Prefabricated assembled cap beam structure connected by shear keys and construction method

By adopting shear bond connections and prefabricated holes in the prefabricated cover beam structure, the problems of high-altitude operation complexity and construction risks in the prior art are solved, and higher structural stability and construction efficiency are achieved.

CN111893870BActive Publication Date: 2024-11-15FUZHOU UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010891881.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-08-31
Publication Date
2024-11-15
Estimated Expiration
2040-08-31

AI Technical Summary

Technical Problem

The existing prefabricated cover beam connection method requires high altitude operation, the installation is complex and cumbersome, and there is construction risk, and the bite and density of the shear bond and the cover beam structure are insufficient.

Method used

The prefabricated assembled cover beam structure connected by shear keys includes pre-buried concave steel grooves and prefabricated holes. The shear key consists of a horizontal substrate, high-strength bolts, top caps and universal hinges. The stable connection is achieved by connecting the steel plate and the bolts. After installing the shear bonds on site, use epoxy resin adhesive layer and prestressed steel bars to tighten.

Benefits of technology

It reduces the risk of high-altitude operations, improves the occlusivity and density of the shear bond and the cover beam structure, makes the overall structure more stable, and simplifies position determination and construction time during the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111893870B_ABST
    Figure CN111893870B_ABST
Patent Text Reader

Abstract

The present invention relates to a prefabricated assembled cap beam structure connected by shear keys and a construction method, comprising a cap beam installed on a pier beam, characterized in that: the cap beam comprises two cap beam units spliced ​​together by connecting parts, the cap beam unit is spliced ​​with the corresponding pier beam through the connecting parts, the connecting parts comprise shear keys, connecting steel plates, and concave steel grooves, the bottom surface of the cap beam unit is pre-embedded with a concave steel groove in the transverse direction, the splicing surface of one cap beam unit is pre-embedded with a concave steel groove in the longitudinal direction, the splicing surface of the other cap beam unit and the upper end surface of the pier beam are provided with prefabricated holes for accommodating shear keys and connecting steel plates, an adhesive layer is provided between the splicing surfaces of the two cap beam units and between the connecting surfaces of the cap beam unit and the pier beam, the splicing surface of the structure has strong shear resistance, the shear keys are installed on the ground, the bite and tightness of the shear keys and the cap beam structure can be effectively improved, and the overall structure is more stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a prefabricated assembled cap beam structure connected by shear keys and a construction method. Background Art

[0002] In recent years, the prefabricated and assembled cap beams that have been gradually promoted and applied have adopted the process of factory production and on-site installation, which has greatly accelerated the construction progress and reduced the on-site operation time. At the same time, due to the reduction of on-site construction, the construction risk has been greatly reduced. At present, most prefabricated cap beams are connected by toothed shear keys or reserved steel bar holes for grouting sleeves. The installation of shear keys requires high-altitude operations, and the on-site construction steps are cumbersome. Summary of the invention

[0003] The invention provides a prefabricated assembled cap beam structure connected by shear keys and a construction method.

[0004] The solution adopted by the present invention to solve the technical problem is a prefabricated assembled cap beam structure connected by a shear key, comprising a cap beam installed on a pier beam, the cap beam comprising two cap beam units spliced ​​together by a connecting piece, the cap beam unit being spliced ​​with the corresponding pier beam through a connecting piece, the connecting piece comprising a shear key, a connecting steel plate, and a concave steel groove, a concave steel groove is pre-embedded in the horizontal direction on the bottom surface of the cap beam unit, a concave steel groove is pre-embedded in the longitudinal direction on the splicing surface of one cap beam unit, and prefabricated holes for accommodating shear keys and connecting steel plates are provided on the splicing surface of the other cap beam unit and the upper end surface of the pier beam;

[0005] The shear key comprises a horizontal base plate, a high-strength bolt and a top cap. The two ends of the horizontal base plate are respectively provided with a vertical flat plate portion A and a flat plate portion B. The inner end of the high-strength bolt passes through the flat plate portion A and is threadedly matched therewith. The top cap is installed on the inner end of the high-strength bolt via a universal hinge. A T-shaped portion perpendicular to the flat plate portion B is installed on the outer end thereof. The T-shaped portion can be embedded in the notch of the concave steel groove. The connecting steel plate is pressed against the inner side of the flat plate portion B by the top cap.

[0006] Adhesive layers are arranged between the joint surfaces of the two cap beam units and between the connection surfaces of the cap beam unit and the pier beam.

[0007] Furthermore, a plurality of bolts A perpendicular to the connecting steel plate and the flat plate portion B are welded at intervals along the length direction on the opposite sides of the fitting surfaces thereof, and the bolts A are accommodated in prefabricated holes.

[0008] Furthermore, the concave steel channel includes a channel steel, a plurality of bolts B perpendicular to the web of the channel steel are welded at intervals along the length direction, the upper ends of the inner sides of the wing plates on both sides of the channel steel are perpendicular to the wing plates, and the plate bodies on both sides and the inner groove of the channel steel surround the T-groove of the T-shaped portion.

[0009] Furthermore, at least two concave steel grooves are arranged on each joint surface at intervals, and each concave steel groove corresponds to a prefabricated hole.

[0010] Furthermore, the shear keys in different concave steel grooves on the same straight line share a connecting steel plate.

[0011] Furthermore, a plurality of corresponding prestressed pipes are provided on the two cap beam units, and prestressed steel bars are passed through the prestressed pipes.

[0012] Furthermore, the bonding layer is an epoxy resin adhesive layer.

[0013] Furthermore, the shear key, stud A and stud B are all made of high-quality carbon structural steel.

[0014] A construction method for a prefabricated assembled cap beam connected by shear keys, comprising the following steps:

[0015] Step 1: Prefabricate cap beam units, pier beams, shear keys, and connecting steel plates, embed concave steel grooves on the bottom surface of the cap beam units, embed concave steel grooves on the splicing surface of one cap beam unit, and reserve prefabricated holes on the splicing surface of the other cap beam unit and the upper end surface of the pier beam;

[0016] Step 2: Transport the components to the site, install the shear key on the ground first, insert the T-shaped part of the shear key into the notch of the corresponding concave steel groove, set a connecting steel plate between the top surface and the concave steel groove, turn and tighten the high-strength bolts, so that the connecting steel plate is pressed against the inner side of the flat plate part B by the top cap, and ensure that the concave steel groove, the connecting steel plate, and the universal hinge do not slide relative to each other;

[0017] Step 3: Use a crane to lift the two cap beam units, apply epoxy resin as a bonding layer on the joint surface of the cap beam units, so that the connecting steel plate and shear key on one cap beam unit can be completely inserted into the prefabricated holes on the other cap beam unit; apply epoxy resin as a bonding layer on the connection between the lower side of the cap beam unit and the pier beam and the upper end surface of the pier beam, and then lower the two cap beam units together, so that the connecting steel plate and shear key on the lower side of the cap beam unit can be completely inserted into the prefabricated holes on the corresponding pier beam;

[0018] Step 4: Lay the pre-prepared prestressed steel bars along the reserved prestressed pipes, tension and anchor the prestressed steel bars using the post-tensioning method, so that the two cap beam units fit tightly together, then remove the crane and perform grouting to seal the prestressed pipes;

[0019] Step 5: Use high-pressure grouting to fill the gaps in the joints. After solidification, use high-pressure epoxy adhesive to inject into the joints to make the bond tighter.

[0020] In step 1, the cap beam unit is cast in sections by short lines during prefabrication, from bottom to top.

[0021] In step 2, at the connection between the cap beam unit and the pier beam, the shear keys in different concave steel grooves on the same horizontal line share a connecting steel plate; at the connection between two cap beam units, the shear keys in different concave steel grooves on the same horizontal line share a connecting steel plate.

[0022] In step 5, when the epoxy adhesive is injected under high pressure, it is injected from one side. After the adhesive flows out from the other side, the injection is stopped and the overflowed epoxy adhesive is wiped off and cleaned.

[0023] Compared with the prior art, the present invention has the following beneficial effects: the joint surface has strong shear resistance, the shear keys are installed on the ground, which greatly reduces the construction risk of high-altitude operations, and at the same time can effectively improve the bite and tightness of the shear keys and the cap beam structure, making the overall structure more stable, and the use of prefabricated holes makes it easier to determine the position during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] The present invention is further described below in conjunction with the accompanying drawings.

[0025] Figure 1 It is a schematic diagram of the longitudinal section of the overall structure;

[0026] Figure 2 It is the connection diagram of shear key and connecting steel plate;

[0027] Figure 3 is the side view of the shear key;

[0028] Figure 4 It is a cross-sectional view of a cap beam unit provided with prefabricated holes;

[0029] Figure 5 This is a top view of the pier beam;

[0030] Figure 6 This is a schematic diagram of a concave steel channel.

[0031] In the figure: 1-cap beam unit; 2-pier beam; 3-shear key; 301-horizontal base plate; 302-high-strength bolt; 303-top cap; 304-T-shaped part; 305-flat plate part A; 306-flat plate part B; 4-concave steel channel; 401-channel steel; 402-plate body; 5-bolt A; 6-bolt B; 7-connecting steel plate; 8-prestressed pipe; 9-prefabricated hole. DETAILED DESCRIPTION

[0032] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0033] like Figure 1-6As shown, a prefabricated assembled cap beam structure connected by a shear key comprises a cap beam installed on a pier beam 2, the cap beam comprises two cap beam units 1 spliced ​​together by a connecting piece, the cap beam unit is spliced ​​with the corresponding pier beam by a connecting piece, the connecting piece comprises a shear key 3, a connecting steel plate 7, and a concave steel groove 4, a concave steel groove is pre-embedded in the horizontal direction on the bottom surface of the cap beam unit, a concave steel groove is pre-embedded in the longitudinal direction on the splicing surface of one cap beam unit, and prefabricated holes 9 for accommodating shear keys and connecting steel plates are provided on the splicing surface of the other cap beam unit and the upper end surface of the pier beam;

[0034] The shear key comprises a horizontal base plate 301, a high-strength bolt 302, and a top cap 303. The two ends of the horizontal base plate are respectively provided with a vertical flat plate portion A305 and a flat plate portion B306. The inner end of the high-strength bolt passes through the flat plate portion A and is threadedly matched therewith. The top cap is installed on the inner end of the high-strength bolt via a universal hinge. A T-shaped portion 304 vertical thereto is installed on the outer end of the flat plate portion B. The T-shaped portion can be embedded in the notch of the concave steel groove. The connecting steel plate is pressed against the inner side of the flat plate portion B by the top cap.

[0035] Adhesive layers are arranged between the joint surfaces of the two cap beam units and between the connection surfaces of the cap beam unit and the pier beam.

[0036] In this embodiment, a plurality of studs A5 perpendicular to the connecting steel plate and the flat plate portion B are welded at intervals along the length direction on the opposite sides of the fitting surfaces, and the studs A are accommodated in prefabricated holes.

[0037] In this embodiment, the concave steel channel includes a channel steel 401, and a plurality of bolts B6 perpendicular to the web of the channel steel are welded at intervals along the length direction. The upper ends of the inner sides of the wing plates on both sides of the channel steel are perpendicular to the wing plates. The plate bodies on both sides and the inner groove of the channel steel surround the T-groove of the T-shaped portion.

[0038] In this embodiment, at least two concave steel grooves are arranged on each joint surface at intervals, and each concave steel groove corresponds to a prefabricated hole.

[0039] In this embodiment, the shear keys in different concave steel grooves on the same straight line share a connecting steel plate.

[0040] In this embodiment, a plurality of corresponding prestressed pipes 9 are provided on the two cap beam units, and prestressed steel bars are inserted into the prestressed pipes.

[0041] In this embodiment, the bonding layer is an epoxy resin adhesive layer.

[0042] In this embodiment, the shear key, stud A, and stud B are all made of high-quality carbon structural steel.

[0043] A construction method for a prefabricated assembled cap beam connected by shear keys, comprising the following steps:

[0044] Step 1: Prefabricate cap beam units, pier beams, shear keys, and connecting steel plates, embed concave steel grooves on the bottom surface of the cap beam units, embed concave steel grooves on the splicing surface of one cap beam unit, and reserve prefabricated holes on the splicing surface of the other cap beam unit and the upper end surface of the pier beam;

[0045] Step 2: Transport the components to the site, install the shear key on the ground first, insert the T-shaped part of the shear key into the notch of the corresponding concave steel groove, set a connecting steel plate between the top surface and the concave steel groove, turn and tighten the high-strength bolts, so that the connecting steel plate is pressed against the inner side of the flat plate part B by the top cap, and ensure that the concave steel groove, the connecting steel plate, and the universal hinge do not slide relative to each other;

[0046] Step 3: Use a crane to lift the two cap beam units, apply epoxy resin as a bonding layer on the joint surface of the cap beam units, so that the connecting steel plate and shear key on one cap beam unit can be completely inserted into the prefabricated holes on the other cap beam unit; apply epoxy resin as a bonding layer on the connection between the lower side of the cap beam unit and the pier beam and the upper end surface of the pier beam, and then lower the two cap beam units together, so that the connecting steel plate and shear key on the lower side of the cap beam unit can be completely inserted into the prefabricated holes on the corresponding pier beam;

[0047] Step 4: Lay the pre-prepared prestressed steel bars along the reserved prestressed pipes, tension and anchor the prestressed steel bars using the post-tensioning method, so that the two cap beam units fit tightly together, then remove the crane and perform grouting to seal the prestressed pipes;

[0048] Step 5: Use high-pressure grouting to fill the gaps in the joints. After solidification, use high-pressure epoxy adhesive to inject into the joints to make the bond tighter.

[0049] In step 1, the cap beam unit is cast in sections by short lines during prefabrication, from bottom to top.

[0050] In step 2, at the connection between the cap beam unit and the pier beam, the shear keys in different concave steel grooves on the same horizontal line share a connecting steel plate; at the connection between two cap beam units, the shear keys in different concave steel grooves on the same horizontal line share a connecting steel plate.

[0051] In step 5, when the epoxy adhesive is injected under high pressure, it is injected from one side. After the adhesive flows out from the other side, the injection is stopped and the overflowed epoxy adhesive is wiped off and cleaned.

[0052] If this patent discloses or involves components or structural parts that are fixedly connected to each other, then, unless otherwise stated, the fixed connection can be understood as: a detachable fixed connection (such as connection using bolts or screws), or as: a non-detachable fixed connection (such as riveting, welding). Of course, the mutual fixed connection can also be replaced by an integrated structure (such as one-piece manufacturing using a casting process) (except where it is obviously impossible to use an integrated molding process).

[0053] In the embodiment, the T-shaped portion can increase the contact surface of the overall structure, increase the resistance generated by friction, and improve the stability of the structure; the concave steel trough and steel plate assembly are anchored in the cap beam unit and the pier beam by bolts, which greatly increases the stability of the structure; the prestressed tendon tensioning and anchoring method greatly shortens the required working time compared to the traditional cast-in-place construction, and effectively shortens the construction period and improves efficiency in large, medium and long-term bridge projects; the shear key forms shear force transmission between the pier beam and the cap beam through the friction between the universal hinge, the connecting steel plate and the concave steel trough, thereby forming a combined working form, which effectively improves the shear resistance of the splicing surface.

[0054] In the description of this patent, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing this patent, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this patent.

[0055] The preferred embodiments listed above further illustrate the objectives, technical solutions and advantages of the present invention in detail. It should be understood that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A prefabricated assembled cap beam structure connected by shear keys, comprising a cap beam installed on a pier beam, Features: The cap beam comprises two cap beam units spliced ​​together by a connecting piece, the cap beam unit is spliced ​​with the corresponding pier beam by a connecting piece, the connecting piece comprises a shear key, a connecting steel plate, and a concave steel groove, the bottom surface of the cap beam unit is pre-buried with a concave steel groove in the transverse direction, the splicing surface of one cap beam unit is pre-buried with a concave steel groove in the longitudinal direction, and the splicing surface of the other cap beam unit and the upper end surface of the pier beam are provided with prefabricated holes for accommodating the shear key and the connecting steel plate; The shear key comprises a horizontal base plate, a high-strength bolt and a top cap. The two ends of the horizontal base plate are respectively provided with a vertical flat plate portion A and a flat plate portion B. The inner end of the high-strength bolt passes through the flat plate portion A and is threadedly matched therewith. The top cap is installed on the inner end of the high-strength bolt via a universal hinge. A T-shaped portion perpendicular to the flat plate portion B is installed on the outer end thereof. The T-shaped portion can be embedded in the notch of the concave steel groove. The connecting steel plate is pressed against the inner side of the flat plate portion B by the top cap. A bonding layer is provided between the joint surfaces of the two cap beam units and between the connection surfaces of the cap beam unit and the pier beam; On the opposite side of the bonding surface of the connecting steel plate and the flat plate portion B, a plurality of bolts A perpendicular thereto are welded at intervals along the length direction, and the bolts A are accommodated in the prefabricated holes; The concave steel channel comprises a channel steel, a plurality of bolts B perpendicular to the web of the channel steel are welded at intervals along the length direction, the upper ends of the inner sides of the wing plates on both sides of the channel steel are perpendicular to the wing plates, and the plate bodies on both sides and the inner notch of the channel steel surround the T-shaped groove of the T-shaped portion; At least two concave steel grooves are arranged on each joint surface at intervals, and each concave steel groove corresponds to a prefabricated hole; Shear keys in different concave steel channels on the same straight line share a connecting steel plate; A plurality of corresponding prestressed pipes are arranged on the two cap beam units, and prestressed steel bars are passed through the prestressed pipes.

2. The prefabricated assembled cap beam structure connected by shear keys according to claim 1, Features: The bonding layer is an epoxy resin adhesive layer.

3. The prefabricated assembled cap beam structure connected by shear keys according to claim 1, Features: The shear key, stud A and stud B are all made of high-quality carbon structural steel.

4. A construction method for a prefabricated assembled cap beam connected by shear keys, using the prefabricated assembled cap beam structure connected by shear keys as claimed in claim 3, It is characterized in that The following steps are involved: Step 1: Prefabricate cap beam units, pier beams, shear keys, and connecting steel plates, embed concave steel grooves on the bottom surface of the cap beam units, embed concave steel grooves on the splicing surface of one cap beam unit, and reserve prefabricated holes on the splicing surface of the other cap beam unit and the upper end surface of the pier beam; Step 2: Transport the components to the site, install the shear key on the ground first, insert the T-shaped part of the shear key into the notch of the corresponding concave steel groove, set a connecting steel plate between the top surface and the concave steel groove, turn and tighten the high-strength bolts, so that the connecting steel plate is pressed against the inner side of the flat plate part B by the top cap, and ensure that the concave steel groove, the connecting steel plate, and the universal hinge do not slide relative to each other; Step 3: Use a crane to lift the two cap beam units, apply epoxy resin as a bonding layer on the joint surface of the cap beam units, so that the connecting steel plate and shear key on one cap beam unit can be completely inserted into the prefabricated holes on the other cap beam unit; apply epoxy resin as a bonding layer on the connection between the lower side of the cap beam unit and the pier beam and the upper end surface of the pier beam, and then lower the two cap beam units together, so that the connecting steel plate and shear key on the lower side of the cap beam unit can be completely inserted into the prefabricated holes on the corresponding pier beam; Step 4: Lay the pre-prepared prestressed steel bars along the reserved prestressed pipes, tension and anchor the prestressed steel bars using the post-tensioning method, so that the two cap beam units fit tightly together, then remove the crane and perform grouting to seal the prestressed pipes; Step 5: Use high-pressure grouting to fill the gaps in the joints. After solidification, use high-pressure epoxy adhesive to inject into the joints to make the bond tighter.

5. The construction method of the prefabricated assembled cap beam connected by shear keys according to claim 4, Features: In step 1, the cap beam unit is cast in sections by short lines during prefabrication, and is cast in sections from bottom to top; In step 2, at the connection between the cap beam unit and the pier beam, the shear keys in different concave steel grooves on the same horizontal line share a connecting steel plate; at the connection between two cap beam units, the shear keys in different concave steel grooves on the same horizontal line share a connecting steel plate; In step 5, when the epoxy adhesive is injected under high pressure, it is injected from one side. After the adhesive flows out from the other side, the injection is stopped and the overflowed epoxy adhesive is wiped off and cleaned.