat iron frame and two second wheels, the two second wheels are respectively arranged on the opposite inner sides of the second flat iron frame, the second flat iron frame is sleeved on the outer side of the first flat iron frame on the other end of the first support column leg (26), the two second wheels are located below the first wheel and on both sides of the web of the sub-track (11), and can move along both sides of the web of the same sub-track (11); the first wheel can move along the upper flange of the same sub-track (11).

6. The lifting device according to claim 2, characterized in that: Each component of the tooling trolley (2) is a rectangular steel square tube, and the two relatively retractable column legs of the second supporting column leg (27) are fastened and fixed by bolts.

7. The lifting device according to claim 2, characterized in that: Each triangular support reinforcement frame (25) comprises: two oblique support reinforcement rods (251) and one transverse support reinforcement rod (252), which are connected end to end to form a triangle.

8. The lifting device according to claim 2, characterized in that: Each leveling system (4) comprises: a lifting ring (41), a hand chain hoist (42), a steel wire rope (43) and a shoulder pole beam (44); the lifting ring (41) is suspended on the upper chord (21) of the tooling trolley (2); one end of the hand chain hoist (42) is connected to the lifting ring (41), and the other end is connected to the middle of the steel wire rope (43); the two ends of the steel wire rope (43) are respectively connected to the two ends of the shoulder pole beam (44).

9. The lifting device according to claim 1, characterized in that: The lifting system (3) is a winch.

10. A hoisting construction method, characterized in that: include: S1: According to the roof system and the lifting unit plate, processing the components of the lifting device according to any one of claims 1 to 9 of appropriate size; S2: Select a suitable track installation method and lay the track (1) in the hoisting device on the roof steel structure; S3: Using a tower crane or a truck crane, the whole structure of the work trolley (2), the lifting system (3) and the leveling system (4) of the lifting device is assembled and hoisted to a track (1) laid on the roof steel structure; S4: Accept the lifting device and conduct a pre-lifting test on the lifting device that has passed the acceptance test; S5: adjusting the lengths of the two second support column legs (27) of the tooling trolley (2) in the lifting device to meet the inclination of the tooling trolley (2) and the installation requirements of the lifting unit plate (5); S6: The lifting device (3) of the lifting device lifts the lifting unit plate (5) to above the installation position; S7: adjusting the angle of the hoisting unit plate (5) hoisted by the lifting device (3) based on the leveling system (4) of the hoisting device, and installing the hoisting unit plate (5) after the adjustment is completed; S8: adjusting the length of the two second support column legs (27) of the tooling trolley (2) in the lifting device to the shortest, and moving the tooling trolley (2) along the track (1) to the vicinity of the installation position of the next lifting unit plate (5); S9: Repeat S5 to S7 until all the hoisting unit panels of this track (1) are installed; S10: using a tower crane or a truck crane to hoist the entire structure assembled in S3 onto the next track (1) laid on the roof steel structure, and removing the previous track (1) in S9; S11: Repeat S3 to S10 until all the hoisting unit panels of all the tracks are installed; S12: The entire lifting device is dismantled and the lifting construction is completed.

Citation Information

Cited By

  • Photovoltaic panel mounting device on curved roof structure and use method

    CN119801213A

  • Photovoltaic panel installation device on curved roof structure and use method

    CN119801213B