By optimizing the layout in the concrete segmental beam steel bar processing production line, the raw material storage area, unloading area, steel bar parts processing area, material preparation area, steel bar assembly area and transfer area are arranged in different large gantry crane work spaces in order of operation, solving the problem It solves the problems of low production efficiency and waste of resources caused by the simple traditional layout, and achieves efficient steel bar processing and production.
Patent Information
- Application Number
- CN202011333162.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-11-24
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2040-11-24
AI Technical Summary
The traditional concrete segmental beam steel bar processing workshop has a simple layout and is not suitable for emerging technologies based on steel bar components. This results in difficult production line layout, affects efficiency and resource utilization, and causes problems such as high manpower demand, low production efficiency, and resource waste.
A concrete segment beam steel bar processing production line based on steel bar parts is designed. The raw material storage area, unloading area, steel bar parts processing area, material preparation area, steel bar assembly area and transfer area are arranged in different large-scale gantry cranes in order of operation. Within the space, multiple pieces of equipment and storage racks are used to coordinate partitions, optimize logistics relationships, and set up multiple small gantry cranes to reduce gantry crane manufacturing costs.
A rationally laid out, concise and efficient steel bar processing production line has been realized, which improves production efficiency, reduces resource waste, and solves the problems of high manpower demand and low production efficiency.
Smart Images

Figure CN112404316B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of concrete segment beam reinforcement processing production system, and more specifically, to a concrete segment beam reinforcement processing production line based on reinforcement components. Background Art
[0002] The traditional concrete segmental beam steel bar processing workshop is mainly composed of three functional areas: raw material storage area, unloading area and steel bar binding area. It cooperates with large gantry cranes to complete the on-site transfer of semi-finished steel bar processing products and the lifting of finished steel bar skeletons out of the factory.
[0003] The traditional concrete segmental beam steel bar processing technology has fewer processes and the layout of the production line is relatively easy. However, for the emerging technologies based on steel bar components, the layout of the production line is difficult due to the large number of large equipment in the factory, the large number and size of steel bar components, and the complex logistics relationships in the factory. If the layout is not appropriate, it will seriously restrict production efficiency or cause waste of resources. The traditional concrete segmental beam steel bar processing workshop has a simple layout and is no longer suitable for emerging technologies based on steel bar components. It is necessary to propose a steel bar processing production line with a reasonable layout, simplicity and efficiency. Summary of the invention
[0004] In order to achieve these purposes and other advantages according to the present invention, a concrete segment beam steel bar processing production line based on steel bar components is provided, which comprises a raw material storage area, a material unloading area, a steel bar component processing area, a material preparation area, a steel bar assembly area and a transfer area in sequence according to the operation sequence, wherein the raw material storage area, the material unloading area and the steel bar component processing area are arranged in the working space of a first large gantry crane; the steel bar assembly area and the transfer area are arranged in the working space of a second large gantry crane, and the working spaces of the first large gantry crane and the second large gantry crane partially overlap, and the overlapping area is set as the material preparation area; wherein,
[0005] The raw material storage area is used to store raw materials, the input end of the raw material storage area is a transport vehicle loaded with the raw materials, and the output end of the raw material storage area is the unloading area or the miscellaneous material preparation area;
[0006] The unloading area is provided with processing equipment to perform primary processing on the raw materials. The input end of the unloading area is the raw material storage area, and the output end of the unloading area is the steel bar parts processing area or the miscellaneous material preparation area.
[0007] The input end of the steel bar component processing area is the unloading area, and the output end of the steel bar component processing area is the steel bar cage preparation area and the steel bar mesh preparation area in the material preparation area; the steel bar component processing area includes the steel bar cage processing area and the steel bar mesh processing area;
[0008] The material preparation area is used to store the parts to be made into the steel bar skeleton, the input end of the material preparation area is the raw material storage area, the unloading area and the steel bar parts processing area, and the output end of the material preparation area is the loading area of the steel bar assembly area;
[0009] The steel bar assembly area is composed of a plurality of steel bar assembly units, each of which includes a loading area and an assembly area, wherein the loading area and the assembly area are arranged in the working space of the third small gantry crane, the input end of the steel bar assembly area is the material preparation area, and the output end of the steel bar assembly area is the transfer area;
[0010] The transfer area is composed of at least one transverse moving trolley, which transfers the finished steel bar skeleton from the steel bar processing workshop to the concrete pouring pedestal. The input end of the transfer area is the steel bar assembly area, and the output end of the transfer area is the concrete pouring pedestal.
[0011] According to a preferred embodiment of the present invention, in the concrete segmental beam steel bar processing production line based on steel bar components, the processing equipment in the unloading area includes a steel bar sawing machine, a steel bar bending machine, a stirrup welding machine and a hook bar unloading machine.
[0012] According to a preferred embodiment of the present invention, in the concrete segment beam steel bar processing production line based on steel bar components, the steel cage processing area is provided with a plurality of steel cage feeding equipment and a plurality of welding equipment, and the steel mesh processing area includes a plurality of steel mesh feeding equipment, a plurality of welding equipment and a plurality of bending equipment.
[0013] According to a preferred embodiment of the present invention, in the concrete segmental beam steel bar processing production line based on steel bar parts, the meshes are stacked in layers through the storage rack, and the order of mesh stacking should be coordinated with the order of mesh assembly, that is, the meshes that are lifted first should be stacked on the upper layer of the storage rack, and all meshes of the same segmental beam are independently stacked for overall transportation.
[0014] According to a preferred embodiment of the present invention, in the steel bar processing production line for concrete segment beams based on steel bar components, in the steel bar assembly area, the assembly area is a steel bar assembly cradle.
[0015] According to a preferred embodiment of the present invention, in the concrete segment beam steel bar processing production line based on steel bar components, the material preparation area includes a steel cage preparation area, a steel mesh preparation area and the miscellaneous material storage area, wherein the steel cage preparation area is used to store web steel cages; the steel mesh preparation area is used to store various types of steel meshes; the miscellaneous material storage area is used to store hook bars, reserved steel bars, tooth block steel bars, and cut corrugated pipes and steel strands.
[0016] According to a preferred embodiment of the present invention, in the steel bar processing production line for concrete segment beams based on steel bar components, the steel bar component processing area includes a steel bar cage processing area and a steel bar mesh processing area, wherein the steel bar cage processing area is used for laying and welding operations during the preparation of the steel bar cage; the steel bar mesh processing area is used for bending, laying and welding operations during the preparation of the steel bar mesh.
[0017] According to a preferred embodiment of the present invention, in the steel bar processing production line for concrete segment beams based on steel bar components, in the steel bar assembly area, the loading area includes a steel bar cage storage area, a steel bar mesh storage area, a storage rack storage area and a miscellaneous material storage area, wherein the storage rack storage area is used to temporarily store storage racks in an empty state. The input end of the loading area is the material preparation area, and the output end is the assembly area; the loading area and the assembly area are arranged in the working space of the third small gantry crane, and the third small gantry crane is arranged in the second large gantry crane.
[0018] According to a preferred embodiment of the present invention, in the concrete segment beam steel bar processing production line based on steel bar components, the moving direction of the third small gantry crane is consistent with the long side direction of the steel bar assembly frame, so that the manufacturing cost of the gantry crane can be minimized under the premise of the same lifting capacity. The lifting capacity of the gantry crane should be greater than the weight of the largest steel bar component.
[0019] The present invention includes at least the following beneficial effects: the concrete segment beam steel bar processing system based on steel bar components of the present invention has a reasonable layout, is concise and efficient, and can solve the problems of large manpower demand, low production efficiency and waste of resources faced by the prior art.
[0020] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the framework structure of the concrete segment beam steel bar processing production line based on steel bar components in the present invention.
[0022] Figure 2 It is a schematic diagram of the framework structure of the steel bar assembly area described in the above embodiment. DETAILED DESCRIPTION
[0023] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0024] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art can think of other obvious variations. The basic principles of the present invention defined in the following description can be applied to other embodiments, variations, improvements, equivalents, and other technical solutions that do not deviate from the spirit and scope of the present invention.
[0025] Those skilled in the art should understand that, in the disclosure of the present invention, the orientation or position relationship indicated by the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. are based on the orientation or position relationship shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the above terms should not be understood as limiting the present invention.
[0026] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.
[0027] like Figure 1-2 As shown, a preferred embodiment of the present invention provides a concrete segment beam steel bar processing production line based on steel bar components. The entire system is arranged in the working space of two large gantry cranes, which is more convenient to move. When the entire system needs to be relocated, the above-mentioned processing and production system includes a raw material storage area 1, a material unloading area 2, a steel bar component processing area 3, a material preparation area 4, a steel bar assembly area 5 and a transfer area 6 according to the operation sequence, wherein the raw material storage area 1, the material unloading area 2 and the steel bar component processing area 3 are arranged in the working space of the first large gantry crane 7; the steel bar assembly area 5 and the transfer area 6 are arranged in the working space of the second large gantry crane 8, and the working spaces of the first large gantry crane 7 and the second large gantry crane 8 partially overlap, and the overlapping area is set as the material preparation area 4; wherein,
[0028] The raw material storage area 1 is used to store raw materials, mainly including steel bars, coils, steel strands, corrugated pipes, anchors, wire ties and other raw materials that need to be processed. The input end of the raw material storage area 1 is a transport vehicle loaded with the raw materials, and the output end of the raw material storage area 1 is the unloading area 2 or the miscellaneous material preparation area; anchors, wire ties and other raw materials that do not need to be processed can be directly taken as needed and transported to the above-mentioned miscellaneous material preparation area.
[0029] The unloading area 2 is provided with processing equipment to perform preliminary processing on the raw materials. The input end of the unloading area is the raw material storage area, and the output end of the unloading area is the steel bar parts processing area or the miscellaneous material preparation area.
[0030] The steel bar component processing area 3, the input end of the steel bar component processing area 3 is the unloading area 2, and the output end of the steel bar component processing area 3 is the steel bar cage material preparation area and the steel bar mesh material preparation area; the steel bar component processing area includes a steel bar cage processing area 31 and a steel bar mesh processing area 32;
[0031] The material preparation area 4 is used to store the parts to be made into the steel bar skeleton. The input end of the material preparation area 4 is the raw material storage area 1, the unloading area 2 and the steel bar parts processing area 3. The output end of the material preparation area 4 is the loading area 51 of the steel bar assembly area 5.
[0032] The steel bar assembly area 5 is composed of a plurality of steel bar assembly units 51, each of which includes a loading area 511 and an assembly area 512, wherein the loading area 511 and the assembly area 512 are arranged in the working space of the third small gantry crane 8, the input end of the steel bar assembly area 5 is the material preparation area 4, and the output end of the steel bar assembly area 5 is the transfer area 6;
[0033] The transfer area 6 is composed of at least one transverse moving trolley 61, which transfers the finished steel bar skeleton from the steel bar processing workshop to the concrete pouring pedestal. The input end of the transfer area 6 is the steel bar assembly area 5, and the output end of the transfer area 6 is the concrete pouring pedestal.
[0034] In another embodiment of the present invention, in the concrete segmental beam steel bar processing production line based on steel bar components, the processing equipment in the unloading area 2 includes a steel bar sawing machine, a steel bar bending machine, a stirrup welding machine and a hook bar unloading machine.
[0035] In another embodiment of the present invention, in the concrete segmental beam steel bar processing production line based on steel bar components, the steel cage processing area is provided with a plurality of steel cage feeding equipment and a plurality of welding equipment, and the steel mesh processing area includes a plurality of steel mesh feeding equipment, a plurality of welding equipment and a plurality of bending equipment.
[0036] In another embodiment of the present invention, in the concrete segmental beam steel bar processing production line based on steel bar parts, the meshes are stacked in layers through the storage rack, and the order of mesh stacking should be coordinated with the order of mesh assembly, that is, the meshes that are lifted first should be stacked on the upper layer of the storage rack, and all meshes of the same segmental beam are independently stacked for overall transportation.
[0037] In another embodiment of the present invention, in the steel bar processing production line for concrete segment beams based on steel bar components, in the steel bar assembly area, the assembly area is a steel bar assembly cradle.
[0038] In another embodiment of the present invention, in the steel bar processing production line for concrete segmental beams based on steel bar components, the preparation area 4 includes a steel cage preparation area 41, a steel mesh preparation area 42 and the miscellaneous material storage area 43, wherein the steel cage preparation area 41 is used to store web steel cages, which are stored vertically or horizontally by means of a bracket; the steel mesh preparation area 42 is used to store various types of steel meshes, which are stacked in layers by means of storage racks, and the order in which the steel meshes are stacked should be coordinated with the order in which the steel meshes are assembled, that is, the steel meshes that are lifted first should be stacked on the upper layer of the storage rack, and all meshes of the same segmental beam should be stacked independently for overall transportation; the miscellaneous material storage area 43 is used to store hook bars, reserved steel bars, tooth block steel bars, and cut corrugated pipes and steel strands.
[0039] In another embodiment of the present invention, in the steel bar processing production line for concrete segment beams based on steel bar components, the steel bar component processing area 3 includes the steel bar cage processing area 31 and the steel bar mesh processing area 32, wherein the steel bar cage processing area 31 is used for laying and welding operations in the steel bar cage preparation process; the steel bar mesh processing area 32 is used for bending, laying and welding operations in the steel bar mesh preparation process.
[0040] In another embodiment of the present invention, in the steel bar processing production line for concrete segment beams based on steel bar components, in the steel bar assembly area 5, in each of the steel bar assembly units 51, the loading area 511 includes a steel bar cage storage area 5111, a steel bar mesh storage area 5112, a storage rack storage area 5113 and a miscellaneous material storage area 5114, wherein the storage rack storage area is used to temporarily store storage racks in an empty state. The input end of the loading area is the material preparation area, and the output end is the assembly area; the loading area and the assembly area are arranged in the working space of the third small gantry crane.
[0041] In another embodiment of the present invention, in the concrete segment beam steel bar processing production line based on steel bar components, the moving direction of the third small gantry crane is consistent with the long side direction of the steel bar assembly frame, so that the manufacturing cost of the gantry crane can be minimized under the premise of the same lifting capacity. The lifting capacity of the gantry crane should be greater than the weight of the largest steel bar component.
[0042] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. A concrete segment beam steel bar processing production line based on steel bar parts, characterized in that: According to the operation sequence, it includes a raw material storage area, a material unloading area, a steel bar component processing area, a material preparation area, a steel bar assembly area and a transfer area, wherein the raw material storage area, the material unloading area and the steel bar component processing area are arranged in the working space of the first large gantry crane; the steel bar assembly area and the transfer area are arranged in the working space of the second large gantry crane, and the working spaces of the first large gantry crane and the second large gantry crane partially overlap, and the overlapping area is set as the material preparation area; wherein, The raw material storage area is used to store raw materials, the input end of the raw material storage area is a transport vehicle loaded with the raw materials, and the output end of the raw material storage area is the unloading area or the miscellaneous material preparation area; The unloading area is provided with processing equipment to perform primary processing on the raw materials. The input end of the unloading area is the raw material storage area, and the output end of the unloading area is the steel bar parts processing area or the miscellaneous material preparation area. The input end of the steel bar component processing area is the unloading area, and the output end of the steel bar component processing area is the steel bar cage preparation area and the steel bar mesh preparation area in the material preparation area; the steel bar component processing area includes the steel bar cage processing area and the steel bar mesh processing area; The material preparation area is used to store the parts to be made into the steel bar skeleton, the input end of the material preparation area is the raw material storage area, the unloading area and the steel bar parts processing area, and the output end of the material preparation area is the loading area of the steel bar assembly area; The steel bar assembly area is composed of a plurality of steel bar assembly units, each of which includes a loading area and an assembly area, wherein the loading area and the assembly area are arranged in the working space of the third small gantry crane, the input end of the steel bar assembly area is the material preparation area, and the output end of the steel bar assembly area is the transfer area; The transfer area is composed of at least one transverse trolley, which transfers the finished steel bar skeleton from the steel bar processing workshop to the concrete pouring pedestal. The input end of the transfer area is the steel bar assembly area, and the output end of the transfer area is the concrete pouring pedestal. The processing equipment in the blanking area includes a steel bar sawing machine, a steel bar bending machine, a stirrup welding machine and a hook bar blanking machine; The steel cage processing area is provided with a plurality of steel cage material distribution equipment and a plurality of welding equipment, and the steel mesh processing area includes a plurality of steel mesh material distribution equipment, a plurality of welding equipment and a plurality of bending equipment; The steel bar component processing area includes a steel bar cage processing area and a steel bar mesh processing area, wherein the steel bar cage processing area is used for laying and welding operations during the steel bar cage preparation process; the steel bar mesh processing area is used for bending, laying and welding operations during the steel bar mesh preparation process.
2. The concrete segment beam steel bar processing production line based on steel bar parts according to claim 1 is characterized in that: The steel meshes are stacked in layers on storage racks. The order of stacking the steel meshes should be coordinated with the order of mesh assembly, that is, the steel meshes that are lifted first should be stacked on the upper layer of the storage rack, and all the steel meshes of the same segment beam should be stacked independently to facilitate overall transportation.
3. The concrete segment beam steel bar processing production line based on steel bar parts according to claim 1 is characterized in that: In the steel bar assembly area, the assembly area is a steel bar assembly frame.
4. The concrete segment beam steel bar processing production line based on steel bar parts according to claim 1 is characterized in that: The material preparation area includes the steel cage preparation area, the steel mesh preparation area and the miscellaneous material preparation area, wherein the steel cage preparation area is used to store the web steel cage; the steel mesh preparation area is used to store various types of steel meshes; the miscellaneous material preparation area is used to store hook bars, reserved steel bars, tooth block steel bars, and cut corrugated pipes and steel strands.
5. The concrete segment beam steel bar processing production line based on steel bar parts according to claim 3 is characterized in that: In the steel bar assembly area, the loading area includes a steel cage storage area, a steel mesh storage area, a storage rack storage area and a miscellaneous material storage area, wherein the storage rack storage area is used to temporarily store storage racks in an empty state; the input end of the loading area is a material preparation area, and the output end is an assembly area; the loading area and the assembly area are arranged in the working space of a third small gantry crane, and the above-mentioned third small gantry crane is arranged in the second large gantry crane.
6. The concrete segment beam steel bar processing production line based on steel bar parts according to claim 5 is characterized in that: The moving direction of the third small gantry crane is consistent with the long side direction of the steel bar assembly frame, so that the manufacturing cost of the gantry crane can be reduced to the maximum extent under the premise of the same lifting capacity.
Citation Information
Patent Citations
Reinforcing cage forming system
CN105312457A
Prefabricated concrete component production system
CN105690552A
Reinforcing steel bar mesh welding production line
CN108405767A
Reinforced steel bar cage manufacturing method and system
CN110153336A
Fabricated pier prefabricated plant site function layout structure and design method
CN111571800A