Construction joint waterproof structure suitable for reconstruction of tunnel lining and construction method thereof
By designing the construction joints in a staggered stage and setting up multiple water stop glue and waterproof coils, the problems of small contact area and low waterproofing capacity after tunnel lining reconstruction are solved, and multi-level waterproofing and construction efficiency are improved.
Patent Information
- Application Number
- CN202010237320.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-30
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2040-03-30
AI Technical Summary
After the reconstruction of existing tunnel lining, the construction joint contact area is small, the waterproofing capacity is low, and the drilling and reinforcement process is complicated and the craftsmanship efficiency is low.
Design a malfunctional construction joint structure, set up at least three water stop glue, and lay waterproof coils between the existing lining and initial support to reduce drilling reinforcement, improve contact area and waterproofing capacity.
The bonding capacity of new and old concrete has been enhanced, multi-level waterproofing has been achieved, waterproofing has been improved, construction processes have been simplified, and construction efficiency has been improved.
Smart Images

Figure CN111271097B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel engineering, in particular to a construction joint waterproof structure suitable for reconstructing tunnel lining and a construction method thereof. Background Art
[0002] Some tunnels in my country have quality defects and diseases such as voids behind the existing lining, insufficient thickness of the existing lining, water leakage at construction joints and cracks in the existing lining, which affect the safety of railway operations. In serious cases, the existing tunnel lining structure needs to be dismantled and reconstructed. After reconstruction, the contact surface between the existing tunnel lining and the reconstructed tunnel lining will inevitably produce new and old concrete construction joints, which are the weak links in the overall stress bearing and self-waterproofing of the structure.
[0003] At present, the conventional construction joint after the reconstruction of the tunnel lining is a plane structure. Due to the limitation of the contact area of the construction joint, its waterproofing is only provided by setting a waterstop in the middle of the construction joint. In addition, in the reinforced concrete lining section, in order to meet the specification requirement that the overlap of the steel bar joints in the same cross-sectional area should not exceed 50%, it is necessary to drill holes and plant reinforcement at the existing lining construction joint. The construction process is complicated and the work efficiency is low. After the existing construction joint structure is dismantled, the original two waterproofing measures of the embedded waterstop and the waterstop strip cannot be restored, and the waterproofing ability is reduced. Summary of the invention
[0004] The purpose of the present invention is to provide a construction joint waterproof structure suitable for reconstructing tunnel lining and a construction method thereof in view of the problems in the prior art such as small contact area of construction joint after reconstruction of tunnel lining, no space for setting multi-level waterproofing, reduced waterproofing ability, small bonding surface of new and old concrete, need to strengthen the overall stress of the structure at the construction joint, complicated construction process of drilling and planting reinforcement, and low construction efficiency.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] A construction joint waterproof structure suitable for reconstructing tunnel linings includes an existing lining, a reconstructed lining and an initial support, wherein a staggered construction joint is formed between the existing lining and the reconstructed lining, at least three water stop adhesives are provided on the staggered construction joint, and a waterproofing roll is laid between the existing lining and the initial support. Since the construction joint is designed as a staggered structure, the lap joint of the lining structure steel bars at the construction joint meets the specification requirement that the same cross-sectional area is not greater than 50%, and there is no need to drill holes and plant steel bars at the construction joint, which reduces the construction process and improves the construction efficiency.
[0007] The present invention provides a waterproof structural system for the contact surface of the existing lining and the reconstructed lining construction joint that combines prevention, interception and drainage, provides a multiple waterproof structure, and a staggered construction joint contact surface, which increases the contact surface area, enhances the bonding ability of new and old concrete, realizes multi-level waterproofing, improves the waterproofing ability, and realizes the staggered arrangement of steel bar joints. The present invention has the advantages of strong operability, safety and reliability, and significant economic and social benefits for the reconstruction of tunnel lining sections.
[0008] As a preferred embodiment of the present invention, the staggered construction joint includes a plurality of construction joint contact surfaces, and at least one layer of the water-stopping glue is provided on each of the construction joint contact surfaces to improve the waterproof capability.
[0009] As a preferred embodiment of the present invention, the contact surface of the construction joint is coated with a penetrating epoxy resin waterproof coating.
[0010] As a preferred embodiment of the present invention, the width of the water-stopping adhesive is greater than or equal to 2 cm.
[0011] As a preferred embodiment of the present invention, the overlapping length of the existing lining and the waterproof membrane of the initial support is greater than 15 cm.
[0012] As a preferred embodiment of the present invention, the initial support is pre-buried with an annular blind pipe, and a drainage groove is reserved at the bottom of the reconstructed lining, the annular blind pipe is connected to the drainage groove, and the drainage groove is connected to the tunnel side ditch, so that the tunnel groundwater can be smoothly introduced into the side ditch.
[0013] As a preferred embodiment of the present invention, the drainage trough includes a notch, a half-cut PE pipe is pre-buried in the notch, a steel bar fixing ring is fixed on the outer surface of the half-cut PE pipe, and a skeleton steel bar is provided between the half-cut PE pipe and the steel bar fixing ring, and the notch is filled with a micro-expanding cement sealer.
[0014] The present invention also discloses a construction method for a construction joint waterproof structure suitable for reconstructing a tunnel lining. The construction method for the construction joint waterproof structure suitable for reconstructing a tunnel lining comprises the following steps:
[0015] Step 1: Partially dismantle the existing lining and form a staggered construction joint;
[0016] Step 2: laying a waterproofing membrane on the existing lining surface and overlapping it with the waterproofing membrane of the initial support, wherein the overlap width is greater than 15 cm;
[0017] Step three: at least one layer of water-stop glue is provided on each contact surface of the staggered construction joints, the width of the water-stop glue is greater than or equal to 2 cm, and the reconstructed lining is constructed.
[0018] The construction method of the present invention designs the tunnel lining construction joint into a staggered structure, which eliminates the need to drill holes and plant reinforcement bars at the construction joint, reduces construction procedures, improves construction efficiency, and realizes multi-level waterproofing, thereby improving waterproofing capability.
[0019] As a preferred embodiment of the present invention, the step three further comprises: cleaning the concrete within a range of 20 cm on both sides of the staggered construction joint, and applying a penetrating epoxy resin waterproof coating.
[0020] As a preferred embodiment of the present invention, the step 2 further includes: after the demolition is completed, pre-embed annular blind pipes in the initial support to the vicinity of the arch foot, and the step 3 further includes: constructing drainage grooves in the reconstructed lining.
[0021] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0022] (1) The present invention provides a waterproof structural system for the contact surface of the existing lining and the reconstructed lining construction joint that combines prevention, interception and drainage, provides a multiple waterproof structure, and a staggered construction joint contact surface, which increases the contact surface area, enhances the bonding ability of new and old concrete, realizes multi-level waterproofing, improves the waterproofing ability, and realizes the staggered arrangement of steel bar joints. The present invention has the advantages of strong operability, safety and reliability, and significant economic and social benefits for the reconstruction of tunnel lining sections.
[0023] (2) The construction method described in the present invention designs the tunnel lining construction joint into a staggered structure, which eliminates the need to drill holes and plant reinforcement at the construction joint, thereby reducing the construction process and improving construction efficiency. It also achieves multi-level waterproofing and improves waterproofing capability. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a structural schematic diagram of a construction joint waterproof structure suitable for reconstructing a tunnel lining according to the present invention.
[0025] Figure 2 yes Figure 1 AA cross-section diagram in.
[0026] Figure 3 yes Figure 1 BB cross section in.
[0027] Figure 4 It is a structural schematic diagram of the drainage trough described in the present invention.
[0028] Icons: 1-existing lining, 2-reconstructed lining, 3-initial support, 4-annular blind pipe, 5-drainage trough, 51-half-cut PE pipe, 52-skeleton steel bar, 53-steel fixing ring, 54-notch, 55-micro-expansive cement sealer, 6-offset construction joint, 61-construction joint contact surface, 7-waterstop glue, 8-waterproof membrane. DETAILED DESCRIPTION
[0029] The present invention will be described in detail below in conjunction with the accompanying drawings.
[0030] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0031] Example 1
[0032] like Figure 1-Figure 3 As shown, a construction joint waterproof structure suitable for reconstructing tunnel lining includes an existing lining 1, a reconstructed lining 2 and an initial support 3. A staggered construction joint 6 is formed between the existing lining 1 and the reconstructed lining 2. The staggered construction joint 6 includes three construction joint contact surfaces 61. A waterproof glue 7 is provided on each of the construction joint contact surfaces 61. The width of the waterproof glue 7 is 2 cm. A penetrating epoxy resin waterproof coating is applied to each of the construction joint contact surfaces 61. Before applying, a wire brush should be used to clean the surface of the secondary lining concrete to ensure that the concrete surface is clean. The amount used is not less than 0.5 kg / m 2 , apply the paint no less than 2 times.
[0033] The surface of the existing lining 1 is paved with a waterproof coiled material 8, and the waterproof coiled material 8 of the existing lining 1 is welded to the waterproof coiled material of the initial support 3, and the overlap length is greater than 15 cm.
[0034] In addition, after the existing lining 1 is removed, an annular blind pipe 4 is embedded in the initial support 3, and a drainage groove 5 is reserved at the bottom of the reconstructed lining 2. The annular blind pipe 4 is connected to the drainage groove 5, and the drainage groove 5 is connected to the tunnel side ditch to drain groundwater smoothly.
[0035] Specifically, the annular blind pipe 4 is a perforated corrugated pipe wrapped with non-woven fabric, which is led to the vicinity of the arch foot and connected to the drainage trough 5. Figure 4As shown, the drainage trough 5 includes a notch 54, in which a half-cut PE pipe 51 is pre-buried, a steel bar fixing ring 53 is fixed to the outer surface of the half-cut PE pipe 51, and three full-length skeleton steel bars 52 are arranged between the half-cut PE pipe 51 and the steel bar fixing ring 53, and steel bar burrs are staggered and welded to enhance the adhesion between it and the subsequent shotcrete, and the notch 54 is filled with a micro-expansive cement sealer 55 for sealing.
[0036] Example 2
[0037] A construction method for a construction joint waterproof structure suitable for reconstructing a tunnel lining, wherein the construction joint waterproof structure suitable for reconstructing a tunnel lining as described in Example 1 comprises the following steps:
[0038] Step 1: Partially dismantle the existing lining 1, first cut the edge in place using a cutting process, then chisel off the lining concrete to reduce disturbance and damage to the lining outside the replacement range; when chiseling off the construction joint, attention should be paid to the form of the construction joint contact surface 61 to form a staggered construction joint 6;
[0039] Step 2: After the removal is completed, pre-embed the annular blind pipe 4 in the initial support 3 to the vicinity of the arch foot;
[0040] Step 3: Before reconstructing the tunnel lining, a waterproofing membrane 8 is laid on the surface of the existing lining 1 and is well welded with the waterproofing membrane 8 of the initial support 3. The overlap width is greater than 15 cm. The laying process of the waterproofing membrane 8 should meet the requirements of relevant specifications to prevent the waterproofing membrane 8 from cutting the secondary lining;
[0041] Step 4: a layer of water-stop glue 7 is provided on each construction joint contact surface 61 of the staggered construction joint 6, and the width of the water-stop glue 7 is greater than or equal to 2 cm;
[0042] Step 5: Clean the concrete within 20 cm on both sides of the staggered construction joint 6 and apply a penetrating epoxy resin waterproof coating;
[0043] Step 6: construct the reconstructed lining 2, and cut grooves on its inner edge to form drainage grooves 5 as drainage channels to drain groundwater into the side ditches.
[0044] like Figure 4 As shown, the notch 54 is made by a cutting saw. If a structural steel bar is encountered during the notching process, it can be cut off. The end of the notch should be 2 to 4 mm smaller than the diameter of the half-cut PE pipe 51, so as to fit closely with the half-cut PE pipe 51. After the notching is completed, the groove body is washed with high-pressure water (or high-pressure wind) to remove slag, dust and loose concrete blocks.
[0045] The open end of the half-cut PE pipe 51 is embedded inward into the bottom of the groove, and is fixed with a steel bar fixing ring 53 at a circumferential spacing of 15 cm, with an anchoring depth of 5 cm; after the half-cut PE pipe 51 is fixed, three full-length skeleton steel bars 52 are inserted between the half-cut PE pipe 51 and the steel bar fixing ring 53, and the steel bar burrs are staggered and welded to enhance the adhesion between it and the subsequent shotcrete.
[0046] After the skeleton reinforcement 52 is installed and checked, it is sealed with a micro-expansion cement seal 55, and after reaching the strength, the surface is polished and smoothed. So far, the drainage trough 5 is completed as a drainage channel to drain groundwater into the side ditch.
[0047] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A construction joint waterproof structure suitable for reconstructing tunnel lining, characterized in that: It comprises an existing lining (1), a reconstructed lining (2) and an initial support (3), wherein a staggered construction joint (6) is formed between the existing lining (1) and the reconstructed lining (2), at least three layers of water stop glue (7) are provided on the staggered construction joint (6), and a waterproofing membrane (8) is laid between the existing lining (1) and the initial support (3); The initial support (3) is pre-buried with an annular blind pipe (4), and a drainage groove (5) is reserved at the bottom of the reconstructed lining (2), the annular blind pipe (4) is connected to the drainage groove (5), and the drainage groove (5) is connected to the tunnel side ditch; The drainage trough (5) comprises a notch (54), a half-cut PE pipe (51) is pre-buried in the notch (54), a steel bar fixing ring (53) is fixed on the outer surface of the half-cut PE pipe (51), and a skeleton steel bar (52) is provided between the half-cut PE pipe (51) and the steel bar fixing ring (53), and the notch (54) is filled with a micro-expansion cement sealing body (55); The staggered construction joint (6) comprises a plurality of construction joint contact surfaces (61), and at least one layer of the water-stopping glue (7) is provided on each of the construction joint contact surfaces (61); The overlapping length of the waterproof coiled material (8) of the existing lining (1) and the initial support (3) is greater than 15 cm.
2. The construction joint waterproof structure suitable for reconstructing tunnel lining according to claim 1 is characterized in that: The construction joint contact surface (61) is coated with a penetrating epoxy resin waterproof coating.
3. The construction joint waterproof structure suitable for reconstructing tunnel lining according to claim 1 is characterized in that: The width of the water-stop glue (7) is greater than or equal to 2 cm.
4. A construction method for a construction joint waterproof structure suitable for reconstructing a tunnel lining, characterized in that: The construction of a waterproof construction joint structure suitable for reconstructing a tunnel lining as described in any one of claims 1 to 3 comprises the following steps: Step 1: partially dismantle the existing lining (1) and form a staggered construction joint (6); Step 2: laying a waterproofing coiled material (8) on the surface of the existing lining (1) and overlapping it with the waterproofing coiled material (8) of the initial support (3), wherein the width of the overlap is greater than 15 cm; Step three: at least one layer of water-stop glue (7) is provided on each construction joint contact surface (61) of the staggered construction joint (6), wherein the width of the water-stop glue (7) is greater than or equal to 2 cm, and the reconstructed lining (2) is constructed.
5. A construction method for a construction joint waterproof structure suitable for reconstructing a tunnel lining according to claim 4, characterized in that: The step three also includes: cleaning the concrete within a range of 20 cm on both sides of the offset construction joint (6), and applying a penetrating epoxy resin waterproof coating.
6. A construction method for a construction joint waterproof structure suitable for reconstructing a tunnel lining according to claim 4, characterized in that: The step 2 also includes: after the removal is completed, pre-embedding an annular blind pipe (4) in the initial support (3) to the vicinity of the arch foot, and the step 3 also includes: constructing a drainage ditch (5) located in the reconstructed lining (2).