Brushing device for improving construction efficiency of SMW construction method pile

By designing a brushing device for SMW working piles, the problem of the inability to reuse the steel bars is solved, the construction efficiency and quality are improved, the steel loss is reduced, and the recycling of construction materials is realized.

CN222284933UActive Publication Date: 2025-01-03THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420567528.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-22
Publication Date
2025-01-03
Estimated Expiration
2034-03-22

AI Technical Summary

Technical Problem

In the construction of SMW piles, steel bars cannot be reused, resulting in waste of steel resources and the existing technology is difficult to improve construction efficiency and quality.

Method used

A brushing device is designed, including a storage box, friction reducing agent outlet, plastic brush and wooden stick handle, which is used to improve the brushing efficiency and quality of H-shaped steel friction reducing agent and ensure the reuse of construction materials.

Benefits of technology

The coating efficiency and quality of H-shaped steel friction reducing agent has been improved, the construction efficiency and quality of SMW piles have been improved, the loss of steel is reduced, and the recycling of construction materials has been realized.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222284933U_ABST
    Figure CN222284933U_ABST
Patent Text Reader

Abstract

The utility model provides a brushing device for improving the construction efficiency of an SMW construction method pile, and relates to the technical field of construction of construction method piles, the brushing device comprises a storage box, the storage box is used for storing an antifriction agent, the bottom of the storage box is provided with an antifriction agent outlet, and the bottom of the storage box is provided with a brush at the lower end of the antifriction agent outlet. And a handle is arranged at one side part of the storage box. The H-shaped steel antifriction agent brushing device can improve the H-shaped steel antifriction agent brushing efficiency and quality, further improves the SMW construction method pile construction efficiency and quality, improves the working efficiency, meanwhile guarantees that construction materials can be repeatedly used, and reduces steel loss.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of SMW pile construction, in particular to a coating device for improving the SMW pile construction efficiency. Background Art

[0002] With the rapid development of the national economy, resource and energy issues are becoming the main problem restricting growth. Therefore, the State Council has timely put forward policies to build a conservation-oriented society and develop a circular economy. The main methods for the civil construction industry to achieve the above goals are: strive to use construction materials that can be turned over in construction and adopt construction processes that ensure that construction materials can be reused, realize recycling, improve resource utilization, and minimize the use of construction processes that consume disposable materials.

[0003] The H-beam of the SMW method can be reused, generally at least four times. However, in the construction process of underground continuous wall and bored pile as enclosure, a large amount of steel bars are used, which cannot be recycled and reused, resulting in a huge consumption of steel resources. my country has become the world's largest steel producer and consumer, and my country's steel dependence on foreign countries is very high, mainly reflected in the shortage of iron ore resources, most of which need to be imported. Therefore, it is necessary to try to adopt construction processes such as the SMW method that can reduce the consumption of resources such as steel.

[0004] Although the SMW method still has the above-mentioned problems and focuses of attention in its application, as a new technology to be promoted and applied, under the premise of meeting the engineering technical requirements, the SMW method is selected as the retaining structure, which has incomparable advantages over underground continuous walls and bored piles plus waterproof curtains as retaining structures. Therefore, as investors and designers, after technical and economic comparison, they generally give priority to the SMW method as the retaining structure. Therefore, as a construction company, it is necessary to strengthen the construction management and technical innovation of the SMW method. How to improve construction efficiency, improve construction quality, and save construction time during the construction process is the main problem to be solved by the construction unit. Summary of the invention

[0005] In view of the above-mentioned prior art, the utility model proposes a coating device for improving the construction efficiency of SMW method piles.

[0006] The utility model provides a coating device for improving the construction efficiency of SMW piles, comprising a storage box for storing a friction reducer, a friction reducer outlet being arranged at the bottom of the storage box, a brush being arranged at the bottom of the storage box at the lower end of the friction reducer outlet, and a handle being arranged at one side of the storage box.

[0007] Preferably, the friction reducer outlet is arranged in the middle of the bottom of the storage box and is arranged along the length direction of the storage box.

[0008] Preferably, the brush is made of plastic.

[0009] Preferably, the handle is a wooden stick.

[0010] Preferably, the handle is connected to the lower part of the storage box by two screws.

[0011] Compared with the prior art, the beneficial effects of the utility model are as follows: the utility model provides a coating device for improving the construction efficiency of SMW method piles, which can improve the efficiency and quality of H-shaped steel friction reducer coating, thereby improving the construction efficiency and quality of SMW method piles, improving work efficiency, and at the same time ensuring that construction materials can be reused and reducing steel loss. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the structure of the painting device in the embodiment of the utility model.

[0013] In the figure: 1. Storage box; 2. Friction reducer outlet; 3. Plastic brush; 4. Handle; 5. Screw. DETAILED DESCRIPTION

[0014] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below with reference to specific illustrations.

[0015] Example: Figure 1 A coating device for improving the efficiency of SMW pile construction is shown, comprising a storage box 1, the storage box 1 is used to store a friction reducer, a friction reducer outlet 2 is arranged in the middle of the bottom of the storage box 1, the friction reducer outlet 2 is arranged along the length direction of the storage box 1, a plastic brush 3 is arranged at the bottom of the storage box 1 at the lower end of the friction reducer outlet 2, a handle 4 is arranged at the lower part of one side of the storage box 1, the handle 4 is a wooden stick, and the handle 4 is connected to the storage box 1 by two screws 5.

[0016] The coating device is applied to improve the construction efficiency of SMW piles, and the construction method includes the following steps:

[0017] Step 1: The surface of the I-beam is ground upon arrival. If the required length of the H-beam is not enough, it needs to be welded. The welds are all full-groove welds. After welding, use a grinding wheel to grind the welds until they are as flat as the steel surface.

[0018] Step 2: After welding and grinding the I-beam, start applying the friction reducer. First, heat the friction reducer material with an electric heating rod until it is completely melted. Stir it with a stirring rod until the thickness is even before applying it to the H-beam.

[0019] Step 3: After the friction reducer is heated, use the brushing device to pour the friction reducer into the storage box 1, push the brush forward, and use a crane to turn over the other side after one side is constructed, and continue to brush. The brushing device can greatly improve the efficiency of friction reducer coating and ensure uniform thickness, ensuring that the I-beam can be inserted within 30 minutes after the three-axis pile is formed, and then the construction of the next pile can be started.

[0020] The above are only implementation methods of the present utility model, and are not intended to limit the patent scope of the present utility model. Any equivalent structure made using the contents of the specification and drawings of the present utility model, directly or indirectly used in other related technical fields, are also within the patent protection scope of the present utility model.

Claims

1. A coating device for improving the construction efficiency of SMW piles, characterized in that: The invention comprises a storage box for storing the friction reducer, wherein a friction reducer outlet is arranged at the bottom of the storage box, a brush is arranged at the bottom of the storage box at the lower end of the friction reducer outlet, and a handle is arranged at one side of the storage box.

2. The coating device for improving the construction efficiency of SMW piles according to claim 1, characterized in that: The friction reducer outlet is arranged in the middle of the bottom of the storage box and is arranged along the length direction of the storage box.

3. The coating device for improving the construction efficiency of SMW piles according to claim 1 or 2, characterized in that: The brush is made of plastic.

4. The coating device for improving the construction efficiency of SMW piles according to claim 1 or 2, characterized in that: The handle is a wooden stick.

5. The coating device for improving the construction efficiency of SMW piles according to claim 1 or 2, characterized in that: The handle is connected to the lower part of the storage box by two screws.