Assembled balcony prefabricated partition board structure and assembly method thereof

Through the prefabricated balcony partition panel structure, the connecting steel bars and embedded sleeve structures are used to achieve rapid assembly of balcony partition walls, solving the problems of long construction time and seasonal impact in traditional methods, improving construction efficiency and avoiding Steel corrosion.

CN110512773BActive Publication Date: 2024-12-06SHENZHEN CAPOL INT & ASSOC CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910934940.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-09-29
Publication Date
2024-12-06
Estimated Expiration
2039-09-29

AI Technical Summary

Technical Problem

In the prior art, the construction of balcony partition walls requires the use of bricks or blocks to build. The construction time is long and affected by seasonal temperature, making it difficult to use prefabricated parts.

Method used

The prefabricated balcony partition panel structure is adopted, and the connecting steel bars and embedded sleeve structures between the concrete prefabricated partition panels and the upper and lower balconies are connected by fixed connection with mortar to achieve rapid assembly of the balcony partition wall.

Benefits of technology

It effectively shortens the construction time, avoids the influence of seasonal temperature, improves construction efficiency, and solves the problems of exposed and corrosion of steel bars in traditional methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110512773B_ABST
    Figure CN110512773B_ABST
Patent Text Reader

Abstract

The present invention discloses an assembled balcony prefabricated partition wall panel structure and an assembly method thereof, wherein the assembled balcony prefabricated partition wall panel structure comprises: an upper balcony, a concrete prefabricated partition wall panel arranged below the upper balcony, and a lower balcony arranged below the concrete prefabricated partition wall panel; a first connecting steel bar is arranged at the top of the concrete prefabricated partition wall panel, and the first connecting steel bar is used for fixed connection with the upper balcony; a pre-embedded sleeve structure is arranged at the bottom of the concrete prefabricated partition wall panel, and a second connecting steel bar is installed in the pre-embedded sleeve structure, and the second connecting steel bar is used for fixed connection with the lower balcony. The present invention innovates the traditional balcony partition wall construction technology of manually building with bricks or blocks by using the prefabricated balcony prefabricated partition wall panel structure, and replaces it with assembled buildings, which can effectively shorten the construction time, and is less affected by seasonal temperature during construction, so it can greatly improve the construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of building technology, and in particular to an assembled balcony prefabricated partition board structure and an assembly method thereof. Background Art

[0002] In today's construction field, prefabricated construction technology is becoming more and more mature, and prefabricated parts are gradually occupying an increasingly higher proportion in high-rise buildings. Its advantages such as fast construction speed, high production efficiency, good product quality, and no seasonal influence are highly respected by the construction industry. Prefabricated technology has now become a construction technology that is mandatory for national and local governments.

[0003] However, there are still many limitations in prefabricated and assembled buildings today. For example, balcony partitions in multi-storey buildings. In the prior art, the construction of balcony partitions is mostly still in the technical state of using masonry or on-site cast-in-place. Since the structure of balcony partitions is more complicated than that of ordinary walls, there are many additional parts such as window frames, sliding doors, railings, and pre-buried water pipe boxes. The existence of these additional parts will lead to reduced wall strength of balcony partitions, difficulty in pre-reservation and pre-embedding, and complex construction procedures, which greatly increases the construction efficiency and difficulty on site. Therefore, it is difficult to use prefabricated assembly parts. However, the traditional method of using bricks or blocks for masonry is time-consuming, the on-site material stacking is chaotic, and it is greatly affected by seasonal temperatures. For example, in the north, concrete is frozen in winter and cannot be constructed normally. In addition, for projects currently constructed using aluminum molds, it is also impossible to build masonry on the exterior walls.

[0004] Therefore, the existing technology still needs to be improved and developed. Summary of the invention

[0005] The technical problem to be solved by the present invention is that, in view of the above-mentioned defects of the prior art, an assembled balcony prefabricated partition board structure and an assembly method thereof are provided, aiming to solve the shortcomings of the prior art that the construction of balcony partitions requires the use of bricks or blocks for masonry, the construction time is long, and it is affected by seasonal temperature.

[0006] The technical solution adopted by the present invention to solve the technical problem is as follows:

[0007] A prefabricated balcony partition board structure, wherein the prefabricated balcony partition board structure comprises: an upper balcony, a prefabricated concrete partition board arranged below the upper balcony, and a lower balcony arranged below the prefabricated concrete partition board; a first connecting steel bar is arranged at the top end of the prefabricated concrete partition board, and the first connecting steel bar is used for fixed connection with the upper balcony; an embedded sleeve structure is arranged at the bottom end of the prefabricated concrete partition board, and a second connecting steel bar is installed in the embedded sleeve structure, and the second connecting steel bar is used for fixed connection with the lower balcony.

[0008] In the assembled balcony prefabricated partition board structure, the first connecting steel bar is a limiting steel bar, and the limiting steel bar includes a steel bar, a steel rod, an anchor bolt or a rivet.

[0009] The assembled balcony prefabricated partition board structure, wherein the upper balcony is a prefabricated balcony, and the upper balcony is provided with a first cup-shaped hole for accommodating the first connecting steel bar, and the first cup-shaped hole is filled with mortar for fixing the first connecting steel bar.

[0010] The assembled balcony prefabricated partition board structure, wherein when the first connecting steel bar is an anchoring steel bar, the upper balcony is a cast-in-place balcony, and the anchoring steel bar is anchored into the upper balcony and is anchored and connected to the upper balcony.

[0011] The assembled balcony prefabricated partition board structure, wherein the embedded sleeve structure is a threaded sleeve, and a threaded structure is arranged inside the threaded sleeve.

[0012] The assembled balcony prefabricated partition board structure, wherein the first end of the second connecting steel bar is provided with a threaded section for spiral connection with the threaded sleeve.

[0013] The assembled balcony prefabricated partition board structure, wherein the second end of the second connecting steel bar is a limiting steel bar, and is arranged in a second cup-shaped hole reserved on the prefabricated lower balcony or the cast-in-place lower balcony, and the second cup-shaped hole is filled with mortar for fixing the second end of the second connecting steel bar in the cup-shaped hole of the lower balcony.

[0014] The assembled balcony prefabricated partition board structure, wherein the concrete prefabricated partition board is provided with a lightweight filling block for reducing weight and rigidity.

[0015] The assembled balcony prefabricated partition board structure, wherein the lightweight filling blocks are locally arranged or continuously arranged along the height direction of the concrete prefabricated partition board.

[0016] An assembly method of the assembled balcony prefabricated partition board structure as described above, wherein the assembly method comprises:

[0017] Screwing the second end of the second connecting steel bar having the threaded section into the pre-embedded sleeve structure at the bottom end of the prefabricated concrete partition board;

[0018] Filling mortar into the second cup-shaped hole reserved on the prefabricated lower balcony or the cast-in-place lower balcony, and receiving the prefabricated concrete partition board, so that the lower balcony is connected and fixed to the concrete prefabricated partition board;

[0019] The first connecting steel bar reserved at the top of the prefabricated concrete partition board is inserted into the first cup-shaped hole reserved on the prefabricated upper balcony and filled with mortar to fix it, or the first connecting steel bar is anchored into the cast-in-place upper balcony to complete the assembly of the prefabricated balcony prefabricated partition board structure.

[0020] Beneficial effects of the present invention: The present invention innovates the traditional balcony partition wall built by hand with bricks or blocks, and replaces it with an assembled structure, which can effectively shorten the construction time and is not affected by seasonal temperature during construction. At the same time, this embodiment connects and fixes the precast concrete partition board with the upper balcony and the lower balcony through connecting steel bars (including first connecting steel bars and second connecting steel bars), and because the bottom of the precast concrete partition board is provided with an embedded sleeve structure, the embedded sleeve structure is used to install the second connecting steel bar, so that the connection between the precast concrete partition board and the lower balcony is different from the traditional connection method, which is more conducive to the installation between the lower balcony and the precast concrete partition board, and the method of anchoring steel bars into reserved holes and pouring mortar can effectively solve the problem of steel corrosion caused by exposed steel bars or steel parts connection. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a structural diagram of an embodiment of the assembled balcony prefabricated partition board structure of the present invention.

[0022] Figure 2 It is an assembly step diagram of an embodiment of the assembled balcony prefabricated partition board structure of the present invention.

[0023] Figure 3 It is a structural diagram of a threaded sleeve of an assembled balcony prefabricated partition board structure of the present invention.

[0024] Figure 4 It is a structural diagram of the limiting steel bars of the assembled balcony prefabricated partition board structure of the present invention.

[0025] Figure 5 It is a structural diagram of the anchoring steel bars of the assembled balcony prefabricated partition board structure of the present invention.

[0026] Figure 6 It is a structural diagram of the grouting sleeve structure of the assembled balcony prefabricated partition board of the present invention.

[0027] Figure 7 The present invention is a flowchart of the assembly method of the assembled balcony prefabricated partition board structure. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solution and advantages of the present invention clearer and more specific, the present invention is further described in detail below with reference to the accompanying drawings and examples. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0029] It should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0030] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or suggesting their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0031] In the existing construction scheme for building balcony partitions, since the balcony partition structure is relatively complex and has many additional parts, most of them use the method of manual brick or block laying. This method has a long construction period and is greatly affected by the seasonal temperature environment. If an assembled balcony prefabricated partition board can be used, the construction period can be shortened, the shackles of seasonal temperature can be eliminated, and production efficiency can be improved.

[0032] Based on the above technical problems, the present invention provides a prefabricated balcony partition board structure, the various structural components of which are as follows: Figure 1 As shown, the prefabricated balcony prefabricated partition board structure includes: an upper balcony 300, a prefabricated concrete partition board 200 arranged below the upper balcony 300, and a lower balcony 100 arranged below the prefabricated concrete partition board 200; a first connecting steel bar 210 is arranged at the top of the prefabricated concrete partition board 200, and the first connecting steel bar 210 is used for fixed connection with the upper balcony 300, and an embedded sleeve structure 240 is arranged at the bottom end of the prefabricated concrete partition board 200, and a second connecting steel bar 220 is installed in the embedded sleeve structure 240, and the second connecting steel bar 220 is used for fixed connection with the lower balcony 100.

[0033] In this embodiment, the precast concrete partition board 200 is connected and fixed to the upper balcony 300 and the lower balcony 100 by connecting steel bars (including a first connecting steel bar 210 and a second connecting steel bar 220), and since a precast concrete partition board 200 is provided with an embedded sleeve structure 240 at the bottom, the embedded sleeve structure 240 is used to install the second connecting steel bar 220, so that the connection form between the precast concrete partition board 200 and the lower balcony 100 is different from the traditional connection method, which is more conducive to the installation between the lower balcony 100 and the precast concrete partition board 200.

[0034] During specific implementation, the first connecting steel bar 210 can be a limiting steel bar such as a steel bar, a steel rod, an anchor bolt, or a rivet. The limiting steel bars and anchoring steel bars are used in different assembly scenarios, respectively, to play the role of positioning and fixing the structure. Preferably, the precast concrete partition board 200 in this embodiment is a prefabricated part (i.e., prefabricated). Regardless of whether the first connecting steel bar 210 is a limiting steel bar or an anchoring steel bar, the first connecting steel bar 210 is pre-buried in the top of the precast concrete partition board 200, and a portion is exposed. The exposed portion is used to connect to the upper balcony 300. Specifically, when the first connecting steel bar 210 uses a limiting steel bar (such as Figure 4 As shown in the figure), the upper balcony 300 is a prefabricated balcony, and the upper balcony 300 is provided with a first cup-shaped hole 310 for accommodating the first connecting steel bar 210 (i.e., the limiting steel bar). The diameter of the upper opening of the first cup-shaped hole 310 is slightly larger than the lower opening, and the diameter of the lower opening is slightly larger than the cross-sectional diameter of the first connecting steel bar 210 (to facilitate the first connecting steel bar 210 to extend into the first cup-shaped hole 310 from the lower opening). During the specific installation, the exposed part of the first connecting steel bar 210 (i.e., the exposed part of the limiting steel bar) can be connected and fixed to the upper balcony 300 by pouring mortar 400 into the first cup-shaped hole 310, which is equivalent to adding a steel bar to the interior of the upper balcony 300. The first connecting steel bar 210 can play a role in positioning and fixing. The upper balcony 300 is fixedly connected to the concrete partition wall strip 200 through the first connecting steel bar 210. When the first connecting steel bar 210 is an anchoring steel bar (such as Figure 5As shown in the figure), the upper balcony 300 is a cast-in-place balcony, so the exposed portion of the first connecting steel bar 210 is directly anchored into the upper balcony 300. Specifically, during installation, when the upper balcony 300 is cast in situ, the exposed portion of the first connecting steel bar 210 is cast into the interior of the upper balcony 300 on site, which is equivalent to casting the upper balcony 300 and the precast concrete partition board into one body, thereby achieving a fixed connection between the upper balcony 300 and the concrete partition board 200. Preferably, since the exposed portion of the anchoring steel bar is used for anchoring connection with the upper balcony 300 during cast-in-situ production, in order to further strengthen the anchoring connection, the exposed portion of the anchoring steel bar in this embodiment is configured to be curved (such as Figure 5 As shown in the figure, compared with the limit steel bar, the curved anchor steel bar has a stronger connection effect and can withstand higher amplitude shaking and pressure, so the building strength is more reliable. Figure 1 As shown in , the first cup-shaped hole 310 in this embodiment is divided into two parts, namely an upper part and a lower part. The lower part of the first cup-shaped hole 310 is used to connect the exposed part of the first connecting steel bar 210, and the upper part of the first cup-shaped hole 310 is used when installing the upper layer of concrete partition wall strips. Similarly, the second cup-shaped hole 110 can also be divided into two parts.

[0035] Preferably, in the prefabricated balcony partition wall structure, the bottom end of the concrete partition wall strip 200 is provided with an embedded sleeve structure 240, and the connection and fixation between the concrete partition wall strip 200 and the lower balcony 100 are achieved through the second connecting steel bar 220 and the embedded sleeve structure 240. The embedded sleeve structure 240 is set as a threaded sleeve (such as Figure 3 As shown), the interior of the threaded sleeve is provided with a threaded structure, and when the threaded sleeve is used, the first end of the first connecting steel bar is provided with a threaded section, and the threaded section is connected to the threaded structure in the threaded sleeve. Furthermore, the threaded sleeve is embedded in the precast concrete partition board 200, and its lower end is flush with the bottom surface of the precast concrete partition board 200. The upper end is also provided with a horizontal cross brace 241. Since the threaded sleeve is embedded in the precast concrete partition board 200, its function is similar to that of an anchoring steel bar. The threaded sleeve is more securely fixed in the precast concrete partition board 200 by means of the horizontal cross brace 241. When the threaded structure provided inside the threaded sleeve is connected to the first end of the second connecting steel bar 220 (i.e. Figure 1 When the threaded sections arranged at the upper end of the second connecting steel bar 220 in the concrete are matched with each other, the threaded sections that match each other are tightly combined, so that the second connecting steel bar 220 is fixed to the bottom end of the precast concrete partition board 200 and will not be separated from each other due to shaking or vibration.

[0036] Preferably, the embedded sleeve structure 240 can also use a grouting sleeve, such as Figure 6 As shown, the grouting sleeve consists of a connecting cavity 252, a lower port 251, and grouting sleeves 253 and 254. The grouting sleeve is prefabricated inside the prefabricated concrete partition board 200, and its lower port 251 is on the same horizontal line as the bottom surface of the prefabricated concrete wall board 200. When the first end of the second connecting steel bar 220 is sleeved in the connecting cavity 252, mortar can be poured into the connecting cavity 252 through the grouting sleeves 253 and 254, so that the second connecting steel bar 220 is fixed in the grouting sleeve.

[0037] Furthermore, the second end of the second connecting steel bar 220 (i.e. Figure 1 The lower end of the second connecting steel bar 220 is set to be a limiter, such as a steel bar, a steel bar, an anchor bolt or a rivet (i.e., no thread is set), and the second end of the second connecting steel bar 220 is used to connect with the lower balcony 100. During assembly, whether the lower balcony 300 is a prefabricated balcony or a cast-in-place balcony, the second end of the second connecting steel bar 220 is placed in the second cup-shaped hole 110 reserved on the prefabricated lower balcony 110 or the cast-in-place lower balcony 100, and then the mortar 400 is filled into the second cup-shaped hole 110 to fix the second end of the second connecting steel bar 220 in the second cup-shaped hole 110. Since the first end of the second connecting steel bar 220 is fixed to the bottom end of the concrete prefabricated partition board 200, and the second end of the second connecting steel bar 220 is fixed in the lower balcony 100, the concrete prefabricated partition board 200 and the lower balcony 100 are fixedly connected through the second connecting steel bar 220.

[0038] Preferably, in order to make the upper balcony 300 and the concrete prefabricated partition wall board 200 more accurate during assembly and avoid the phenomenon of offset, in this embodiment, a protrusion can be provided at the middle position of the top of the concrete prefabricated partition wall board 200, and a groove corresponding to the protrusion can be provided at the middle position of the bottom of the upper balcony 300. If the upper balcony 300 is a prefabricated balcony, a groove matching the protrusion can be provided at the middle position of the bottom of the upper balcony 300 when the upper balcony 300 is prefabricated. When the upper balcony 300 is a cast-in-place balcony, it is only necessary to cast a groove matching the protrusion when casting the upper balcony 300. When the protrusion cooperates with the groove, it plays a positioning role, so that the installation of the upper balcony 300 and the concrete prefabricated partition wall board 200 is more accurate and stable. Of course, in this embodiment, mortar 400 can also be applied on the contact surface where the groove and the protrusion cooperate to enhance the combined strength of the upper balcony 300 and the precast concrete partition wall board 200. In this embodiment, the top of the lower balcony 100 and the bottom of the precast concrete partition wall board 200 can also be installed and positioned in the same manner, so that the installation of the lower balcony 100 and the precast concrete partition wall board 200 is more accurate and stable.

[0039] In the solution of the present invention, the lower balcony 100 and the upper balcony 300 are actually of the same structure. When using different embodiments of prefabrication or cast-in-place, the lower balcony and the upper balcony 300 use the same assembly method, i.e. prefabrication and hoisting or cast-in-place.

[0040] Preferably, the precast concrete partition board 200 is provided with a lightweight filling block 230 for reducing weight and stiffness; in addition to being lightweight and usable for weight reduction, the lightweight filling block 230 also has a certain thermal insulation effect, which can reduce the overall stiffness of the precast concrete partition board 200 and prevent the precast concrete partition board 200 from affecting structural safety during structural stress. Since the lightweight filling block 230 has a certain thermal insulation effect, when the precast concrete partition board 200 has different internal and external temperatures, the lightweight filling block 230 can control the deformation of the concrete walls on both sides of the insulation board, so that the wall panel will not have cracks and other safety hazards due to excessive deformation.

[0041] Preferably, the lightweight filling blocks 230 are locally arranged or continuously arranged along the height direction of the prefabricated concrete partition board 200; Figure 1The light filling blocks 230 shown are arranged locally, that is, the interior of the concrete precast partition wall panel 200 is filled with a plurality of light filling blocks 230, and the light filling blocks 230 are arranged at intervals from each other, so that the light filling blocks 230 can maximize the overall strength of the concrete precast partition wall panel 200 while exerting their own performance (weight reduction, rigidity reduction and heat preservation), so as to improve the service life of the concrete precast partition wall panel 200. When the light filling blocks 230 are arranged uninterruptedly along the height direction of the concrete precast partition wall panel 200, the structural integration of the concrete precast partition wall panel 200 can be ensured, and the safety of the wall can be ensured.

[0042] Furthermore, if Figure 1 As shown, the assembled balcony prefabricated partition board structure of the present invention is also provided with a waterproof structure, which includes an upper waterproof structure 320 and a lower waterproof structure 250. Specifically, the lower waterproof structure 250 is arranged at the connection between the top of the concrete prefabricated partition board 200 and the upper balcony 300, and the upper waterproof structure 320 is arranged at the bottom of the upper balcony 300; the upper waterproof structure 320 is shaped as a protrusion with a slope, and the protrusion with the slope is located on the outer side of the wall of the upper balcony 300, and the lower waterproof structure 250 is shaped as a groove with a slope, and the upper waterproof structure 320 and the lower waterproof structure 250 are matched in shape and fit tightly during installation; when it rains outside the wall, due to the internal slope structure of the waterproof structure, even if rainwater penetrates into the contact gap, it is impossible to continue to penetrate into the wall against the slope; during assembly, waterproof mortar 400 or other adhesives with waterproof properties can also be added to the connection contact surface between the upper balcony 300 and the concrete prefabricated partition board 200 to enhance the waterproof and fixing effects.

[0043] Furthermore, the present invention also provides an assembly method of the assembled balcony prefabricated partition board structure as described above, Figure 7 The present invention is a schematic diagram of a preferred construction method for assembling a prefabricated balcony partition board structure. The assembly method comprises the following steps:

[0044] S100, screwing the second end of the second connecting steel bar having the threaded section into the embedded sleeve structure at the bottom end of the prefabricated concrete partition board;

[0045] S200, filling mortar into a second cup-shaped hole reserved on the prefabricated lower balcony or the cast-in-place lower balcony, and receiving the prefabricated concrete precast partition board, so that the lower balcony is connected and fixed to the concrete precast partition board;

[0046] S300, insert the first connecting steel bar reserved at the top of the prefabricated concrete partition board into the first cup-shaped hole reserved on the prefabricated upper balcony, and fill it with mortar to fix it, or anchor the first connecting steel bar into the cast-in-place upper balcony to complete the assembly of the prefabricated balcony prefabricated partition board structure.

[0047] like Figure 2 As shown, the method adopts a prefabricated assembled balcony prefabricated partition board structure. In this embodiment, the upper balcony 300, the lower balcony 100 and the concrete partition board 200 are all prefabricated.

[0048] In step S100, Figure 2 -A, first install the prefabricated lower balcony 100 to the designated position and fix it, then screw the prefabricated concrete prefabricated partition board 200 with the second connecting steel bar 220 through the embedded sleeve structure 240 under the wallboard according to the arrow direction shown in the figure, that is, the embedded sleeve structure 240 is a threaded sleeve. Specifically, the threaded sleeve has a thread inside that matches the threaded section of the first end of the second steel bar 220. When the threaded sleeve 240 is screwed with the first end of the second connecting steel bar 220, the matching threads fit tightly, so that the second connecting steel bar 220 is tightly connected to the threaded sleeve, and will not be separated from each other due to shaking or vibration. Preferably, a horizontal cross brace 241 is also provided on the upper part of the threaded sleeve 240, and the function of the horizontal cross brace 241 is equivalent to anchoring steel bars. During the prefabrication process of the prefabricated concrete partition board 200, the threaded sleeve 240 is strengthened in bonding strength with the prefabricated concrete partition board 200 due to the function of the horizontal cross brace 241.

[0049] In step S200, the step 200 is to realize the fixed connection between the lower balcony 100 and the concrete 200 by the second connecting steel bar 220. In this embodiment, the lower balcony 100 can be a prefabricated balcony or a cast-in-place balcony. No matter it is a prefabricated balcony or a cast-in-place balcony, the lower balcony 100 is preset with a second cup-shaped hole 110. Specifically, Figure 2-B, in this embodiment, the concrete prefabricated partition wall panel 200 that has been screwed with the second connecting steel bar 220 of the threaded sleeve can be hoisted on the lower balcony 100. Before hoisting the concrete prefabricated partition wall panel 200, the second cup-shaped hole 110 preset in the lower balcony 100 is first filled with mortar 400; preferably, the mortar 400 is piled on the plane where the cup mouth of the second cup-shaped hole 110 is located, and the thickness of the piled mortar 400 is about 2CM. Finally, the concrete prefabricated partition wall panel 200 is hoisted, and the second connecting steel bar 220 at the lower part thereof is The second end of 20 is slowly inserted downward along the second cup-shaped hole 110, and then the precast concrete partition board 200 is adjusted so that its outer vertical surface is in the same plane as the outer vertical surface of the lower balcony 100. Due to the dead weight of the precast concrete partition board 200, its bottom plane squeezes the above-mentioned piled mortar 400, causing the mortar 400 to overflow. The overflowed mortar can be evenly applied to the joints between the precast concrete partition board 200 and the lower balcony 100, thereby enhancing the waterproof effect of the wall joints and making the wall surface more beautiful. Of course, in this embodiment, the precast concrete partition board 200 on which the second connecting steel bar 220 has been screwed with the threaded sleeve can be hoisted on the lower balcony 100, and then the second end of the second connecting steel bar 220 is inserted into the second cup-shaped hole 110 of the lower balcony 100 (at this time, the second end of the second connecting steel bar 220 is not completely inserted into the second cup-shaped hole 110, so that there is enough space for grouting in the second cup-shaped hole 110), and then the second cup-shaped hole 110 is filled with mortar 400, thereby achieving the connection and fixation of the precast concrete partition board 200 and the lower balcony 100.

[0050] In step S300, Figure 2 -C, hoist the upper balcony 300 on the above-mentioned installed precast concrete partition board 200. Preferably, referring to the assembly method of the above-mentioned precast concrete partition board 200 and the lower balcony 100, when hoisting the upper balcony 300, in this embodiment, the exposed portion of the first connecting steel bar 210 is inserted into the first cup-shaped hole 310 of the upper balcony 300 (at this time, the exposed portion of the first connecting steel bar 210 is not completely inserted into the first cup-shaped hole 310, so that there is enough space for grouting in the first cup-shaped hole 310), and then fill the first cup-shaped hole 310110 with mortar 400. Due to the dead weight of the upper balcony 300, the upper balcony 300 fits tightly with the concrete partition wall strips 200, and may also cause the mortar 400 to overflow. Therefore, in this embodiment, the overflowed mortar 400 can be evenly applied to the joints between the upper balcony 300 and the prefabricated concrete partition wall panels 200, which not only enhances the waterproof effect of the wall joints, but also makes the wall surface more beautiful.

[0051] Furthermore, the prefabricated balconies in this embodiment are stacked, that is, after the assembly of this layer is completed, it can continue to be stacked upward in sequence according to the same steps. When the prefabricated partition board structure of the prefabricated balcony is installed on the upper layer, the upper balcony 300 in this embodiment becomes the lower balcony 100 of the superstructure, and its reserved first cup-shaped hole 310 becomes the second cup-shaped hole 110, that is, the upper balcony 300 and the lower balcony 100 have the same essential structure, and only the relative name changes during the floor change; this illustrates that the prefabricated partition board structure of the prefabricated balcony can be continuously assembled upward according to this instruction manual.

[0052] In summary, the present invention provides an assembled balcony prefabricated partition board structure and an assembly method thereof, wherein the assembled balcony prefabricated partition board structure includes an upper balcony, a concrete prefabricated wall panel, a lower balcony and a first connecting steel bar, a second connecting steel bar, a first cup-shaped hole, a second cup-shaped hole 3, an embedded sleeve structure, etc.; the assembled balcony prefabricated partition board structure assembled by this method innovates the traditional method of manually stacking bricks or blocks, can greatly reduce the construction period, save labor costs, and is not affected by the environmental season and temperature, effectively improving the construction efficiency.

[0053] It should be understood that the application of the present invention is not limited to the above examples. For ordinary technicians in this field, improvements or changes can be made based on the above description. All these improvements and changes should fall within the scope of protection of the claims attached to the present invention.

Claims

1. An assembled balcony prefabricated partition board structure, characterized in that: The assembled balcony prefabricated partition wall structure comprises: an upper balcony, a concrete prefabricated partition wall panel arranged below the upper balcony, and a lower balcony arranged below the concrete prefabricated partition wall panel; a first connecting steel bar is arranged at the top of the concrete prefabricated partition wall panel, and the exposed portion of the first connecting steel bar is used for fixed connection with the upper balcony; an embedded sleeve structure is arranged at the bottom of the concrete prefabricated partition wall panel, and a second connecting steel bar is installed in the embedded sleeve structure, and the exposed portion of the second connecting steel bar is used for fixed connection with the lower balcony; The prefabricated balcony partition board structure described above, wherein the embedded sleeve structure is a threaded sleeve or a grouting sleeve, and a threaded structure is provided inside the threaded sleeve; In the prefabricated balcony partition board structure, the second end of the second connecting steel bar is a limiting steel bar and is arranged in a second cup-shaped hole reserved on the prefabricated lower balcony or the cast-in-place lower balcony, and the second cup-shaped hole is filled with mortar for fixing the second end of the second connecting steel bar in the second cup-shaped hole of the lower balcony; A horizontal cross brace is also provided on the upper part of the threaded sleeve; The first connecting steel bar is a limiting steel bar, and the limiting steel bar includes a steel bar, a steel rod, an anchor bolt or a rivet; When the first connecting steel bar is a limiting steel bar, the upper balcony is a prefabricated balcony, and the upper balcony is provided with a first cup-shaped hole for accommodating the limiting steel bar, and the first cup-shaped hole is filled with mortar for fixing the limiting steel bar; When the first connecting steel bar is an anchoring steel bar, the upper balcony is a cast-in-place balcony, and the anchoring steel bar is anchored into the upper balcony and is anchored and connected to the upper balcony; The first cup-shaped hole and the second cup-shaped hole are both divided into an upper part and a lower part, the upper part of the first cup-shaped hole is used to connect with the exposed part of the first connecting steel bar, and the upper part of the second cup-shaped hole is used to connect with the exposed part of the second connecting steel bar; The grouting sleeve is composed of a connection cavity, a lower port, and a pouring sleeve. The grouting sleeve is prefabricated inside the prefabricated concrete partition board. The lower port and the bottom surface of the prefabricated concrete wall board are in the same horizontal line. After the first end of the second connecting steel bar is sleeved in the connection cavity, mortar is poured into the connection cavity through the pouring sleeve to fix the second connecting steel bar in the grouting sleeve. A protrusion is arranged at the middle position of the top of the precast concrete partition board, and a groove corresponding to the protrusion is arranged at the middle position of the bottom of the upper balcony. If the upper balcony is a precast balcony, a groove matching the protrusion is arranged at the middle position of the bottom of the upper balcony when the upper balcony is precast; and when the upper balcony is a cast-in-place balcony, it is only necessary to cast a groove matching the protrusion when casting the upper balcony. Apply mortar on the contact surface between the groove and the protrusion; The prefabricated balcony partition board structure is also provided with a waterproof structure, which includes an upper waterproof structure and a lower waterproof structure, wherein the lower waterproof structure is provided at the connection between the top of the concrete prefabricated partition board and the upper balcony, and the upper waterproof structure is provided at the bottom of the upper balcony; the upper waterproof structure is provided in a shape of a protrusion with a slope, the protrusion with a slope is located on the outer side of the wall of the upper balcony, the lower waterproof structure is provided in a shape of a groove with a slope, and the upper waterproof structure and the lower waterproof structure are matched in shape and fit tightly during installation; The connection contact surface between the upper balcony and the prefabricated concrete partition board is coated with waterproof mortar.

2. The assembled balcony prefabricated partition board structure according to claim 1 is characterized in that: The first end of the second connecting steel bar is provided with a threaded section for spiral connection with the threaded sleeve.

3. The assembled balcony prefabricated partition board structure according to claim 1 is characterized in that: Lightweight filling blocks for reducing weight and rigidity are arranged in the concrete prefabricated partition wall panels.

4. The assembled balcony prefabricated partition board structure according to claim 3 is characterized in that: The lightweight filling blocks are arranged locally or continuously along the height direction of the prefabricated concrete partition board.

5. An assembly method of the assembled balcony prefabricated partition board structure according to any one of claims 1 to 4, characterized in that: The assembly method comprises: Screwing the second end of the second connecting steel bar having the threaded section into the pre-embedded sleeve structure at the bottom end of the prefabricated concrete partition board; Filling mortar into the second cup-shaped hole reserved on the prefabricated lower balcony or the cast-in-place lower balcony, and receiving the prefabricated concrete partition board, so that the lower balcony is connected and fixed to the concrete prefabricated partition board; The first connecting steel bar reserved at the top of the prefabricated concrete partition board is inserted into the first cup-shaped hole reserved on the prefabricated upper balcony and filled with mortar to fix it, or the first connecting steel bar is anchored into the cast-in-place upper balcony to complete the assembly of the prefabricated balcony prefabricated partition board structure.