A method and system for testing the physical interface consistency of a battery energy storage power station

By implementing physical interface consistency testing in battery energy storage power stations, the problems of equipment interchangeability and interoperability are solved, the plug-and-play function is realized, and the system is scalable and reliable.

CN110430089BActive Publication Date: 2024-11-19CHINA ELECTRIC POWER RESEARCH INSTITUTE CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910542653.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-06-21
Publication Date
2024-11-19
Estimated Expiration
2039-06-21

AI Technical Summary

Technical Problem

The prior art has failed to effectively solve the problem of physical interface consistency of battery energy storage power stations, resulting in a lack of interchangeability and interoperability of equipment, affecting the implementation of plug-and-play functions.

Method used

A method for physical interface consistency testing of battery energy storage power stations is proposed. Communication test, logic test, fault test, basic functional test and operation test are performed successively through the system framework to ensure the consistency of standardized interfaces between communication paths and circuit AC and DC buses.

Benefits of technology

It improves the interchangeability and interoperability of battery energy storage power station equipment, realizes plug-and-play functions, and enhances the scalability and reliability of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110430089B_ABST
    Figure CN110430089B_ABST
Patent Text Reader

Abstract

A method and system for testing the physical interface consistency of a battery energy storage power station, comprising: based on the system framework of the battery energy storage power station, executing test strategies in sequence for communication paths and circuit AC and DC buses; if all strategies are passed, completing the consistency test; the test strategies include: communication test, logic test, fault test, basic function test and operation test; from the level of weak current physical interface and strong current physical interface, a standard test method for connecting each device component in a plug-and-play battery energy storage power station to the battery energy storage power station is established; a standard test method for connecting the plug-and-play battery energy storage power station as a whole to the power grid is established.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electric power automation equipment, and in particular to a method and system for testing the physical interface consistency of a battery energy storage power station. Background Art

[0002] Energy storage is an inevitable choice for the future development of the power industry. Due to the needs of large-scale consumption of renewable energy, power peak and frequency regulation, friendly access to distributed energy, user-side demand response, and friendly interaction between electric vehicles and power grids, energy storage will play an indispensable role in the future power system. At present, there are many ways of energy storage available, among which electrochemical batteries are gradually gaining attention due to their fast response, easy modular assembly, and convenient installation. With the development of battery energy storage technology, the power, efficiency, cycle life and cost performance of batteries have been significantly improved.

[0003] At present, the research on battery energy storage technology in random power generation mainly focuses on the energy storage configuration mode and capacity optimization, while there is still a lack of systematic discussion on the construction plan and flexible operation of battery energy storage system. Expanding the scope of use of battery energy storage system, giving full play to the advantages of battery energy storage system in emergency situations, and solving the problems that may exist in the large-scale application of energy storage further highlight the importance of energy storage equipment with plug-and-play function. By conducting research on plug-and-play technology of battery energy storage power stations, the effectiveness and convenience of grid connection of battery energy storage system can be improved, and help can be provided for the research and development of urban energy Internet technology. The battery components and their battery management system BMS, energy storage converters and their control systems in the currently built battery energy storage power stations may be provided by different manufacturers. The communication protocols and equipment characteristics of each manufacturer are not the same, resulting in the lack of interchangeability of the core key equipment of the energy storage system, which brings difficulties to the system integration and plug-and-play function of the energy storage power station.

[0004] In the prior art, the published invention application CN 108600015 A proposed, from the perspective of unified communication standards, to build a self-description model of a battery energy storage power station and a communication interaction method based on the IEC61850 standard model, and made useful explorations on the plug-and-play implementation of a battery energy storage power station. However, it did not take into account the properties of a battery energy storage power station as a high-power electrical device, and the communication layer is a weak interface of the control system, and did not describe how to achieve plug-and-play at the physical interface of the high-voltage layer. In view of the layered architecture characteristics of battery energy storage power stations and the plug-and-play application requirements, it has become particularly urgent to study the consistency test method of the standard physical interface of battery energy storage power stations, and to improve the interchangeability and interoperability of battery cells, energy storage inverters and other equipment in battery energy storage power stations. Summary of the invention

[0005] In order to solve the above-mentioned deficiencies in the prior art, the present invention provides a method and system for testing the physical interface consistency of a battery energy storage power station.

[0006] The technical solution provided by the present invention is:

[0007] A method for testing the physical interface consistency of a battery energy storage power station, the method comprising:

[0008] Based on the system framework of the battery energy storage power station, the test strategy is executed sequentially for the communication path and the circuit AC and DC bus;

[0009] If all policies pass, the conformance test is complete;

[0010] The test strategy includes: communication test, logic test, fault test, basic function test and operation test.

[0011] Preferably, based on the system framework of the battery energy storage power station, the test strategy is executed sequentially for the communication path and the circuit AC and DC bus, including:

[0012] Conduct communication tests on different communication media of the communication path;

[0013] When the communication test is passed, a logic test is performed on the AC and DC buses of the circuit;

[0014] When the logic test is passed, the components of the battery energy storage power station and the control system are sequentially subjected to fault testing, basic function testing and operation testing based on the communication path and the circuit AC and DC bus;

[0015] Among them, when a test strategy fails, the subsequent strategies will be stopped and no longer executed.

[0016] Preferably, the communication test includes:

[0017] Acquire different communication media in the communication path and communication protocols corresponding to the different communication media;

[0018] Send n groups of data to each station on the communication path through the weak current physical interface, and receive n groups of data fed back by each station;

[0019] Performing data verification based on the n sets of feedback data and the communication protocol point table;

[0020] If all n groups of data pass, the communication test passes;

[0021] Otherwise, the communication test fails.

[0022] Preferably, the logic test includes:

[0023] Obtaining the battery pack, energy storage converter and battery energy storage power station in the energy storage unit;

[0024] Connect the battery pack to the DC bus of the energy storage converter, the energy storage converter to the secondary AC bus of the transformer of the battery energy storage power station, and the battery energy storage power station to the grid-side AC bus through a circuit breaker;

[0025] Based on the strong electric physical interface, the opening and closing signals are sent to the battery pack, energy storage converter and battery energy storage power station in sequence through the DC bus or AC bus;

[0026] If the corresponding circuit breakers all operate correctly, the logic test passes;

[0027] Otherwise, the logic test fails.

[0028] Preferably, the fault test includes:

[0029] Send fault data to the energy storage unit control system, the power station control system and the integrated dispatching control center system of the energy storage power station respectively based on the communication path that passes the communication test;

[0030] Based on the fault data, an instruction to disconnect the circuit breaker is issued in real time and accurately, and the circuit breaker is shut down, and then the fault information is archived and reported;

[0031] When the energy storage unit control system, power station control system and integrated dispatching control center all issue instructions accurately and process them, the fault test is passed;

[0032] Otherwise the fault test fails.

[0033] Preferably, the basic function test includes:

[0034] Based on the upper and lower level relationship between the energy storage unit control system, power station control system and integrated dispatching control center system;

[0035] Based on the communication paths and battery energy storage power stations that have passed the fault test and logic test, the superior issues operating instructions to the lower level;

[0036] Based on the operating instructions, if the energy storage unit battery assembly, energy storage unit and energy storage power station functions are all operating correctly, the basic function test is passed;

[0037] Otherwise, the basic functional test fails;

[0038] Among them, the integrated dispatching control center system, the power station control system and the energy storage stand-alone control system are in a superior to subordinate relationship.

[0039] Preferably, the running test includes:

[0040] The integrated dispatching control center system issues dispatching instructions to the power station control system;

[0041] When the battery energy storage power station operates normally according to the dispatch instruction, the operation test passes;

[0042] Otherwise, the operation test fails;

[0043] Among them, the dispatching instructions include: peak shaving and valley filling, voltage-frequency support, auxiliary frequency regulation, power quality optimization and emergency backup power supply.

[0044] A battery energy storage power station physical interface consistency test system, the system comprising:

[0045] Test module: used for the system framework of the battery energy storage power station, and executes the test strategy for the communication path and the circuit AC and DC bus respectively;

[0046] Pass module: used for consistency testing if all strategies are passed;

[0047] The different test strategies include, in sequence: communication path test, logic test, fault test, basic function test and operation test.

[0048] Preferably, the test module comprises: a communication test unit, a logic test unit and a subsequent test unit;

[0049] The communication test unit is used to perform communication tests on different communication media of the communication path;

[0050] The logic test unit is used to perform a logic test on the AC and DC bus of the circuit after the communication test passes;

[0051] The subsequent test unit is used to perform fault tests, basic function tests and operation tests on the components and control system of the battery energy storage power station in sequence based on the communication path and the circuit AC and DC bus after the logic test passes;

[0052] Among them, when a test strategy fails, the subsequent strategies will be stopped and no longer executed.

[0053] Preferably, the communication test unit comprises: an acquisition subunit, a sending subunit, a verification subunit and a test pass subunit;

[0054] The acquisition subunit is used to acquire different communication media in the communication path and communication protocols corresponding to the different communication media;

[0055] The sending subunit is used to send n groups of data to each station of the communication path based on the information interface, and receive n groups of data fed back by each station;

[0056] The verification subunit is used to perform data verification based on the n groups of feedback data and the communication protocol point table;

[0057] The test pass subunit is used for if all n groups of data pass, the communication test passes;

[0058] Otherwise, the communication test fails.

[0059] Compared with the prior art, the present invention has the following beneficial effects:

[0060] 1. The technical solution provided by the present invention includes: based on the system framework of the battery energy storage power station, the test strategies are executed in sequence for the communication path and the circuit AC and DC bus; if all strategies are passed, the consistency test is completed; the test strategies include: communication test, logic test, fault test, basic function test and operation test; from the level of weak current physical interface and strong current physical interface, a standard test method for connecting each device component in the plug-and-play battery energy storage power station to the battery energy storage power station is established; a standard test method for the overall access of the plug-and-play battery energy storage power station to the power grid.

[0061] 2. The technical solution provided by the present invention can improve the interchangeability and interoperability of various equipment components in the plug-and-play battery energy storage power station, and has positive guiding significance and reference value for developing plug-and-play battery energy storage power station equipment with enhanced scalability and reliability, and solving the implementation problems of flexible grid-connected technology of battery energy storage power stations. BRIEF DESCRIPTION OF THE DRAWINGS

[0062] Figure 1 This is a flow chart of the physical interface consistency test method of the battery energy storage power station of the present invention;

[0063] Figure 2 This is a schematic diagram of the plug-and-play battery energy storage power station system architecture of the present invention;

[0064] Figure 3 This is a schematic diagram of the communication layering of the plug-and-play battery energy storage power station of the present invention;

[0065] Figure 4 It is a schematic diagram of multiple energy storage units of the present invention being connected to a battery energy storage power station through parallel expansion;

[0066] Figure 5 It is a basic flow chart of the plug-and-play battery energy storage power station physical interface consistency test method of the present invention;

[0067] Figure 6 It is a detailed flow chart of the physical interface consistency testing method of the plug-and-play battery energy storage power station of the present invention. DETAILED DESCRIPTION

[0068] In order to better understand the present invention, the content of the present invention is further described below in conjunction with the accompanying drawings and examples.

[0069] Embodiment 1:

[0070] The purpose of the present invention is to disclose a method for testing the physical interface consistency of a plug-and-play battery energy storage power station, and to establish standard test steps for orderly and stable access of various parts in a plug-and-play battery energy storage power station, such as Figure 1 As shown:

[0071] Step 1: Based on the system framework of the battery energy storage power station, the test strategies are executed in sequence for the communication path and the circuit AC and DC buses;

[0072] Step 2: If all policies pass, the consistency test is completed;

[0073] The different test strategies include, in sequence: communication path test, logic test, fault test, basic function test and operation test.

[0074] Step 1: Based on the system framework of the battery energy storage power station, the test strategies are executed in sequence for the communication path and the circuit AC and DC buses;

[0075] The system architecture of the plug-and-play battery energy storage power station is as follows: Figure 2 As shown in the figure, a battery energy storage power station is usually composed of multiple energy storage units connected in parallel for expansion. A single energy storage unit (or energy storage unit) is mainly composed of a battery pack, a battery management system (BMS), a power storage converter (PCS), an energy storage unit control system (referred to as machine control), and switchgear.

[0076] The battery energy storage station is divided into weak current physical interface and strong current physical interface. Figure 3 As shown, it includes three levels: (1) The battery energy storage power station is equipped with a power station control system (referred to as station control), which can communicate bidirectionally with the power system integrated dispatching and control center (referred to as integrated control) to achieve optimized dispatching and operation control of the power station system. (2) The machine control and station control can also communicate bidirectionally to achieve coordinated control of multiple energy storage units in the power station. (3) The machine control of each energy storage unit and the BMS can also communicate bidirectionally to achieve battery charging and discharging management. Strong electrical physical interface such as Figure 4 As shown, it includes: (1) the battery pack is connected to the DC bus of the PCS or DC / DC link through the DC circuit breaker K1; (2) the DC\DC link is connected to the DC / AC link of the PCS through the circuit breaker K4. It is worth noting that according to different application scenarios and battery output characteristics, the DC\DC link is not necessarily set; (3) the PCS is connected to the secondary side of the transformer of the battery energy storage power station through the AC circuit breaker K2; (4) the battery energy storage power station is connected to the power grid through the AC circuit breaker K3.

[0077] Step 2: If all policies pass, the consistency test is completed;

[0078] The basic flow chart is as follows Figure 5 As shown, it mainly includes the following 5 steps:

[0079] Step 1: Communication test. It includes three levels of communication test: (1) Communication physical interface matching, communication protocol consistency and communication point table test between the battery management system BMS and the energy storage unit control system (referred to as machine control) that constitutes the battery energy storage power station; (2) Communication physical interface matching, communication protocol consistency and communication point table test between the machine control and the battery energy storage power station control system (referred to as station control); (3) Communication physical interface matching, communication protocol consistency and communication point table test between the station control and the power system integrated dispatching control center (referred to as integrated control).

[0080] The specific methods and steps of communication testing are as follows:

[0081] Step 1): Connect the communication medium through the weak current physical interface and establish the communication line. The BMS communicates with the machine control through coaxial cable, and the communication protocol adopts CAN2.0b; the machine control and the station control communicate through optical fiber, and the communication protocol adopts IEC104; the station control and the integrated control communicate through optical fiber, following the IEC61850 protocol.

[0082] Step 2): Randomly test the communication point table to check the consistency of the communication protocol. If the BMS sends a group of data to the machine control, the group of data is random data or specified data in the BMS communication point table, such as battery type, current SOC, single cell voltage data, etc. The machine control will repackage the received group of data and transmit it to the BMS, which will verify the group of data. Multiple groups of different data can be sent cyclically for communication testing. If multiple groups of data are verified, it means that the communication protocol consistency check has passed. The communication protocol consistency test between machine control and station control, and station control and integrated control can be deduced in this way.

[0083] If the communication test passes, the next test can be performed. Otherwise, the test is stopped and the physical interface consistency of the battery energy storage power station fails.

[0084] Step 2: Logic test. This includes three levels of logic testing: (1) DC contactor opening and closing test of the battery module connected to the energy storage unit; (2) AC circuit breaker opening and closing test of the energy storage unit connected to the battery energy storage power station; (3) AC circuit breaker opening and closing test of the battery energy storage power station connected to the power system.

[0085] The specific method of logic testing is:

[0086] Take the DC contactor opening and closing test of the battery assembly connected to the energy storage unit side as an example. Through the strong electric physical interface, the control relay input circuit and output circuit of the DC contactor are connected to the machine control switch control module. The machine control sends multiple closing and opening control signals to the DC contactor to observe whether the DC contactor can operate accurately. If it can operate accurately, it means that the logic test has passed. The AC circuit breaker opening and closing test of the energy storage unit connected to the battery energy storage power station and the AC circuit breaker opening and closing test of the battery energy storage power station connected to the power system can be deduced in the same way.

[0087] If the logic test passes, the next fault test can be performed. Otherwise, the test is stopped and the physical interface consistency of the battery energy storage power station fails.

[0088] Step 3: Fault testing. This includes three levels of fault testing: (1) simulating the fault status of battery modules to test whether the fault handling mechanisms of BMS and machine control are normal; (2) simulating the fault status of a single energy storage unit to test whether the fault handling mechanisms of machine control and station control are normal; (3) simulating the fault status of a battery energy storage power station to test whether the fault handling mechanisms of station control and integrated control are normal.

[0089] The steps and methods of fault testing are as follows:

[0090] Manually simulate a set of fault data for a given machine control, or lower the upper limit of the machine control fault to simulate various battery component or single-cell fault states, such as battery voltage over-limit, charging current over-limit, single-cell battery voltage imbalance, and temperature over-limit, etc., to test the machine control's recognition and handling of faults. When a serious over-limit occurs, disconnect the DC contactor and shut down in real time, and archive the fault information and report it to the station control. The fault simulation test of the machine control and station control, and the fault simulation test of the station control and integrated control are similar.

[0091] If the fault test passes, the next test can be performed, otherwise, the test is stopped and the physical interface consistency of the battery energy storage power station fails.

[0092] Step 4: Basic function test. This includes three levels of basic function tests: (1) The machine control issues control instructions to the BMS to test the charging and discharging functions of the battery components; (2) The station control issues control instructions to the machine control to test the functions of the energy storage motor being connected to the battery energy storage power station or being disconnected from the battery energy storage power station, constant power grid connection, and constant voltage operation; (3) The integrated control issues dispatching instructions to the station control to test the functions of the battery energy storage power station being connected to and disconnected from the grid, constant power grid connection, and constant voltage operation;

[0093] If the basic function test is passed, the next test can be carried out. Otherwise, the test is stopped and the physical interface consistency of the battery energy storage power station has not passed.

[0094] Step 5: Run test. The integrated control system issues dispatch instructions to the station control system to test whether the battery energy storage power station can operate normally according to the instructions.

[0095] If the running test passes, the physical interface consistency of the battery energy storage power station passes; otherwise, the test is stopped and the physical interface consistency of the battery energy storage power station fails.

[0096] The dispatching instructions described in step 5 correspond to the advanced application functions of the battery energy storage power station, including but not limited to the following: peak shaving and valley filling, voltage-frequency support, auxiliary frequency regulation, power quality optimization, and emergency backup power supply.

[0097] Steps 1 to 5 are sequentially progressive, such as Figure 6 As shown, if the test content included in the preceding step of any step fails, the physical interface consistency test result fails.

[0098] The physical interface of the battery energy storage power station includes a weak current interface, which corresponds to the communication interface of each control system; it also includes a strong current interface, which corresponds to the AC and DC busbars of each part of the main circuit connected through the circuit breaker.

[0099] Embodiment 2:

[0100] Based on the same concept invention, the present invention also provides a physical interface consistency test system for a battery energy storage power station, the system comprising:

[0101] Test module: used for the system framework of the battery energy storage power station, and executes the test strategy for the communication path and the circuit AC and DC bus respectively;

[0102] Pass module: used for consistency testing if all strategies are passed;

[0103] The different test strategies include, in sequence: communication path test, logic test, fault test, basic function test and operation test.

[0104] The test module includes: a communication test unit, a logic test unit and a subsequent test unit;

[0105] The communication test unit is used to perform communication tests on different communication media of the communication path;

[0106] The logic test unit is used to perform a logic test on the AC and DC bus of the circuit after the communication test passes;

[0107] The subsequent test unit is used to perform fault tests, basic function tests and operation tests on the components and control system of the battery energy storage power station in sequence based on the communication path and the circuit AC and DC bus after the logic test passes;

[0108] Among them, when a test strategy fails, the subsequent strategies will be stopped and no longer executed.

[0109] The communication test unit includes: an acquisition subunit, a sending subunit, a verification subunit and a test pass subunit;

[0110] The acquisition subunit is used to acquire different communication media in the communication path and communication protocols corresponding to the different communication media;

[0111] The sending subunit is used to send n groups of data to each station of the communication path based on the information interface, and receive n groups of data fed back by each station;

[0112] The verification subunit is used to perform data verification based on the n groups of feedback data and the communication protocol point table;

[0113] The test pass subunit is used for if all n groups of data pass, the communication test passes;

[0114] Otherwise, the communication test fails.

[0115] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0116] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0117] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0118] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0119] The above are merely embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are included in the scope of the claims of the present invention to be approved.

Claims

1. A method for testing the physical interface consistency of a battery energy storage power station, characterized in that: The method comprises: Based on the system framework of the battery energy storage power station, the test strategy is executed sequentially for the communication path and the circuit AC and DC bus; If all policies pass, the conformance test is complete; The test strategy includes: communication test, logic test, fault test, basic function test and operation test; Based on the system framework of the battery energy storage power station, the test strategies are executed sequentially for the communication path and the circuit AC and DC bus, including: Conduct communication tests on different communication media of the communication path; When the communication test is passed, a logic test is performed on the AC and DC buses of the circuit; When the logic test is passed, the components of the battery energy storage power station and the control system are sequentially subjected to fault testing, basic function testing and operation testing based on the communication path and the circuit AC and DC bus; Among them, when a test strategy fails, the subsequent strategies will be stopped and no longer executed; The communication test comprises: Acquire different communication media in the communication path and communication protocols corresponding to the different communication media; Send n groups of data to each station on the communication path through the weak current physical interface, and receive n groups of data fed back by each station; Performing data verification based on the n sets of feedback data and the communication protocol point table; If all n groups of data pass, the communication test passes; Otherwise, the communication test fails; The logic test includes: Obtain battery packs, energy storage converters and battery energy storage power stations in single energy storage units; Connect the battery pack to the DC bus of the energy storage converter, the energy storage converter to the secondary AC bus of the transformer of the battery energy storage power station, and the battery energy storage power station to the grid-side AC bus through a circuit breaker; Based on the strong electric physical interface, the opening and closing signals are sent to the battery pack, energy storage converter and battery energy storage power station in sequence through the DC bus or AC bus; If the corresponding circuit breakers all operate correctly, the logic test passes; Otherwise, the logic test fails; The fault test comprises: Send fault data to the energy storage unit control system, the power station control system and the integrated dispatching control center system of the energy storage power station respectively based on the communication path that passes the communication test; Based on the fault data, an instruction to disconnect the circuit breaker is issued in real time and accurately, and the circuit breaker is shut down, and then the fault information is archived and reported; When the energy storage unit control system, power station control system and integrated dispatching control center all issue instructions accurately and process them, the fault test is passed; Otherwise the fault test fails; The basic functional tests include: Based on the upper and lower level relationship between the energy storage unit control system, power station control system and integrated dispatching control center system; Based on the communication paths and battery energy storage power stations that have passed the fault test and logic test, the superior issues operating instructions to the lower level; Based on the operating instructions, if the energy storage unit battery assembly, energy storage unit and energy storage power station functions are all operating correctly, the basic function test is passed; Otherwise, the basic functional test fails; Among them, the integrated dispatching control center system, the power station control system and the energy storage stand-alone control system are in a superior to subordinate relationship; The running test includes: The integrated dispatching control center system issues dispatching instructions to the power station control system; When the battery energy storage power station operates normally according to the dispatch instruction, the operation test passes; Otherwise, the operation test fails; Among them, the dispatching instructions include: peak shaving and valley filling, voltage-frequency support, auxiliary frequency regulation, power quality optimization and emergency backup power supply.

2. A battery energy storage power station physical interface consistency test system, characterized in that: The system comprises: Test module: used for the system framework of the battery energy storage power station, and executes the test strategy for the communication path and the circuit AC and DC bus respectively; Pass module: used for consistency testing if all strategies are passed; The test strategy includes, in sequence: communication path test, logic test, fault test, basic function test and operation test; The test module includes: a communication test unit, a logic test unit and a subsequent test unit; The communication test unit is used to perform communication tests on different communication media of the communication path; The logic test unit is used to perform a logic test on the AC and DC bus of the circuit after the communication test passes; The subsequent test unit is used to perform fault tests, basic function tests and operation tests on the components and control system of the battery energy storage power station in sequence based on the communication path and the circuit AC and DC bus after the logic test passes; Among them, when a test strategy fails, the subsequent strategies will be stopped and no longer executed; The communication test unit includes: an acquisition subunit, a sending subunit, a verification subunit and a test pass subunit; The acquisition subunit is used to acquire different communication media in the communication path and communication protocols corresponding to the different communication media; The sending subunit is used to send n groups of data to each station on the communication path through the information interface, and receive n groups of data fed back by each station; The verification subunit is used to perform data verification based on the n groups of feedback data and the communication protocol point table; The test pass subunit is used for if all n groups of data pass, the communication test passes; Otherwise, the communication test fails; The logic test unit comprises: Obtain battery packs, energy storage converters and battery energy storage power stations in single energy storage units; Connect the battery pack to the DC bus of the energy storage converter, the energy storage converter to the secondary AC bus of the transformer of the battery energy storage power station, and the battery energy storage power station to the grid-side AC bus through a circuit breaker; Based on the strong electric physical interface, the opening and closing signals are sent to the battery pack, energy storage converter and battery energy storage power station in sequence through the DC bus or AC bus; If the corresponding circuit breakers all operate correctly, the logic test passes; Otherwise, the logic test fails; The subsequent test unit includes: a fault test unit, a basic function test unit and an operation test unit; The fault testing unit comprises: Send fault data to the energy storage unit control system, the power station control system and the integrated dispatching control center system of the energy storage power station respectively based on the communication path that passes the communication test; Based on the fault data, an instruction to disconnect the circuit breaker is issued in real time and accurately, and the circuit breaker is shut down, and then the fault information is archived and reported; When the energy storage unit control system, power station control system and integrated dispatching control center all issue instructions accurately and process them, the fault test is passed; Otherwise the fault test fails; The basic function test unit comprises: Based on the upper and lower level relationship between the energy storage unit control system, power station control system and integrated dispatching control center system; Based on the communication paths and battery energy storage power stations that have passed the fault test and logic test, the superior issues operating instructions to the lower level; Based on the operating instructions, if the energy storage unit battery assembly, energy storage unit and energy storage power station functions are all operating correctly, the basic function test is passed; Otherwise, the basic functional test fails; Among them, the integrated dispatching control center system, the power station control system and the energy storage stand-alone control system are in a superior to subordinate relationship; The running test unit includes: The integrated dispatching control center system issues dispatching instructions to the power station control system; When the battery energy storage power station operates normally according to the dispatch instruction, the operation test passes; Otherwise, the operation test fails; Among them, the dispatching instructions include: peak shaving and valley filling, voltage-frequency support, auxiliary frequency regulation, power quality optimization and emergency backup power supply.