A trolley for full-section tunnel excavation, rock drilling and steel arch installation
By designing a mechanical and electrical liquid building vehicle device with a variety of hydraulic and mechanical functions, the problem of complex and slow speed of steel drilling and steel arch of rock drilling and steel arches during the tunnel excavation process has realized the mechanization and intelligence of tunnel construction , Improved construction efficiency.
Patent Information
- Application Number
- CN201910259461.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-04-02
- Publication Date
- 2025-01-24
- Estimated Expiration
- 2039-04-02
AI Technical Summary
In the prior art During tunnel excavation, rock drilling and steel arch frame installations have problems such as complex operation and slow speed, making it difficult to achieve mechanization and intelligence of construction.
Design a large electromechanical liquid building vehicle device with functions such as moving wheels, telescopic beams, hydraulic rock drill systems, hydraulic telescopic arms, and telescopic booms can be achieved. Installation of steel arch.
The mechanization and intelligence of tunnel construction have been realized, the construction speed and efficiency are improved, the operation process is simplified, and it is suitable for excavation and steel arch of the tunnel.
Smart Images

Figure CN109931005B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a large electro-hydraulic trolley device which can be used for tunnel excavation, rock drilling, anchor drilling and steel arch installation. The device belongs to the field of special equipment for tunnel excavation, blasting, rock drilling and early support construction. Background Art
[0002] A trolley is a general term for a structure used in tunnel construction. Tunnel excavation begins with face rock drilling and blasting. After mucking, anchor rods are drilled and installed, followed by steel arch support and shotcrete spraying. Currently, rock drilling is mostly done manually with air guns or multi-arm chisels (2-3 arms), requiring multiple positioning and securing of the trolley. Steel arch installation is often done manually using simple trolleys, which is slow. A large electro-hydraulic trolley system, universally applicable for full-face tunnel excavation, blasting, drilling, anchor rod drilling, and steel arch installation, could significantly improve construction speed and ease of operation and installation.
[0003] The trolley has motorized travel, automatic level holding system, one-time fixed coordinate positioning drilling rig, remote control actuator, and construction vehicles and equipment inside the tunnel can pass through the gantry.
[0004] Two rows of lifting beams are hung on the front door frame of the trolley, and 2-3 pairs of hydraulic rock drilling rigs are installed on each row of beams.
[0005] The crossbeam can be raised and lowered on the gantry to adjust the cable fixation; the hydraulic rock drill can be moved left and right on the crossbeam to adjust the cable fixation; each hydraulic rock drill can adjust the cable fixation at axial and radial angles to cover the drilling of blasting holes at any angle in the entire axial section of the tunnel and the drilling of anchor holes at any angle in the entire radial direction; the hydraulic excavation pneumatic feed water presses out the rock slag ash from the drill hole.
[0006] The trolley is equipped with a steel arch frame for installing the small trolley and has the function of electromechanical and hydraulic three-dimensional movement adjustment and rope fixing; a telescopic boom is provided for lifting and clamping the steel arch frame.
[0007] Small back-held intelligent remote control actuator; displays various control information data. Currently, there are no such trolleys or similar products in China. Summary of the Invention
[0008] The purpose of the present invention is to design an innovative large-scale equipment for blasting drilling, anchor drilling and steel arch installation in tunnel excavation construction, so as to achieve mechanized, intelligent and rapid construction and improve the comprehensive efficiency and functional composition of tunnel construction.
[0009] To achieve the above-mentioned purpose, the technical solution adopted by the present invention is a trolley for full-section tunnel excavation, rock drilling and steel arch installation, including a moving roller 1, a telescopic beam 2, a bottom lifting support beam 3, a top lifting support beam 4, a rock drilling system 5, a supporting hydraulic telescopic arm 6, a hydraulic rod 7, a top supporting hydraulic telescopic arm 8, a telescopic boom 9, a steel arch trolley 10 and a hydraulic system 11.
[0010] The bottom lifting support beam 3 and the top lifting support beam 4 are arranged in parallel. A hydraulic cylinder is installed between the bottom lifting support beam 3 and the top lifting support beam 4 to adjust the distance between the bottom lifting support beam 3 and the top lifting support beam 4. Two sets of telescopic beams 2 are provided: one set of telescopic beams 2 is installed at the bottom of the bottom lifting support beam 3, and the other set of telescopic beams 2 is installed at the top of the top lifting support beam 4. The bottom of the bottom lifting support beam 3 is equipped with a movable roller 1.
[0011] The rock drilling system 5 is arranged at the end of the telescopic beam 2; support columns are provided on both sides of the top of the top lifting support beam 4, and the sides of the support columns are provided with supporting hydraulic telescopic arms 6, hydraulic rods 7 and top hydraulic telescopic arms 8. The supporting hydraulic telescopic arms 6, hydraulic rods 7 and top hydraulic telescopic arms 8 are connected to form a steel arch support system; the supporting hydraulic telescopic arms 6 and the top hydraulic telescopic arms 8 are arranged in parallel, the bottom of the hydraulic rod 7 is fixed on the supporting hydraulic telescopic arms 6, and the top of the hydraulic rod 7 is installed on the bottom of the top hydraulic telescopic arms 8; the supporting hydraulic telescopic arms 6 are used to support and fix the installed steel arch, and the top of the hydraulic rod 7 is the hydraulic telescopic part.
[0012] The support truss is bolted to the support columns and installed at the top of the tunnel excavation. A steel arch trolley 10 and a telescopic boom 9 are installed on top of the support truss. The telescopic boom 9 is used to lift the steel arch, and the steel arch trolley 10 is used to assemble the steel arch. A hydraulic system 11 is installed on the bottom lifting support beam 3 through a counterweight.
[0013] The movable roller 1 is driven by a driving motor and can move along the tunnel axis.
[0014] The telescopic beam 2 is connected to the bottom lifting support beam 3 and the top lifting support beam 4 through a rotating motor, and the horizontal direction of the telescopic beam 2 is adjusted by the rotating motor.
[0015] The rock drilling system 5 consists of a transverse drive motor 12 and a hydraulic rock drill 13. The transverse drive motor 12 is mounted on the telescopic beam 2, and the hydraulic rock drill 13 is mounted on the transverse drive motor 12. The position of the hydraulic rock drill 13 on the tunnel excavation face is adjusted by the transverse drive motor 12.
[0016] Compared with existing technologies, 1) this invention enables drilling at any angle in the tunnel's longitudinal and radial directions. 2) The positions of the bottom and top lifting support beams can be adjusted to accommodate different tunnel construction needs. 3) A mobile trolley is installed to facilitate the hoisting, adjustment, and fixation of the steel arch. 4) The hydraulic system drives and controls the hydraulic components of the entire device, ensuring stable, centralized control, and easy operation. 5) Multiple types of work can be coordinated and performed simultaneously, ensuring construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 Schematic diagram of the full-section drilling trolley.
[0018] Figure 2 Schematic diagram of axial drilling blasting hole. DETAILED DESCRIPTION
[0019] The present invention is described in detail below with reference to the accompanying drawings and embodiments.
[0020] A trolley for full-section tunnel excavation, rock drilling and steel arch installation includes a moving roller 1, a telescopic crossbeam 2, a bottom lifting support beam 3, a top lifting support beam 4, a rock drilling system 5, a supporting hydraulic telescopic arm 6, a hydraulic rod 7, a top supporting hydraulic telescopic arm 8, a telescopic boom 9, a steel arch trolley 10 and a hydraulic system 11.
[0021] The bottom lifting support beam 3 and the top lifting support beam 4 are arranged in parallel. A hydraulic cylinder is installed between the bottom lifting support beam 3 and the top lifting support beam 4 to adjust the distance between the bottom lifting support beam 3 and the top lifting support beam 4. Two sets of telescopic beams 2 are provided: one set of telescopic beams 2 is installed at the bottom of the bottom lifting support beam 3, and the other set of telescopic beams 2 is installed at the top of the top lifting support beam 4. The bottom of the bottom lifting support beam 3 is equipped with a movable roller 1.
[0022] The rock drilling system 5 is arranged at the end of the telescopic beam 2; support columns are provided on both sides of the top of the top lifting support beam 4, and the sides of the support columns are provided with supporting hydraulic telescopic arms 6, hydraulic rods 7 and top hydraulic telescopic arms 8. The supporting hydraulic telescopic arms 6, hydraulic rods 7 and top hydraulic telescopic arms 8 are connected to form a steel arch support system; the supporting hydraulic telescopic arms 6 and the top hydraulic telescopic arms 8 are arranged in parallel, the bottom of the hydraulic rod 7 is fixed on the supporting hydraulic telescopic arms 6, and the top of the hydraulic rod 7 is installed on the bottom of the top hydraulic telescopic arms 8; the supporting hydraulic telescopic arms 6 are used to support and fix the installed steel arch, and the top of the hydraulic rod 7 is the hydraulic telescopic part.
[0023] The support truss is bolted to the support columns and installed at the top of the tunnel excavation. A steel arch trolley 10 and a telescopic boom 9 are installed on top of the support truss. The telescopic boom 9 is used to lift the steel arch, and the steel arch trolley 10 is used to assemble the steel arch. A hydraulic system 11 is installed on the bottom lifting support beam 3 through a counterweight.
[0024] The movable roller 1 is driven by a driving motor and can move along the tunnel axis.
[0025] The telescopic beam 2 is connected to the bottom lifting support beam 3 and the top lifting support beam 4 through a rotating motor, and the horizontal direction of the telescopic beam 2 is adjusted by the rotating motor.
[0026] The rock drilling system 5 consists of a transverse drive motor 12 and a hydraulic rock drill 13. The transverse drive motor 12 is mounted on the telescopic beam 2, and the hydraulic rock drill 13 is mounted on the transverse drive motor 12. The position of the hydraulic rock drill 13 on the tunnel excavation face is adjusted by the transverse drive motor 12.
[0027] like Figures 1 to 2 As shown, the device of the present invention completes the processing and assembly of parts in the factory and performs preliminary simulation tests according to relevant construction specifications. The device is then transported to the construction site and assembled into a large-scale electro-hydraulic trolley device that can be used for full-section tunnel excavation, blasting drilling, anchor drilling and steel arch frame installation. It enters the full-section tunnel excavation work station and carries out tests and verifications on various design functions such as rock drilling and steel arch frame installation according to the requirements of construction specifications and equipment operating procedures, and improves and perfects the finalized production.
[0028] The entire device is divided into a trolley frame system, a lifting and transverse beam system, a mobile rotary mechanical hydraulic and pneumatic drilling rig system, a hydraulic differential horizontal travel system and a hydraulic telescopic arm winch lifting mechanism.
[0029] This device has obvious advantages: 1) one machine with multiple uses and complete functions; 2) fast, efficient and convenient construction; 3) universal application in highway, railway and tunnel combinations.
Claims
1. A trolley for full-section tunnel excavation, rock drilling and steel arch installation, characterized in that: It comprises a moving roller (1), a telescopic crossbeam (2), a bottom lifting support beam (3), a top lifting support beam (4), a rock drilling system (5), a supporting hydraulic telescopic arm (6), a hydraulic rod (7), a top supporting hydraulic telescopic arm (8), a telescopic boom (9), a steel arch frame trolley (10) and a hydraulic system (11); The bottom lifting support beam (3) and the top lifting support beam (4) are arranged in parallel, and a hydraulic cylinder is provided between the bottom lifting support beam (3) and the top lifting support beam (4), and the distance between the bottom lifting support beam (3) and the top lifting support beam (4) is adjusted by the hydraulic cylinder; two groups of telescopic beams (2) are provided, one group of telescopic beams (2) is arranged at the bottom of the bottom lifting support beam (3), and the other group of telescopic beams (2) is arranged at the top of the top lifting support beam (4); and a movable roller (1) is provided at the bottom of the bottom lifting support beam (3); The rock drilling system (5) is arranged at the end of the telescopic crossbeam (2); support columns are arranged on both sides of the top of the top lifting support beam (4); the sides of the support columns are provided with a supporting hydraulic telescopic arm (6), a hydraulic rod (7) and a supporting top hydraulic telescopic arm (8); the supporting hydraulic telescopic arm (6), the hydraulic rod (7) and the supporting top hydraulic telescopic arm (8) are connected to form a steel arch support system; the supporting hydraulic telescopic arm (6) and the supporting top hydraulic telescopic arm (8) are arranged in parallel, the bottom of the hydraulic rod (7) is fixed on the supporting hydraulic telescopic arm (6), and the top of the hydraulic rod (7) is installed on the bottom of the supporting top hydraulic telescopic arm (8); the supporting hydraulic telescopic arm (6) is used to support and fix the installed steel arch, and the top of the hydraulic rod (7) is a hydraulic telescopic part; The support truss is fixed to the support column by bolt connection, the support truss is arranged at the top of the tunnel excavation, and the steel arch frame trolley (10) and the telescopic boom (9) are arranged at the top of the support truss; the telescopic boom (9) is used to hoist the steel arch frame, and the steel arch frame trolley (10) is used to assemble the steel arch frame; the hydraulic system (11) is installed on the bottom lifting support beam (3) through a counterweight; The telescopic crossbeam (2) is connected to the bottom lifting support beam (3) and the top lifting support beam (4) via a rotating motor, and the horizontal direction of the telescopic crossbeam (2) is adjusted via the rotating motor; The rock drilling system (5) is composed of a transverse drive motor (12) and a hydraulic rock drill (13). The transverse drive motor (12) is sleeved on the telescopic crossbeam (2), and the hydraulic rock drill (13) is mounted on the transverse drive motor (12). The position of the hydraulic rock drill (13) on the tunnel excavation surface is adjusted by the transverse drive motor (12).
2. The trolley for full-section tunnel excavation, rock drilling and steel arch installation according to claim 1, characterized in that: The movable roller (1) is driven by a driving motor, and the movable roller (1) is capable of moving along the axis of the tunnel.
Citation Information
Patent Citations
Jumbo for full-section excavation rock drilling and steel arch mounting of tunnel
CN209976479U