Combined transport and installation equipment for immersed tubes and transport and installation method
Through the immersed tube combined transportation and installation equipment, the floating beam mechanism and hull components are used to solve the problems of complex ship scheduling and high equipment cost in the immersed tube floating process, and realize low-cost and efficient immersed tube transportation and installation. Improved equipment flexibility and utilization.
Patent Information
- Application Number
- CN201910429089.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-05-22
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2039-05-22
AI Technical Summary
The existing immersed tube floating technology has problems such as complex ship-to-ship scheduling, long construction period, and high cost. Special equipment has high production costs, low utilization rates, and high requirements for waterways, which limits the use and dispatch of equipment.
The immersed tube combined transportation and installation equipment is used. The equipment includes a floating beam mechanism and two parallel hulls. The transportation and installation of the immersed tube are realized through winches and hoisting components. The equipment has a simple structure, low production cost, and can be customized according to construction needs. It is assembled into integrated equipment and disassembled into independent construction mechanisms after completion of transportation and installation to improve the utilization rate of the equipment.
It reduces construction costs, improves equipment utilization, simplifies construction dispatch, reduces requirements for waterways, enables flexible equipment assembly and disassembly, and is suitable for immersed tube transportation and installation construction.
Smart Images

Figure CN110053720B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to immersed tube tunnel construction technology, and in particular to immersed tube combined transport and installation equipment and a transport and installation method. Background Art
[0002] The immersed tube method is a construction method for underwater tunnels. An immersed tube tunnel is an underwater tunnel built by floating several sections of prefabricated immersed tubes to the surface construction site and installing them one by one in a dredged foundation trench. The existing immersed tube floating technology generally requires the use of multiple high-power tugboats to tow and transport the immersed tubes. The use of multiple tugboats to transport immersed tubes has the problems of complex scheduling between ships, long construction period and high cost.
[0003] In order to solve this problem, Chinese patent CN206187298U discloses a self-propelled underwater tunnel immersed tube transport and installation integrated ship. According to the structure of the immersed tube, an integrated ship equipment specially used for immersed tube transportation is independently designed. However, this special ship equipment needs to be produced separately and can only be used to transport immersed tubes. The equipment production cost is high and the equipment utilization rate is low. The use of this special equipment will increase the construction cost. At the same time, the positions of various mechanisms of the special ship equipment are relatively fixed, resulting in a large overall volume. During its dispatching process, it has high requirements on the water depth and width of the channel, which limits the use of the equipment and is inconvenient for construction dispatching. Summary of the invention
[0004] In view of the shortcomings of the prior art, the technical problem to be solved by the present invention is to provide a combined immersed tube transportation and installation equipment and a transportation and installation method. The equipment has a simple structure and uses existing transport ships as the main components. The equipment production cost is low, which can reduce the construction cost. The equipment can be assembled into an integrated immersed tube transportation equipment according to construction requirements, which is convenient for use in immersed tube transportation and installation construction. After the immersed tube transportation and installation is completed, it can be flexibly disassembled into multiple mechanisms that can be independently constructed and dispatched, which can improve the utilization rate of the equipment and facilitate construction dispatch.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] A combined transport and installation device for immersed tubes comprises a floating buoy beam mechanism, two parallel hulls and a winch installed on the hulls, wherein the floating buoy beam mechanism is provided with a traction point for connecting the winch cable; the floating buoy beam mechanism comprises a lifting beam and a buoy with adjustable draft, the lifting beam comprises a beam frame with two ends detachably connected to the two hulls, and a lifting assembly arranged between the two hulls for lifting the immersed tube, the two ends of the beam frame serving as connecting ends between the beam frame and the hulls, the connecting ends being erected on the hull deck, the hull deck being provided with a connecting component for connecting the connecting ends, the lifting assembly being installed on the beam frame, and the buoy being installed below the beam frame so that the beam frame floats on the water surface.
[0007] A combined transport and installation device for a submerged tube comprises a floating buoy crossbeam mechanism, two parallel hulls and a winch installed on the hulls, wherein the floating buoy crossbeam mechanism is provided with a traction point for connecting the winch cable; the floating buoy crossbeam mechanism comprises a lifting beam and a buoy with an adjustable draft, the lifting beam comprises a beam frame with two ends detachably connected to the two hulls, and a lifting assembly arranged between the two hulls for lifting the submerged tube, the lifting assembly is installed on the beam frame, and the buoy is installed below the beam frame so that the beam frame floats on the water surface.
[0008] Preferably, the hull may be configured as a barge.
[0009] Preferably, the traction point may be a hanging point arranged on the crossbeam frame, and there are at least two traction points.
[0010] Preferably, the crossbeam frame is arranged perpendicular to the length direction of the hull, and the connecting component is a tie point arranged on the hull deck, and the tie point can be connected to the connecting end arranged above it by a rope.
[0011] Preferably, the length of the connecting end is 0.5-1m.
[0012] Preferably, the floating body comprises a buoyancy box provided with a ballast water tank, and the ballast water tank is provided with a filling and drainage unit.
[0013] Preferably, the injection and drainage unit may include an injection and drainage port connected to the ballast water tank, the injection and drainage port is connected to a water pipe of a two-way water pump, and another water pipe of the two-way water pump can be inserted into the water body where the buoyancy box is located.
[0014] Preferably, the number of the pontoons is two, the pontoons are arranged between the two hulls, and the two pontoons are symmetrically arranged on both sides of the immersed tube.
[0015] Preferably, the pontoon is a rectangular pontoon, and the length direction of the pontoon is arranged parallel to the length direction of the hull.
[0016] Preferably, the hoisting assembly comprises a cable lifting mechanism, a hook is provided at the end of the rope of the cable lifting mechanism, and the hook can be connected to a preset lifting point on the top of the immersed tube.
[0017] Preferably, the cable lifting mechanism comprises two winches capable of lifting and lowering the cable in the vertical direction, the winches are symmetrically arranged on both sides of the vertical plane where the central axis of the immersed tube is located, and the winch body is installed below the crossbeam frame.
[0018] Preferably, the floating body cross beam mechanism is provided in plurality.
[0019] Preferably, the number of the floating body cross beam mechanisms is two, and the cross beam frames of the two floating body cross beam mechanisms are arranged in parallel.
[0020] The present invention also discloses a immersed tube transport and installation process using the immersed tube combined transport and installation equipment, comprising the following steps:
[0021] Hull in place: two parallel hulls are moved to the designated equipment assembly position and then positioned;
[0022] Equipment assembly: the rope of the winch on the hull is connected to the traction point of the floating buoy beam mechanism through a hook, the winch is started to drag the floating buoy beam mechanism to a preset position between the two hulls, the draft of the buoy is lowered until the connecting end of the beam frame is lowered to contact the hull deck, and the connecting end and the hull are detachably connected through a connecting component, thus completing the assembly of the submerged tube combined transport and installation equipment;
[0023] Loading the immersed tube: starting the hull to drive the immersed tube combined transport and installation equipment to the location of the immersed tube, and using the lifting assembly to connect and lift the immersed tube, thus completing the loading of the immersed tube;
[0024] Transport and installation of immersed tubes: start the ship to tow the immersed tubes and float the immersed tubes to the designated installation location, then position the ship. After the immersed tubes are pulled down to the designated placement location by the lifting assembly, release the connection between the immersed tubes and the lifting assembly, and the installation of the immersed tubes is completed;
[0025] Equipment dismantling: the connection between the connecting end of the beam frame and the connecting part of the hull is released, so that the hull is separated from the floating buoy beam mechanism, and the disassembly of the immersed tube combined transport and installation equipment is completed.
[0026] Compared with the prior art, the advantages and positive effects of the present invention are as follows: the present invention provides a combined immersed tube transportation and installation equipment and a transportation and installation method. The equipment has a simple structure and uses existing transport ships as the main components. The equipment production cost is low, which can reduce the construction cost. The equipment can be assembled into an integrated immersed tube transportation equipment according to construction requirements, which is convenient for use in immersed tube transportation and installation construction. After the immersed tube transportation and installation is completed, it can be flexibly disassembled into multiple mechanisms that can be independently constructed and dispatched, which can improve the utilization rate of the equipment and facilitate construction dispatch. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a top view of the assembled state of the immersed tube assembled transport and installation equipment of the present invention;
[0028] Figure 2 It is a schematic diagram of the structure of the assembled state of the immersed tube assembled transport and installation equipment of the present invention;
[0029] Figure 3 It is a structural schematic diagram of the floating floating body cross beam mechanism of the present invention;
[0030] Figure 4 It is a schematic diagram of the assembly process of the immersed tube combined transport and installation equipment of the present invention;
[0031] In the above figure: 1-lifting beam, 11-beam frame, 111-connecting end, 112-lifting point, 12-lifting assembly, 121-winch, 122-cable, 2-hull, 21-anchor point, 3-winch, 4-floating body, 41-pontoon, 5-submerged tube. DETAILED DESCRIPTION
[0032] The present invention is described in detail below by way of exemplary embodiments. However, it should be understood that elements, structures, and features in one embodiment may also be beneficially combined in other embodiments without further description.
[0033] It should be noted that, in the description of the present invention, the directions or positional relationships indicated by terms such as “inside”, “outside”, “up”, “down”, “left”, “right”, “front” and “back” are based on the positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.
[0034] Example:
[0035] like Figures 1 to 4As shown, a combined transport and installation equipment for immersed tubes comprises a floating buoy beam mechanism, two parallel hulls 2 and a winch 3 installed on the hulls 2, wherein the floating buoy beam mechanism is provided with a traction point for connecting the rope of the winch 3; the floating buoy beam mechanism comprises a lifting beam 1 and a buoy 4 with adjustable draft, the lifting beam 1 comprises a beam frame 11 whose two ends are detachably connected to the two hulls 2, and a lifting assembly 12 arranged between the two hulls 2 for lifting the immersed tube 5, the two ends of the beam frame 11 serve as connecting ends 111 between the beam frame 11 and the hull 2, the connecting ends 111 are erected on the deck of the hull 2, a connecting component for connecting the connecting ends 111 is provided on the deck of the hull 2, the lifting assembly 12 is installed on the beam frame 11, and the buoy 4 is installed below the beam frame 11 to make the beam frame 11 float on the water.
[0036] The immersed tube transport and installation process using the above-mentioned immersed tube combined transport and installation equipment includes the following steps:
[0037] Hull in place: two parallel hulls 2 are moved to the designated equipment assembly position and then positioned. The hull 1 can be moved to the designated position in any conventional manner, or can be positioned in any existing positioning manner, such as the hull 2 can be moved to the designated position by an anchor windlass and then anchored;
[0038] Equipment assembly: The rope of the winch 3 on the hull 2 is connected to the traction point of the floating buoy beam mechanism through a hook, and the winch 3 is started to drag the floating buoy beam mechanism to the preset position between the two hulls 2, and the draft of the buoy 4 is lowered until the connecting end 111 of the beam frame 11 is lowered to contact the deck of the hull 2, and the connecting end 111 and the hull 2 are detachably connected through the connecting component, so that the assembly of the submerged tube combined transportation and installation equipment is completed;
[0039] Loading the immersed tube: starting the hull 2 to drive the immersed tube combined transport and installation equipment to the location of the immersed tube 5, and using the lifting assembly 12 to connect and lift the immersed tube 5, thus completing the loading of the immersed tube 5;
[0040] Transport and installation of immersed tubes: start the hull 2 to tow the immersed tube 5 and float the immersed tube 5 to the designated installation position, then position the hull 2. After the immersed tube 5 is pulled down to the designated sinking position by the lifting assembly 12, release the connection between the immersed tube 5 and the lifting assembly 12, and the installation of the immersed tube 5 is completed;
[0041] Equipment dismantling: the connection between the connecting end 111 of the beam frame 11 and the connecting part of the hull 2 is released, so that the hull 2 is separated from the floating buoy beam mechanism, and the dismantling of the submerged tube combined transport and installation equipment is completed.
[0042] The combined transport and installation equipment for immersed tubes of the present embodiment has a simple structure, with the existing transport ship hull 2 as the main component, which can make full use of the existing construction ships, reduce the equipment production cost, and further reduce the construction cost. By adopting the above-mentioned equipment and construction process, the equipment can be assembled into an integrated transport equipment for immersed tubes 5 according to construction requirements, which is convenient for use in the transport and installation construction of immersed tubes 5. After the transport and installation of immersed tubes 5 are completed, the integrated equipment can be flexibly disassembled into two transport ships and a floating buoy crossbeam mechanism that can be independently constructed and dispatched, thereby improving the utilization rate of the equipment. At the same time, the disassembled equipment has lower requirements on the water depth and width of the channel when navigating, which is convenient for construction and dispatch.
[0043] Specifically, the hull 2 can be configured as a conventional transport ship such as a barge.
[0044] Specifically, the traction point may be a suspension point 112 disposed on the beam frame 11 , and at least two traction points may be provided. For example, a winch 3 is provided on each of the two hulls 1 , and two suspension points 112 are correspondingly provided above the beam frame 11 .
[0045] Specifically, the crossbeam frame 11 is arranged perpendicular to the length direction of the hull 2, and the connecting component is a tie point 21 arranged on the deck of the hull 2, and the tie point 21 can be connected to the connection end 111 arranged above it by a rope. The tie point 21 fixed on the deck of the hull 2 is used as the connecting component, and the connection end 111 and the tie point 21 are connected by a rope, so that the connection end 111 and the hull 2 can be easily connected and disassembled, thereby facilitating the assembly and disassembly of the equipment and facilitating the flexible use of the equipment.
[0046] Specifically, the length of the connection end is 0.5-1m. The connection end is set to an appropriate length to ensure the stable connection between the hull 2 and the beam frame 11 while preventing the connection end 111 extending from the beam frame 11 from being too long to affect the transportation of the floating buoy beam mechanism.
[0047] Specifically, the floating body 4 includes a pontoon 41 provided with a ballast water tank, and the ballast water tank is provided with a filling and drainage unit. The draft of the pontoon can be conveniently achieved by filling and draining the ballast water tank of the pontoon 41. The filling and drainage unit is for filling the ballast water tank, but the pontoon 41 sinks and the draft increases. The filling and drainage unit is for draining the ballast water tank, but the pontoon 41 floats and the draft decreases. The current pontoon 41 with adjustable ballast water volume can conveniently achieve the height adjustment of the lifting beam 1 above the pontoon 41.
[0048] Specifically, the injection and drainage unit may include an injection and drainage port connected to the ballast water tank, the injection and drainage port is connected to a water pipe of a two-way water pump, and another water pipe of the two-way water pump can be inserted into the water body where the buoyancy tank 41 is located.
[0049] Specifically, there are two pontoons 41 , which are disposed between the two hulls, and the two pontoons 41 are symmetrically disposed on both sides of the immersed tube 5 .
[0050] Specifically, the pontoon 41 is a rectangular parallelepiped pontoon, and the length direction of the pontoon 41 is arranged parallel to the length direction of the hull 2 .
[0051] Specifically, the hoisting assembly 12 includes a cable lifting mechanism, and a hook is provided at the end of the rope 122 of the cable lifting mechanism, and the hook can be connected to a preset lifting point on the top of the immersed tube 5.
[0052] Specifically, the cable lifting mechanism includes two winches 121 that can lift and lower cables in the vertical direction. The winches 121 are symmetrically arranged on both sides of the vertical plane where the central axis of the immersed tube 5 is located, and the main body of the winch 121 is installed below the crossbeam frame 11. The lifting height of the immersed tube can be raised and lowered by retracting and releasing the rope of the winch, which is convenient for the transportation and sinking of the immersed tube.
[0053] In addition, other hoisting devices capable of adjusting the height of the immersed tube hoisting may also be used as the hoisting assembly 12 .
[0054] Specifically, the floating buoy cross beam mechanism is provided in a plurality. The use of a plurality of floating buoy cross beam mechanisms to simultaneously hoist, transport and install the same section of the immersed tube can better ensure the stability of the transportation and sinking operations.
[0055] Specifically, the floating body cross beam mechanisms are provided in two, and the cross beam frames 11 of the two floating body cross beam mechanisms are arranged in parallel.
[0056] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.
Claims
1. A method for combined transport and installation of immersed tubes, using a combined transport and installation device for immersed tubes, characterized in that: The combined transport and installation equipment for immersed tubes comprises a floating buoy crossbeam mechanism, two parallel hulls and a winch installed on the hulls, wherein the floating buoy crossbeam mechanism is provided with a traction point for connecting the winch cable; the floating buoy crossbeam mechanism comprises a lifting beam and a buoy with adjustable draft, the lifting beam comprises a crossbeam frame with two ends detachably connected to the two hulls respectively, and a lifting assembly arranged between the two hulls for lifting the immersed tube, the two ends of the crossbeam frame serve as connecting ends between the crossbeam frame and the hull, the connecting ends are erected on the hull deck, the hull deck is provided with a connecting component for connecting the connecting ends, the lifting assembly is installed on the crossbeam frame, and the buoy is installed on The crossbeam frame is arranged below so that the crossbeam frame floats on the water surface; the crossbeam frame is arranged perpendicular to the length direction of the hull, and the connecting component is a tie point arranged on the deck of the hull, and the tie point can be connected with a rope to the connecting end arranged above it; the floating body includes a pontoon provided with a ballast water tank, and the ballast water tank is provided with a filling and drainage unit. The filling and drainage unit is for filling the ballast water tank with water, which can make the pontoon sink and increase the draft depth, and the filling and drainage unit is for draining the ballast water tank, which can make the pontoon float and reduce the draft depth; the pontoon is provided with two pontoons, and the pontoon is arranged between the two hulls, and the two pontoons are symmetrically arranged on both sides of the submerged tube; the pontoon is a rectangular pontoon, and the length direction of the pontoon is arranged parallel to the length direction of the hull; The immersed tube combined transport and installation method comprises the following steps: Hull in place: two parallel hulls are moved to the designated equipment assembly position and then positioned; Equipment assembly: the rope of the winch on the hull is connected to the traction point of the floating buoy beam mechanism through a hook, the winch is started to drag the floating buoy beam mechanism to a preset position between the two hulls, the draft of the buoy is lowered until the connecting end of the beam frame is lowered to contact the hull deck, and the connecting end and the hull are detachably connected through a connecting component, thus completing the assembly of the submerged tube combined transport and installation equipment; Loading the immersed tube: starting the hull to drive the immersed tube combined transport and installation equipment to the location of the immersed tube, and using the lifting assembly to connect and lift the immersed tube, thus completing the loading of the immersed tube; Transport and installation of immersed tubes: start the ship to tow the immersed tubes and float the immersed tubes to the designated installation location, then position the ship. After the immersed tubes are pulled down to the designated placement location by the lifting assembly, release the connection between the immersed tubes and the lifting assembly, and the installation of the immersed tubes is completed; Equipment dismantling: the connection between the connecting end of the beam frame and the connecting part of the hull is released, so that the hull is separated from the floating buoy beam mechanism, and the disassembly of the immersed tube combined transport and installation equipment is completed.
2. The method for combined transport and installation of immersed tubes according to claim 1, characterized in that: The length of the connecting end is 0.5-1m.
3. The method for combined transport and installation of immersed tubes according to claim 1, characterized in that: The hoisting assembly comprises a cable lifting mechanism, a rope end of the cable lifting mechanism is provided with a hook, and the hook can be connected to a preset lifting point on the top of the immersed tube.
4. The method for combined transport and installation of immersed tubes according to claim 3 is characterized in that: The cable lifting mechanism includes two winches that can lift and lower the cable in the vertical direction. The winches are symmetrically arranged on both sides of the vertical plane where the central axis of the immersed tube is located, and the winch body is installed below the crossbeam frame.
5. The method for combined transport and installation of immersed tubes according to claim 1, characterized in that: The floating body cross beam mechanism is provided in plurality.
Citation Information
Patent Citations
Integrative ship of self -navigation formula subaqueous tunnel immersed tube delivery installation
CN206187298U
Immersed tube combined type transportation and installation equipment
CN210126614U
Complex to surface and carry sunken submarines and other ships
RU2390460C1